Beruflich Dokumente
Kultur Dokumente
*
G.R. No. 158768. February 12, 2008.
_______________
* FIRST DIVISION.
467
468
469
470
CORONA, J.:
1
This petition for review on certiorari seeks to set aside the
decision
2
of the Court of 3Appeals (CA) in CA-G.R. CV No.
61353 and its resolution denying reconsideration.
In 1992, respondent Primetown Property Group, 4
Inc.
awarded the contract for the structural works of its 32-
storey Makati Prime Tower (MPT) to petitioner Titan- 5
Ikeda Construction and Development Corporation. The
parties 6 formalized their agreement
7
in a construction
contract dated February 4, 1993.
Upon the completion of MPT’s structural works,
respondent awarded the 8P130,000,000 contract for the
tower’s architectural works (project) to petitioner. Thus, on
January 31, 9
1994, the parties executed a supplemental
agreement. The salient portions thereof were:
_______________
471
_______________
472
_______________
See Exhibit “A-10,” id., p. 484. Art. XIX of the construction contract provided:
ARTICLE XIX
CONSTRUCTION MANAGER’S STATUS
473
16
report, ITI informed respondent that petitioner, at that
point, had only accomplished 31.89% of the 17
project (or was
11 months and six days behind schedule).
Meanwhile, petitioner and respondent were discussing
the possibility of the latter’s take over of the project’s
supervision. Despite ongoing negotiations, respondent did
not obtain petitioner’s consent in hiring ITI as the project’s
construction manager. Neither did it inform petitioner of
ITI’s September 7, 1995 report.
On October 12, 1995, petitioner sought 18to confirm
respondent’s plan to take over the project. Its letter
stated:
_______________
Contra, Exhibit “A-9,” id., pp. 483-484. The construction contract provided:
ARTICLE XVII
RESCISSION OF CONTRACT
474
_______________
insure its completion within the required time, including any extension thereof,
and in any of these cases, [RESPONDENT] shall have the right to rescind
this contract by giving notice in writing to that effect to [PETITIONER]
and its bondsmen. [RESPONDENT] shall then take over the [project] and
proceed to complete the same on its own account.
17.1. It is further agreed and understood that in case of rescission,
[RESPONDENT] shall ascertain and fix the value of the [project] completed by
[PETITIONER] such usable materials on the [project] taken.
17.2. In the event that the total expenditures of [RESPONDENT] supplying the
scope of [PETITIONER’S] work to complete the project, including all charges
against the project prior to rescission of the contract, and not in excess of the
contract price, then the difference between the said total expenditures of
[RESPONDENT] and the contract price may be applied to settle claims, if any,
with the conformity of [PETITIONER] filed by workmen employed on the project
and by suppliers furnishing materials therefor. The balance, if any should be paid,
to the [PETITIONER] but no amount in excess of the combined value of the
unpaid completed work and retained percentage at the time of the rescission of
this contract shall be paid. No claim for prospective profits on the work done after
rescission of this contract shall be considered or allowed.
7.3. [PETITIONER] and its sureties shall likewise be liable to [RESPONDENT]
for any loss caused to [RESPONDENT] in excess of the contract price. (emphasis
supplied)
“Rescission” under article XVII of the construction contract never took place.
Respondent notified neither petitioner nor its bondsmen that it was invoking its
right to rescind under the contract. On the contrary, it was petitioner who drafted
the October 12, 1995 letter-agreement. (The said letter was printed on petitioner’s
letterhead.) Thus, the succeeding paragraphs quoted above are inapplicable in this
case.
475
_______________
Change Orders
a) CO #1 P 7,496,125.80
b) CO #2 160,975.87
c) CO # 3167,191.15
d) CO #4 311,799.71
e) Penthouse rework (structural) 1,228,781.08
f) Equipment support for MOS precast items 605,788.38
Architectural Works
g) Structural additive CO #1 41,400.00
h) Structural additive CO #2 276,177.00
i) VAT for structural (42,077,577 x 0.07) 2,945,430.39
j) VAT for architectural (May 31) 1,849,640.00
k) [Respondent’s] share in modular cabinets 2,694,400.00
l) Letter dated October 2, 1995 under “A” Nos. 37,688.00
1, 8, 12, 16
m) Letter dated October 2, 1995 under “B” Nos. 4, 726,878.05
11, 12, 17, 18, 19, 22 & 23 and VAT for modular
cabinets
476
_______________
25 Demand letter dated October 26, 1997. Exhibits “6” and “7,” Records,
pp. 500-504. The breakdown of the accounts is as follows:
477
_______________
Records show that at the time petitioner was working on the (MPT)
project, it was also working on respondent’s Sunnette Tower and Citadel
projects. It is unclear in relation to which project this cost was incurred.
27 A management certificate attests to the fact that the condominium
corporation is at least 60% Filipino (or that foreigners own not more than
40% of that corporation). It is a condition precedent to the issuance of
condominium certificates of title.
28 Rollo, pp. 62-63.
29 Docketed as HLRB Case No. 9657. Petitioner prayed for the issuance
of the management certificate and condominium certificates of title and
the delivery of keys to its respective buyers. Records, pp. 48-53.
478
_______________
479
_______________
480
_______________
481
VOL. 544, FEBRUARY 12, 2008 481
Titan-Ikeda Construction & Development Corporation vs.
Primetown Property Group, Inc.
_______________
See also 1 Jose B.L. Reyes and Ricardo C. Puno, AN OUTLINE OF PHILIPPINE
CIVIL LAW, 1957 ed., 42-43. The following are the essential requisites of the
action (action in rem verso):
46 Id., p. 17.
47 Id., pp. 67-70.
482
_______________
48 Id.
49 Austria v. Gonzales, Jr., 465 Phil. 355, 364; 420 SCRA 414, 421
(2004).
50 CIVIL CODE, Art. 1305.
483
51
The parties first entered into a contract for a piece of work
when they executed the supplemental agreement.
Petitioner as contractor bound itself to execute the project
for respondent, the owner/developer, in consideration of a
price certain (P130,000,000). The supplemental agreement
was reciprocal in nature because the obligation of
respondent to pay the entire contract price depended on the
obligation of petitioner to complete the project (and vice
versa).
Thereafter, the parties entered into a second contract.
They agreed to extinguish the supplemental agreement as
evidenced by the October 12, 1995 letter-agreement which
was duly acknowledged
52
by their respective
representatives.
While the October 12, 1995 letter-agreement stated that
respondent was to take over merely the supervision of the
project, it actually took over the whole project itself. In fact,
respondent subsequently
53
hired two contractors in
petitioner’s stead. Moreover, petitioner’s project engineer
at site only monitored the progress of architectural
54
works
undertaken in its condominium units. Petitioner never
objected to this arrangement; hence, it voluntarily
surrendered its participation in the project. Moreover, it
judicially admitted in its answer that respondent took over
the entire project, not merely its supervision,
55
pursuant to
its (respondent’s) long-range plans.
Because the parties agreed to extinguish the
supplemental agreement, they were no longer required to
fully perform
_______________
Art. 1713. By the contract for a piece of work the contractor binds himself to
execute a piece of work for the employer, in consideration of a certain price or
compensation. The contractor may either employ only his labor or skill or also
furnish the material.
484
485
_______________
486
_______________
487
_______________
488
Article XIV
DELAYS AND ABANDONMENT
_______________
64 Solid Homes v. Tan, G.R. Nos. 145156-57, 29 July 2005, 465 SCRA
137, 147-148.
65 Supra note 10. The supplementary agreement clearly stated the
construction contract, save those matters explicitly discussed in the
former, governed the project.
66 Exhibit “A-7,” Records,p. 481.
489
dent took over the project for the sole reason that such
move was part of its (respondent’s) long-term plan.
Respondent, on the other hand, relied on ITI’s
September 7, 1995 report. The construction contract
67
named
GEMM, not ITI, as construction manager. Because
petitioner did not consent to the change of the designated
construction manager, ITI’s September 7, 1995 report could
not bind it.
In view of the foregoing, we hold that petitioner did not
incur delay in the performance of its obligation.
The supplemental 68
agreement was a contract for a
stipulated price. In such contracts, the recovery of
additional costs (incurred due to changes in plans or
specifications) is governed by Article 1724 of the Civil Code.
490
Furthermore:
_______________
491
_______________
492
_______________
raising any question that should have been put in issue and decided in
previous proceedings.
79 See Metro Manila Transit Corporation v. D.M. Consortium, Inc., G.R.
No. 147594, 7 March 2007, 517 SCRA 632, 642.
493
SO ORDERED.
Petition granted.
——o0o——
494