Sie sind auf Seite 1von 23

Construction of Service Road (Extension)

at Showroom Zone in Duqm

CONSTRUCTION OF SERVICE ROAD (EXTENSION) AT


SHOWROOM ZONE IN DUQM

METHOD STATEMENT

SUBMISSION DATE: Tuesday, 23-07-2019

METHOD STATEMENT PAGE 1 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

TABLE OF CONTENTS
1 GENERAL INFORMATION AND SCOPE ....................................................................... 3

1.1 PROJECT LOCATION ............................................................................................................. 3


1.2 PROJECT DESCRIPTION ....................................................................................................... 4
1.3 TIMELINE .............................................................................................................................. 4
1.4 SCOPE OF W ORKS .............................................................................................................. 4
1.5 TYPICAL DRAWINGS ............................................................................................................. 5
1.5.1 Site plan .......................................................................................................................... 5
1.5.2 Roads Cross Section .................................................................................................... 5
1.5.3 Roundabout Cross Section .......................................................................................... 6
1.6 MAIN QUANTITIES................................................................................................................. 7
2 CONSTRUCTION STRATEGY AND METHODOLOGY ................................................. 8

2.1 SEQUENCING AND PLANNING, MATERIALS AND WORK FRONTS ........................................ 8


2.2 ROADWORKS METHODOLOGY ............................................................................................. 9
2.2.1 The Workfronts and Assumed Productivities ............................................................ 9
2.2.2 Earthworks...................................................................................................................... 9
2.2.3 Subgrade Construction ............................................................................................... 11
2.2.4 Aggregate Base Course ............................................................................................. 12
2.2.5 Bituminous Pavement ................................................................................................. 13
2.3 PIPE CULVERT ................................................................................................................... 16
2.3.1 Foundation Prepration and Bedding ........................................................................ 16
2.3.2 Pipe Laying................................................................................................................... 16
2.3.3 Backfilling for Structures ............................................................................................ 16
2.4 ROAD LIGHTING AND ELECTRICAL INSTALLATION .............................................................. 17
2.4.1 Installation of Lighting Poles and Earthing .............................................................. 17
2.5 UTILITY WORK .................................................................................................................... 18
2.5.1 Sequence of Work Zones .......................................................................................... 18
2.6 SIDEWALKS ........................................................................................................................ 19
2.7 ROAD FURNITURE .............................................................................................................. 21
2.7.1 Road Marking............................................................................................................... 21
2.7.2 Road Signs ................................................................................................................... 22
2.8 SITE INSTALLATION AREA (OFFICE, STORAGE) .................................................................. 23
2.8.1 Labour Resources ....................................................................................................... 23
2.8.2 Equipment Resources ................................................................................................ 23
2.8.3 Material Procurement and Logistics ......................................................................... 23
2.9 SUBCONTRACTORS ........................................................................................................... 23

METHOD STATEMENT PAGE 2 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

1 GENERAL INFORMATION AND SCOPE


1.1 PROJECT LOCATION

METHOD STATEMENT PAGE 3 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

1.2 PROJECT DESCRIPTION


The project is in Governorate of Duqm of Al-Wusta Region. SEZAD has recently completed construc-
tion of a part of internal roads network at Airport Showroom Zone in Duqm. It is now intention of
the Client to extend the aforementioned road near SEZAD Headquarter in both directions

1.3 TIMELINE
The overall completion period is eight (8) months which includes mobilization period. The Period of
Commencement from the Engineer’s order to commence is thirty (30) days. The Period of Mainte-
nance is three hundred and sixty-five (365) days, or one (1) year.

1.4 SCOPE OF WORKS


The project consists of extension of newly constructed road R4A-1. The length of service road ex-
tension is 1.09 km on southern end and 1.77 km on northern end. The overall extended length of
the service road will be approx. 2.86 Km.

The project involves construction of two (2) roundabouts, each at start and end of project, one (1)
Floodway at station 3+700, drainage ditch, embankment protection along right side of the embank-
ment, and other protection works

■ Site clearance, including removal of existing structure wherever required


■ Removal of existing pavement wherever required
■ Earthwork (excavation and embankment)
■ Concrete construction for pipe culverts
■ Sub-grade preparation
■ Aggregate base course construction
■ Bituminous base course
■ Loose riprap works
■ Reinforced concrete slope protection
■ Sidewalk (precast curb and tile works)
■ Road Signs and Pavement Markings and Road studs
■ Road lighting works

METHOD STATEMENT PAGE 4 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

1.5 TYPICAL DRAWINGS


1.5.1 Site plan

1.5.2 ROADS CROSS SECTION

METHOD STATEMENT PAGE 5 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

1.5.3 ROUNDABOUT CROSS SECTION

METHOD STATEMENT PAGE 6 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

1.6 MAIN QUANTITIES


Activity Quantity UoM Remarks
Clearing and Grubbing 49,500 m2
Unclassified Excavation 15,000 m3
Borrow Excavation 73,500 m3
Subgrade Preparation in cut 10,000 m2
Aggregate Base Course 8,395 m3
Bituminous Base Course 2,516 m3
Pipe Culvert 100 Lin.m
Loose Riprap 2,700 m3
Precast Curb 15,900 Lin.m
Precast Concrete Block 11,652 m2
Reinforced Concrete Slope Protection 1,100 m3
Electrical Cables for Road Lighting 12,000 Lin.m
Road Lighting Luminaries & Columns 115 No.

METHOD STATEMENT PAGE 7 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2 CONSTRUCTION STRATEGY AND METHODOLOGY


Construction will be managed by STRABAG and sub-contractors under STRABAG’s supervision.

2.1 SEQUENCING AND PLANNING, MATERIALS AND WORK


FRONTS

One important aim of sequencing is to provide as early as possible a parallel working space for po-
tential works.

Works will be organized as such that major activities are started immediately with the award of
contract.

The site activities sequence shown as:

METHOD STATEMENT PAGE 8 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.2 ROADWORKS METHODOLOGY


2.2.1 THE WORKFRONTS AND ASSUMED PRODUCTIVITIES
Description of Work Quantities Unit Teams/ Production/ Production/day
day Team
Clearing and Grubbing 49,500 m2 1 7,000 7,000
Unclassified Excavation 15,000 m3 1 1,000 1,000
Borrow Excavation 73,500 m3 1 1000 1000
Aggregate Base Course 8,385 m3 1 800 800
Bituminous Base Course 2,516 m3 1 350 350

2.2.2 EARTHWORKS
The key staff and equipment dedicated for proceeding these works will be as follows:

■ Site personnel
▪ Site supervisor-Responsible for this activity
▪ Earthwork foreman-Responsible for this activity
▪ Land surveyors-Responsible for boundary limits, level of excavation, thickness of layers of
subgrade, subbase etc.
▪ Chainman- Assist the surveyors
▪ Lab technician
▪ Laboratory assistant
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator

■ Survey instruments
▪ Total station
▪ GPS
▪ Auto level

■ Plant, Machinery and Vehicles


▪ Grader
▪ Wheel loader
▪ Excavators
▪ Tipper Trucks 10m³
▪ Tipper Trucks 18m³
▪ Compactors
▪ Vibratory Rollers 24 Tons
▪ Mobile crusher plant
▪ Water tankers
METHOD STATEMENT PAGE 9 of 23
Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.2.2.1 SITE CLEARANCE


Before excavation, we will clear all work areas of rubbish, vegetation and unsuitable materials.
When clearing, the sequence of operations depends on the type of trees, the terrain, and planned
construction. After establishing the boundaries of the clearing, select spoil areas for disposal of all
cleared material based on the shortest haul, a downgrade slope, effective camouflage, and general
accessibility. Start clearing at the disposal area and move in each direction away from it. These ma-
terials will be loaded onto trucks by wheeled loaders and disposed at a location approved by the
Engineer.

2.2.2.2 EXCAVATION AND FILL


Excavation will be carried out by teams of wheel loader and excavators. The size of equipment will
be chosen by the Contractor to suit the ambient conditions.

