© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. 296S-HO1-1
296S/HO1/D.1/712/C.1
UCS2 Objective Statement
© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. 296S-HO1-2
UCS2 Deliverables
© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. 296S-HO1-3
Handout 2
296S/HO2/D.1/712/C.1
Hands-On Exercise 5.2: UCS2 Resource Optimization
D a y N u m b e r + T a sk A l l o c a t i o n
Resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Albert
Jean
Leslie
Marie
Paul
Contractor
© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. HO2-2
Hands-On Exercise 5.2: UCS2 Resource Optimization
D a y N u m b e r + T a sk A l l o c a t i o n
Resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Albert
Jean
Leslie
Marie
Paul
Contractor
© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. HO2-3
Handout 3
Suggested Solution to
Hands-On Exercise 5.2:
UCS2 Resource Optimization
296S/HO3/D.1/712/C.1
Suggested Solution to Hands-On Exercise 5.2
Replace Albert with Jean on task H; Albert not over-allocated
Replace Marie with Contractor on tasks D and G
Replace Marie with Leslie on tasks C and F; Marie not over-allocated
Replace Jean with Marie on task E; Jean not over-allocated
Move non-critical task I and dependent task K to start one day later using float
Replace Leslie with Contractor on tasks I and K; Leslie not over-allocated
Extend duration of task E from 3 to 6 days (assuming this task can be extended, and using float)
Keep Marie assignment to task E; remove Paul from task E
Replace Paul with Marie on task K; Paul no longer over-allocated
Replace Marie with Jean on task L
Note:
• Reduced task E float from 7 days to 4 days, reduced tasks I and K float to 1 day
• Keep all critical tasks assigned to permanent staff
• Contractor is working only on non-critical tasks, with permanent staff
• Marie is working on non-critical tasks only with a lot of float available
• Task E extended to 6 days with single resource (Marie) assigned
• Jean assigned to all critical tasks full time for duration of project schedule
© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. HO3-2
Suggested Solution to Hands-On Exercise 5.2
D a y N u m b e r + T a sk A l l o c a ti o n
Resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Albert A A A A B B B D D D D D D D G G G G J J J J J J J J L L
Jean A A A A C C C C C F F F F F F F F H H H H H H H H H H L L
Leslie C C C C C F F F F F F F F H H H H H H H H H H L L
Marie E E E E E E I I I K K K K K
Paul B B B F F F F F F F F J J J J J J J J L L
Contractor D D D D D D D G G G G I I I K K K K K
© Learning Tree International, Inc. All rights reserved. Not to be reproduced without prior written consent. HO3-3