Sie sind auf Seite 1von 15

Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

go thyssenkrupp
Cover Sheet TON 1931D001
Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
1
Rev. 03 I Page 1 of 15

TECHNICAL SPECIFICATION
Page Description Revision
1 Cover Sheet 03
2 Vessel Design Data Sheet 03
3 __ Nozzle Sheet 02
4 Sketch 03
5 Detail
6 Nozzle Length
7 Nozzle Load Table/Figures 01
8 General Requirements 03
9 - 10 Additional requirements 03
11 Inspection Data Sheet, Classification Group 4, Page 1 (IDS)
12 Inspection Data Sheet, Classification Group 4, Page 2 (IDS)
13 Applicable Codes & Standards 03
14 - 15 Summary of Documentation 03

i
.
03 1FP Alter techn. negotiation 25.09.2018 A.B oh. 25.09.2018 . Poth 25.09.2018 Wie w

, s
25.09.20181. aw 25.09.2018 1.3r17
. hichte
02 IFI Issue for Inquiry: 25.07.2018 F. Graw 25.07.2018 Dr. Richter 25.07.2018 Wieschnew
corrosion allowance and Ski

insulation thk. changed, 25.07.2018 A. Polosin 25.07.2018 J.-M. Poth


editorial changes
01 IFI Issue for Inquiry: Nozzle 29.05.2018 F. Graw 29.05.2018 Dr. Richter 29.05.2018 S. Boehm
Loads changed; Material +
Rev. Status Description Date Prepared Date Checked Date Approved AC

Category Code: 3

Customer Document ID:


40066
Shown an PID: 22501
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Vessel Design Data Sheet TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 2 of 15
1 Quantity Operat. / Stand-by 1 0 Nominal Volume m³ 5
2 Position (Horiz/Vertical) Vertical Shell Diameter, Outside mm
3 Process Fluid Thermalöl Shell Diameter, Inside mm 1600
4 Height (TL-TL) of Shell mm 3200
5 Physical Condition LG Width mm
6 Class of Hazard combustible 1 3) Max.Fill.Lev.In Oper.Cond. %/mm / 01
7 Density Solid/Bulk kg/m³ Material Process Side C.S.
8 Density Liquid kg/m³ 691 6) Surf.- Treatm./Coat. (Proc. Side) 02
9 Density Vapour/Gas kg/m³
10 pH-Value Insulation Type Heat insulation
11 H2-Partial Pressure In/Out bara Internals Dip pipes
12 Max Operating Temperature °C 160 300
13 Max Operating Pressure bara 4 8 Heating / Cooling Device
14 Operating Temperature °C 270 Filling Rate m³/h 10
15 Operating Pressure bara 4.5 Breathing Gas Rate In / Out m³/h
16 Allowable Pressure barg -1 10
17 Allowable Temperature °C -15 320
18
Abbreviations for Physical Condition: (S)olid, (L)iquid, (G)as, (V)apour, (IDX) Index for Remarks
20 Design Code 2014/68/EU Part Materials Remarks
21 EN 13445 Shell P265GH
22 Corros. Allow., for Calc mm 1 Heads P265GH DIN 28011 02
23 Joint Efficiency 0.85 Shell Flange 03
24 Seismic Loads DIN EN 1998-1 Zone 0 Supports P265GH / S235JR 03
25 Wind Loads DIN EN 1991-1-4 WZ 2 7) Clips P265GH / S235JR 03
26 Inspection by Client, TKIS,3rd Party Nozzle Pipes P265GH
© 2018

27 Test Pressure barg Acc. to Code Nozzle Flange P245GH EN 1092-1


28 Heat Treatment Acc. to Code Internals Welded P265GH / S235JR 02
29 Non-Destructive Test Acc. to Code Internals Removable P265GH / S235JR 02
30 Derusting C.S. SA 2.5 Bolts / Nuts Inside 25CrMo4 EN 1515-4 4) 01
31 Painting See ES-Y1 5) Bolts / Nuts Outside 25CrMo4 EN 1515-4 4) 02
32 Pickling and Passivation Gaskets Inside Graphite 2)
33 Insulation mm 200 8) Gaskets Outside Graphite 2) 03
34 Weight, Delivery kg 1) Gaskets Shell Flange
35 Weight, with Proc. Fluid kg 1) Davit S235JR DIN 28124-4
36 Weight, Water Filled kg 1) Footring 02
37 Lifting Lugs / Trunnions P265GH / S235JR
38 Anchor Bolts 5.6 01
39 Demister
40 Ladders/Platforms
41
42 Remarks :
43 1) to by specified by the Vendor
2) TRBS 2152-2 Chapter 2.4.3.2 needs to be applied: Permanently technical tight flange connections must be executed. Graphite gaskets
(Kempchen corrugated metallic gasket W1A 1.4571 / 2,9mm) can be used. The connection must be examined according to EN 1591-1 with
leakage class L0.01.
3) Fluidgroup
4) 3.1 certificate acc. EN 10204 required: Material acc. to EN 10269:1999.
5) System 3i (prime coat only).
6) 691 kg/m3 at 270°C, density up to approx. 854 kg/m3 at 20°C.
7) by tkIS.
8) TRAS 320.
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Nozzle Sheet TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. Page 3 of 15
Nozzle Designation DN PN Standard Flange Flange Pipe dimensions Remarks Rev.
Symbol mm EN Type Facing mm
I01 Temperatur 50 25 1092-1 11 B1 with Blind Flange 03
I02 Level - LS 80 25 1092-1 11 B1 with Blind Flange 03
I03 Level - LIC 150 25 1092-1 11 B1 with Blind Flange 03
I04 Level - LS 80 25 1092-1 11 B1 with Blind Flange 03
M01 Manhole 800 25 1092-1 11 B1 with Cover and Davit 03
N01 Thermalöl outlet 80 25 1092-1 11 B1 03
N02 Overflow 50 25 1092-1 11 B1 03
N03 Thermalöl filling 50 25 1092-1 11 B1 with dip pipe 03
N03A for nozzle N03 80 25 1092-1 11 B1 03
N04 Thermalöl Inlet 50 25 1092-1 11 B1 with dip pipe 03
N04A for nozzle N04 80 25 1092-1 11 B1 03
N05 Spare Nozzle 80 25 1092-1 11 B1 with Blind Flange 03
N06 Spare Nozzle 50 25 1092-1 11 B1 with Blind Flange 03
© 2018

Remark:
Design and Testing of Blind Flanges and Manholes acc. to EN 1591 (Leakage class L0,01).
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Sketch TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 4 of 15

200
© 2018
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Detail TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 5 of 15
© 2018
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Nozzle Length TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 6 of 15
© 2018
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Nozzle Load Table/Figures TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 7 of 15
© 2018
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

General Requirements TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 8 of 15
1 Info Description Rev.
2 General
3 Stress analysis shall be performed by the manufacturer in accordance with design specifications
4 Specified wall thicknesses are minimum values and shall be increased if required by stress calculation
5 Nozzle necks shall be least DN 50/ 2". They shall be reduced to the required nominal flange size if necessary.
6 Bolts, nuts and gaskets for joints with tapped holes have to be supplied by the vessel manufacturer.
7
8 Supplies Shall Include the following Items
9 Davits for manholes
10 Base ring template
11 Clips for ladders
12 Clips for platforms
13 Clips for davits
14 Clips for pipe supports
15 Supports for insulation
16 Supports for fireproofing insulation acc. to UN 2004 - 02
17 Additional gaskets for flanges with cover and blindflanges 3x
18 Additional bolts and nuts, as spare 10%
19 Lifting lugs for erection
20 Lifting trunnions and tailing lug for erection
21 2 separate earthing connections to be provided 180 degree apart resp. 1 per saddle, if not otherwise specified
22 All internals
23 Additional glasses and gaskets for water gauges
24 Demister
25 Platforms and ladders plus bolts and nuts, as spare
26 Spare parts for 2 years to be quoted separately
© 2018

27 Bolts, nuts and gaskets for connecting piping


28 Test flange
29 Lifting lugs on channels and bonnets
30 For applicable standards see page ' Index of Applicable Codes and Standards' 01
31 Bolts and nuts for connection to steelwork 03
32
33 Remarks :
34
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Additional requirements TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 9 of 15
1 Nozzles

Type, nominal diameter, pressure rating, sealing face and quantity of the nozzles are specified in the
DS.

Seamless pipes shall be used for carbon steel nozzles up to including DN 300 and for stainless steel
nozzles up to including DN 100. The inner edges of the nozzles shall be chamfered.

Drain nozzles shall be flush with the inside of the vessel wall.

Level-gauge nozzles installed underneath the vessel shall protrude 50 mm into the vessel as
measured from the inside thereof.

1.1 Minimum nozzle lengths


The minimum nozzle lengths are specified in the Nozzle Length Sketch.
1.2 Bolt holes
The bolt holes shall be arranged non-axially and symmetrically about the main flange axes. The main
flange axes shall be arranged coincidentally with, or parallel to, those of the vessel.
2 Inspection openings
If the lowest vessel manhole is more than 1200 mm above the lowermost vessel tangent line,
vertical ladder rungs and grab handles must be provided on the inside of the vessel.
3 Internals (if applicable)

3.1 Fixed internals


Fixed internals, such as supporting rings, grids, supports etc., must be attached to the
vessel/equipment shell or head by continuous welds on both sides.
© 2018

3.2 Removable internals


Removable internals must be designed to permit installation and removal via the manhole of the
vessel.
3.3 Components weighing > 25 kg
Vessels/equipment or removable vessel/equipment components weighing > 25 kg must be provided
with lugs which shall, with due consideration for the centre of gravity, be located so as to enable the
component to be lifted to the installation position.

4 External fasteners
The required bolt elongation, the tightening force and the instructions for tightening or loosening the
bolted joints shall be specified in the workshop drawing.
5 Vacuum stiffeners/rings 03
Vacuum stiffeners/rings are permissible if fully covered by insulation.
6 Preparation for packing 03

The vessels and process equipment shall be thoroughly cleaned and dried inside and outside.

All flange sealing faces and all machined surfaces must be provided with a suitable temporary
protective coating against corrosion (e.g. Tectyl) and protected by means of plastic caps.

The bolt threads shall be greased using grease containing molybdenum sulphide (e.g. Molykote).

All loose parts shall be suitably packed, if necessary, in crates or boxes, in order to protect them
against damage in transit.

Internals supplied together with the related equipment shall be provided with suitable temporary holder
to be marked and labelled “Remove after assembly of the equipment”.

Partly prefabricated vessels or process equipment that are supplied as detached parts shall be
appropriately supported to prevent deformation. Open ends shall be covered to prevent the ingress
of dirt and foreign matters.
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Additional requirements TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 10 of 15
6.1 Packing instructions 03
The packing instructions according to engineering specification ES 10 MS-ST-01 shall be met for
packing and shipment.
© 2018
Plant Client Code Doc ID Project No.
HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547
INSPECTION DATA SHEET (IDS) for Pressure Vessels and Heat Exchangers TON 1931D001
Classification Group No. 4 Item RXL-HE-03-BV0030
Thermaloelkreislauf 300°C - Vorlagebehaelter All Codes Rev. 03 Page 11 of 15
1 The tests indicated are minimum requirements. They have to be performed in addition to the tests specified in the codes and standards.
2 In case of discrepancies between the inspection data sheet (IDS) and the workshop documents approved by
3 ThyssenKrupp Industrial Solutions, the latter shall apply. The manufacturer shall be responsible that the required tests are performed
4 and that the inspector is invited in due time to witness the tests. The manufacturer shall try to perform as many individual tests as
5 possible on the same day, provided that the fabrication process permits such a procedure.
6 Inspection by
7 Manuf. TKIS
8 PRE INSPECTION MEETING (PIM) - only if requested by TKIS or Client
9 MATERIAL TEST AT SEMI FINISHED PRODUCTS
10 In accordance with design code ∆ ×
11
12
13
14 EXAMINATION OF WELD EDGES
15 In accordance with design code ∆ ×
16
17
18
19
20 WELDING
21 Welding and testing schedule on form UF V360-21 part 1 or approved schedule of manufacturer ×
22 Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) in acc. with to applicable design code ×
23
24
25 HEAT TREATMENT (if required)
26 Visual and dimensional check before PWHT
27 MP of temporary welds before PWHT
28 Heat treatment plan and record ×
29
30 NONDESTRUCTIVE TESTS prior to pressure test (after final heat treatment)
31 RT, UT, MT, PT in accordance with design code ∆ ×
32 PT: 100% weld ring gasket, first and top layer of fillet seam and closing seams ∆ ×
33 Visual and dimensional check before pressure test in case of no PWHT
34
35
36
37 NONDESTRUCTIVE TESTS after pressure test
38 only if specified in design code or other referenced standards / specifications
39
40
41 FINAL INSPECTION
42 Visual check, inside and outside
43 Dimensional check; report and / or "as built" drawing with required and actual main dimensions ∆
44 Completeness check
45 Record of production test plates ∆ ×
46 Leakage test nozzle reinforcements / lining ∆
47 Pressure test ( for pressure test on shell sides of heat exchangers, otherwise ) ∆ /
48 Material certificate compare with marking / picture of marking ∆
49 Pickling, passivation, blasting- if required, check of performance
50 Drying, cleanliness, inside and outside
51 Painting / corrosion protection, if required
52 Data of nameplate correspondence with drawing
53 Documentation, submit at final inspection
54
55 SYMBOL EXPLANATION
56 Holding Point, Fabrication stop until inspection has been performed or written release note is given
57 Advise of inspection, Fabrication may be continued if inspector is not present after invitation issued in due time
58 ∆ Examination with test report
59 × Review of test report
60 Spot Check
61
62 LS = Longitudinal seam MT = Magnetic particle examination DDS = Design Data Sheet
63 CS = Circumferential seam PT = Liquid penetrant examination t = Wall thickness
64 NCS = Shell-nozzle seam UT = Ultrasonic examination DN = Nominal pipe size (NPS)
65 AS = Attachment seam RT = Radiographic examination HAZ = Heat affected zone
66 TS = T-Joints DK = Leakage class acc. to UN V416-02 part 1
67 continued on sheet E_IDS42 line 68
© 2018 E_IDS41
Plant Client Code Doc ID Project No.
HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547
INSPECTION DATA SHEET (IDS) for Pressure Vessels and Heat Exchangers TON 1931D001
Classification Group No. 4 Item RXL-HE-03-BV0030
Thermaloelkreislauf 300°C - Vorlagebehaelter
All Codes Rev. 03 Page 12 of 15
68 Continued from sheet E_IDS41, line 67
69
70
71
72 SPECIAL REQUIREMENTS FOR HEAT EXCHANGERS and SPECIAL TESTS
73 Inspection by
74 Manuf. TKIS
75 HEAT EXCHANGER TUBES FOR HEAT EXCHANGERS AND COILS
76 Tests of tubes according to ES-AD6 para. 10 ∆
77 Depending on DK and material Eddy Current -, UT- and Pressure Test may be required
78 TUBE-TO-TUBESHEET JOINTS test acc. to UN V416-02 part 1 (DK class acc. to DDS)
2)
79 Tube-to-tubesheet test specimen, if required acc. to UN V416-02 part 1 /
2)
80 Start of tube to tubesheet welding /
2)
81 Leak test with air / bubble formation agent 1st pass 1) ∆ /
2)
82 PT 1st pass 100% 1) ∆ /
2)
83 Leak test top pass (prior to tube expansion and PT) ∆ /
2)
84 PT top pass (prior to expansion and prior to heat treatment), 100% ∆ /
2)
85 PT top pass (after expansion and after heat treatment), 100% ∆ /
86 1) Leak and PT test after 1st pass may be skipped based on agreement with TKIS in case of welding both passes in one run.
87 2) for DK 1 and DK 2, for DK 3
88 OTHER TESTS FOR HEAT EXCHANGERS
89 Visual examination of shell inside (before bundle insertion) ∆
90 Check of tolerance for drillholes in tubesheets and baffle plates ∆
2)
91 Inspection of tube bundle /
2)
92 Insertion of tube bundle /
2)
93 Measuring of tube expansion on 5%, min. on 10 tubes per tubesheet, (if expansion is specified) ∆ /
94 Hydrostatic test, tube side ∆
95 Hydrostatic test, shell side ∆
96 Assembly check of stacked heat exchangers
97 PT: Transition radius channel to tubesheet after pressure test ∆
98 PT or MT: cold bent tubes after annealing ∆ ×
99 RT: 2% of tube to tubesheet welds but not less than 5 welds on each tubesheet ∆
100 for cooling water and / or corrosive acids on shell- and / or tubeside.
101 In case that any inadmissible defect is found by this RT inspection the scope of testing shall be increased to 25 %.
102 If within this increased scope any further inadmissible defect is found then the testing scope shall finally be 100%
103 BFU type heat exchangers: Check of longitudinal gasket assembly
104
105 SPECIAL TESTS
106 UT: Weld overlays and clad material ∆
107 Copper sulphate test or equivalent test: weld overlay and welds on clad material ∆
108 PT: Weld overlay and welds on clad material ∆
109 UT: Clad plates after forming ∆ ×
110 Examination of surface preparation prior to lining or coating (rubber lining, synthetic resin, coating) acc.to applicable standards
111 Examination of lined or coated surfaces (rubber lining, synthetic resin, coating) according to applicable standards ∆
112 Hardness test when using metal gasket: flange face and gasket ∆
113
114 SPECIAL TESTS (if specified in DDS and / or engineering spec.)
115 Positive Material Identification (PMI) ∆
116 Leakage test with helium / NH3 (vacuum test) ∆
117
118 SYMBOL EXPLANATION
119 Holding Point, Fabrication stop until inspection has been performed or written release note is given
120 Advise of inspection, Fabrication may be continued if inspector is not present after invitation issued in due time
121 ∆ Examination with test report
122 × Review of test report
123 Test respectively execution
124
125
126 LS = Longitudinal seam MT = Magnetic particle examination DDS = Design Data Sheet
127 CS = Circumferential seam PT = Liquid penetrant examination t = Wall thickness
128 NCS = Shell-nozzle seam UT = Ultrasonic examination DN = Nominal pipe size (NPS)
129 AS = Attachment seam RT = Radiographic examination HAZ = Heat affected zone
26.09.2018 09:40