2.2.2.2.1 Sources of Materials for embankment fill


STRABAG owns a quarry in Duqm which is located about 50 km from beginning of project.

There are private wells in the vicinity of the project site from where water for construction can be
obtained.

The working drawings for excavation will be submitted for approval for individual sites or each loca-
tion prior to start of the excavation. Referring to the approved construction drawings, the excava-
tion layout will be marked w.r.t. the grids and axis lines as the case may be as per the site condition.

■ All material transported to site will undergo a quality control verification process;
■ All materials transported away from the site will be accounted for with tally sheets;
■ If a material needs to be stockpiled it will be in the area where required and if not required it
will be moved offsite.

METHOD STATEMENT PAGE 10 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.2.2.3 DISPOSAL OF UNSUITABLE/SURPLUS MATERIAL


The Contractor will dispose unsuitable material to areas out of right of way on both sides of the
alignment, the possible disposal area is about 20 km away from the project .

2.2.3 SUBGRADE CONSTRUCTION


As per the QA/QC report of our laboratory, existing material after crushing and screening can be
used for the preparation of subgrade as it is suitable. It will be then watered to achieve the opti-
mum moisture content and compacted by using smooth vibrating rollers.

■ Wheel loaders and excavators will be used for excavation and graders prepare the embank-
ment layers and sub-grade.

METHOD STATEMENT PAGE 11 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

■ If top soil exists this will be cleaned and material will be scrapped away.
■ Prior to excavation adjacent to existing underground services, as built drawings will be made
in order to determine the exact location and for record of existing utilities.
■ Site testing of compaction will be to be carried as mentioned in the specifications.
■ Construction of the next course will only commence after the previous course has been ap-
proved by the Engineer.

2.2.4 AGGREGATE BASE COURSE


Equipment dedicated for proceeding these works will be as follows:

■ Finisher
■ Steel drum roller
■ Grader or Paver
We plan to deploy One (1) crew each having the productivity of 800-900 m3 per day
■ The layer will be compacted using 10-15 ton vibrating rollers.
■ Our standard work method for these works is to place the first layer using graders and placing
of second layer with a finisher. This method is adjusted to suit local conditions.
■ The site supervisor will be responsible for applying the required number of passes by equip-
ment for the compaction.
■ Materials is available from the proposed borrow pit locations.

METHOD STATEMENT PAGE 12 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.2.5 BITUMINOUS PAVEMENT


We will prepare asphalt mix designs before beginning the work. A copy of calibration certificates for
the batching plant, laboratory equipment and material test result will be provided.

We plan to deploy one (1) crew for asphalt each having the productivity of 350 m3 per day. We
have foreseen for setup our own asphalt plant on site.

The key staff and equipment dedicated for proceeding these works will be as follows:

■ Site personnel
▪ Site engineer-Responsible for these works
▪ Lab technician-Responsible for testing of asphalt
▪ Site supervisor
▪ Asphalt foreman
▪ Asphalt workers
▪ Helpers
▪ Land surveyors-Responsible for layout and thickness of pavement layers
▪ Chainman- Assist the surveyors
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator
▪ Asphalt plant operator
▪ Helpers asphalt plant

■ Survey instruments
▪ GPS
▪ Total station
▪ Auto level

■ Plant, Machinery and Vehicles


▪ Asphalt finisher
▪ Bitumen sprayer capacity 5000 liters or 8000 litres
▪ Trucks

METHOD STATEMENT PAGE 13 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

▪ Tandem Rollers e.g BW 161 AD, BW 174 AD4


▪ Pneumatic tyre rollers 218 Tons
▪ Asphalt plant
▪ Core cutters

■ Before laying of each course a notice will be given to the Engineer to inform about the coming
works.

2.2.5.1 BITUMINOUS PRIME COAT


After preparing the surface, the prime coat will be applied through bitumen distributors.

2.2.5.2 BITUMINOUS BASE COURSE


We plan to deploy one (1) crew for asphalt paving. Each paving crew will be assigned for asphalt
paving to achieve 400m3 per crew on average.

