Sie sind auf Seite 1von 45

Ref. Title Page No. Ref. Title Page No.

15.1 General 15-1 15.3.4 Method of Measurement 15-7


15.3.5 Basis of Payment 15-7
15.1.1 Scope 15-1
15.3.6 Items in the Bill of Quantities 15-7
15.1.2 Design 15-1
15.1.3 Regulations and Standards 15-1 15.4 Package Medium Voltage
15.1.4 Factory Tests 15-1 Switching Stations 15-7
15.1.5 Field Tests 15-1
15.4.1 Description 15-7
15.1.5.1 General 15-1
15.4.2 Materials 15-8
15.1.5.2 Insulation Resistance Test 15-2
15.4.3 Construction Requirements 15-8
15.1.6 Lighting Columns Tests – Pre-shipment 15-2
15.4.4 Method of Measurement 15-8
15.1.7 Switchgear Tests 15-2
15.4.5 Basis of Payment 15-8
15.1.8 Completed Tests 15-2
15.4.6 Items in the Bill of Quantities 15-8
15.1.9 General Technical Conditions 15-2
15.1.10 Approval 15-3 15.5 33kV and 11 kV Pole Mounted
15.1.11 Erection 15-3 Transformer Sub-Stations 15-8
15.1.12 Manuals 15-4
15.5.1 Description 15-8
15.1.13 Handling 15-4
15.5.2 Materials 15-8
15.1.14 Spares 15-4
15.5.3 Construction Requirements 15-9
15.1.15 Road Lighting 15-4
15.5.4 Method of Measurement 15-9
15.1.16 Sign Lighting 15-4
15.5.5 Basis of Payment 15-9
15.1.17 Medium Voltage and Substation Work -
15.5.6 Items in the Bill of Quantities 15-9
Generally 15-5
15.1.18 Method of Measurement 15-5 15.6 Feeder Pillars 15-9
15.1.19 Basis of Payment 15-5
15.6.1 Description 15-9
15.1.20 Items in the Bill of Quantities 15-5
15.6.2 Materials 15-9
15.2 Medium Voltage Intake 15.6.3 Construction Requirements 15-11
Switching Stations 15-5 15.6.4 Method of Measurement 15-11
15.6.5 Basis of Payment 15-11
15.2.1 Description 15-5
15.6.6 Items in the Bill of Quantities 15-11
15.2.2 Materials 15-5
15.2.3 Construction Requirements 15-6 15.7 Electrical Cables 15-11
15.2.4 Method of Measurement 15-6
15.7.1 Description 15-11
15.2.5 Basis of Payment 15-6 15.7.2 Materials 15-12
15.2.6 Items in the Bill of Quantities 15-6
15.7.2.1 Low Voltage Cables 15-12
15.3 Package Sub-stations 15-6 15.7.2.2 Medium Voltage (M.V) Cables 15-12
15.7.2.3 Metal Gland Parts 15-12
15.3.1 Description 15-6
15.7.2.4 Cable Trays 15-12
15.3.2 Materials 15-6
15.7.3 Construction Requirements 15-12
15.3.3 Construction Requirements 15-7
15.7.3.1 Cable Jointing and Termination 15-13

♦ 1-0
Ref. Title Page No. Ref. Title Page No.
15.7.3.2 Field Quality Control 15-13 15.11.2.2 Controllers 15-21
15.7.3.3 Earthing 15-13 15.11.2.3 Signal Equipment 15-22
15.3.4 Protection 15-14 15.11.2.4 Signal Operation 15-23
15.7.4 Method of Measurement 15-14 15.11.3 Construction Requirements 15-23
15.7.5 Basis of Payment 15-14 15.11.3.1 Cables 15-23
15.7.6 Items in the Bill of Quantities 15-14 15.11.3.2 Controller Root 15-23
15.11.3.3 Ducts 15-23
15.8 Road Lighting Masts, Columns
15.11.3.4 Draw Pits 15-24
and Luminaires 15-14
15.11.3.5 Pole installation 15-24
15.8.1 Description 15-14 15.11.3.6 Miscellaneous 15-24
15.8.2 Materials 15-14 15.11.3.7 Completion 15-24
15.8.2.1 Masts and Columns - General 15-14 15.11.4 Method of Measurement 15-24
15.8.2.2 Columns 15-15 15.11.5 Basis of Payment 15-25
15.8.2.3 High Masts 15-15 15.11.6 Items in the Bill of Quantities 15-25
15.8.2.4 Road Lighting Luminaires and Lamps 15-16
15.12 Overheight Vehicle Detection
15.8.2.5 Flood Lights 15-18
System 15-25
15.8.3 Construction Requirements 15-18
15.8.4 Method of Measurement 15-19 15.12.1 Description 15-25
15.8.5 Basis of Payment 15-19 15.12.2 Design Criteria for Materials
15.8.6 Items in the Bill of Quantities 15-19 and Components 15-25
15.12.3 Operational Requirements 15-25
15.9 Overhead Sign Illumination 15-19
15.12.4 Physical Requirements 15-26
15.9.1 Description 15-19 15.12.5 Construction Requirements 15-27
15.9.2 Materials 15-19 15.12.6 Method of Measurement 15-27
15.9.3 Construction Requirements 15-19 15.12.7 Basis of Payment 15-27
15.9.4 Method of Measurement 15-20 15.12.8 Items in the Bill of Quantities 15-27
15.9.5 Basis of Payment 15-20
15.13 Emergency Roadside
15.9.6 Items in the Bill of Quantities 15-20
Telephone System 15-27
15.10 Under Bridge Lighting 15-20
15.13.1 Description 15-27
15.10.1 Description 15-20 15.13.2 Regulations and Standards 15-28
15.10.2 Materials 15-20 15.13.3 Definitions and Mode of Operation 15-28
15.10.2.1 Surface Mounted Luminaires 15-20 15.13.4 Products and Materials 15-29
15.10.2.2 Recessed Mounted Luminaires 15-20 15.13.4.1 Pillar Design and Manufacture 15-29
15.10.3 Construction Requirements 15-21 15.13.4.2 Pillar Dimensions and Weight 15-29
15.10.4 Method of Measurement 15-21 15.13.4.3 Frangibility 15-29
15.10.5 Basis of Payment 15-21 15.13.4.4 Pillar Materials and Color 15-29
15.10.6 Items in the Bill of Quantities 15-21 15.13.4.5 IP Rating 15-29
15.13.4.6 Vibration and Shock 15-29
15.11 Traffic Signals 15-21
15.13.4.7 Wind 15-29
15.11.1 Description 15-21 15.13.4.8 Temperature 15-29
15.11.2 Materials 15-21 15.13.4.9 Lightning Protection 15-30
15.11.2.1 General 15-21 15.13.4.10 Vermin Ingress 15-30

♦ 1-0
Ref. Title Page No. Ref. Title Page No.
15.13.4.11 Vandalism 15-30 15.16.3.1 Labeling 15-37
15.13.4.12 Pillar Identification 15-30 15.16.3.2 Testing and Commissioning 15-38
15.13.4.13 Concrete 15-30 15.16.4 Method of Measurement and Basis
15.13.4.14 Steelwork 15-30 of Payment 15-38
15.13.5 Power Supply 15-30
15.17 Civil Works for Electrical
15.13.5.1 Power Supply 15-30
Installations 15-38
15.13.5.2 Battery 15-30
15.13.5.3 Battery Charging 15-30 15.17.1 Description 15-38
15.13.5.4 Solar Panel 15-30 15.17.2 Materials 15-38
15.13.6 Construction Requirements 15-31 15.17.3 Construction Requirements 15-39
15.13.6.1 Drawings 15-31 15.17.3.1 Bases for Poles and Equipment 15-39
15.13.6.3 Anchor Bolt Assembly 15-31 15.17.3.2 Cable Trenches and Ducts 15-39
15.13.6.4 Pillar Mounted Telephone 15-31 15.17.4 Method of Measurement 15-40
15.13.6.5 Grouting of Pillar Base 15-31 15.17.5 Basis of Payment 15-40
15.13.7 Method of Measurement 15-31 15.17.6 Items in the Bill of Quantities 15-40
15.13.8 Basis of Payment 15-31
15.13.9 Items in the Bill of Quantities (Unit) 15-31

15.14 Public Lighting Management


and Control System 15-31
15.14.1 Description 15-31
15.14.2 General Requirements 15-31
15.14.3 Detailed Technical Specification 15-32
15.14.4 Remote Control Management Software 15-33
15.14.5 Hardware 15-35
15.14.6 Method of Measurement 15-35
15.14.7 Basis of Payment 15-35
15.14.8 Items in the Bill of Quantities 15-36

15.15 Earthing 15-36


15.15.1 Description 15-36
15.15.2 Materials 15-36
15.15.3 Construction Requirements 15-36
15.15.4 Earth Resistance Test 15-37
15.15.5 Method of Measurement 15-37
15.15.6 Basis of Payment 15-37
15.15.7 Items in the Bill of Quantities 15-37

15.16 Labeling, Testing and


Commissioning 15-37
15.16.1 Description 15-37
15.16.2 Materials 15-37
15.16.3 Construction Requirements 15-37

♦ 1-0
♦ 1-0
15.1 General such quality may not be stated specifically in this
Specification.
15.1.1 Scope 3 All materials and products shall be new and
manufactured by manufacturers approved by the
1 This Sub-section describes general requirements for
concerned authority. Furthermore, they shall be sound
electrical systems, including medium voltage substations,
and uniform in quality, size, shape, color and texture and
packaged substations, cables and feeder pillars, road and
free from cracks, warpage or other defects.
under-bridge lighting, traffic signals, illuminated signs,
detection system and emergency telephone system, and 4 All warranties as applicable that are available from
all associated work. Specific requirements for each system the manufacturers shall be submitted to the Engineer in
are given in the relevant Sub-sections of this Section. original documents.

2 Subsidiary (complementary) items which are not


15.1.4 Factory Tests
expressly specified but are necessary for completion of
the work shall be supplied and installed by the Contractor 1 All equipment and materials shall be subject to pre-
and their costs are deemed to be included in the rates and shipment inspection and testing at the manufacturers’
prices for the relevant work. premises. The Contractor, in coordination with the
3 The power supply connection for the lighting manufacturers of relevant materials shall arrange for the
systems shall be coordinated with and obtained from a pre-shipment inspection and testing by the authorized
nearby source assigned by the concerned local power representative of the Engineer at the manufacturers’
authority. premises.

4 The Contractor shall pay all power connection 2 The Contractor shall make all necessary
charges and fees imposed by the Local Power Authorities arrangements and pay all expenses in this regard
and Municipalities, including execution of all civil works including representation, travelling and transportation,
(trench, ducts). boarding, lodging and any other associated cost for the
pre-shipment inspection procedures and witnessing of
5 The work shall be complete in every respect for
the tests at the manufacturer’s premises. In lieu of the
satisfactory operation in compliance with the
above tests the Engineer, at his sole discretion, may
specifications and standards laid down by the respective
accept test certificates by an approved laboratory of
authority and as given herein.
international standards.

15.1.2 Design 3 The Contractor shall obtain from the manufacturer


and submit to the Engineer for approval, the complete
1 The location of light fittings, poles, feeder pillars, details of tests to be performed describing the procedures,
distribution transformers and cables, etc. are shown for test observations and expected results. All test certificates
guidance on the Drawings. Final locations shall be subject shall be in compliance with recognized international
to the road configuration, lighting calculations and standards as approved by the Engineer and the Concerned
approval by the Concerned Authorities. Authority.
2 The Contractor shall coordinate with the Engineer 4 The Contractor shall ensure availability of all tools,
and shall determine the exact position and location of all instruments, test equipment, materials etc., and all
lighting and electrical equipment with respect to other qualified personnel required for the testing, setting and
services and site requirements. adjustment of all equipment and materials including
3 The Contractor shall be responsible for proper putting the same into operation.
lighting distribution on the road surface from the 5 The Contractor shall inform the Engineer of the date
proposed luminaires and other equipment after and time of test for each piece of equipment at least two
installation and commissioning and shall be fully weeks in advance. The witnessing of tests by the Engineer
responsible for maintaining the entire road lighting or his representative shall not absolve the Contractor from
system during the maintenance period of the Works. his responsibility for the proper functioning of the
equipment, and for furnishing the guarantees. All test
15.1.3 Regulations and Standards results shall be supplied in triplicate.
1 The Contractor shall comply with the regulations and
requirements of the concerned authorities, and shall get
15.1.5 Field Tests
all necessary approvals of the shop drawings from the 15.1.5.1 General
respective authority after obtaining approval of the
Engineer. If the road lighting works are executed by a Sub- 1 Upon completion of the installations, the Contractor
Contractor, the Contractor has to ensure that the Sub- shall perform field tests on all equipment, materials and
Contractor is approved by the Concerned Authority. systems. All tests shall be conducted in the presence of
2 The quality of equipment shall be of the best grade the Engineer for the purpose of demonstrating equipment
for each type as approved by the Engineer, even though and system’s compliance with the Specification. The
Contractor shall submit for Engineer’s approval, complete

♦ 15-1 ♦
details of tests to be performed, equipment used, permanent set test and breaking load test. When the
describing the procedure, test observations and expected columns in the Works are limited in number, the
results. manufacturer may supply result of tests already done for
prototype testing on such columns, or supply calculation
15.1.5.2 Insulation Resistance Test based results, in lieu of carrying out deflection, permanent
1 Before making connections at the ends of each cable set and breaking load tests.
run or joint between cables, the insulation resistance test 3 Passive Safety of Support Structures:
of each cable section shall be made. Each conductor of a If requested by the Concerned Authority, tests shall be
multicore cable shall be tested individually with each of carried out on each type of column in accordance with BS
the other conductor of the group and also with earth. If EN12767: 2007 level 4. Costs of such tests for
insulation resistance test readings are found to be less columns/high masts will be included under separate items
than the specified minimum in any conductor, the entire in the Bill of Quantities.
cable shall be replaced and tests repeated on the new
cables. If cable joints are provided, then each cable 15.1.7 Switchgear Tests
section shall be tested and joints made only after the tests
have been made satisfactorily. Finally the completed 1 Each circuit breaker shall be operated electrically and
cable length including the joints shall be tested. mechanically or only mechanically if it is not electrically
operated. All interlocks and control circuits shall be
2 All switchgear shall be given an insulation resistance
checked for proper connections in accordance with the
test after installation, but before any wiring is connected.
wiring diagrams furnished by the manufacturer and
Insulation tests shall be made between open contacts of
approved by the Engineer
circuit breakers, switches and between each phase and
earth. Refer to Sub-section 15.16 for details. 2 The Contractor shall properly identify the phases of
all switchgear and cables for connections to give proper
3 If the insulation resistance of the circuit under test is
phase sequence.
less than the specified value, the cause of the low reading
shall be determined and rectified. Corrective measures 3 Trip circuits shall be checked for correct operation
shall include dry-out procedure by means of heaters, if and rating of equipment served. The correct size arid
equipment is found to contain moisture. Where corrective function of fuses, disconnect switches, number of
measures are carried out, the insulation resistance interlocks, indicating lights, alarms and remote control
readings shall be taken after the correction has been made devices shall be in accordance with approved
and repeated twice at 12 hours interval. manufacturer drawings. Name plates shall be checked for
proper designation of equipment served.
4 The maximum range for each reading in the three
successive tests shall exceed 20% of the average value.
After tests have been made, the equipment shall be
15.1.8 Completed Tests
reconnected as required. 1 After any equipment has been tested, checked for
operation, etc., and is accepted by the Engineer, the
15.1.6 Lighting Columns Tests – Pre- Contractor shall be responsible for the proper protection
shipment of that equipment so that subsequent testing of other
equipment does not cause any damage to the already
1 The tubular steel columns shall be tested and the
tested equipment.
results recorded for each test by the manufacturer in the
presence of an authorized representative of the Engineer
in the manufacturer’s premises. The material weight and
15.1.9 General Technical Conditions
dimensions of columns as specified shall be certified by 1 Electrical work shall include the submission by the
the manufacturer. The columns shall be inspected for Contractor of shop drawings and calculations required by
compliance and will be rejected if they are found to be the Specification, as well as the provision of literature and
outside the specified tolerances. samples for the approval process.
2 Loading Test: 2 All plant and equipment shall be supplied with the
The columns shall be cantilevered horizontally, rigidly necessary fittings, accessories and parts for the complete
supported at base plate and loads applied at right angle to installation, irrespective of whether all such fittings and
the axis of the pole at the required point, i.e. at some accessories are listed in the Specification and Drawings.
distance from top. Tests shall be as follows: 3 Installations shall be complete, tested, ready for
• Deflection test. operation and fully integrated with other parts of the
construction and the utility supply. The Contractor shall
• Permanent set test
make available facilities for utility providers during
• Breaking load test
commissioning.
A sample comprising four columns shall be selected at
4 Electrical work shall comply with the concerned
random out of each lot of 1000 and subjected to deflection
authority rules and regulations, and be carried out in
test. One column per thousand shall be tested for accordance with the recommendations of the International

♦ 15-2 ♦
Electro-technical Commission (IEC) and in compliance plasticizer and shrinkage of the PVC due to high
with the following: temperature (uPVC).
i. Relevant standards issued by the appropriate
authorities in the Sultanate of Oman including 15.1.10 Approval
the Ministry of Transport and Communications 1 Details of the manufacturers of proposed plant and
(MOTC). equipment shall be submitted for prior approval of the
ii. BS 7671:2008, Requirements for electrical Concerned Authority and Engineer. Approval of any
Installations; (IEE Wiring Regulations (UK) as manufacturer will not constitute approval of his products.
published by the Institution of Electrical The Contractor shall ascertain that the approved
Engineers, London, 17th Edition (or the latest manufacturers are capable of supplying the required
edition). equipment and in conformity with the Specification.
iii. Engineering and safety recommendations of G39
2 The Contractor shall submit to the Engineer for his
‘Model Code of Practice’ of the IEE.
approval, in particular, the following luminaire criteria
iv. Recommendations for the Lighting of Roads for
before placing an order:
Motor and Pedestrian Traffic – CIE-115 or
equivalent and equal standards. i. Detailed literature on each luminaire, lamp and
control gear including manufacturer’s name,
5 Electric power will be supplied by the concerned
catalogue number, rating, material specification,
power authority at a defined voltage, 3-phase, 3 or 4 wires,
overall dimensions, operating characteristics and
50Hz. It shall be distributed from sub-station feeder pillars
principles
at 415/240 V, 3-phase, 4-wire having solidly grounded
ii. Details of changes to standard luminaires if
neutral at the transformer neutral point. Single phase
proposed for adaptation to conditions of
equipment shall be connected between phases and
installation or to meet the Specification
neutral in a way to balance the three phases.
requirements.
6 The voltage at any point in an installed power iii. Photometric data for lighting calculations
distribution network shall not deviate from nominal including polar light distribution curves,
voltage level by more than 5% under normal system coefficient of utilization, glare classification,
operating conditions. efficiency, depreciation factors etc.
7 The equipment shall be capable of giving continuous iv. Calculations of luminance and illumination levels
and trouble-free service in the conditions given in Table and glare, as recommended, using approved
15.1.9-1. It shall be designed and constructed to withstand software and methods
full load operation when exposed to sun, dust storms, 3 Fully equipped samples of any item requested by the
corrosive agents, occasional heavy rain and a high level of Concerned Authority or Engineer shall be delivered as
ultra violet radiation. soon as possible to the Concerned Authority before
placing of orders for the material or products, without
Maximum ambient shade hindering the planned program and progress of work.
50°C
temperature 4 The Contractor shall not order any electrical
Minimum ambient equipment or part, plant or fitting before receiving
-2°C
temperature approval for it. The Engineer may verify the performance
Maximum temperature of and quality of the samples submitted by instructing tests
80°C
metal surface in direct sunlight to be carried out. Approval of samples shall not relieve
the Contractor of his obligations regarding the suitability
Humidity 100%
of the equipment and their performance, once installed.
As per project 5 The Contractor shall submit for prior approval by the
Altitude
requirement Engineer detailed working drawings and shop drawings
Table 15.1.9.1: Operating Conditions for Equipment showing the physical layout of equipment, location of
masts and columns, foundation details, erection and
8 The component parts of each electrical system or installation details, and wiring diagrams. Details shall
piece of equipment shall be the latest product of a single include bolts, nuts, brackets, rods and any small or large
manufacturer, of standard design and dimensions, and item that is necessary for the construction, all to the
similar parts shall have been in satisfactory service for at satisfaction of the Engineer and Concerned Authority.
least two years
15.1.11 Erection
9 The maximum gust speed at 10m above ground level
in open level country for a 1 in 50 year return period shall 1 The Contractor shall submit to the Engineer a
be taken as: 55m/s (198 km/h) schedule of the parts and equipment to be erected. If
10 PVC sleeves where used, shall be of the long chain requested by the Engineer the Contractor shall open up for
high molecular mass type capable of reducing the loss of inspection before erection any plant or equipment which
has been delivered to the Site partly assembled.

♦ 15-3 ♦
2 The Contractor shall satisfy himself as to the 15.1.15 Road Lighting
correctness of the electrical and mechanical connections
1 The Contractor shall provide detailed computerized
to plant and equipment installed before it is
calculations to demonstrate that the luminaires proposed
commissioned.
meet the criteria for illumination and luminance given in
3 Operation of plant and equipment still under the the Specification, standards and shown on the Drawings.
control of the Contractor but which is made live shall be
2 Upon completion of a lighting installation as
subject to a ‘Permit to Work’ procedure in a format agreed
specified the Contractor shall carry out measurements of
with the Engineer and the respective authorities.
the illumination levels on the Site in accordance with
clause 15.16 and submit the results to show that the
15.1.12 Manuals
design levels and uniformities have been achieved. The
1 Prior to the final acceptance of the installation the maintained illumination and luminance levels shall be as
Contractor shall submit to the Engineer six sets of given in Table 15.1.15.1.
operation and maintenance manuals for the installed plant 3 Illumination lighting levels shall be measured for all
and equipment. The manuals shall be A4 size in loose leaf the traffic lanes.
binders containing the following:

Secondary

Distributor
i. Single line diagrams of the complete network

National

Arterial

Access
Routes

Routes

Routes

Routes

Routes
properly labeled
Characteristic
ii. Control, protection and circuit diagrams for all
equipment.
iii. Setting up, commissioning and operating
Average
instruction.
Luminance level
iv. Trouble shooting procedures. 2 2 1.5 1.5 0.75
Lav (cd/m2)
v. Maintenance instructions including schedules for (maintained)
preventative maintenance. Overall
vi. Complete recommended spare parts list uniformity 0.4 0.4 0.4 0.4 0.4
including part numbers and the manufacture’s UO = LMin/ Lav
name, address, telephone and fax numbers. Longitudinal
vii. Name of the manufacturer’s local authorized uniformity
0.7 0.7 0.7 0.7 0.6
of each lane
representative and service agent.
UL = LMin/LMax
Maximum
15.1.13 Handling threshold 10% 10% 15% 15%
-
Increment (TI)
1 The Contractor shall provide slings, lifting tackle and
Road surface
cranes for the safe handling of items supplied and shall be
characteristics
responsible for obtaining and keeping up to date the R3* R3 R3 R3 R3
CIE classification
necessary test certificates for this handling equipment. with qo = 0.07
Protection of surfaces and floors during installation shall Average
be the responsibility of the Contractor. Horizontal
Illuminance 35 35 25 25 12
15.1.14 Spares E av. (Lux)
(maintained)
1 Spare parts indicated in the Bill of Quantities shall be Illuminance
supplied suitably packed for transportation to Site and Uniformities 1:3 1:3 1:3 1:3 1:3
long term storage. They shall include fastenings, lugs, and EMin/Eav
screws needed for their attachment. Identification labels EMin/EMax 1:6 1:6 1: 6 1: 6 1: 6
shall be attached to the outside and also enclosed within
*(R3: asphalt road surface with rough texture, slightly
the storage case.
specular)
2 Spares for routine maintenance shall be listed and
Table 15.1.15.1: Maintained Road Illumination and
supplied in quantities equal to 5% (rounded up to the next
Luminance Levels
whole unit) of installed quantities of each type of column,
cable, joint, lamp, control gear, circuit breaker, fuse,
luminaire, luminaire cover and associated bolts, nuts, 15.1.16 Sign Lighting
lampholders, etc. 1 The illuminance level and uniformity shall be
3 Any additional spare parts recommended by the calculated and measured on the sign surface at the
manufacturers, but not named above, shall be included in vertices of the grids defined by dividing it into 1m x 1m
the list. squares and shall be better than the following:
Average illuminance (EAV) : 200-400 lux
Uniformity (EMin: EMax) : 1:6

♦ 15-4 ♦
2 The luminaires or floodlights shall be of purpose i. Danger High Voltage.
built design incorporating the specified size and type of ii. Keep Out.
lamps.
iii. Telephone number of emergency
3 The luminaires or floodlights shall be of pleasing contact.
aesthetic appearance with high quality finish, and shall
Additionally, instruction plates shall be posted inside high
comply with BS EN 12899-1, IEC 60598-1, IEC 60598-2-3,
voltage rooms and shall help operating staff to evacuate in
IEC 60598-2-5 and other related parts of this standard as
case of emergency.
applicable.

15.1.18 Method of Measurement


15.1.17 Medium Voltage and Substation
Work - Generally 1 The provision of power supply from the Concerned
Authority to the assigned position of the feeder pillar,
1 Medium-voltage switchgear and control gear
including cable, (KWh-meter), connections at both ends
standards and substation work, equipment and
and all necessary related civil works shall be given as a
component parts are to comply with the following
unit.
standards:
Common specifications: IEC 62271-1 2 Spare parts for routine maintenance and any special
Metal-enclosed switchgear and control gear for rated spare parts ordered by the Engineer shall each be given as
voltages above1 kV and up to and including 52kV items.
IEC 62271-200
High-voltage alternating current circuit- breakers 15.1.19 Basis of Payment
IEC 62271-100 1 The provision of power supply to the feeder pillar
Insulation coordination IEC 60071 shall be paid by number of units, which shall include
Alternating current switch-fuse combinations coordination with the Concerned Authority and for them
IEC 62271-105 to provide power supply to the feeder pillars, including
High-voltage A C. disconnectors and earthing switches subscription fees, supply and installation of breakers,
IEC 62271-102 cables, KWh metering, execution and completion of all the
Switches for rated voltages above 1 kV and less than related civil works.
52 kV IEC 62271-103
2 Spare parts shall be paid for according to the
Metering and protective current transformers (CTs)
completely delivered items by type and quantities as per
IEC 60044-1
the approved list.
Metering and protective voltage transformers (VTs)
Capacitive IEC 60044-5(IEC 60186)
Inductive IEC 60044-2 15.1.20 Items in the Bill of Quantities
Relays IEC 60255 i Power supply connection to the feeder pillar. (nr)
Surge arrestors IEC 60099-5
ii Spare parts (5% as per the approved list. (L.S)
Reading instruments IEC 60051
Watt-hour meters IEC 60521, 62052-11
62053-21,-22,-23 15.2 Medium Voltage Intake Switching
Power transformers IEC 60076, 60354, Stations
60076-11,-10
60156 15.2.1 Description
Insulating oil IEC 60296
1 This Sub-section describes requirements for
Sulphur hexafluoride IEC 60376
supplying, installing, testing and putting into operation the
Fuses IEC 60282-1
M.V. switchgear which shall be in accordance with
Climate conditions IEC 60721-3-3
concerned authority specifications and approval, at
and IEC 60721-3-4
locations indicated on Drawings.
Neutral earthing resistance (when required)IEEE std 32.
For all substations, switching and package stations, the 15.2.2 Materials
short circuit capacity rating, the low voltage control and
1 Medium voltage intake and switching units shall
power supply where needed or other provisions, have to
comprise panels containing the following equipment as
be coordinated with the Concerned Authority and
shown on the Drawings and as required by the concerned
provided accordingly.
authority:
2 Contractor shall provide danger signs in both Arabic
i. Circuit breakers for network control.
and English according to Omani standards made of heavy
ii. Circuit breakers for outgoing circuits.
duty corrosion proof metal, each of not less than 200mm x
300mm installed on all sides of substations, to clearly The panels shall be equipped with floor mounting
indicate to approaching people the hazard. These signs framework, skid bases, internal wiring, labels and cable
shall include:

♦ 15- 5♦
sockets. The assembly shall allow for cable access from 15.2.5 Basis of Payment
below without dismantling any structural members.
1 The amount of completed and accepted work
2 The network control circuit breakers shall be measured as provided for above will be paid for at the unit
manually charged, spring operated, fitted with integral rate stated in the Bill of Quantities and shall be full
earthing of the characteristics given by the Concerned compensation for equipping, supplying materials,
Authority. installation, testing and putting into operation, labor,
3 Voltage transformers shall be installed and transport, equipment, tools, spare parts and other items
connected to the primary side of the breaker, to supply the necessary for the proper completion of the work.
lighting and small power for the switching station.
Voltage transformers shall be isolatable and fused on 15.2.6 Items in the Bill of Quantities
primary and secondary sides.
i Medium voltage intake switching station
4 The outgoing circuit breakers shall be manually
(type) (voltage) (rating) (reference drawings) (nr)
charged, spring operated, fitted with integral earthing of
the characteristics given by the concerned authority and
as shown on the drawings. 15.3 Package Sub-stations
5 Tripping of breakers shall be by direct acting primary
trip coil or by current transformer operated direct acting 15.3.1 Description
trip coils. A neon indicator connected to a voltage
1 This Sub-section describes requirements for
capacitor divider indicating voltage presence shall be
supplying, installing, testing and putting into operation,
fitted on each circuit breaker.
factory assembled package sub-stations and connecting to
6 Intake stations shall be supplied with the necessary the medium voltage supply and the low voltage
accessories to form complete operating installations, distribution network.
including the following:
i. Rubber gloves 15.3.2 Materials
ii. Rubber mat extending the full length of the
1 Package sub-stations shall be completely self-
equipment
contained, factory assembled in a totally enclosed, vandal
iii. KV potential testers
and weather resistant housing, ready for placing into
iv. Spare fuses
position upon a concrete base pad.
v. Test plugs
vi. Safety and operating instructions 2 Package sub-station shall comprise of a single
vii. Framed and glazed medium voltage line integrated metal housing, with three totally segregated
diagrams compartments, accommodating MV switch-gear, MV/LV
viii. Wall mounted cupboards, with mortice lock and distribution transformer and LV switchgear. Degree of
three keys each. protection shall be IP 54 for switchgear (MV or LV)
enclosures and IP 23 for transformer housing. MV and LV
15.2.3 Construction Requirements connections to corresponding transformer terminals are to
be insulated and inaccessible without the use of tools.
1 The Contractor shall coordinate with and get
3 The MV live parts shall be completely enclosed in
approval from the selected manufacturer of the switching
lockable compartments, which shall be segregated for
plant on the proposed civil works before starting
maximum safety, but give the necessary access for
construction.
cabling and connections, IP5X minimum, in accordance
2 The construction of the buildings shall comply with with IEC 62271. Cables shall enter and leave the
the requirements of Subsection 15.17. compartments from below. A chain link fence 2m high
3 The equipment shall be lifted into position within the shall be provided around the sub-station with a lockable
station upon prepared foundations. The station gate.
switchboards may be installed complete or in sections. 4 The medium voltage switchgear shall consist of two
The units shall then be tested before and after incoming (2) ring main SF6 switches and one switch-fuse (sealed for
and outgoing cables are connected. life), with fuses mounted in a separate compartment.
Handle design is to ensure delay between closing and re-
15.2.4 Method of Measurement opening of main switch or earthing switch, to provide an
1 The approved work shall be measured by the number anti-reflex operation. It shall be impossible to move earth
of medium voltage intake switching stations, installed in switch inadvertently into or from earth position except
station building (excluding building) and put into when main switch is in the open position. Indication of
operation after testing, and acceptance by the concerned switch position shall be mechanical, directly connected to
authority. moving contacts. Each switch shall have a padlocking
device in the open, closed and earth positions. Semaphore
type indicators shall be provided to indicate on, off, earth-
on earth off positions, protected with polycarbonate

♦ 15- 6♦
covers. The fuse access shall be interlocked to prevent it with a compartment housing the accessories to form a
being opened unless the switch is off and earthed at both complete operating installation as follows:
ends. i. Rubber gloves.
5 The ring main switches shall be fitted with cable ii. Spare fuses.
boxes and glands. The cables shall be connected to the iii. Safety and operating instructions.
fixed mating contacts by flexible connectors provided with iv. Medium voltage line diagram.
a slotted hole. v. Low voltage circuit diagram with designations.
Alternatively, MV switchgear compartment cable terminal vi. kV potential tester
connectors shall be conical stress-relieving, epoxy sealed vii. Kilowatt hour metering as per requirements
end, bolted, straight/elbow, molded rubber, plug-in, or Additionally, instruction plates shall be posted inside high
other type, complete with all accessories as may be voltage rooms and shall help operation staff to evacuate in
suggested by manufacturer and approved by the case of emergency.
concerned authority.
6 MV switchgear compartment potential indicators 15.3.3 Construction Requirements
shall be neon indicators, provided at front of each unit, 1 The Contractor shall agree with the selected
one per phase, using capacitive potential divider to manufacturer of the package sub-station on details for the
indicate voltage at switch-disconnector cable terminals. proposed civil works and shall have shop drawings
7 MV switchgear compartment accessories are to approved before construction starts.
include the following: 2 The Contractor shall install the package sub-station
i. Two N.C. and two N.O. auxiliary contacts on unit upon the concrete base using the appropriate lifting
each switch. gear to prevent damage. When correctly located, the unit
ii. Earth fault indicator, operated by core-balance shall be bolted in position and tested before and after
type current transformer, located near and connecting the incoming and outgoing cables.
outside cable box/ terminations with indicator
visible from the front and with automatic reset. 15.3.4 Method of Measurement
iii. Shunt trip release on switch-fuse combination.
1 Package sub-stations shall be measured by the
8 The transformer feeder switch shall have a trip
number of complete units supplied, installed, tested, put
button or shall trip automatically by fuse operation. An
into operation and accepted by the Concerned Authority,
interlock shall be provided so that the switch-fuse cannot
including time switch and connection.
be put back into service until the faulty fuse has been
replaced.
15.3.5 Basis of Payment
9 The low voltage switchboard shall be a separately
enclosed metal compartment with lockable doors within 1 The amount of completed and accepted work measured
the package housing and shall be of equal construction to as provided for above will be paid for at the unit rate
the feeder pillar. It shall consist of a triple pole and neutral stated in the Bill of Quantities and shall be considered as
manually operated main circuit breaker of the molded full compensation for supplying and installing the sub-
case pattern of the required ampere interrupting capacity. station, testing, putting into operation, handing over,
Overload and short circuit release mechanisms including all materials, labor, transport, equipment, tools
comprising thermal and magnetic trips and earth leakage and other items necessary for the proper completion of
protection (30mA), shall be provided. the work.

10 Three ammeters fitted with selector switch,


15.3.6 Items in the Bill of Quantities
maximum demand indicator and current transformers
shall be incorporated along with a voltmeter with selector i Package sub-station (type) (reference)
switch and protection fuse. (rating) (voltage) (nr)
11 A single phase socket outlet of 16-250 DIN rating
complete with plug top and a 12W fluorescent lighting 15.4 Package Medium Voltage
fitting of the integral battery/inverter emergency type, with
Switching Stations
switching facility to allow emergency light to be initiated
shall be mounted adjacent to the low and medium voltage
switchgear panels and shall be prewired at the factory.
15.4.1 Description
12 The low voltage panel circuits serving the lighting 1 This Sub-section describes requirements for
shall be supplied through triple pole circuit breakers and supplying, installing, testing and putting into operation
triple pole contactors (one set per circuit) which shall be factory assembled package medium voltage switching
dual photo-electric cell controlled. The low voltage panel stations, and connecting to the medium voltage electrical
and components shall meet the requirements specified in supply network.
Subsection 15.6. The package sub-station shall be fitted

♦ 15- 7♦
15.4.2 Materials Engineer. The transformers and all accessories shall
conform to the requirements, standards and specifications
1 Package switching stations shall be self-contained;
of the concerned authority and the Contractor shall obtain
factory assembled conforming to MV Switchgear
all necessary approvals from the Concerned Authority in
specification in Sub-section 15.3.
this regard.
2 The switching station shall contain 3 extensible SF6
switch units with space for one additional SF6 switch. The 15.5.2 Materials
switches shall be fitted with cable boxes and glands
suitable to receive the incoming cables and shall have 1 Metal work shall be hot-dipped galvanized to BS EN
operating positions at the front of the unit. The switching ISO 1461 and ASTM A123 and ASTM A153, whichever is
mechanisms shall be independent manual type. more stringent, after fabrication.

3 Switching stations shall be supplied with accessories 2 Transformers shall be painted by the manufacturer.
as for sub-stations with the exception of the low voltage Standard identification plates shall be fixed.
circuit diagrams. 3 Bushings and insulators shall have a minimum
4 Emergency lighting if required by the Concerned Creepage value of 40mm/kV.
Authority, shall be coordinated with the Concerned 4 The transformer station supports shall be ‘H’ type
Authority and be provided as specified in Sub-section 15.3, construction, using 11m long, preservative treated,
Clause 15.3.2 (11). wooden (Pinus Sylvestris) poles type. The support system
shall be fitted with 4 stay sets, each comprising tubular
15.4.3 Construction Requirements stay-rods, wood stay insulators, galvanized steel wire of
minimum diameter 4mm and pole clamps. The poles
1 Construction requirements shall be as specified in
shall be fitted with galvanized mild steel cross arms to
Sub-section 15.3, Clause 15.3.3.
support the transformer.

15.4.4 Method of Measurement 5 The 11kV fuse units shall be 3 phase expulsion drop-
out type with 900mm phase to phase spacing and fitted
1 Package medium voltage substations work shall be with re-wireable fuse elements.
measured by the number of units supplied, installed, put
6 The 33kV switch fuse units shall be 3 phase, vertical
into operation, accepted by and handed over to the
mounting, with 1050mm phase to phase spacing. The
concerned authority, including connection to the MV
switch shall include a treated wooden, insulated,
supply, fees, and the cost of power connection from the
operating handle at 1.2m from ground level. The fuses
assigned source.
shall be of the expulsion drop-out type, fitted with re-
wireable fuse elements.
15.4.5 Basis of Payment
7 The transformers shall be the pole mounted type
1 The amount of completed and accepted work with outdoor bushings on both medium and low voltage
measured as provided for above will be paid for at the unit sides and shall have the characteristics given in Table
rate stated in the Bill of Quantities, which rate shall be full 15.5.2-1.
compensation for supplying, installing the station, testing 8 The low voltage units shall be 3 outdoor pole mount
and putting into operation, connection labor, transport, porcelain cut-outs fitted with appropriately rated HRC
equipment, tools and other items necessary for the proper fuses.
completion of the work.
Rating As indicated on drawings
15.4.6 Items in the Bill of Quantities Phases 3
i Package medium voltage switching Winding Connections: Delta 3 wire primary
station (type) (reference) (voltage). (nr) Star 4 wires sld earthed
neutral secondary
15.5 33kV and 11 kV Pole Mounted Tappings Dyn 11
Transformer Sub-Stations Impedance Medium voltage off-circuit
+5% to -5% in 2.5%steps
15.5.1 Description
Cooling Oil filled natural
1 This Sub-section describes requirements for
Temperature Rise:
supplying, installing, testing and putting into operation
pole mounted transformer sub-stations and connecting to Oil 40°C
the medium voltage supply on one side and the low Windings 50°C
voltage distribution network on the other side. Table 15.5.2.1: Pole Mounted Transformer Characteristics
2 The capacity of pole mounted transformers shall be
as shown on the Drawings and or as directed by the

♦ 15- 8♦
15.5.3 Construction Requirements testing and putting into satisfactory operation feeder
pillars for road lighting networks as shown on Drawings.
1 The Contractor shall coordinate and agree the
location of pole mounted transformer stations with the 2 The Contractor shall submit data for approval,
Engineer prior to commencing the installation. The poles including but not limited to the following:
shall be installed in concrete at 2.2m centers for the 33kV i. Construction details, standards to which pillars
system and 1.8m centers for the 11kV system. comply, current carrying capacities of bus bars,
2 The Contractor shall install the equipment using the de-rating factors employed for breakers and bus
appropriate lifting gear to prevent damage. The medium bars.
and low voltage connections shall be made only after the ii. Manufacturer’s catalogue cuts for all
equipment is correctly installed and tested. components.
iii. Dimensional and electrical characteristics and
15.5.4 Method of Measurement samples of breakers used
3 The Contractor shall submit drawings for approval,
1 Pole mounted transformer sub-stations shall be
including but not limited to the following:
measured by the number of units supplied, installed, put
into operation and accepted by the Concerned Authority. i. External dimensions of feeder pillars
ii. Details of base foundation
2 The rate shall include for transformer, 11m long
iii. Details of breaker ratings, bus bars
preservative treated supporting wooden poles, platform
iv. Glands, joints, etc
for mounting transformer, galvanized mild steel cross
v. Mounting details
arms, stay sets, insulators, post insulators and support
assembly, 4mm diameter galvanized steel wire, 33kV or
15.6.2 Materials
11kV fuse units, low voltage HRC fuses and all other
necessary hardware, GI guards and anti-climbing device, 1 Feeder pillars shall comply with IEC 60439-1 and /or
earthing with or without chamber, 33kV or 11kV other equally approved standards
connections, connection to the medium voltage supply 2 The feeder pillar shall be a totally enclosed cabinet,
and low voltage distribution network and all other fully self-contained, dust proof, weather proof, vermin
accessories. proof and suitable for mounting outdoors exposed to dust,
rain and direct sunlight (IP55).
15.5.5 Basis of Payment
3 The cabinets shall be reinforced free standing
1 The amount of completed and accepted work structures, manufactured from 2mm thick steel with bolted
measured as provided for above will be paid for at the unit reinforced corner construction. They shall be of the dwarf
rate stated in the Bill of Quantities, which rate shall be type with a bolting down base for mounting on a pre-
considered full compensation for supplying and installing formed concrete pad suitably furnished for all incoming
the complete sub-station, including supporting poles and and outgoing cables from below ground level within a
platform, earthing, testing, connecting, putting into duct system.
operation, and for materials, labor, transport, equipment, 4 Cabinets shall have two hinged lockable doors to
tools, supplies and other items necessary for the proper provide full front access. The roof of the cabinets shall be
completion of the work as specified. slanted and have water drip edges.

15.5.6 Items in the Bill of Quantities


Moulded case Four pole, equipped with overload
i Pole mounted transformer sub-station, Circuit Breakers andshort circuit release mechanism
(…KVA), 33KV/415V/240V, 3-phase, 4-wire, MCCB’s comprising thermal and magnetic
(to IEC 60947-2) trips(IEC 60947-2 sequence III).
solidly earthed neutral, (Ref. as
Triple-pole, magnetic type , to
Contactors
shown on dwgs). (nr) interrupt an inductive load equal
(to IEC 60947-4-
to the indicated rating.
ii Pole mounted transformer sub-station, 1)
Utilization Cat. AC-5a and AC- 5b
(…KVA), 11KV/415V/240V, 3-phase, Fully insulated, rated 1.25 the main
4-wire, solidly earthed neutral, incoming molded case breaker frame
size at 50 degrees C, with three
(Reference as shown on drawings). (nr) Bus bars, 3 ammeters each fitted with maximum
phase + full demand indicator with associated
15.6 Feeder Pillars neutral current transformers, and voltmeter
with selector switch and protection
fuse.
15.6.1 Description PVC/PVC single core 1000 v grade,
Internal
1 This Sub-section describes requirements for with copper conductors, rated as
Cabling
required and suitably laced or clipped.
supplying, complete feeder pillar(s), installing, mounting,
Table 15.6.2.1: Feeder pillar fittings

♦ 15- 9♦
5 Feeder pillars shall be complete with equipment and welding silver alloy with arc quenching metallic devices of
fittings incorporating molded-case circuit breakers approved construction. Cable terminals shall be solderless
controlling the main supply and the outgoing circuits. anti-turn box lug or clamp type with set screws suitable
Feeder pillars shall have the fittings given in Table 15.6.2.1. for copper or aluminum cables.
6 Equipment, busbars, and conductors within the pillar 11 MCCBs generally shall be thermal-magnetic type for
shall be fully insulated such that there are no live parts or ratings below 600 A frame size, unless otherwise shown
connections exposed. The feeder pillar shall have a 50mm on the Drawings. MCCBs 600 A and larger shall be
x 6mm high conductivity copper main earth bar for electronic solid-state trip type. All circuit breakers shall be
grounding purposes. A distribution diagram showing 3-pole unless otherwise shown on Drawings.
circuit connections, MCCB ratings, cables sizes and 12 Thermal magnetic circuit breakers shall include, on
references shall be suitably fixed to the inside of the each pole, a bi-metallic inverse time-delay over-current
cabinet door. Feeder pillars shall be secured against trip element for small overloads and instantaneous
unauthorized access by means of wedge locks protected magnetic over-current trip element for operation under
by brass plugs and operated by a special key. short-circuit conditions. Circuit breakers 250 A frame size
7 A single phase socket outlet of 16-250 DIN rating and larger shall have adjustable instantaneous trips.
complete with plug top and a 12W fluorescent lighting
13 Thermal over-current trips shall be compensated to
fitting of the integral battery/inverter emergency type, with
allow for ambient temperature higher at breaker than at
switching facility to allow emergency light to be initiated
protected circuit or device. Compensation shall be
shall be mounted adjacent to the low panels and shall be
applicable between 25 and 50 deg. C. Where thermal
prewired at the factory.
settings are adjustable, range of adjustment shall not
8 Feeder pillars shall be finished with the following exceed maximum trip rating shown on the Drawings.
internal and external treatments:
14 When tripped automatically by over-current
i. De-rust. condition, operating mechanism of circuit breaker shall
ii. De-grease. assume an intermediate position clearly indicated by the
iii. One coat of sprayed zinc chromate primer. handle between on and off positions.
iv. Two coats exterior paint, dark grey to BS 381C
15 Circuit breakers 250 A to 600/630 A frame size shall
shade 632.
have interchangeable thermal and electronic trip units.
9 The low voltage distribution circuits serving the
16 Non-interchangeable trip circuit breakers shall have
street lighting installation shall be supplied through a
sealed covers. Circuit breakers with interchangeable trips
triple-pole contactor which shall be dual photo-electric cell
shall have trip unit covers sealed to prevent tampering.
controlled by two photocells connected and mounted in
parallel with a timer .as specified below. An override 17 Circuit breaker ratings shall be non-current limiting,
facility shall be provided for maintenance. fully rated (100%) with continuous duty at site conditions,
and with frame size and interrupting capacity to IEC 60947-
a) Contactors shall be, electro-magnetic type,
2, sequence III (rated ultimate short-circuit breaking
class AC 5a or AC 5b to IEC 60947-4, designed
capacity), and maximum trip rating as shown on the
to withstand large initial currents of discharge
Drawings. Interrupting capacities at specified voltage and
lamps or tungsten lamp loads respectively, and
frequency shall meet IEC 60947-2 test sequence I, II, III and
rated not less than overload setting of
IV for circuit breakers of utilization category B.
protective device upstream. Contacts are to be
double break, silver cadmium plated, having 18 Circuit breaker design shall allow addition of
self-cleaning wiping action. Control is to be electrical operator, control and interlocking functions,
provided by phase-neutral (maximum 240 V) under-voltage release, shunt-trip coils, alarm and auxiliary
split-coil, for on/off activation by local and/or switches, padlocking devices, key-lock devices, and the
by remote direct-wired means. Contactor is to like. Such accessories shall be provided where shown on
be mechanically latched. Control circuit is to the Drawings.
be fused. Auxiliaries are to include local pilot 19 The photo-electric control shall consist of omni-
lights, parallel remote indicating circuit, 2 N.O. directional cadmium cell thermal relay of high quality,
and 2 N.C. auxiliary contacts. employing solid state photo-variable conductance
10 Circuit breakers shall be totally enclosed, molded elements giving a 2:1 on/off ratio with sensitivity to switch
case, (MCCBs) constructed from high quality, high on lights when the daylight illumination reduces to 70 lux.
temperature resistant, tropicalized, moulded insulating This allows for the high pressure sodium lights striking
materials, for normal operation at 70 deg. C within time, taking into account of the rather fast rate of daylight
enclosures, to approved standards, provided with quick- intensity drop off in the region.
make, quick-break, trip-free switching mechanism The photo electric cells shall be mounted at the top of the
manually operated by front toggle type handle and nearest column or high mast or at the top of the feeder
automatically tripped under overcurrent conditions. Multi- pillar and connected to the feeder pillar.
pole breakers shall have common integral trip bar for 20 A solar dial time switch shall be of the quartz,
simultaneous operation of all poles. Contacts shall be non- electronic type, capable of operating for at least 100 hours

♦ 15- 10♦
in case of power failure. Timer shall be of settable type 15.6.4 Method of Measurement
once throughout the year and to be set at definite periods
1 Feeder pillars shall be measured by the number of
for switching on and off.
units supplied, installed, put into operation after testing
21 Instruments shall be housed in enameled, square, and acceptance by the concerned authority.
metal cases for flush installation. Scale and markings shall
be protected and sealed. Accuracy of instruments shall be 15.6.5 Basis of Payment
within 2% unless otherwise specified.
1 The amount of completed and accepted 'work
22 Voltmeters shall be the moving iron type, with centre
measured as provided for above will be paid for at the unit
zero adjuster, range 1.25 times nominal system voltage 90
rate stated in the Bill of Quantities which rate shall be full
degree angle, size 76x76 mm.
compensation for supplying, installing feeder pillar,
Voltmeter selector switch shall be 7-position rotary type. testing, putting into operation the pillar, and for labor,
23 Ammeters (Number = 3) shall be moving iron type, transport, material, equipment, tools, photo-electric cells,
with centre zero adjuster, range 2 times nominal circuit timer, supplies and other items necessary for the proper
amperage, 90 degree angle size 76x76mm. completion of the work as specified.
Ammeter selector switch shall be 7-position rotary type.
24 Current transformers, shall be suited to the nominal
15.6.6 Items in the Bill of Quantities
current of plant protected, short circuit level and burden. i Feeder pillar, (size, rating (A))
Current transformers shall be of the indoor dry type, rated
(No. of ways, type and reference)
secondary 5A. Rated primary current core size and
accuracy shall be determined from circuit data. (415/240V). (nr)

25 Voltage transformers shall be provided where


required, complete with primary and secondary fuses and
15.7 Electrical Cables
disconnecting device.
15.7.1 Description
26 The feeder pillar shall have a separate compartment
containing a three phase kWH meter. 1 This sub-section describes requirements for
27 Wiring supplying and installing cables into trenches or through
pre-installed ducts, including connecting, terminating and
i. Wiring shall be modular and neatly arranged on
circuit testing.
master terminal boards with suitable numbering
strips and appropriate cartridge type fuses where 2 The Contractor shall submit data for approval
required including, but not limited to, the following:
ii. Connections shall be made at front of terminal i. Constructional details, standards to which cables
board and with no live metal exposed. comply, current carrying capacities, derating
iii. Metal cases of instrument, control switches, factors for grouping and temperature.
relays, etc… shall be connected, by bare copper ii. Manufacturer's catalogue cuts.
conductors not less than 2.5 mm2 section, to iii. Dimensional and electrical characteristics.
nearest earthing bar. iv. Samples of each cable and wire and, if requested
iv. Control wiring shall be copper, PVC insulated, 85 by the Engineer, other accessories.
degrees C, 600V grade, and PVC sheathed v. Voltage drop calculations for each circuit in
cables. Finely stranded copper conductor, silicon schedule form.
rubber insulated cables shall be used in 3 Unless otherwise specified or shown on the
proximity to higher temperature components Drawings, cables and other feeders shall have copper
and as flexible cable. conductors. Cable conductors shall be stranded for
v. Wires shall be fitted with numbered ferrules of sections 4 mm2 and above, based on IEC 60228 Class 2.
approved type at each termination Signal and control cables shall have solid conductors
28 Anti-condensation heaters with disconnect switch unless otherwise specified. Flexible cords shall have
and pilot lamp shall be provided in feeder pillars finely stranded conductors. Conductors of single-core
controlled by thermostat and/or humidistat where cables 25 mm2 and above shall be compacted. Multi-core
required. cables 35 mm2 and above shall be sectoral shape.
4 Conductor sizes shall be as shown on the Drawings.
15.6.3 Construction Requirements Conductors with cross-sectional area smaller than
1 Construction requirements shall be as specified in specified will not be accepted.
Sub-section 15.3, Clause 15.3.3 for package substation 5 Wiring insulation shall be color coded or otherwise
work. identified as required by the applicable regulations as
follows:
Neutral: blue.
Protective earth: green-and-yellow striped.

♦ 15- 11♦
Phase colors: brown, black and grey as appropriate. 15.7.2.2 Medium Voltage (MV) Cables
6 Maintain color coding throughout installation.
1 Medium voltage cables, insulation and rating shall
Phase-conductors for which outer jacket is not color-coded
comply with BS 6622 and IEC 60502-2 for voltages up to 33
shall have engraved alphanumeric marks (L1, L2, L3) or
kV and IEC 60840 for voltages above 30kV up to 150 kV
color coded heat-shrinkable sleeves.
(Um=170 kV). MV cables shall be capable of a conductor
operating temperature of 90°C under worst ambient
15.7.2 Materials conditions at full load rating. Each phase shall be
15.7.2.1 Low Voltage Cables identified by a distinctive marking on the cable. The cable
insulation grade (voltage designation) and manufacturer
1 Unarmored cable shall be PVC insulated and shall shall be embossed on the cable over the sheath. The
comply with BS 6004. Conductors shall be not less than semi-conductive layer shall be removable without the use
2.5mm² cross section. of tools.
2 Single core PVC insulated (85 deg. C.) non-sheathed
2 MV cables shall be in accordance with the concerned
single conductor cables for wiring in conduit shall have
authority specification (MEW Standard OES 2 -
annealed copper conductors, compacted, generally with
Underground Cable Installations).
concentric strands and insulated with flame retardant,
moisture and heat resistant PVC/C to IEC 60227 and 15.7.2.3 Metal Gland Parts
IEC60332-1, suitable for wet locations and for conductor
temperature of 85 deg. C. 450/750 V grade. 1 Metal gland parts shall be brass, bright dipped, and
shall have a polychloroprene inner sheath, sealing ring,
3 Multi-core PVC insulated (85 deg. C.) cables (0.6/1
armor clamping cone, armor nut and captive
kV): shall have annealed, copper conductors, compacted,
polychloroprene outer sheath sealing ring. During
insulated with PVC/C to IEC 60227, moisture and heat
assembly the gland shall not induce torque in the cable
resistant, suitable for wet locations and fully rated
sheath or armor. A polychloroprene shroud shall be fitted
conductor temperature of 85 deg. C, laid up, bedded with
over the gland.
suitable filler and sheathed with flame retardant PVC/ST2,
general purpose sheathing to international standards (IS 15.7.2.4 Cable Trays
5831: 1984 and IEC 60502-1).
1 Medium cable trays shall be galvanized steel, flanged
4 Cables within lighting columns, high masts and
with heavy duty folded reinforced edge, and slotted. Cable
signs shall comply with BS 6004 and shall have separate
channel shall be galvanized steel.
PVC (green striped yellow) insulated earthing cable
installed. Cables for recessed lighting shall be 3 core
15.7.3 Construction Requirements
copper, utilizing one core for earthing.
5 Armored cable shall be PVC/SWA/PVC to BS 6346 or 1 Before any underground and ducted cabling is
BS 5467 and IEC60502-1, IEC 60811 and IEC 60332-1. installed, copies of the test certificates from the
Directly buried cables shall be armored type unless manufacturer shall be submitted to the Engineer for
otherwise indicated on the Drawings. approval. The certificate shall show that the supplied
cable satisfies the appropriate standards.
6 Armored cables shall have single layer of galvanized
steel wire armor with flame retardant PVC/ST2 over- The sizes of low voltage copper conductor cables shall be
sheath. Armoring shall comply with BS 1442 and shall as shown on the Drawings. Care shall be taken so that
provide 50% conductivity of phase conductor conductivity voltage drop at the far end of the cable does not exceed
as a minimum. 5% of the nominal voltage. Cables manufactured only by
reputed firms shall be used, provided they fulfill all the
7 Cable covers for underground directly buried cable
requirements of the Specification and the concerned
protection shall be to BS 2484, with sand cushion around
authority standards.
cable and a layer of 200 mm wide protective concrete
bricks over the sand along the entire route of the cable. 2 Cable joints and terminations shall be completed
The bricks shall be laid in such a way as to provide equal with the correct specified materials, tapes, stress cones,
margin of cover on both sides of the cable. A warning tape glands, sleeves and bonds. Joints shall be made in
shall be laid throughout the length of the trench. accordance with the cable manufacturer's
recommendations and BS 6910-1. No through joints shall
8 Cables shall be terminated at equipment
be allowed in low voltage cables where adequate
switchboards, and isolators, using mechanical cable
manufacturer's lengths are available.
glands, in accordance with the manufacturer's
recommendations. 3 A sample site-constructed cable termination and
through-joint shall be submitted to the Engineer prior to
9 Buildouts with cable lengths are required from
any jointing commencing on site.
designers.
4 Termination of cables shall be either crimped or
soldered. Through-joints shall be complete with

♦ 15- 12♦
manufacturer's recommended metal sleeves and shall be 2 Perform the following in advance of independent
located in a cable draw-pit tests:
5 For underpass luminaires PVC insulated, PVC i. Test cables insulation resistance.
sheathed, SWA cable shall be pulled through already ii. Test circuits continuity.
laid/buried uPVC ducts or conduits in underpass slabs or iii. Furnish a set of applicable specifications and
concrete structures. manufacturer’s recommendations to test
6 The pulling of cables through ducts or conduits shall organization.
be started only after the conduit (uPVC) system is iv. Make power available at test locations.
completely installed and all outlet boxes, junction boxes 3 Schedule tests and notify Engineer at least one week
etc. are fixed in position. in advance of schedule for test commencement.
7 The contractor where not in conflict with these 4 Provide megger testers of various ranges as
Specifications shall carry out the requirements and abide applicable, and HV test equipment as necessary for testing
where necessary with Series 1400 (Electrical Work for MV installations. Use 1000 V megger on installations with
Road Lighting and Traffic Signs) and Series 1500 nominal voltage over 500 V up to 1000 V, and 5000 V
(Motorway Communications) of the DMRB found under megger for initial checks on MV installations (up to 15 kV).
UK Standards for highways. 5 On installations of medium-voltage cables and before
electrical circuitry has been energized, demonstrate
15.7.3.1 Cable Jointing and Termination
product capability and compliance with requirements.
i. Through joints will not be allowed in feeder 6 MV Cable Testing: Provide cable test set with D.C.
cables where adequate manufacturer's lengths output voltage and ampere range sufficient to test MV
are available. Where a joint is necessary, it shall cables. Cables are to be laid in position (trench or duct
be made inside boxes, handholes or manholes. bank), jointed where applicable, but left uncovered, with
ii. Through joints and terminations shall be carried ends free of equipment and clear of ground.
out strictly in accordance with cable
7 MV Cable Testing: D.C. test voltage is to be applied
manufacturer's recommendations, and made
between core under test and the screen in steps, pausing
with correct specified materials, boxes, tapes,
one minute or more each step (first step being the A.C.
compounds or mixtures, stress cones, glands
rms rated voltage of the cable, followed by two equal
and bonds as applicable.
steps) up to maximum test voltage. At each step, and for
iii. Qualifications of operatives shall be submitted to
the last 5-15 minutes duration at maximum test voltage,
the Engineer prior to work commencing on site.
the ammeter (normally a micro-ammeter) is to be
Joints are to be filled with epoxy resin after
monitored closely and recorded. If, except as voltage is
taping unless contrary to cable manufacturer's
increased, the current starts to increase, test is to be
recommendations. Sample site constructed
stopped and the installation inspected and tested for the
cable terminations and through-joints shall be
fault.
submitted to the Engineer prior to commencing
work on site. Samples are to be constructed in i. Each cable/core is to be tested independently.
the presence of the Engineer and shall be Maximum D.C. test voltage for grounded neutral
available for test and inspection in accordance system is to be 3 times rated A.C. rms voltage of
with manufacturer's recommendations. cable.
iv. Cutting tools for jointing and terminating cables ii. Alternative test if approved by the Engineer, is to
are to be purpose made, to prevent damage to apply A.C. rms voltage up to 1.5 times A.C. rms
insulation in general, and to cable shielding of rating of cable (26 kV for 17.5 kV cable), applied
MV cables. for 15 minutes, by an approved A.C. test set.
v. Cleaning of lacquer on conductors shall be by Readings are to be within same range and in
use of non-scratch scouring sponge and white accordance with IEC 60502.
spirit or equal approved. iii. Replace or correct malfunctioning cables and
vi. Tighten electrical connectors and terminals, accessories at Project site, and retest to
including screws and bolts, in accordance with demonstrate compliance until reaching
manufacturers published torque-tightening satisfactory conditions as per international
values. Where manufacturer’s torque standards/ regulations; otherwise, remove and
requirements are not indicated, tighten replace with new units and retest.
connectors and terminals to comply with
15.7.3.3 Earthing
international standards.
1 The armoring on cables shall be bonded to the
15.7.3.2 Field Quality Control metalwork and to the earthing system in accordance with
1 Cable tests shall be carried out in accordance with the applicable regulations.
the requirements of the applicable regulations and 2 Shielded cable shall be earthed at terminations,
standards. splices and separable insulated connectors. Earth metal

♦ 15- 13♦
bodies of terminators, splices, cable and separable 15.8.2 Materials
insulated connector fittings and all hardware to be in
accordance with manufacturer’s written instructions. 15.8.2.1 Steel Masts and Columns - General

1 Steel Masts and columns shall be fabricated from


15.7.3.4 Protection
steel, in accordance with Section 6, and hot dip galvanized
1 Provide final protection and maintain conditions, in a to BS EN ISO 1461 (inside and outside) or in accordance
manner acceptable to manufacturer and installer, to with ASTM A123 and A385 to Engineers approval. They
prevent entrance of moisture into the cables and to ensure shall be in sections not less than 10m in length, and shall
medium-voltage cables are without damage or be joined on site by pressure over-lapping or slip joints
deterioration at hand-over. which shall have a minimum length of 1.5 times the
diameter of the joint. Columns up to 12m high shall be
15.7.4 Method of Measurement supplied in one piece.

1 Road lighting cable shall be measured in linear 2 The walls of columns shall be a minimum thickness
meters for each size and type of cable as shown on the of 3mm with a minimum ultimate strength of 370N/mm²
Drawings or as directed by the Engineer, installed in duct and a minimum yield strength of 240N/mm². Masts and
(excluding duct) or directly buried in trench (excluding columns over 13m in height shall have a minimum wall
trench), complete with required accessories, including all thickness of 4mm, a minimum ultimate strength of
types of cable jointing and terminations, accessories such 520N/mm² and a minimum yield strength of 360N/mm².
as clamps, channels, clips, connectors, tugs, tapes and any 3 Masts and columns when installed and fully
other item which is not stated above but is considered equipped, shall have safety factors in accordance with
necessary for completion of the work. Technical Report No. 7 of the Institution of Public Lighting
2 Underpass lighting cable shall be measured in linear Engineers (UK): 2003 or latest edition. They shall be
meters for each size and type of cable as shown on the capable of withstanding the gust wind velocity stated in
Drawings or as directed by the Engineer, complete with Clause 15.1.9 blowing in the most unfavorable direction at
required accessories including cable trays, pulling of cable a height of ten meters above ground level. The deflection
in already installed/buried conduit or uPVC ducts in slab, at the top of the mast or column shall not exceed 1/40 of
all type of jointing and terminations and any other item the height.
which is not stated above but is considered necessary for With a wind velocity of 198km/hr on the full projected area
completion of the work. of column, bracket and luminaire(s) a factor of safety of 3
3 The approved cable work shall be measured by the on minimum tensile strength shall be maintained and
linear meter of cable installed plus an allowance of 2m at horizontal deflection at lantern position shall not exceed
each end for termination and jointing. 1/40.

4 Trenches, ducts, warning tapes, and markers for 4 The Contractor shall submit to the Engineer detailed
cables are measured separately under Sub-section 15.17. manufacturer’s design calculation sheets and supporting
data to show that the masts and columns and foundation
15.7.5 Basis of Payment designs respectively are safe and meet the above
requirements. The submitted calculations shall include the
1 The amount of completed and accepted cable work following:
as provided for above will be paid for at the unit rates
i. The deflection at the top of the mast or column at
stated in the Bill of Quantities which rate shall be full
the designed wind speed.
compensation for supplying materials, installing, testing,
ii. The natural frequency of the mast or column.
putting into operation, and for labor, transport, equipment
iii. The critical wind speed for resonance.
tools, supplies and other work items necessary for the
iv. The damping characteristics of the mast or
proper completion of the work as specified.
column.
v. The steel stresses under resonant conditions.
15.7.6 Items in the Bill of Quantities vi. The value of acceleration at the top of the mast
i Electrical cable (type) (voltage) (size) (lin.m) or column under resonant conditions.
vii. Welding procedure details.
viii. Procedure details ensuring that the flange plate
15.8 Road Lighting Masts, Columns
is not laminated.
and Luminaires ix. Details of the joints between the mast or column
sections and between the bottom section and
15.8.1 Description flange plate.
1 This Sub-section describes requirements for supply, x. Details of the base compartment with the
erection upon prepared foundations and putting into method of reinforcement at the door area and
service road lighting masts and columns complete with means adopted for making the door
operating mechanisms, brackets, luminaires, control gear weatherproof and tamper-proof.
and cabling.

♦ 15- 14♦
All the above shall be submitted for approval by the terminals, and for incoming and outgoing 3 phase 4 wire
Engineer before manufacturing commences. cable. Terminal blocks shall be high temperature, non-
Delivery shall not be done until factory tests are inflammable, non-toxic material with high quality fixing
completed to the satisfaction of the Engineer. screws and individual terminal for each termination.

5 A hot dip galvanized steel flange base plate of 4 One circuit breaker, single pole 15 A shall be
sufficient (20mm minimum) thickness, free from provided for each phase leading to a luminaire. Circuit
laminations, shall be welded to the base of the mast or breakers shall be compensated and rated for 50 deg. C
column, fully developing the strength of the section. ambient temperature with interrupting capacity as
Supplementary gussets shall be provided between the specified under other Sub-sections of the Specification,
bolt holes drilled in the flange, if necessary. The underside and shall be mounted in weatherproof enclosure at
of the flange and the inside of the pole to a height of baseboard. Wiring shall be PVC insulated 3 core or 4 core
500mm shall be painted with bitumen. The outside of the 85 deg. C conductor temperature. Cable shall be at least 4
pole and the flange if under ground level shall also be mm² copper conductor.
painted with bitumen up to ground level.
15.8.2.3 Steel High Masts
6 A door shall be provided in the masts and columns to
permit access to the circuit breaker assembly, junction box, 1 Masts shall be of the height specified on the
and winch (where provided) mounted on a backboard Drawings, hot dipped galvanized of multi-sided cross-
made of durable non-hygroscopic material. The door shall section with a continuous taper made of formed sheet
be weatherproof and fitted with a heavy duty lock. A steel, electrically welded. They shall be delivered to site in
stainless steel 12mm diameter earthing bolt shall be sections and be the slip joint type. Masts shall be
welded inside near the access door. assembled on site by means of pressure over-lapping or
slip joints which shall have a minimum length of 1.5 times
7 Where indicated on drawings and covered in the
the diameter of the joint. Site welding will not be allowed.
BOQ. masts and columns shall be painted with two (2)
coats of epoxy resin paint to an approved color or high 2 The luminaire rings or brackets shall be constructed
gloss finish as required by the Concerned of galvanized steel in accordance with Section 6. Where
Authority/Engineer. necessary, they shall be in two halves joined by bolted
flanges to permit removal. For masts with a moveable
8 The Contractor shall produce a certificate from a
luminaire ring, rollers with a serf canting mechanism shall
structural engineering authority that columns and masts
be provided made of water resistant non-marking material
meet the above requirements. In addition, an agreed
with oil-impregnated bronze bushings.
official testing authority’s certificates shall be presented to
guarantee the life-time and resistance of the products 3 The weatherproof wiring chambers shall have
under worst climatic conditions. terminal blocks, neutral bars, grounding bolts for electrical
connections, and facilities on the luminaire ring to allow
9 The Contractor shall submit a guarantee from the
testing of luminaires while in the lowered position.
manufacturer stating that the design lifetime of the
Cabling shall be in accordance with Sub-section 15.7. The
columns and masts is a minimum of twenty five (25) years
high mast cables shall conform to Technical Report No. 7
after installation under the worst site conditions in Oman.
as given in Paragraph 15.8.2.1, Item 3.
If any column or mast or any part thereof fails within the
guarantee period, subject to corrosion, the Contractor 4 The luminaire raising and lowering lead assembly if
shall replace them free of charge. Without this guarantee fitted shall be manufactured of non-corrosive metals and
the lighting columns and/or masts will not be the operating cable sleeves shall be enclosed and run on
approved/accepted. stainless steel shafts. The luminaire ring or bracket shall
be supported by a 3-cable winching system. Flexible
15.8.2.2 Steel Columns stainless steel stranded aircraft cables entirely suitable for
the application, with factor of safety 5 times safe working
1 Columns shall carry either single or double
load of the winch, shall support the luminaire ring
luminaires or any combination up to six luminaires as
assembly. Nylon or similar stops installed on the steel
shown on the Drawings and shall be of circular cross
cable shall support the luminaire ring assembly in extreme
section. Any special requirement for octagonal cross
lower position to within 900 mm above the base of the
section will be shown on Drawings or in design schedules.
mast. Provisions shall be made to prevent the power cable
2 The luminaires shall be rigidly fixed and bolted to the from winding around the steel hoisting cable.
column or column arms to prevent wind rotation or Arrangements shall be provided for the electricity and
vibration. support cables to be separated before passing over their
3 Columns with one or two luminaires shall be respective pulleys, and close fitting guides shall be
connected over one phase and neutral. Columns with provided so that the cables cannot disengage from the
three or more luminaires shall be connected over 3 phases pulleys during operation. A steadying system shall keep
and neutral, unless otherwise shown on the Drawings. the luminaire ring in the correct top position preventing
Bolted terminals and cable lugs of the sizes shown on rotation around its vertical axis.
Drawings shall be provided with 3 phase and neutral

♦ 15- 15♦
5 Winching systems shall have a lifting capacity of at zone of protection for the mast head frame and luminaires.
least double the weight of the luminaire ring assembly The terminal shall be bonded to the mast to ensure the
and shall be fitted with an approved safety system to discharge is dissipated via the earth and ground terminal
control the ring assembly in the event of a suspension without damage to the steel winch cables or electric cable.
cable failure.
15.8.2.4 Glass Reinforced Polyester (GRP) Columns
6 Winches shall be capable of normal operation using
either a portable power tool or by hand, and shall 1 This specification is for columns applicable to coastal
incorporate a torque limiter which can be adjusted and roads in general, where heights of 4m to 14m are required
locked. Winches shall be self-sustaining without brakes or and as shown on layout drawings.
clutches which require maintenance and shall be totally 2 GRP columns shall be manufactured by the
enclosed and self-lubricating. centrifugal casting process and shall withstand wind
7 Termination of winch cables shall not involve speeds up to 220km/hr.
distortion or twisting of the cable structure. One full layer 3 GRP columns shall be highly resistant to impact,
of turns shall remain on the drum when the luminaire ring deflection and bending, and shall be highly safe in case of
is fully lowered or alternatively the drums shall be a collision, fire resistant (using special resins), electrically
grooved to ensure a tidy cable lay. non-conductive and safe without grounding.
8 The head frame shall be covered by a shaped 4 GRP columns shall be corrosion proof, resistant to
protective aesthetic canopy as shown on the Drawings chemical reactions, with UV protection against
and designed to give a coordinated appearance of head weatherability and shall have a guaranteed lifetime of 25
frame with the luminaire ring when the latter is in the years. A reinforced lockable hinged access door of
raised position. minimum height of 300mm at a height from ground level
9 Two red aircraft obstruction lights within cast of 600mm shall be provided.
aluminium bodies shall be fitted at the top of each high 5 The columns shall be either of the burial type or the
mast attached to the luminaire ring and arranged to flanged base type, with suitable cable access as shown on
project through the canopy. A transformer and relay shall drawing/details. Flanged base plates shall be of galvanized
automatically connect the second lamp in the event of steel equal in construction to flange plates used on steel
lamp failure. columns (15mm to 20mm thickness) with four anchor
10 High mast distribution equipment shall be mounted bolts and convenient cable entry, bitumen coated on the
in a weatherproof enclosure on the baseboard of the lower inside and outside. Pigment color range shall be
compartment of the high mast and shall comprise a back submitted with the proposal and color shall be selected by
plate chassis complete with: the Engineer before approval is granted on the
i. 1 x 60 Amperes triple pole main incoming manufacturer.
molded case circuit breaker (MCCB) and neutral 6 Standards for GRP columns shall be as follows:
assembly for luminaire circuits. i. Specific Gravity: 1.65 Kg / dm3 (UNI 7092/72)
ii. 1 x 20 Amperes single pole MCCB and neutral ii. Glass Fiber Content (% by weight): 45-55 %
assembly for each luminaire circuit. iii. Water Absorption: 0.5 % (UNI ISO 62)
iii. 1 x 15 Amperes single or triple pole MCCB and iv. E-Modulus: 22000 ± 2000 MPa (UNI 5819/66)
neutral assembly connected to the incoming v. Tensile Strength: 400 ± 50 MPa (UNI 5819/66)
supply and serving a 16A-250V DIN or 16A-415V vi. Flexural Strength: 350 ± 50 MPa (UNI 7219/73)
DIN socket outlet complete with 3-pin plug to suit vii. Compressive Strength: 200 ± 50 MPa (UNI
the raising and lowering mechanism. 4279/72)
iv. A multi-pin plug and socket outlet with guard viii. Impact Strength: > 180 kJ / m2 (UNI 6062/67)
ring. ix. Dielectric Strength: 3 – 7 kV / mm (UNI 4291/72)
11 The breakers shall be designed, manufactured and x. Surface Insulation Resistance: 1010 – 1013 (UNI
tested in compliance with IEC 60947-2 sequence III, 4288/72)
calibrated at 50 degrees C. The breakers shall have xi. Thermal Conductivity: 0.2 – 0.3 kCal / m⁰C (UNI
interrupting capacity exceeding 10 kA. 7891)
12 The 16A-250 V or 16A-415 V socket outlet for supply xii. Coefficient of Linear Expansion: 15 – 17
to the portable raising and lowering power tool shall be 1/(⁰C*106) (UNI 6061/67)
connected to the MCCB via a flexible connection to ensure xiii. Temperature Class: F
accessibility. xiv. Overall Length: 3 – 14 m
xv. Top Diameter (3 – 7 m poles): 60 mm
13 Each high mast supplying ground sign lighting shall
xvi. Top Diameter (8 – 14 m poles): 94 mm
be equipped with an additional 15 amp circuit breaker to
xvii. Conicity (slope to determine the bottom): 18 mm
supply the sign lighting installation. The circuit breaker
per linear meter length
shall be installed inside the mast distribution box.
xviii.Steel fortification (at the top): required
14 Masts shall be equipped with a lightning protection xix. Steel base plate: optional
air terminal of the correct height to provide the required xx. GRP base plate cover: available