130 TS = T-Joints DK = Leakage class acc. to UN V416-02 part 1


131
132
133
134
© 2018 E_IDS42
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Applicable Codes & Standards TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 13 of 15
1 Info Type Description Issue Date Rev.
2 Global Codes & Standards
3 2014/68/EU Pressure Equipment Directive
4 2006/42/EC Maschinery Directive
5 EN 13445 Unfired pressure vessels
6 WHG Wasserhaushaltsgesetz
7 VAwS Verordnung über Anlagen zum Umgang mit wassergefährdenden Stoffen
8 TA Luft Technische Anleitung zur Reinhaltung der Luft
9 TRBS 2152-2 Vermeidung oder Einschränkung gefährlicher explosionsfähiger Atmosphäre 2012-03 03
10 TRAS 320 Technische Regel fuer Anlagensicherheit 320 03
11 TEMA Standards Class R (for the severe requirements of petroleum processing) 9th
12 TEMA Standards Class C (for general commercial application) 9th
13 TEMA Standards Class B (for chemical process service) 9th
14 Manufacturer Standard
15
16 Company Standards: tkIS Project Engineering Specifications
17 PES-PU-E Electrical Equipment and Functions in Package Units (ELT-G000-EC-00003)
18 PES-Y1 Painting (CMG-G000-EC-00001)
19 PES-Y2 Insulation (CMG-G000-EC-00002)
20 DES-CP-EQS-01 STANDARD SPECIFICATION 01 - Welding of chrome-nickel steels and nickel alloys
21 DES-CP-EQS-03 STANDARD SPECIFICATION 03 - Welding of pressure vessel steel
22 1) DES-CP-EQS-05 STANDARD SPECIFICATION 05 - Requirements regarding the minimum scope of the equipment manufacturer's docume
23
24 Company Standards: UN
25 UN 2003-01 tkIS Standard Earthing connections for vessels and equipment 2015-08
26 UN 2004-06 Insulation clips for vertical steel vessels 2016-03
© 2018

