Beruflich Dokumente
Kultur Dokumente
net/publication/283210199
CITATION READS
1 24,888
1 author:
Eda Buchner
Yeditepe University
21 PUBLICATIONS 6 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Eda Buchner on 28 March 2016.
Today
Actual
Costs (AC) Planned
Value (PV)
Cumulative
Value
Is this project
Earned over/under budget?
Value (EV)
Is it ahead of/behind
schedule?
Time
Cost Management Key Terms
PV - Planned Value, estimated value of the planned work
EV – Earned Value, estimated value of work done
AC – Actual Cost, what you paid
BAC – Budget at Completion, the budget for the total job
EAC –Estimate at Completion, what is the total job
expected to cost?
ETC – Estimate to Complete, forecasted costs to complete
job
VAC – Variance at Completion, how much over/under
budget do we expect to be?
Cost Management Process?
Three processes
Estimate Costs
Determine Budget
Control Costs
Minimal customization
No change in procurement systems during
accounts payable implementation
Cost/Benefit Analysis BSR was broken down into a three-year cash
& Internal Rate of Return (IRR) outlay without depreciation. Costs are
represented in thousands. Capital and expenses
are combined in this example.
Example: Business Systems Replacement
Project Cash Flow Analysis
FY95 FY96 FY97 3 Year Future Annual
Total Costs/Savings
($000) ($000) ($000) ($000) ($000)
Costs
Oracle/PM Software 992 500 0 1492 0
(List Price)
60% Discount (595) (595)
Oracle Credits (397) 0 (397)
Net Cash for Software 0 500 500
Software Maintenance 0 90 250 340 250
Hardware & Maintenance 0 270 270 540 270
Consulting &Training 205 320 0 525 0
Tax & Acquisition 0 150 80 230 50
Total Purchased Costs 205 1330 600 2135 570
Information Services & 500 1850 1200 3550 0
Technology (IS&T)
Finance/Other Staff 200 990 580 1770
Total Costs 905 4170 2380 7455 570
Savings
Mainframe (101) (483) (584) (597)
Finance/Asset/PM (160) (1160) (1320) (2320)
IS&T Support/Data Entry (88) (384) (472) (800)
Interest 0 (25) (25) (103)
Total Savings (349) (2052) (2401) (3820)
Value (VAC)
Graph Target
Cost &
Schedule
Planned
Schedule
Value (PV) Variance
(Time)
Earned
Value (EV)
Earned Value Formulas
NAME FORMULA NOTES
Cost Variance (CV) EV-AC Negative = Over budget
Positive = Under budget
Schedule Variance EV-PV Negative = Behind Schedule
(SV) Positive = Ahead of Schedule
Cost Performance EV/AC How much are we getting for every
Index (CPI) dollar we spend?
Schedule Perform EV/PV Progress as % against plan
Index (SPI)
Estimate to EAC-AC How much more do we have to
Complete (ETC) spend?
Variance at BAC-EAC At the end of the day, how close will
Completion (VAC) we be to plan?
Estimate at See following slide
Completion (EAC)
Earned Value Formulas (Cont’d)
NAME FORMULA NOTES
Estimate at
Completion (EAC)
BAC/CPI Use if no variances from
BAC have occurred
Project Current
Start Status BAC
PV
EAC
AC ETC
Example: . Earned Value Calculations for
One Activity After First Week
Example: Earned Value Calculations for a
One-Year Project After Five Months
Example Figure:Earned Value
Chart for Project After Five Months