♦ 15- 16♦
7 Tests and approvals for GRP columns shall conform 6 Luminaire protectors shall be heat and shock
to the following Standards: resistant glass, mounted into suitable frame assembly
i. General Outdoor Lighting Pole Specifications: fixed to body by captive screws, and secured by extra
ASTM – D4923-01 safety clamps to allow replacement of protector and
ii. Tensile Strength: DIN EN ISO 527-2 reflector, for maintenance purposes without danger of the
iii. Elongation: DIN EN ISO 527-2 cover falling to the ground. Ozone resistant ethylene
iv. Flextural Test. (bending): DIN EN ISO 14125 propylene or approved equivalent rubber shall ensure
v. Impact Bending Test: DIN 53435 sealing of the front glass, to maintain the required degree
vi. Rate of Burning: ASTM – D635-03 of protection IP65.
vii. Dielectric Breakdown Voltage: ASTM – D149-97a 7 Lamp sockets shall be high grade porcelain, mounted
viii. DC Resistance: ASTM – D257-99 in support brackets with provision to adjust lamps
ix. Outdoor Weathering: ASTM – D1435-99 vertically and axially. Lamp support and locking system
8 Mechanical properties for GRP columns shall shall grip and prevent lamp movement in operation.
conform to the following Standards: 8 Ballast and control gear shall be mounted in
i. Tensile Strength: DIN EN ISO 527-2 luminaire in separate compartment isolated to protect the
ii. Elongation at break: DIN EN ISO 527-2 electrical accessories from the direct radiant heat emitted
iii. Bending Strength: DIN 53390 by the lamp, and with enclosed terminal blocks fitted with
iv. E-modulus: DIN EN ISO 14125 quick-disconnect electrical leads. Where required, control
v. Impact Strength: DIN 53435 gear shall be contained in the prewired box, having an
enclosure of IP 54, and mounted on luminaire ring
15.8.2.5 Road Lighting Luminaires and Lamps separately from luminaires.

1 Luminaires shall be of the totally enclosed type, 9 Control gear shall be plug in type for operation at 240
complying with IEC 60598-1, IEC 60598-2-1, and IEC 60598- V, A C. single phase, 50 Hz. Ballast shall be tropicalized
2-3 (or latest version), dust protected and splash proof, class H insulated, specially selected for particular type of
divided into two compartments. The first compartment lamp used, and lamps shall be able to start with at least +/-
shall be protected by clear glass or acrylic polycarbonate 10% variation of nominal voltage and continue in normal
sealed to the frame and hinged and shall house the optical operation with dips attaining 20% for four seconds.
system with polished and anodized pressed aluminum Control gear losses shall not exceed 10% of normal lamp
reflector, conforming to at least degree IP 66 of IEC 60529, wattage. RFI suppression device shall be provided. Refer
under all operating conditions. The second compartment to CISPR. Power factor shall be compensated to at least
shall consist of the electrical accessories (control gear), 0.9 lagging or better.
cable feed terminals and side entry mounting socket to at 10 Control gear (choke, capacitor, ignitor, etc.) shall be
least IP 54. suitable to stand up to 85 degrees C. ambient temperature
2 Luminaires shall be shock resistant and specially of the enclosure.
designed to house required lamps, electrical gear and 11 Internal connections shall be with high quality heat
accessories. Body shall be corrosion resistant, extruded, resistant wire insulated for 105 deg. C and with porcelain
pressure die-cast or fabricated aluminum alloy, optically connectors. Control gear shall comply with the IEC 60947-
sealed, mechanically strong and easy to maintain. 3 or relevant equivalent British Standard specification or
Luminaire housing made from glass reinforced plastic or other acceptable International equivalent.
other synthetic material shall not be acceptable. 12 HRC fuse cartridges, suitably rated and conforming
3 Luminaire bodies constructed of fiber reinforced with IEC 60269, shall be provided, complete with base, for
polyester or pressed aluminum may be accepted subject protection of the luminaire. Fuse shall be rated to
to approval of the Engineer and the quality of the product withstand starting current and shall be preferably located
and its resistance to heat from direct sunlight and/or heat in control gear enclosure.
emitted from the lamp/control gear. The decision of the 13 Terminal blocks shall be of the suitable screw-tunnel
Engineer in this respect is final and not subject to type, clearly marked with arrangement to facilitate
discussion. maintenance, quick replacement and easy disconnection
4 Exposed metal parts of luminaires shall be factory of individual components.
finished, stove enamelled, with suitable corrosion 14 Types of lamps are to be as follows:
resisting paint capable of resisting heat emitted by lamp a) High pressure sodium lamps shall be type
during continuous operation, and under full sunlight SON-T (tubular), in accordance with IEC60662
conditions. Color shall be agreed with the Engineer. for dimensions and characteristics, and IEC
5 Mirror reflectors shall be single piece, with 99.5% 62035 for safety, with guaranteed average
purity, anodized and glazed aluminium or die cast with rated life (down to 80% output) above 12,000
super-purity aluminium vapor-deposited, and coated with hours, and having initial luminous output equal
transparent layer of silicon protection against wiping. to or above the following:

i. 16500 lumens for 150 W lamps.

♦ 15- 17♦
ii. 31500 lumens for 250 W lamps. and to the luminance and illuminance results achieved.
iii. 55000 lumens for 400 W lamps. The decision of the Engineer in this respect is final and not
iv. 135000 lumens for 1000 W lamps subject to discussion.
17 Luminaires shall provide a distribution generally in
b) High pressure mercury vapor lamps shall be to accordance with IEC 60598-1, IEC 60598-2-2, IEC 60598-2-3,
IEC 60188, and shall include quartz discharge cut-off or semi-cut-off classification, as required by the
tube in an internally coated ovoid outer tube. design standards for type and class of road.
Coating shall be ytrium vanadate phosphur
with color temperature of 3300 deg. K. 15.8.2.6 Flood Lights
Guaranteed rated life (down to 80% output)
1 Flood lights shall be totally enclosed type, weather,
shall be above 8000 hours and initial luminous
dust and shock resistant, IP 65 to IEC 60529, and shall
output above the following:
conform to the requirements and types shown on
i. 3800 lumens for 80 W lamps drawings or be of approved equal make.
ii. 6500 lumens for 125 W lamps 2 Housing shall be of high pressure die-cast aluminium
iii. 14000 lumens for 250 W lamps. alloy, closed on front by hinged framed glass protector
highly resistant to thermal and mechanical shocks, and set
c) Metal halide lamps shall comprise quartz
in position by at least eight heavy duty stainless steel
discharge tube enclosed in clear tubular hard-
spring clamps with silicon rubber sealing gasket.
glass outer bulb, operating on same principle
Enclosure shall be in accordance with IEC Publication
as all gas discharge tubes with iodide additives,
60598-2-5.
indium, thalium and sodium in the mercury
discharge, to increase intensity in three 3 Reflectors shall be high purity (over 99% reflectance)
spectral bands; blue, green and yellow-red with anodized aluminium, secured in precision aligned internal
high color rendering. Lamps up to 150 W shall tracks to provide beam distribution required.
be provided with electronic ballast. Lamps shall 4 Connection box shall be located at rear of floodlight
be to IEC 61167 with E40 base. Guaranteed 2
body with gland connections to accept 4 mm PVC/PVC
average life shall not be less than 10000 hours three core cables. Lamp and control gear shall be
and luminous outputs, after 100 hours burning, mounted in two separate and isolated compartments.
shall be above the following:
5 Control gear shall be plug-in type, 240 V, 50 Hz,
i. 32500 lumens for 400 W lamps power factor compensated to at least 0.9 lagging. Ballasts
ii. 90000 lumens for 1000 W lamps and ignitors shall be of type specially adapted for make of
iii. 190000 lumens for 2000 W lamps lamps selected. Ignitors shall be electronic thyristor type.
Lamp shall be able to start with at least +/-10% from line
d) Low pressure sodium lamps shall be type SOX voltage, and with normal operation dips up to 20% for four
or SOX (E) and shall conform to IEC 60192:2001, seconds. Compensation shall ensure that there is no large
with guaranteed average life above 18000 hrs increase in operating current during starting. Control gear
and having initial luminous output equal to or losses shall not exceed 10%. Cables for internal wiring in
above the following: control gear compartments shall be single core 2.5 mm2
SOX type: copper conductors with suitable high temperature
insulation and sheath.
i. 4800 lumens for 35W lamp
ii. 8100 lumens for 55W lamp 6 Exposed metal parts of floodlights shall be painted
iii. 13500 lumens for 90W lamp with corrosion and heat resistant paint, resisting operating
iv. 22500 lumens for 135W lamp temperatures attained in direct sunlight while lamp is
v. 33000 lumens for 185W lamp burning.
7 Floodlights shall be located as shown on the
SOX E type:
Drawings and mounted on specially designed brackets to
i. 1800 lumens for 18W lamp allow swiveling in any desired direction and locking firmly
ii. 3600 lumens for 26W lamp in final position. Protractor scale shall be provided for
iii. 5800 lumens for 36W lamp accurate setting.
iv. 10500 lumens for 66W lamp 8 Bolted earthing terminal shall be provided in each
v. 17000 lumens for 91W lamp fitting.
vi. 26000 lumens for 131W lamp

15 Permissible base temperature shall not be greater 15.8.3 Construction Requirements


than 250 deg. C, and maximum bulb temperature not 1 Lighting masts/columns shall be handled,
greater than 550 deg. C. Lamp burning position for 2000 transported and erected in such a way so as to avoid any
W, 240 V lamp is to be possible up to 75 degrees. damage. Any damage to pole or galvanizing shall be made
16 Multi-piece mirror reflectors may be accepted subject good to the satisfaction of the Engineer.
to satisfaction of the Engineer of the quality of the product,

♦ 15- 18♦
2 The lighting masts/columns shall be stored clear of into operation, and for erecting material, labor, equipment
soil, ground water or other rust producing materials. The tools, supplies and other work items necessary for the
fixing of poles shall be carried out in accordance with proper completion of the work as specified.
manufacturer’s instructions and good engineering practice.
3 Masts/columns shall be bolted to concrete bases 15.8.6 Items in the Bill of Quantities
constructed in accordance with Sub-section 15.17 and i. High mast assembly (type) (height) (No
erected in accordance with the mast manufacturer's and type of luminaires) (reference dwg.) (nr)
instructions. The column or mast shall be vertical to within ii. Lighting columns (type) (number
0.1% of its height. Final setting and adjustment of the of arms) (height) (type of luminaire)
luminaires shall be carried out after the masts are erected (reference drawing.) (nr)
and operational. iii. Column/high mast testing (Lump Sum)
4 The Contractor shall be responsible until final hand-
over for correcting the alignment of any column or bracket 15.9 Sign Illumination
to its original position except where it is due to vehicle
impact.
15.9.1 Description
5 Where lighting columns/masts are to be installed in
the vicinity of overhead power lines, the Contractor shall 1 This Sub-section describes requirements for
inform the Engineer and act as directed. He shall maintain supplying, installing and putting into operation the
clearances from the power lines as the Concerned illumination of overhead and roadside signs where shown
Authority’s requirements. on the Drawings or directed by the Engineer.

6 Masts/columns shall be erected to the height and


15.9.2 Materials
with the luminaires as shown on the Drawings. Each
luminaire shall house the required lamp oriented to give 1 Luminaires where used to illuminate signs shall be
the illumination and luminance on the road surfaces as wide angled floodlights of the totally enclosed type
stated in Clause 15.1.15, (3) and Table 15.1.15.1. conforming to IEC 60598-1, -2-5( Luminaires – Floodlights)
7 Luminaires on columns shall be aligned parallel with and BS EN 12899-1:2001 (Fixed Vertical Road Traffic Signs,
the longitudinal profile of the road and set at 90° to the Fixed Signs). The body of the floodlight shall be
centre line. composed of an extruded aluminum alloy box closed on
the front by a protector of vandal resistant glass. The
8 High masts incorporating mobile luminaire rings
protection rating shall be IP 65 to IEC 60529.
shall be capable of supporting a portable personnel cage
for maintenance. The Contractor shall provide the cage 2 The lamp and control gear shall be mounted in two
which shall be capable of safely carrying two persons plus separate compartments. Alternatively, the control gear
servicing equipment. may be housed remotely. Power factor compensation
shall be 0.9 or better.
9 The Contractor shall number all the columns/masts
with high quality paint using stencil for 50mm high 3 Photo-electric control units shall be of the plug-in
lettering. The numbering shall be at 1200mm from the type. The control unit losses shall not exceed 10% of the
bottom of pole towards the road. The numbering shall be nominal lamp wattage. A device shall be provided for the
in a manner as directed by the Engineer. suppression of radio and television interference to CISPR
15 requirements.
15.8.4 Method of Measurement
15.9.3 Construction Requirements
1 Each type of high mast assembly and lighting
column shall be measured separately and shall include 1 The signs shall be adjusted and set correctly relative
brackets luminaires/ floodlights, lamps, terminal blocks, to the vertical plane and the road axis before the electrical
circuit breakers and switchgear, internal wires and cabling, installation work is started. Floodlights and associated
control gear, obstruction lights (if needed), and earthing, fixings shall not obstruct the sign face viewed from the
cable entries, mounting brackets/arms, complete as road. Screening shall be added to the top or bottom
specified, erected, tested and put into operation. edges of the sign to prevent glare to oncoming traffic.

2 Testing of high masts and lighting columns, at the 2 Sign supports and gantries are specified in Sub-
factory and on Site, is given as an item, to cover for all section 14.1.
tests and reports and test certificates. 3 Overhead gantry or cantilever sign lighting shall be
located and mounted as shown on the drawings.
15.8.5 Basis of Payment Mounting shall be provided for each floodlight allowing it
to be swiveled in any direction and locked.
1 The amount of completed and accepted work
measured as provided for above will be paid for at the unit 4 Feeder cable shall be routed via a duct in the
rates stated in the Bill of Quantities which rate shall be full supporting frame or gantry up to platform height and
compensation for supplying, installation, testing, putting terminated into a non-automatic isolator switch. A circuit