■ Each Civil Engineer will be responsible for construction of the bituminous base course in-
cluded in his Section under supervision of the Project Manager.
■ The bituminous Base Course will be laid through the paver.
■ The paving width will be determined depending on the total width of the road.
■ Asphalt base course will be transported to site by trucks.
■ The mix will be delivered to the site at temperature between 140 to 170 Celsius.
■ The trucks will be covered with tarpaulin to retain the temperature and prevent oxidation.
■ The compaction first pass by tandem roller without vibration and PTR will compact the mix
close to the paver.
■ During laying levels are checked to control the screed and if required, to adjust it.
■ During and after final rolling, the evenness, levels and thickness will be checked.
■ In case of longitudinal joints, old asphalt will be cut with a cutting wheel or a disk cutter.
Transverse joints are carried out by cutting with a jackhammer to achieve good bonding with
the existing pavement.

METHOD STATEMENT PAGE 14 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

■ Materials and work testing will be performed by the Lab technician in accordance with the
Standard Specifications for Road & Bridge Construction, June 2010 and the Special Specifica-
tion in the Site’s Laboratory.

METHOD STATEMENT PAGE 15 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.3 PIPE CULVERT


2.3.1 FOUNDATION PREPRATION AND BEDDING
Foundation will be most likely involved with excavation; the most important excavation limitations
are trench width and depth. As excavation progresses, trench grades should be continuously
checked against the elevations established in culvert profile.

After the foundation prepared, aggregate bedding material shall be laid to receive the pipe culvert.
Bedding thickness of no less than the specification. The width of the bedding material should equal
the width of the pipe (span plus twice the wall thickness) and the length of the bedding material
should equal the length of the pipe.

2.3.2 PIPE LAYING


Placement of pipe culvert should start at the outlet end of the line of pipe sections. The bell end
should point upstream and the spigot or tongue should point downstream. Unless otherwise ap-
proved by the engineer, loads from construction equipment transferred to a pipe section before,
during, or after fill placement, either directly or through the fill, should not be greater than the
loads assumed in the design.

2.3.3 BACKFILLING FOR STRUCTURES


Only selected granular material that will produce a stable, dense, backfill will be used for structure.

Transport of the material will be made by tipper trucks and placing by excavators, small sized wheel
loaders or by hand depending on the depth, location and quantity of fill to be placed.

Structure will not be subject to the pressure of backfilling until the strength of the concrete has
been achieved.

At pipe culverts and storm sewers the backfill will be completed around the culvert as specified
level of the original ground line.

METHOD STATEMENT PAGE 16 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.4 ROAD LIGHTING AND ELECTRICAL INSTALLATION

Street lighting involves the installation of lighting poles, lighting fixtures, relative cabling and the
earth bonding of the poles.

■ The street lighting works will be performed in conjunction with sub-contractors.


■ Material will be approved prior to ordering.
■ Street lighting poles will be as approved.
■ The height of the street lighting poles will be as per drawings.
■ The axis of each lighting pole will be located by co-ordinates.

2.4.1 INSTALLATION OF LIGHTING POLES AND EARTHING


■ The lighting poles will be installed by crane, including brackets, cut-outs, luminaire, flexible
cable and termination.

METHOD STATEMENT PAGE 17 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.5 UTILITY WORK


The work of this project features substantial amount of utility installations mentioned below.

■ Specialized works will be performed by qualified sub-contractors.

2.5.1 SEQUENCE OF WORK ZONES


The utility works will start first where no roadwork is foreseen and as soon as the material (pipes,
cable, ducts) has been approved and procured.

A technical report accompanied by drawing will recognize findings and difficulties encountered on
site. Photographs illustrating the progress and any problems encountered will be included in the
monthly report for the Employee’s reference and comments.

METHOD STATEMENT PAGE 18 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

The major activities to be adopted for these utilities works are following:

■ Pipe laying
■ Duct laying
■ cable laying
The pipe laying works, which we consider can be started even before subgrade construction
because in general the excavation depths for these pipe laying are below existing ground.

2.6 SIDEWALKS
The works for sidewalk interlocks and curb stones will be executed as per the approved drawings.

The key staff and equipment dedicated for proceeding these works will be as follows:

■ Site personnel
▪ Site supervisor-Responsible for these works
▪ Foremen
▪ Helpers

METHOD STATEMENT PAGE 19 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

▪ Land surveyors-Responsible for layout and levels


▪ Chainman- Assist the surveyors
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator

■ Survey instruments
▪ GPS
▪ Total station
▪ Auto level
▪ Measuring tape
▪ Straight edge

■ Plant, Machinery and Vehicles


▪ Mobile cranes 30 Tons
▪ Water tankers
▪ Trucks 25.5 Hp
▪ Plate compactors 70 kg
▪ Small wheel loader

■ Before execution of the work, testing for the quality and the size of material will be done.
■ All tests and results will be submitted to the Engineer for approval.
■ The material and the size of the interlock tiles and the curb stones will be as per the drawings
and standard specifications.
■ Execution will be done under the supervision of the responsible site engineer.
■ Proper compaction and preparation of the subgrade beneath the sidewalk is essential.

METHOD STATEMENT PAGE 20 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.7 ROAD FURNITURE


The key staff and equipment dedicated for proceeding these works will be as follows:

■ Site personnel
▪ Site engineer-Responsible for these works
▪ Road marking foremen
▪ Helpers
▪ Land surveyors-Responsible for setting out
▪ Chainman- Assist the surveyors
▪ Operators/drivers-Operate the equipment
▪ Helpers- Assist the equipment operator

■ Survey Instruments
▪ GPS
▪ Total station

■ Plant, Machinery and Vehicles


▪ Mobile crane 30 Tons
▪ Road marking machine

2.7.1 ROAD MARKING


■ After setting out of main axis, road marking will be done by our specific road marking unit as
per standards and specifications under the supervision of the responsible site engineer.
■ The material for the road marking will be approved by the Engineer.

METHOD STATEMENT PAGE 21 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.7.2 ROAD SIGNS


■ Before ordering the material, a sample will be provided to the Engineer to allow assessment
of the quality of material, size and type of the signs.
■ After the approval work will be executed.

METHOD STATEMENT PAGE 22 of 23


Construction of Service Road (Extension)
at Showroom Zone in Duqm

2.8 SITE INSTALLATION AREA (OFFICE, STORAGE)


The offices will be portable buildings of the Portacabin™ type or prefabricated buildings sandwich
panel type.

We foresee to use our existing camp at SIDRA Quarry approx. 50 km form the project location.

2.8.1 LABOUR RESOURCES


Our major works in Oman are in completion stage and we have enough resources available to con-
tinue utilizing our machinery and manpower for the this project.

As per our estimate we will require about 70 workers at peak.

2.8.2 EQUIPMENT RESOURCES


STRABAG Oman has successfully delivered projects all over the country for the last 45 years by uti-
lizing own and hired plant and equipment from the local market. In case the need arises STRABAG
can utilize resources from the affiliated companies of the Group in the region.

2.8.3 MATERIAL PROCUREMENT AND LOGISTICS


Water for the construction works will be obtained from public and private wells which are located
near the project location.

Other construction materials, as far available on the local market, will be procured locally; other-
wise they will be imported.

2.8.3.1 LOCALLY PROCURED MATERIALS


Locally procured materials will include ducts, pipes, and steel reinforcement. Further required for
material production are cement and bitumen.

2.8.3.2 IMPORTED MATERIALS


In case we should take over the supply of imported material from subcontractors, with the award of
contract Material Approval Sheet (MAS) will be submitted to Engineer and once approved, material
will be ordered accordingly so that there is no delay in construction.

2.9 SUBCONTRACTORS
Major subcontractors will be required for the following works:

■ Street light works

METHOD STATEMENT PAGE 23 of 23

Das könnte Ihnen auch gefallen