27 UN V 416-02 Vessels and Equipment, Tube-to-tubesheet joints 2016-05


28 UF V351-6 2 year spare parts
29
30 General
31 Requirements for Vendor Documents PMG-G000-BD-00013 00 02
32 NozzleSpecApp Consideration of Nozzle Loads on Vessels 01
33
34 Classification Group and Leakage Class
35 Vessel Group 4
36 Heat Exchanger Shell Side Group Tube Side Group Leakage Class
37
38 Fatigue Loading
39 Fatigue Loading Design No. of Loading Cycles From barg To barg
40
41 Remarks :
42 1) Version C
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Summary of Documentation TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 14 of 15

Document For Information For Review For Approval For Erection Doc. For Final Doc.

Dispatch of No. of Dispatch of No. of Dispatch of No. of Dispatch of No. of Dispatch of No. of
Documents copies Documents copies Documents copies Documents copies Documents copies

12 weeks 4 weeks
Priced spare part PDF+
after after PDF
list XLS
P.O. delivery

4 weeks
Fabrication
after P.O. PDF
schedule
each month

4 weeks
Material status
after P.O. PDF
report
each month

8 weeks 4 weeks
Stress calculation after PDF after PDF
P.O. delivery

Foundation loads 8 weeks 4 weeks


Foundation drawing after PDF after PDF
1) P.O. delivery

Arrangement
8 weeks 4 weeks
© 2018

drawing
after PDF after PDF
(for 1st checking)
P.O. delivery
1)

Arrangement 1 weeks
drawing after reciept PDF
(revised issue) of comments

12 weeks 4 weeks
Detail drawing
after PDF after PDF
(for 1st checking)
P.O. delivery

1 weeks
Detail drawing
after reciept PDF
(revised issue)
of comments

Welding procedure 12 weeks 1 months 4 weeks


and testing after PDF before PDF after PDF
schedule P.O. delivery 2) delivery

8 weeks 1 months 4 weeks


Transportation
after PDF before PDF after PDF
sketch
P.O. delivery delivery

Remarks
1) penalized
2) If necessary

Final Documentation in correspondance with "Requirements for Vendor Documents" and DES-CP-EQS-05.
Plant Client Code Doc ID Code Project No.

HHCR RÜTGERS RÜTGERS EQS-1931-EC-00001 KXEO-00547

Summary of Documentation TON 1931D001


Thermaloelkreislauf 300°C - Vorlagebehaelter Item RXL-HE-03-BV0030
Rev. 03 Page 15 of 15

Document For Information For Review For Approval For Erection Doc. For Final Doc.

Dispatch of No. of Dispatch of No. of Dispatch of No. of Dispatch of No. of Dispatch of No. of
Documents copies Documents copies Documents copies Documents copies Documents copies

1 months 4 weeks
Operation/main
before PDF after PDF
-tenance instruction
delivery delivery

4 weeks
Material test
after PDF
certificates
delivery

4 weeks
Test/inspection
after PDF
certificates
delivery

1 months 4 weeks
Storage instructions
before PDF after PDF
2)
delivery delivery
© 2018

Remarks
1) penalized
2) If necessary

Final Documentation in correspondance with "Requirements for Vendor Documents" and DES-CP-EQS-05.

Das könnte Ihnen auch gefallen