♦ 15- 19♦
breaker board within the enclosure shall distribute power accessories. Body shall be one piece extruded aluminium
to the individual floodlights. (magnesium - silicon alloy) having a wall thickness of not
5 Roadside sign lighting shall be as described in Items less than 2.5 mm.
3 and 4 above, but with the adjustable mountings on top 2 Exposed metal parts of luminaires shall be factory
of support poles. The poles shall be positioned 1.8m in finished, stove enamelled, with corrosion resisting paint
front of the signs and parallel with the sign face and shall capable of resisting heat emitted by lamp during
be checked and shimmed to be perpendicular before continuous operation. The whole assembly shall be
tightening down. treated against corrosion by anodizing the aluminium.
6 The cable from the sub-station or feeder pillar shall 3 Mirror reflectors shall be 99.5% purity, polished
be routed into the pole via the duct in the base and looped aluminium reflectors and coated with transparent layer of
into a circuit breaker located behind the pole access cover. silicon protection against wiping.
7 Lighting where required for signs located in 4 Control gear shall be mounted on a "plug-in" type
sidewalks in urban areas shall be mounted on the top of control gear tray, and shall be housed in a self contained
the sign supporting poles, projecting in front of the top sealed box.
edge of the sign and braced. 5 Earth wire shall be connected through the plug and
8 The earth of the cables shall be bonded to the earth socket connector to ensure that the earth potential is
terminal of each enclosure. maintained on the gear tray when it is being removed
from the luminaire for maintenance purposes.
15.9.4 Method of Measurement 6 Luminaires shall have a hinged front glass with at
1 Each type of overhead or roadside lighting assembly least 2 hinges assembly which shall comprise a clear
shall be measured separately by the number of complete toughened glass plate, not less than 5.0 mm thick, capable
floodlight installations supplied, erected and put into of swinging to the vertical position. The front glass
operation, complete with lamps, supporting steel work, assembly shall seat on to a neoprene non rotting type
switchgear, control gear, interconnecting cables and gasket and once seated shall provide the required degree
earthing as necessary. of protection. Glass used shall be shatter proof (of the type
which once broken, no part of the glass will fall on the
15.9.5 Basis of Payment carriageway). Each luminaire shall have an HRC fuse for
protection.
1 The amount of completed and accepted work 7 Luminaires shall be complete with their mounting
measured as provided for above will be paid for at the unit
accessories and shall be supported from uni-strut
rates stated in the Bill of Quantities which rates shall be
galvanized steel channel fixed to the soffit of the bridge.
full compensation for supplying, installation, testing, Fixing details shall be submitted to the Engineer for
putting into operation, for materials, labor, transport,
approval.
equipment tools, supplies and other work items necessary
8 Lamp sockets shall be high grade porcelain, mounted
for the proper completion of the work as specified.
in support brackets with provision to adjust lamps
vertically and axially. Lamp support and locking system
15.9.6 Items in the Bill of Quantities
shall grip and prevent lamp movement during operation.
i. Overhead sign lighting (gantry or cantilever) 9 Ballast and control gear shall be mounted in
(reference drawing.) (nr) luminaire in separate compartment isolated from the lamp
ii. Roadside sign lighting (sign ref. no.) and with enclosed terminal blocks fitted with quick-
(reference. drawing.) (nr) disconnect electrical leads. Where required, control gear
shall be contained in the prewired box, having an
15.10 Under Bridge Lighting enclosure of IP 65, and mounted on luminaire ring
separately from luminaires. Control gear shall be plug in
15.10.1 Description type for operation at 240 V, A.C. single phase, 50 Hz.
Ballast shall be specially selected for particular type of
1 This Sub-section describes requirements for
lamps used, and lamps shall be able to start with at least
supplying, and installing under bridge surface luminaires
+/-10% variation of nominal voltage and continue in
and/or recessed lighting in prepared cutouts such as in
normal operation with dips attaining 20% for four seconds.
concrete structures.
Control gear losses shall not exceed 10% of normal lamp
wattage. RFI suppression device shall be provided. Power
15.10.2 Materials factor shall be compensated to at least 0.9 lagging.
15.10.2.1 Surface Mounted Luminaires 15.10.2.2 Recessed Mounted Luminaires
1 The fitting shall be totally enclosed, dust and jet
1 Luminaires shall comply with IEC 60598-1, IEC 60598-
proof, conforming to at least IP65 of IEC 60529, and 2-2, and IEC 60598-2-3
conforming with IEC 60598-1, shock resistant and specially
designed to house the required lamps, electrical gear and

♦ 15- 20♦
2 Luminaires shall be recessed flush mounted 15.11 Traffic Signals
weatherproof type including lamps, a frame for the
concrete opening and a housing for the control gear. 15.11.1 Description
3 The luminaire body shall be made from epoxy 1 This Sub-section describes requirements for the
powder coated galvanized sheet steel or from extruded or design, supply, installation, commissioning and
pressure die-cast corrosion resistant aluminium alloy. monitoring/review of traffic signal installations and all
Aluminium shall be anodized and painted grey. associated signal equipment.
4 Luminaires within 4m of finished ground level shall 2 The terms used are as defined in the Highway Design
be vandal resistant. Standards.
5 The luminaires shall have a hinged front glass
assembly of prismatic toughened glass, not less than 15.11.2 Materials
6.5mm thick, fixed and sealed into a metal frame which
15.11.2.1 General
shall have a rapid closing device They shall be fitted with
'trimming plates' to provide a flush appearance. 1 The equipment shall function satisfactorily for an
6 The protection rating shall be IP65 to IEC 60529 for all input voltage of 240v ±15% and input frequency 50Hz ±4%.
luminaires in the underside of bridge superstructures and If required a form of automated stabilizer shall be
luminaires in walls. incorporated.
7 The optical system, electrical control gear and lamp 2 All signal equipment should be suitable for operation
shall be mounted on a 'plug-in' type reflector gear tray. in the climatic conditions of Oman. The equipment should
The ground wire connection shall be taken through the be operational between -15°C and +60°C, and resistant to
plug and socket connector. dust/sand contamination. A minimum of 5 years operation,
with routine maintenance, should be expected from any
15.10.3 Construction Requirements installed equipment.
3 The equipment shall comply with the requirements
1 The luminaire shall be fixed surface mounted or flush
of the Highway Design Standards for timings, signal
with the concrete surface into a preformed non- corrodible
sequence and associated detectors.
framed opening as pertaining to the lighting unit specified.
4 All signal equipment shall comply with the
2 Wiring shall be ducted in conduits embedded in the
interference limits given in BS EN 55015:2006 (Limits and
structure or hidden from view within the structure and
Methods of Measurement of radio disturbance
shall loop in and out of conduit boxes serving the
characteristics of electrical lighting or similar equipment).
luminaires.
15.11.2.2 Controllers
15.10.4 Method of Measurement
1 Controllers shall be fully programmable and modular
1 Each type of lighting assembly shall be measured in design to allow the replacement of faulty components
separately by the number of lighting units (luminaire, or the addition of extra circuit boards and features as and
lamp, control gear, terminal blocks) supplied, installed and when required.
put into operation.
2 Controllers should have at least the following inbuilt
modes of operation available for use:
15.10.5 Basis of Payment
i. Manual
1 The quantity of completed and accepted work
ii. Fixed time
measured as provided for above will be paid for at the unit
iii. Vehicle actuated
rates stated in the Bill of Quantities which rate shall be full
iv. Urban traffic control
compensation for supplying, installing, testing and putting
v. Pedestrian fixed vehicle period
into service, and for materials, labor, equipment, tools,
vi. Pedestrian vehicle actuated
supplies and other work items necessary for the proper
vii. Bus/light rail transit priority
support and completion of the work as specified.
viii. Part-time
ix. Cable-less linking facility
15.10.6 Items in the Bill of Quantities x. Hurry call
i. Under bridge surface mounted luminaire xi. Emergency priority
(type) (reference drawing.) (nr) xii. Standby software flash mode
ii. Under bridge recessed lighting luminaire
(type) (reference drawing) (nr) 3 Controllers shall utilize solid state lamp switching
cards, with a maximum load per lamp switch card of 20A.
The switch cards should be able to support both ELV and
LV configurations.
4 Standard 240v Low Voltage (LV) Controllers:

♦ 15- 21♦
i. Shall be able to support between 24 and 36 require manual on-site intervention of a maintenance
phase outputs, arranged on up to 4 separate engineer before normal operation is resumed.
phase driver cards, used as required. 15 The controller shall have a fused master switch to
ii. Shall be able to support dimming facilities of isolate the controller. This fuse shall be of a rating
120v, 140v or 160v RMS. calculated from the cumulative load of all signal
iii. Each output lamp switch shall be able to support equipment attached to the controller and done on a site by
a 4A load, with a maximum total lamp load on site basis. A fault on any signal circuit shall not cause
the controller of 20A - 30A. damage to the controller.
16 The electrical supply to the controller shall have its
5 Extra Low Voltage (ELV) controllers:
own fused system which should not be isolated by the
i. Shall be able to support between 24 and 36 controller switch.
phase outputs, arranged on up to 6 separate 17 It shall be possible to isolate all signal lamps by use
phase driver cards, used as required. of a switch and fuse whilst retaining supply to the
ii. Each output lamp switch shall be able to support controller.
a 2A load, with a maximum total lamp load on
18 Controller cabinets shall be housed in weather
the controller of 20A - 40A.
resistant, dust resistant corrosion resistant cabinet. The
iii. Shall have a lamp supply voltage of 48v RMS
front of the cabinet shall have a full length locking door to
with a signal dimming option of 27.5v RMS
allow access to the control equipment. A swing frame
shall be provided to allow access to the rear wiring of
6 Controllers shall provide visual displays of the components. Smaller flap doors can be used to give
current mode of operation and current stage / timings. access to manual panel, telecommunication and electricity
7 Controllers shall have the facility to allow testing to connections as required.
be carried out via a handset port. This shall allow minor
amendments to the controller configuration to be made, 15.11.2.3 Signal Equipment
and allow artificial demands and extensions to be placed 1 Signal poles shall be constructed of galvanized steel,
in the controller for testing purposes. covered by seamless high density polythene. A terminal
8 Controllers shall have the facility to allow for on-site block assembly shall be mounted on the top of the mast,
adjustments to be made to the signal timings, via the covered by a polythene cap.
connection of a handset. These timings should include, 2 Standard signal poles shall be 4m in length. 4.75m
but not be limited to, VA maximum green times, poles may be used when the extra height would enable
intergreens, detector extension timings, detector fault better signal visibility.
management (DFM) values, and the controller’s timetable.
3 6m poles, with two signal heads mounted at different
All signal timings inputted this way shall be subject to pre-
heights, may be used on roads with high speed limits or
determined limits, imposed for safety reasons during the
where a 4m or 4.75m pole would not provide sufficient
initial design.
signal visibility. However, they should not be considered
9 It shall not be possible, through any hardware or as a preferred solution for signal installations where other
software failure of any component of the controller, to options exist.
give a right of way to two conflicting signal phases.
4 Short 2m poles may be used at crossing points to
10 The controller shall have the facility to monitor all house a single pedestrian push button.
equipment connected to it, reporting failures as and when
5 Signal heads shall meet the requirements set out in
they occur.
BS EN 12368:2006. They shall be lightweight, modular
11 The controller shall have an integral lamp monitoring designs with a minimum lens diameter of 200mm to
unit that allows safety critical signal aspects to be 300mm. All signal heads shall contain anti sun-phantom
monitored for lamp failure and appropriate reporting technology. LED signal heads may be utilized as well as
action taken when this occurs. traditional tungsten bulbs.
12 Should any single approach suffer a single red lamp 6 Backing boards shall be provided on all signal heads
failure, then the controller shall report a red lamp failure with an East-West alignment, to enhance signal visibility.
warning (RLF1) On other alignments backing boards are recommended
13 Should two or more red lamps fail on any single and shall be provided if instructed by the Concerned
approach, the controller shall report a second red lamp Authority.
failure (RLF2) and inhibit conflicting pedestrian phases 7 For vehicle detection purposes on a vehicle actuated
from gaining right of way. On standalone pedestrian control strategy, above ground vehicle detectors may be
crossings, the facility shall shut down all signals when this used instead of inductive loop facilities.
condition arises.
8 Where the 85th percentile approach speed is over
14 A single red lamp failure condition can be self-reset if 4km/h, it is recommended that microwave, radar or optical
the controller detects the lamp to be working again, devices be utilized. For stop-line detection of vehicles,
however a two or more red lamp failure condition shall

♦ 15- 22♦
pedestrian detection or where the 85th percentile speed of However, stage skipping must not occur to service a
vehicles is below 4km/h, infra-red or optical detection is demand, unless the stage is demand dependant. In the
recommended. event of a stage being terminated by the expiry of a
9 Inductive loops may be utilized where it is felt that maximum green period, a revertive demand shall be
above ground detection is not suitable for site operation. introduced for that stage.
Where loops are to be installed they shall be 2 meters 8 In fixed time mode, the controller shall cycle through
apart in the direction of traffic flow, and consist of 3 cable all (or pre-defined) stages in a pre-set timing sequence.
turns. 9 In manual control mode, the operation of the stage
buttons shall cause the controller to move to, and to
15.11.2.4 Signal Operation
remain on, the selected stage (subject to the expiration of
1 The signal timing ranges shall be as stated in Table the minimum green period of the current stage and the
15.11.2.1. associated inter-green). An indicative light shall be
provided to show the current state of the controller under
Standard Period Length (s) manual mode.
Minimum Green 4 – 50 (in 1s steps)
15.11.3 Construction Requirements
Vehicle Extension 0.4 – 31.8 (in 0.2s steps)
15.11.3.1 Cables
Maximum Green 0 – 255 (in 1s steps)
1 The wiring of all cables shall meet the IEE Wiring
Leaving Amber 3 (fixed)
Guidelines, 17th Edition (BS 7671).
Starting Amber 2 (fixed)
2 All signal heads on a single traffic phase shall not be
Inter-greens 0 – 254 (in 1s steps) connected to the traffic signal controller on the same cable
Starting Inter-green 8 – 12 (in 1s steps) run.

Phase Delays 0 – 20 (in 1s steps) 3 For new cable runs, 16 core cables with 1.5mm2
cores shall be used for both ELV and LV applications. In all
Pedestrian Blackout 3 – 20 (in 1s steps)
cable runs, 4 cores should be left disconnected for
Table 15.11.2.1: Traffic Signal Timing Ranges redundancy purposes.

2 Provision shall be made for inter-green times 4 All cables shall be tagged in the controller to easily
between stages, and the circuitry shall include safety identify which equipment or pole a cable is connected to.
features to prevent simultaneous display of conflicting 5 Cable tags shall be colored red for cables carrying a
green indications. low voltage (LV) and yellow for cables carrying an extra
3 Manual operation may override all modes, except low voltage (ELV).
UTC control. If manual operation is required at a UTC
15.11.3.2 Controller Root
controlled site, then the UTC computer shall remotely
disconnect its link with the controller. 1 The controller cabinet shall be set on a concrete
4 The modes of operation available by manual plinth, if it is above ground, or in a waterproof pit if below
selection shall be: ground. Design of the plinth or pit shall be submitted to
the Engineer for approval before the plinth or pit is
i. Cableless linking facility (CLF) constructed. The cabinet shall be secured to the plinth or
ii. Vehicle actuated (VA) pit base by suitable anchoring devices. Provision shall be
iii. Fixed time made for ducts and conduits embedded in the plinth or pit
iv. Manual for easy access for cables. Adequate permanent protection
5 Under vehicle actuated mode, when there is an shall be provided to keep the cabinet and its contents free
absence of demands, it shall be possible to revert to an all from damp, dust, vermin and any other harmful
red condition, flashing ambers, or a specified stage. conditions.

6 If the flashing amber is to be used during periods of 2 Alternative materials may be proposed for the
low or no demand, such as night-time, then the flashing Engineer’s approval, such as standard heavy duty plastic
mode shall be preceded by a steady amber and the other underground pits and precast concrete plinths, which
vehicle and pedestrian signals extinguished. The flashing satisfy the requirements for stability and proof against all
rate shall be between 55 and 85 per minute, with equal on environmental conditions.
and off intervals. The flashing mode sequence shall be
15.11.3.3 Ducts
ended by the signals reaching an ‘all red’ period for 3
seconds, followed by the normal start up sequence 1 A system of ducting shall be provided so that all the
leading to a right of way being shown on a pre-defined signal poles and the controller are inter-connected by a
start up stage. duct network. Duct paths should be straight lines, linking
7 Under vehicle actuated mode the controller shall each draw pit in the network. Where a straight line is not
honor vehicle demands as and when they appear.

♦ 15- 23♦
possible, due to sub-surface obstructions, a radius bend of ducts shall be fixed within the base to connect to the
no more than 35° may be used. signals.
2 Ducts shall be laid a minimum of 600mm below the 2 Where conditions prevent construction of the pole
carriageway surface or 450mm below the footway surface. base as stipulated above, the Contractor shall provide
3 Whenever a duct network crosses a road, at least 3 poles with welded steel base plates and anchor bolts to
ducts shall be provided under the carriageway. provide stability, all as approved by the Engineer.

4 Ducts shall be 100mm internal diameter as standard, 3 For high masts, the design of the concrete base and
however, separate 50mm internal diameter ducts may be anchoring devices shall be proposed by the Contractor,
used to carry the electricity supply and telecommunication based on structural calculations for the ambient conditions,
cables to the controller, but no other cables shall be and shall be approved by the Engineer before construction.
installed inside these ducts.
15.11.3.6 Cantilevers and Gantries
5 Spur ducts to the signal pole location, from the
nearest draw-pit shall be provided. These can be 50mm or 1 Where traffic signals need to be mounted on
100mm diameter depending on the number of cables to cantilevers or gantries, those structures should be in
be installed. accordance with the drawings and schedules. Fabricated
steel structures shall be in accordance with Section 6
6 Polypropylene draw cords, break weight 5.5kN shall
(Structural steel and other metal work) and Section 7
be provided in each duct; these draw cords shall be
(Paint) of this Specification.
continuous over their entire length with no joints or knots
and shall extend one meter from each end of the duct. 15.11.3.7 Miscellaneous
They shall be replaced on each cable draw through so that
they can be reused. 1 Upon completion of the work the controller base
shall be filled with a base sealant that dries hard to
7 Cable duct route identification markers in accordance
prevent vermin infestation into the controller cabinet.
with MEW Standard OES 2 shall be provided at 25m
maximum spacing throughout the entire installation and 2 Ducts shall be sealed with a foam substance or wire
at terminations and bends in the route. wool to prevent vermin infestation through the duct
network.
8. Refer to subsection 15.17 – civil works for electrical
and communication installations for any other conditions. 3 Road markings at all installations shall be in
accordance with the Oman Highway Design Standards
15.11.3.4 Draw Pits and Section 14 of these Specifications.

1 Draw pits shall be either constructed of pre-cast 4 On approaches to all pedestrian crossing points,
concrete rings; brick built or reinforced high density special anti-skid road surfacing shall be laid 50m from the
polyethylene. Draw pits shall comply with BS EN 124. crossing studs in the direction of on-coming traffic. The
surfacing shall have a minimum skid resistance value of
2 Draw pits shall not be placed in the carriageway. If
55 when tested in compliance with BS EN 3262-12:2001.
this is unavoidable, then a higher specification draw pit
shall be used, capable of withstanding the loading of 15.11.3.8 Completion
traffic.
1 All signal equipment shall be assessed on site after
3 A master draw pit, minimum size 600mm x 600mm x
installation is completed by use of a commissioning check
600m deep, shall be constructed in front of the controller
list to ensure that the installation is complete and
location to allow the cables to be easily fed into the
complies with the quality and functional requirements of
controller housing.
the Specification.
4 When ducts cross a road, draw-pits, size 1200mm x
2 The Contractor shall submit final close-down
900mm x 900mm deep, shall be installed on either side of
paperwork, to include:
the carriageway and in central islands and medians, to
assist with cable pulling. They should not be installed in i. Site layout drawings (as installed)
the carriageway or installed in a location that would ii. Timing sheets
interfere with any pedestrian movement. iii. Signals hand-over certificate, including test and
5 On longer cable runs, draw pits shall not be more commissioning reports
than 50m apart. iv. Operation and maintenance manuals.

