Beruflich Dokumente
Kultur Dokumente
METHOD STATEMENT
TABLE OF CONTENTS
1 GENERAL INFORMATION AND SCOPE ....................................................................... 3
1.3 TIMELINE
The overall completion period is eight (8) months which includes mobilization period. The Period of
Commencement from the Engineer’s order to commence is thirty (30) days. The Period of Mainte-
nance is three hundred and sixty-five (365) days, or one (1) year.
The project involves construction of two (2) roundabouts, each at start and end of project, one (1)
Floodway at station 3+700, drainage ditch, embankment protection along right side of the embank-
ment, and other protection works
One important aim of sequencing is to provide as early as possible a parallel working space for po-
tential works.
Works will be organized as such that major activities are started immediately with the award of
contract.
2.2.2 EARTHWORKS
The key staff and equipment dedicated for proceeding these works will be as follows:
■ Site personnel
▪ Site supervisor-Responsible for this activity
▪ Earthwork foreman-Responsible for this activity
▪ Land surveyors-Responsible for boundary limits, level of excavation, thickness of layers of
subgrade, subbase etc.
▪ Chainman- Assist the surveyors
▪ Lab technician
▪ Laboratory assistant
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator
■ Survey instruments
▪ Total station
▪ GPS
▪ Auto level
There are private wells in the vicinity of the project site from where water for construction can be
obtained.
The working drawings for excavation will be submitted for approval for individual sites or each loca-
tion prior to start of the excavation. Referring to the approved construction drawings, the excava-
tion layout will be marked w.r.t. the grids and axis lines as the case may be as per the site condition.
■ All material transported to site will undergo a quality control verification process;
■ All materials transported away from the site will be accounted for with tally sheets;
■ If a material needs to be stockpiled it will be in the area where required and if not required it
will be moved offsite.
■ Wheel loaders and excavators will be used for excavation and graders prepare the embank-
ment layers and sub-grade.
■ If top soil exists this will be cleaned and material will be scrapped away.
■ Prior to excavation adjacent to existing underground services, as built drawings will be made
in order to determine the exact location and for record of existing utilities.
■ Site testing of compaction will be to be carried as mentioned in the specifications.
■ Construction of the next course will only commence after the previous course has been ap-
proved by the Engineer.
■ Finisher
■ Steel drum roller
■ Grader or Paver
We plan to deploy One (1) crew each having the productivity of 800-900 m3 per day
■ The layer will be compacted using 10-15 ton vibrating rollers.
■ Our standard work method for these works is to place the first layer using graders and placing
of second layer with a finisher. This method is adjusted to suit local conditions.
■ The site supervisor will be responsible for applying the required number of passes by equip-
ment for the compaction.
■ Materials is available from the proposed borrow pit locations.
We plan to deploy one (1) crew for asphalt each having the productivity of 350 m3 per day. We
have foreseen for setup our own asphalt plant on site.
The key staff and equipment dedicated for proceeding these works will be as follows:
■ Site personnel
▪ Site engineer-Responsible for these works
▪ Lab technician-Responsible for testing of asphalt
▪ Site supervisor
▪ Asphalt foreman
▪ Asphalt workers
▪ Helpers
▪ Land surveyors-Responsible for layout and thickness of pavement layers
▪ Chainman- Assist the surveyors
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator
▪ Asphalt plant operator
▪ Helpers asphalt plant
■ Survey instruments
▪ GPS
▪ Total station
▪ Auto level
■ Before laying of each course a notice will be given to the Engineer to inform about the coming
works.
■ Each Civil Engineer will be responsible for construction of the bituminous base course in-
cluded in his Section under supervision of the Project Manager.
■ The bituminous Base Course will be laid through the paver.
■ The paving width will be determined depending on the total width of the road.
■ Asphalt base course will be transported to site by trucks.
■ The mix will be delivered to the site at temperature between 140 to 170 Celsius.
■ The trucks will be covered with tarpaulin to retain the temperature and prevent oxidation.
■ The compaction first pass by tandem roller without vibration and PTR will compact the mix
close to the paver.
■ During laying levels are checked to control the screed and if required, to adjust it.
■ During and after final rolling, the evenness, levels and thickness will be checked.
■ In case of longitudinal joints, old asphalt will be cut with a cutting wheel or a disk cutter.
Transverse joints are carried out by cutting with a jackhammer to achieve good bonding with
the existing pavement.
■ Materials and work testing will be performed by the Lab technician in accordance with the
Standard Specifications for Road & Bridge Construction, June 2010 and the Special Specifica-
tion in the Site’s Laboratory.
After the foundation prepared, aggregate bedding material shall be laid to receive the pipe culvert.
Bedding thickness of no less than the specification. The width of the bedding material should equal
the width of the pipe (span plus twice the wall thickness) and the length of the bedding material
should equal the length of the pipe.
Transport of the material will be made by tipper trucks and placing by excavators, small sized wheel
loaders or by hand depending on the depth, location and quantity of fill to be placed.
Structure will not be subject to the pressure of backfilling until the strength of the concrete has
been achieved.
At pipe culverts and storm sewers the backfill will be completed around the culvert as specified
level of the original ground line.
Street lighting involves the installation of lighting poles, lighting fixtures, relative cabling and the
earth bonding of the poles.
A technical report accompanied by drawing will recognize findings and difficulties encountered on
site. Photographs illustrating the progress and any problems encountered will be included in the
monthly report for the Employee’s reference and comments.
The major activities to be adopted for these utilities works are following:
■ Pipe laying
■ Duct laying
■ cable laying
The pipe laying works, which we consider can be started even before subgrade construction
because in general the excavation depths for these pipe laying are below existing ground.
2.6 SIDEWALKS
The works for sidewalk interlocks and curb stones will be executed as per the approved drawings.
The key staff and equipment dedicated for proceeding these works will be as follows:
■ Site personnel
▪ Site supervisor-Responsible for these works
▪ Foremen
▪ Helpers
■ Survey instruments
▪ GPS
▪ Total station
▪ Auto level
▪ Measuring tape
▪ Straight edge
■ Before execution of the work, testing for the quality and the size of material will be done.
■ All tests and results will be submitted to the Engineer for approval.
■ The material and the size of the interlock tiles and the curb stones will be as per the drawings
and standard specifications.
■ Execution will be done under the supervision of the responsible site engineer.
■ Proper compaction and preparation of the subgrade beneath the sidewalk is essential.
■ Site personnel
▪ Site engineer-Responsible for these works
▪ Road marking foremen
▪ Helpers
▪ Land surveyors-Responsible for setting out
▪ Chainman- Assist the surveyors
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator
■ Survey Instruments
▪ GPS
▪ Total station
We foresee to use our existing camp at SIDRA Quarry approx. 50 km form the project location.
Other construction materials, as far available on the local market, will be procured locally; other-
wise they will be imported.
2.9 SUBCONTRACTORS
Major subcontractors will be required for the following works: