ENVIRONMENTAL PROFILE For their development in France, the company LR SERVICES


constructed their seventh logistics platform at the Haut Villé
industrial park near Beauvais.
Implementation
This new distribution center, operational since the third quarter of
ECO-CONSTRUCTION 2005, is installed in a tri-temperature (dry, fresh and frozen)
1 Relation of building to its warehouse with a surface area of 9,648 m².
immediate environment LR SERVICES decided to adapt an
2 Integrated choice of ®
HQE approach to this operation
construction products, because of their corporate sense of
systems and procedures
environmental stewardship. This is a
3 Construction site has low voluntary commitment by LR SERVICES
environmental impact to environmental protection in the
ECO-MANAGEMENT broadest sense of the term.
4 Energy management
5 Water management
6 Waste management
7 Maintenance – sustainability
of environmental
performance
COMFORT
8 Hygrothermal comfort
9 Acoustic comfort
10 Visual comfort
11 Olfactory comfort  Delegated Site Manager:  Energy & Fluids Engineers:
Thébault Construction Apave
HEALTH
 Environmental assistant to Site  Environmental consultant:
12 Area health quality Ademe Picardie, Mr. Akli Assal
Manager:
13 Air health quality Cabinet Raoust
14 Water health quality  Architect:
Pascal Thébault
Average Good Very good

Occupancy:
45 operators (including 6
admin.)
Delivery:
October 2005
Parcel:
44,367 m²
Platform:
9,300 m² of floor space
LR Services
Logistics Platform

Technical Data Project management


C coefficient: Cref - 10.1% Estimated water consumption:
3
CO2 emission: 26.4kg/yr/m² 480m /yr  Everyone on site is made fully
Thermal coefficient: Ubat ref - 4.9% Construction site waste: 153.3 aware that the “low-impact
metric tons (74% recyclable) construction charter” is part of
the deal.
 Every new employee is given a
Economic data welcome booklet.
Cost of project: €11M (exclusive of
Energy Management
tax)  Numerous comparative studies
 Focus on cold production
carried out for strategic
“Environmental” part: 5% systems, which represent 75%
choices: analysis of possible
Subsidies: €142.5k (exclusive of tax) of the primary energy
locations, renewable energy
from Ademe Picardie and the Beauvais consumption at the platform.
feasibility studies, lighting
Area Community.
 Warehouse solutions studies, etc.
Estimated ROI: 3 to 4 years for cold
production. - Cold production via an NH3  Computerized document
ammonia compression system management system for
with CO2 distribution efficient traceability and sharing
Site Integration - Installation equipped to recover of documents
heat given off by condenser to
 Site chosen in consideration of  Establishment of higher budget
heat dry warehouse in order to
transport problems for inbound maintain a winter antifreeze than generally allocated to
and outbound goods. The level of +7°C conventional construction
project is situated at the projects, in order to provide for
- Installation controlled by a
barycenter of traffic. Centralized Technical system, important environmental issues
 Site chosen in consideration of providing thermal regulation, such as cold production.
the community’s town planning user comfort, and energy
savings.  Constitution of a project group
and sustainable development to regularly track progress.
policies.  Presence detection system in
areas with variable occupancy  Outcome has been very
positive. Actual results exceed
Interior environment (eg locker rooms, break areas)
objectives set at project launch.
so as to reduce time lights are
 Double-flow ventilation for on.
open-space offices
 Renewal of air in offices and
meeting room: 3 volumes/hour
with adjustable, sound-proofed
air blowers
 Access to daylight in office
space and all areas used by
occupants The benefits of HQE®
Water management ®
Because the HQE approach has
 Skydomes in dry area of
warehouse  Pollution basin and storm basin proven so successful at the
to minimize leak flow. Beauvais site, LR Services is
 High windows at shipping dock considering applying the meth-
level  Recovery of all rain water in a odology to other operations by
pollution basin that can be ®
creating standard HQE ware-
isolated in case of pollution. house specifications.
 Oil separator treatment of road ®
HQE contributes to:
runoff  limiting environmental and health
 Installation of water-saving impact
systems: infrared-controlled  traceability and sustainability of
single-unit faucets, toilets environmental protection
equipped with 3/6-liter double-  corporate citizenship image
flush mechanisms, faucets with  employee involvement in an
timed automatic shutoff in environmental approach linked
showers, spray aerators. with 14001 certification
 savings in operating energy costs.

For further information, contact :


Mr Luc SERVEAU, LR Services