6 Where possible, drawpits shall be located adjacent to


signal poles to allow cables to be spurred off to the pole
15.11.4 Method of Measurement
installation easily. 1 Traffic signal installations shall be measured by the
number of completed sets of signaling equipment and
15.11.3.5 Pole installation
materials installed, modified or modernized at any one
1 Standard 4 meter high poles shall normally be set in location and shall cover all requirements including
a concrete base minimum 600mm x 600mm x 650mm controllers, sensors, signal poles, signal heads, cables,
deep. The depth shall be increased for longer poles. Cable

♦ 15- 24♦
drawpits, ducts, foundations, all completely installed and operation exposed to sun, dust storms, corrosive elements
commissioned. and the adverse climatic conditions at the location.
2 Cantilever and Gantry supports for traffic signal 3 Electronic equipment shall use components of
heads shall be measured by type and number installed, assessed quality in accordance with the system outlined in
and shall include foundations, fixings and mounting. BS 9000 General Requirements for a System for Electronic
3 The unit rates shall be deemed to cover for all work Components of Assessed Quality, or other approved equal.
at each installation location, including design, submission 4 All equipment shall be to the approval of the
of drawings, obtaining approvals from all Concerned Concerned Authority. It shall have a proven in service
Authorities, the supply, construction and installation, record, and documentary evidence of this shall be
transport, and all civil work and miscellaneous items and submitted. Full environmental tests shall be carried out
close-out procedures. on a production sample by an independent testing
authority and a certificate supplied to show the suitability
15.11.5 Basis of Payment of the equipment for use in the specified environment.

1 The amount of completed and accepted work as 5 Materials and components shall be the latest
provided for above, will be paid for at the unit rate stated technology and best of their respective kind and modern
in the Bill of Quantities, which rate shall be full practice, selected and treated so that no corrosion will
compensation for supplying materials, installation, testing occur during the lifetime of the installation estimated at 20
and putting into operation, for labor, transport, equipment, years.
tools supplies and other items necessary for the proper 6 All wiring shall be neatly and securely fixed in
completion of the work. position in an approved manner. The wiring shall be in
high temperature PVC insulated cables or silicon rubber,
15.11.6 Items in the Bill of Quantities color coded for ease of identification. All terminals shall
be of adequate size.
i Traffic Signal Installation
7 NEMA 3R (IP 66 of IEC 60529) rated metallic
(location and designation
equipment enclosures shall be provided with terminals for
shown on drawings) (Lump Sum) attachment of ground safety circuit.
ii Overhead Traffic Signal Support 8 Masts shall be designed and constructed to provide
including foundation (type) (nr) adequate support and stability for the sign and shall be
suitable to support more than one assembly. They shall
be complete with base compartment and pole top
15.12 Overheight Vehicle Detection
compartment complete with terminal chambers for
System connecting incoming cables.
9 Masts shall be constructed from seamless steel,
15.12.1 Description
tubular, with a wall thickness not less than 4.5mm and a
1 This Sub-section describes requirements for the tensile strength of 520 MN/sq.m hot dipped galvanized.
design and installation of the system to detect over-height No machining operation shall be allowed after completion
vehicle/trucks approaching underpass and to display a of the galvanizing process. Masts shall be painted with 2
warning to alert drivers not to enter the underpass. coats of epoxy resin paint to an approved color finish after
completion of the galvanizing process as required by the
15.12.2 Design Criteria for Materials and Concerned Authority / Engineer.
Components 10 Signs shall be mounted on -brackets supporting both
1 The equipment shall be designed to operate on A.C. top and bottom of the sign. Attachment shall be of
240 volts single phase 50 Hz with a voltage variation of stainless steel clamps and mounting brackets which shall
plus 15 percent or minus 20 percent and frequency incorporate a wiring duct for the sign wiring. The
variation of plus or minus four percent. If the equipment is attachment shall allow vertical and angular adjustment of
sensitive to voltage fluctuations within the above stated the sign assembly and shall be suitable for the sign
limits, an automatic voltage stabilizer shall be presentation.
incorporated in the system, along with a stand-by 11 Mounting heights of sign, the type of sign and the
uninterruptible power supply system for maintaining signal presentation shall be as will be detailed by the
system memory. Concerned Authority.
2 Equipment shall be designed and derated for
continuous operation under operating conditions 15.12.3 Operational Requirements
stipulated in Sub-section 15.1. The variation in light 1 All over-height vehicles or vehicle loads traveling
intensity caused by the shadow of passing clouds shall not toward the tunnel shall be detected and a warning signal
interfere with the proper operation of the equipment. The given. Vehicles traveling away from the tunnel shall be
equipment shall be suitable for uninterrupted full load ignored by the detection equipment. Detection of vehicles

♦ 15- 25♦
traveling toward the tunnel shall be counted and recorded 4 Two 1/8 inch (.32 cm) boresight holes are to be
on an installed electronic counting device. located at Top-Middle of each housing. Front and rear
2 The detection system shall consist of visible red or screws are to be installed in these holes so as to insure a
infra red source(s) spectrally matching detector(s) weather tight enclosure, and should be removed to allow
mounted on poles positioned on opposite sides of the alignment of units. Looking through boresight hole from
approach roadway. The alignment and height of the rear of unit so as to see through the boresight hole in front
visible red or infra red beam shall be preset to identify of unit gives the installer a basic means of aiming the unit
vehicles over 4.25m above the roadway at the line of in the proper direction. Focusing the unit on opposite
detection or as requested by the Concerned Authority. sides of the road in the center of the front boresight while
looking through the rear boresight hole ensures that a
3 Positive measures shall be introduced to warn
general alignment is accomplished. This step should be
drivers of a potential accident if they proceed and to
done from both Transmitter and Receiver Unit locations.
instruct them not to continue, whilst causing the least
Fine tuning of alignment can then be done electronically.
possible disturbance or distraction to other motorists.
5 The transmitter unit and the receiver units shall each
4 Warning and instructions for drivers of over-height
be provided with a barrier to protect the operating
vehicles shall be stated on the face of the warning sign
equipment. The enclosure shall maintain its structural
which shall be illuminated internally, i.e., nature of danger
integrity for the operational life of the equipment and shall
“OVERHEIGHT” and action to be taken (“STOP” or “TURN
allow ready access for control adjustment and electrical
RIGHT” or “EXIT RIGHT” or “USE RIGHT (LEFT) LANE,” or
interconnection without the use of any tools except a
“DO NOT ENTER” etc) if the driver proceeds. The action
Phillips head screwdriver.
must cause the driver to become alert to the extent that he
should react as instructed. 6 Each of the equipment units shall be provided with
means for rigidly attaching the unit to a vertical cylindrical
5 Warning Sub-system shall consist of a flashing light,
pole without requiring any machining operation. The
an audible alarm, and an electronic message board.
attachment means shall not stress or deform the unit and
Upon receiving the control signal from the detection shall prevent the movement of the unit in any direction by
subsystem, this warning subsystem is to be activated and the force developed by wind. The mounting means shall
shall respond by alerting the driver to either stop the allow adjustment of the vertical position on the pole. The
vehicle or take an alternative route. The warning mounting means for the transmitter unit and the receiver
subsystem shall comprise the following: unit shall have the capability of adjusting the angular
i. Warning message on LED display orientation of the optical axis in both the horizontal and
ii. Loud audible alarm, 111 dB@ 3m vertical plane over an angular range of plus or minus five
iii. Flashing Red warning light degrees from horizontal. The transmitter and receiver unit
shall be mounted to detect the presence of vehicles that
15.12.4 Physical Requirements exceed the specified vertical height.
7 Warning sign shall meet all electrical /electronic
1 The detector unit shall be solid state with printed
specifications and shall conform, in all essential elements,
circuit boards and regulated power supply. The unit shall
with the provisions of the U.S. D.Q.T, F.H.A. Manual on
be of modular construction. It shall have an effective
Uniform Traffic Control Devices. Plastics on sign faces
range of 3m to 38m with a reaction speed range of one
shall be protected by LEXAN or other material providing
(1)MPH (1.61 km/h) to seventy-five (75) MPH (121 km/h) for
equal or greater defense against flying object damage or
a 2 inch (5 cm) diameter object 1 inch (3 cm) above the
vandalism. Signs shall be activated and time controlled
detection height. It shall provide a fault reporting output
by the Detection unit. Lighting shall be provided by high
upon loss of space/detector power or total failure.
output fluorescent bulbs for message and incandescent
2 Sensors are to have NEMA 6P rated enclosures, bulbs with parabolic reflectors for arrows at the top and
direction selection to be from a selection switch. No tools bottom of sign. Flashers on LED signs should be of
or adjustment is required. 300mm diameter.
3 Four LEDs and meter shall be provided for ease of 8 Sign housing shall be as indicated on drawings and
alignment and testing. Provision shall be made for the provided with rectangular (shape) reinforced aluminum
elimination of the effect of ambient light and an internal capable of withstanding wind loading up 95 km/h and
environmental control element that reduces operational provided with a sun shield projecting at least 36 cm.
failure from fog, condensation and insects. Dimensions Letters and arrows shall be normally blanked out. When
shall not exceed a maximum overall size of 18 x 15 x 10 illuminated, arrows shall be red in color, but can be made
inches (46 x 38 x 25 cm). The housing shall be of high in any color specified (IP 65 rating).
grade extruded aluminum and sheet aluminum of not less
9 Unit mounting poles (shaft) shall be one or two piece,
than 1/8 ″ thickness, and weather sealed for rugged
adjustable height, seamless, round aluminum tube. Poles
durability and extended life. The mounting shall allow for
shall include a handhole centered 46 cm above the bottom
directional adjustment and aiming after initial installation.
of the shaft with a cover secured with stainless steel
screws. Base flange for the attachment of the shaft to the

♦ 15- 26♦
foundation shall be a one piece cast socket of aluminum shall be inserted in the excavation supported at the correct
alloy, with 4 anchor bolts for fixing to the concrete base. level and grouted in. In-situ foundations shall be
10 Single core cables for internal wiring shall be 450/750 constructed as shown on the Drawings with the concrete
volt flexible PVC insulated copper in accordance with BS poured around the reinforcing and holding down bolts
6004:1984 or approved equal standard with high and consolidated in one operation.
temperature insulation where operating in high ambient 7 The position of the anchor bolts and the level of the
temperature conditions. The conductor size shall be in top surface shall be exactly determined and adjusted. PVC
accordance with the circuit requirements. Cables shall be ducts of sizes shown on the drawings shall be installed in
bunched, clipped and properly secured to form a complete the bases for cable access.
wiring loop.
11 Power and signal cabling shall be provided between 15.12.6 Method of Measurement
the receiver unit electronics and the junction box adjacent 1 Over-height vehicle detection systems shall be
to the mounting pole foundation. Power for the receiver measured as the number of completed systems. The rate
and transmitter units will be made available at the junction shall include for supply and installation, testing and
box located adjacent to the mounting pole foundation. commissioning of transmitter and receiver units, warning
12 A solar panel shall be supplied with the OVDS to signs, masts with interconnecting cables and earthing as
make use of solar energy for stand-by power to enable the necessary, cables, including all foundations, ducts,
system to remain powered even under power failure drawpits and associated civil work.
conditions for limited periods.
13 A fault reporting function would be incorporated in 15.12.7 Basis of Payment
the system to detect any malfunctions in the system and
1 The quantity of completed and accepted work
alert the authorities.
measured as provided for above will be paid for at the unit
14 All non current carrying parts of the equipment and rate for a complete operational system stated in the Bill of
installation shall be earthed. Quantities, which rate shall be full compensation for
15 The armoring and screens of all multi-core cables supplying, installing, testing and putting into service, all
installed directly in the ground shall be bonded and materials, transport, labor, equipment, tools, supplies and
connected to the earth bar together with the earth core of other work items necessary for the proper support and
the electricity supply cable. A separate single core copper completion of the work as specified.
PVC insulated (green/yellow) installed back to the
electricity supply point shall be provided if the incoming 15.12.8 Items in the Bill of Quantities
cable does not include the earth.
i Overheight vehicle detection and

15.12.5 Construction Requirements warning system (system complete)


(location shown on drawings) (nr)
1 Associated civil work for ducts, draw pits and pole
bases shall conform to Clause 15.17.3 – Construction
Requirements.
15.13 Emergency Roadside Telephone
2 The Contractor shall supply and install the
System
underground ducts, construct the cable drawpits as
indicated on the Drawings or as required on site for 15.13.1 Description
installation of the cables. The Contractor shall be 1 This Sub-section describes requirements for
responsible for all excavation, draining trenches, forming emergency roadside telephone systems, including
of duct assembly, backfilling, and removal of excess earth detailed engineering, coordination, manufacture, supply,
and restoring finished grade to its original condition. transportation, delivery, installation, jointing, connecting
3 Ducts shall be as specified under Clause 15.7.2. They up, testing, commissioning, setting to work, training and
shall be laid in trenches in close cluster formation. maintenance services during the warranty period. Work
4 Concrete pole bases shall be designed to take into includes:
account the nature of the ground and the dead and i. Coordination with Concerned Authority, existing
imposed loads of the pole and all attachments. They may contractors, and providers of interfaced
be pre-cast or cast in-situ as detailed on the Drawings or systems.
as instructed by the Engineer. ii. Project management.
5 The excavated hole for the pole base shall be well iii. Planning management.
cleaned and its sides compacted and the base and sides of iv. Detailed functional analysis until approval by
the excavation shall be lined with a heavy duty sheet Concerned Authority.
bitumen or polythene waterproof membrane before work v. Finalization of system to the approval of
on the foundation properly commences. Concerned Authority.
6 Where pre-cast foundations are to be installed they vi. Supply of needed system equipment and
components.

♦ 15- 27♦
vii. Transport, unloading, and storage on the Site of xi. BS EN 60118-4:2006 - Hearing aids - Magnetic
the required equipment and components. field strength in audio-frequency induction
viii. Equipment installation. loops for hearing aid purposes.
ix. System installation and configuration. xii. BS EN 60529:2004 - Degrees of protection
x. System integration with interfaced and existing provided by enclosures (IP Code).
systems. xiii. BS 6305:1992 - Analogue inter working and non-
xi. Complete testing of the system (unit tests, interference requirements for Customer
integration tests, final acceptance tests, users’ Equipment for connection to the Public
tests, etc.). Switched Telephone Network.
xii. Training. 3 Other Standards - International Electro-technical
xiii. System implementation, Commission (IEC):
xiv. System roll-out,
i. IEC60068 Environmental Testing
xv. System maintenance after successful initial
ii. Specification for Concrete works, shall be as per
proving period during Warranty,
subsection: Civil Works for Electrical
xvi. Supply of spare parts for 2 years,
Installations
xvii. System maintenance tools delivery,
xviii. Writing and delivering of documentation (user’s 4 Product Data: For each component including
manual, maintenance manual, test reports, etc.) descriptions, colors, complete technical specifications, and
xix. Testing of emergency roadside telephones in manufacturer catalogues for all equipment and materials.
the field. 5 Factory Tests: All equipment and cables are to be
xx. Commissioning of the installation. tested at manufacturer premises, and test certificates, are
xxi. Connection of emergency roadside telephones to be submitted to Engineer before shipping and delivery
to control center to site.
6 Shop Drawings: Submit drawings for approval
15.13.2 Regulations and Standards including, but not limited to, the following:
1 British Standards and Codes of Practice shall apply to i. Detailed system schematic diagram.
the design and installation of the system ii. Detailed layout, locations, and installation of all
2 The following BS are generally applicable and are equipments.
mandatory: iii. Exact routing of all cabling and wiring.
iv. Equipment assemblies and indicate dimensions,
i. BS3573: 1990 - Polyethylene-insulated copper-
weights, required clearances, method of field
conductor telecommunication distribution
assembly, components, and location of each
cable.
field connection.
ii. BS EN60529: 1992 - Specification for
v. Wiring Diagrams: Detail wiring for power,
classification of degrees of protection provided
signal, and control systems and differentiate
by enclosures.
between manufacturer-installed and field-
iii. BS 1363 - Specification for 13 A plugs, switched
installed wiring. Identify terminals to facilitate
and un-switched socket-outlets and boxes.
installation, operation, and maintenance.
iv. BS EN 60898 - Specification for miniature and
Include a single-line diagram showing cabling
moulded case circuit breakers.
interconnection of components.
v. BS 4293 - Specification for residual current-
operated circuit-breakers.
15.13.3 Definitions and Mode of Operation
vi. BS EN ISO 14713: 1999 - Protection against
corrosion of iron and steel in structures - Zinc 1 Description of emergency telephone operation
and aluminum coatings – Guidelines and ASTM i. The principle of this operation is that when a
123. call is initiated in the field, the emergency
vii. BS EN 10327/2004 - Hot dip zinc coatings on roadside telephone automatically calls the
steel sheet. phone number unique to that particular
viii. BS EN ISO 1461: 1999 - Hot dip galvanized telephone. This unique called number is known
coatings on fabricated iron and steel articles - as the ‘indial’ number.
Specifications and test methods. ii. The indial number is connected to control
ix. EN50082-1 - Electromagnetic compatibility center CC (defined by the Concerned Authority).
(EMC) - Generic standards - Immunity for iii. The PABX (private automatic branch exchange)
residential, commercial and light-industrial is programmed to display on a screen:
environments.
a. The pillar number of the calling emergency
x. BS EN 60068-2-78:2002 - Environmental testing -
roadside telephone
Tests - Test Cab: Damp heat, steady state.
b. Its location
c. Any other information as required.

♦ 15- 28♦
i. From the pillar number and other information i. Button to initiate an emergency call to CC.
programmed into the PABX the CC operator ii. Button to annunciate recorded information.
answering the call is able to identify the location iii. Speaker to broadcast the ring tone and voice
of the phone being used, including which side communications.
of the carriageway, without the caller giving any iv. Two microphones to record and monitor voice
details. communication, respectively.
ii. The CC operators and the caller are able to v. IrDA interface with infra red port for
communicate clearly in a two way (duplex) programming the telephone features in the
manner. vicinity of the unit.
iii. In the event of a failure, the emergency roadside vi. Two (2) locks with different keying to secure the
telephone can detect the listed defects and will emergency roadside telephone module to the
automatically initiate a call to the CC manager enclosure (pillar). Keying must be keyed alike
and log the details of the defect. across the manufacturers’ telephones.
iv. The emergency roadside telephone must have
facilities for it to be called remotely by the CC 15.13.4.2 Pillar Dimensions and Weight
manager and perform the listed self-diagnostics 1 The pillar dimensions shall be:
and report the results accordingly.
i. Height 1400mm ± 100mm
2 Supply of network facilities and equipment ii. Width 200mm ± 50mm
i. Network supplier iii. Depth 130mm ± 50mm
2 The pillar weight, including the phone equipment,
a. Telephone equipment shall be
shall weigh less than 60 Kg.
coordinated with the mobile
telecommunications service provider. 15.13.4.3 Frangibility
b. It is mandatory that the local operator be
1 The pillar and solar cell support combination shall be
used for the services.
so designed as to be frangible in the event that it is hit by
ii. Each Emergency Roadside Telephone is to have an errant vehicle. The frangibility requirements must
a unique series of numbers : comply with the definition and requirements of BS EN 40-
2:2004.
a. Pillar number
b. The indial telephone number 15.13.4.4 Pillar Materials and Color
programmed to call the CC phone
1 The pillar shall be constructed from marine grade
number
aluminum with a minimum thickness 3 mm or extruded
c. CC manager phone number aluminum with a minimum thickness 5mm.
d. Phone service number (SIM Card)
15.13.4.5 IP Rating
e. Serial number
1 The pillar shall be designed to IP55 (IEC 60529)
f. A four-digit Personal Identification
Number (ID) 2 The electronics enclosure shall be designed to IP66
(IEC 60529).
g. The Pillar number shall be allocated
based on local authority guidelines. 15.13.4.6 Vibration and Shock
3 Monitoring of emergency roadside telephones
1 The emergency phone must remain operable under
iii. Calls from the emergency roadside telephones the following conditions of vibration: Three axes to: +/-
are handled and monitored by CC. 1.5mm 5-13Hz and+/-1g 13-150Hz tested.

15.13.4 Products and Materials 15.13.4.7 Wind

1 The emergency phone must remain operable after


15.13.4.1 Pillar Design and Manufacture
withstanding wind speeds of up to 198 km/h.
1 The emergency roadside telephone shall be hands-
free, vandal resistant and weather resistant. 15.13.4.8 Temperature

2 The emergency roadside telephone shall be housed 1 The emergency telephone shall comply with the
in a pillar with only the solar cell being pole mounted. following temperature requirements:
3 The emergency roadside telephone shall be housed i. Storage temperatures range -10ºC to +70ºC.
in a plinth mounted pillar of dimensions described in ii. A minimum start up temperature of -5ºC.
Paragraph 15.13.4.2 iii. An operating temperature range -10ºC to +70ºC
4 The emergency roadside telephone shall have as a continuous.
minimum the following features: iv. Storage temperature shock changes up to 10ºC
± 5ºC per minute.

♦ 15- 29♦
15.13.4.9 Lightning Protection 15.13.5 Power Supply
1 Primary protection shall be provided using fitted gas 15.13.5.1 Power Supply
arrestors.
1 The emergency telephone shall operate from either
2 Secondary protection shall be provided using fitted of the following, as shown on the Drawings or instructed
metal oxide varistors. by the Engineer:
3 Earth stake shall be fitted with a conductor no less i. Powered by a 240 V AC mains available from
than 6 mm bonding the earth stake to the base of the the nearest light pole, where possible.
phone pole and to an earth point within the electronics ii. A fitted solar panel and battery combination,
enclosure. supplied by the Contractor.
15.13.4.10 Vermin Ingress 2 Short circuit protection shall be provided.

1 The pillar shall be pest and vermin proof, including 15.13.5.2 Battery
termites, ants, bees, rats and mice.
1 The battery shall have the following characteristics:
15.13.4.11 Vandalism i. Operating temperature range, -10º C - +70º C
ii. Sealed lead acid rechargeable
1 The pillar shall be vandal and impact resistant to
iii. Sealed and operational in any orientation
prevent unauthorized access to the internal equipment.
iv. Maintenance free
Vandal and impact resistance can be defined as being able
v. Minimum 3 years float service life.
to remain functional while withstanding moderate to
vi. Recyclable
severe blows by hand held objects in most circumstances
vii. No memory effect
without suffering more than cosmetic damage.
viii. To provide a minimum of 7 days normal
2 The pillar shall be fitted with an automatic operation under a primary source failure
tilt/vandalism alert feature with configurable sensitivity condition. Normal operation is based on 6 calls
settings with provision for the emergency roadside phone per day at 10 minutes per call for 7 days, the
to make maintenance call and log its location and remaining time being Idle time.
condition with the CC manager.
3 Access to the fixing bolts attaching the phone to the 15.13.5.3 Battery Charging
concrete pad shall only be obtained from inside the 1 The battery shall be charged with a solar cell or from
emergency telephone pillar. a 240V AC mains supply.
15.13.4.12 Pillar Identification 2 Thermal management of the battery charging to
prevent thermal runaway of the battery shall be
1 International telephone symbols and pillar numbers incorporated.
shall be installed on each side of the pillar.
3 The power supply and charging system shall
2 The International telephone symbols and emergency incorporate battery management to monitor the status of
telephone pillar number shall be manufactured using the battery charge and maintain it at its rated float voltage.
British Standard.
4 Should the battery voltage fall below 90% of its
3 The telephone symbol shall be 150mm in height with nominal float voltage an alarm shall be raised.
a spacing of 150mm from the top of the pillar to the top of
the telephone symbol. 15.13.5.4 Solar Panel
4 The pillar number shall consist of 80 D N numerals 1 The solar panel shall be of sufficient size and wattage
installed vertically down the pillar with a spacing of to ensure that the battery receives sufficient charge under
150mm from the bottom of the telephone symbol to the all weather conditions.
top of the first pillar numeral.
2 A bird guard shall be fitted to the solar cell to
15.13.4.13 Concrete discourage birds from sitting on the cell.
3 The solar cell support shall provide a minimum of 4.0
1 All concrete and reinforcement for the bases and
meters clearance between the ground and the solar cell,
anchor bolt assemblies shall be in accordance with Sub-
such that the solar cell is not accessible without a ladder.
section 15.17
4 The solar cell shall be vandal resistant and attached
15.13.4.14 Steelwork to the mounting such that it cannot be removed without
special tools provided by the supplier.
1 All steelwork for the anchor bolt assemblies shall be
hot dipped galvanized in accordance with BS EN ISO 5 The solar panel shall be installed facing North and be
14713: 1999 and BS EN ISO 14761: 1999. angled towards the sun, with the angle being dependant
on the latitude of the location.

♦ 15- 30♦
15.13.6 Construction Requirements 15.13.6.5 Grouting of Pillar Base

15.13.6.1 Drawings 1 After the installation of the emergency telephone, the


Contractor shall impact mortar grout under the pillar base.
1 The Contractor shall prepare drawings to scale and
diagrams as follows:
15.13.7 Method of Measurement
i. Emergency roadside telephone system
schematic diagrams, detailed design, 1 The emergency roadside telephone system shall be
connection diagrams, etc. measured by number of the complete systems, supplied
ii. Construction drawings, including civil works installed tested and put into operation. The unit rates shall
iii. As-built drawings include for all work, including design, supply and
installation, per road; testing, commissioning,
2 All design development drawings, construction
maintenance provision of all drawings and manuals and
drawings, and as-built drawings shall be submitted in hard
all necessary civil works as specified.
copy format as well as in electronic format in the
quantities specified below.
15.13.8 Basis of Payment
3 Quantity of submittals
1 The emergency roadside telephone system shall be
i. Electronic Files: 1 set.
paid for as a lump sum per completed system including
ii. Reproducible hardcopies: 1 set.
transportation, at the unit rate(s) stated in the Bill of
iii. Prints: 3 sets.
Quantities, which shall be full compensation for the
15.13.6.2 Concrete Pad and Pillar Foundation complete system supplied including the roadside
equipment, the network facilities (mobile telecom service)
1 A concrete pad, complete with anchor bolt assembly implementation and putting into operation after testing in
and steel mesh, shall be constructed as detailed in the accordance with the Specification.
Drawings, at each emergency telephone location.

15.13.6.3 Anchor Bolt Assembly 15.13.9 Items in the Bill of Quantities (Unit)
i Emergency Roadside Telephone System
1 The anchor bolt assembly shall include four (4) nuts
and four (4) washers per assembly (Road Ref. No.) (Lump Sum)
2 Sufficient thread shall be provided on each bolt to
allow for the leveling of the pillar when installed. This 15.14 Public Lighting Management and
shall be not less than twice the sum of the nut, washer and Control System (PLMCS)
pillar base plate thickness.
3 All bolts shall be the same length with respect to the 15.14.1 Description
vertical axis of the assembly. The anchor bolt assembly
1 This Sub-section describes requirements for design,
shall be such that the pillar may be mounted parallel to
supply, installation, testing and commissioning of a
the road center line.
complete PLMCS installed in feeder pillars, with individual
15.13.6.4 Pillar Mounted Telephone phase voltage stabilization, dimming, monitoring, remote
control and remote surveillance suitable for later
1 An emergency telephone shall be installed on a connection to server based software for decentralized
concrete pad at each location indicated on the Drawings. operation.
2 Each pillar shall be installed on the anchor bolt 2 The PLMCS comprises:
assembly and adjusted so as to be vertical. The pillar shall
i. Feeder pillar power controller
comply with the requirements of the applicable British
ii. Switching functions
code for structural design for utility services poles for
iii. Remote control management software and
stability.
hardware
3 The emergency telephone shall be installed such that
the buttons, speaker and microphones are facing away 15.14.2 General Requirements
from the direction of traffic flow such that a person using
the emergency telephone is facing the phone and 1 The PLMCS shall control the function of the ordinary
oncoming traffic. feeder pillars (FP).

The pole for the solar cell shall be installed on the side of 2 The PLMCS shall be installed at each feeder pillar
the pillar further away from the curb such that it does not position and control all luminaries of that FP.
obstruct the view of the pillar number when viewed by 3 The PLMCS shall be capable of being upgraded later
drivers approaching the pillar. to have full remote control, including remote servicing,
4 Refer to Series 1500 of the DRMB UK Standards for communication of alarms, down-loading of recorded
highways for all these works. information. and reporting malfunctioning to a control
center.

♦ 15- 31♦
4 The PLMCS shall work with all luminaires; HPS and 19 The transition from lamp warming to planned stage,
HPMV type, equipped with standard magnetic ballast, or any intermediate level regulation process, shall be done
ignitor and PFC capacitor. without disconnection and shall be applied in maximum
5 The PLMCS shall be capable of dimming HPS and steps of 2.2V. The process of dimming shall be even,
HPMV lamps in a range of 100% - 50% and stabilize the without visible steps in luminance.
voltage for MH and FL lamps. It shall be capable of 20 The PLMCS shall incorporate a high accuracy
stabilizing the output voltage for each phase individually astronomical time clock which can be remotely controlled
to +/-1% for input voltage fluctuations from 175V to 264V from the control center.
and shall be able to increase the output voltage by at least 21 Programming and reading of the parameters shall be
30V to compensate for low input voltage. done via PC software, able to read the real time
6 The PLMCS shall be designed to save between 15% measurement and to change all the parameters of the
and 35% of energy on average and shall ensure up to feeder pillar, operable through either a direct cable
double the lamp life. connection between the PC and feeder pillar or with GSM.
7 The PLMCS shall be completely static, that is with no 22 The supplier shall be responsible for installation,
moving parts such as ‘variac-type’ transformers and it testing and commissioning of the system and shall
shall not contain triac based equipment. organize a local 5-days seminar for training.
8 The PLMCS shall be a universal system to work with 23 The PLMCS shall monitor power, voltage, current
any brand of HPS, HPMV, MH or FL lamps, mixed in the and power factor of each lighting circuit and additionally it
same system or circuit of the FP. It shall be independent of shall monitor all other inputs from the FP.
the brand of luminaires used.
24 Communication to the PLMCS shall be via fiber optic
9 The PLMCS shall be operated via, and conform to, interface on TCP/IP protocol.
the local 3-phase 4 wire, solidly earthed neutral, 415 V A C.
25 Future optional features may include the following:
electrical system.
i. The PLMCS shall have the optional capability in
10 The kVa rating installed shall be based on full load
future to add communication with each
shown on the Drawings at pf of 0.8 and a spare capacity
individual lighting point by means of power line
of 30% for future connection of additional loads. In
carrier (no additional cables). With this option it
addition each unit shall be de-rated by 30%.
shall monitor the proper functioning of each
11 Each FP shall have an automatic by-pass system. The lamp, ballast, ignitor and capacitor.
by-pass shall be activated automatically in case of any ii. The PLMCS shall have the capability in future to
malfunction of the PLMCS. switch on and off each individual lighting point
12 The local agent for the PLMCS shall have factory or advertising panel by means of power line
trained and certified personnel to perform commissioning carrier (no additional cables).
and all servicing tasks. iii. Communication to the PLMCS shall be possible
13 The PLMCS shall be a field proven system with at via telephone modem, GSM modem, GPRS
least 1000 similar products installed worldwide. The modem, radio modem, RS232 interface or
chosen supplier shall have similar systems installed in at RS485 interface.
least 5 major cities in the Middle East.
15.14.3 Detailed Technical Specification
14 The PLMCS shall use the latest technology, and
comply with international standards such as CE-mark, CEI 1 Power controller enclosure shall have the following
17-13/1, EN 60439-1 and UL916. PLMCS shall be CE features:
marked and conform to such standards. Under no i. Housing fabricated of fiber-glass reinforced
circumstance shall the system induce harmonic currents polyester or equally approved material
to the supply grid. ii. Protection level: IP54 in accordance with IEC
15 The PLMCS enclosure shall be for outdoor 60529 Standard
installation, IP 54 minimum to IEC 60529, for both the iii. Color: RAL 7032 - 7035
power and electronic parts. iv. Base frame made of hot dipped galvanized steel
16 All system components shall be suitable for v. Safety lock.
operation within a temperature range from -10deg C to 2 Main technical features of power controller shall
+60deg C include:
17 Materials shall be certified to ISO 9002 quality i. Supporting frame made of galvanized steel
standard. ii. Voltage control circuits as provided by
18 Load must be started at each switching on under manufacturer.
nominal conditions (230/240V RMS +-1% each phase) even iii. Serial port RS232 or RS485 for communication
if the input voltage is at 175V for a programmable time, with PC and GSM, and up-to-date software of all
(this is very important to conserve the lamp life and units.
conform to the lamp manufacturer’s warranty).

♦ 15- 32♦
iv. Microprocessor unit (PLC) for control of work xiii. Lithium battery for buffering of RAM memory
cycles, made of high-grade components, and of the time clock, with 2 (two) year
suitable to operate within the temperature autonomy under disconnected mains
range -10°C to +70°C - Printed circuits with conditions; control of charging status, with
galvanic insulation of the tracks. analogue measurement of battery voltage;
v. Regulation and stabilization of voltage on load push-button for disconnection during storage
side through static system without wave period; hot replacement.
dimming (wave-form shall remain perfectly 5 Features for future functions (upgradeable) shall
sinusoidal) for each phase independently. include:
vi. Four pole main breaker, thermal and magnetic
i. Alarms programming menu for values above or
protection, with rated current to suit the size of
below the preset thresholds of input voltage,
controller with a short circuit capacity 50 kA.
output voltage, total current, power and PF.
vii. Indicator lights: mains voltage phase colors.
ii. Display of the following information:
3 Connections:
a. Input voltage of each phase
i. Feeder terminals shall be 5 x 35mm2
b. Output voltage of each phase
ii. Each FP shall have at least 4 outgoing circuits,
each terminated with 5 terminals 16mm2. c. Active power of each phase
Configuration, quantity and circuit current rating d. Reactive power of each phase
of each circuit shall be as indicated on the e. Power factor of each phase
Drawings.
f. Frequency of each phase
4 Functional features of power controller shall include:
g. Analogue input value (m A)
i. Static by-pass, no break execution, suitable to
h. Analogue output value (m A)
operate any combination of mixed types of
lamps iii. Recording of the following statistical data:
ii. Power saving of up to 40% depending on the a. Hours of operation on line
type of lamps connected. b. Hours of operation in the by-pass mode
iii. Efficiency 98.5% (at full load, PF=1)
c. Number of switching cycles of control
iv. Stabilization of output voltage with accuracy +/-
relays
1% with input voltage 200 to 245 V independent
for each phase. d. Stability of mains (steps/minute)
v. Stabilization of changes in mains voltage in e. Total energy consumption
extra-rapid time.
f. Number of black-outs
vi. Setting of the following parameters, separate
g. Number of resets
for each phase: starting voltage, full light
voltage, reduced light voltage, warm-up time, h. Possibility to download the historical data
ramp-up speed, ramp-down speed. recorded in the controller, via portable PC
vii. Selection of dimming percentage and of the or modem or from the control center.
corresponding time zones, up to 10 time zones. iv. Provision for connection to a remote control
viii. Availability of one preset yearly program, with network designed for diagnostic and control of
starting and operating cycles configurable in the whole unit (remote servicing).
accordance with seasonal factors and location.
ix. Availability of one customizable yearly cycle 15.14.4 Remote Control Management (RCM)
with different settings for each season and the Software
possibility to set up to ten time zones over night
time. Software shall be designed to operate a remote control
x. Availability of five customized periodical cycles station for supervision and management of lighting
with possibility to set the requested time, the systems, with the features and functions listed in items 1
days of the week and up to ten time zones over to 8, below:
night time. 1 General features:
xi. Availability of one cycle controlled by analogue i. Standard language is English; further local
input (4 - 20 ma) suitable for dimming from languages with text import during program start
signal sent from a luminance sensor or any up later on, should be possible
other equivalent apparatus. ii. Installation on single PC (stand-alone) or in the
xii. Astronomical time clock with precision of ± 4 Concerned Authority’s server configuration in
minutes/year in a temperature range of -10 to future.
+70°C, or, alternatively, high accuracy clock, iii. Facility to share and to display data via internet
with precision ±1 minutes/year in a temperature iv. SQL database
range -10 to +70°C.

♦ 15- 33♦
v. Safety system for control of all accesses, ix. Remote reading of operative parameters
configurable for the function and the Concerned (technical data, working cycles, clocks, alarms,
Authority’s control. l/0 state, MEM modules settings), active alarms,
vi. Customization of program options records of alarms (in partial or total mode),
vii. Facility to import and export data, already record of measures, monthly data, etc.
present in external database, without the need x. Facility to download the last "n" records
of manual fill-in xi. Facility to program in advance the operation to
viii. Manual backup utility be performed during the connection with the
ix. Window preference for simple access to the controller in field
most-used functions. xii. Remote writing and modification of the
x. Creation of log files of the performed operative parameters
operations. xiii. Real time remote reception of alarms from the
xi. Wide flexibility in customization plants
2 Data list management: xiv. Alarms notification to the technician via SMS or
e-mail, based on customizable rules
i. Loading of data list of plant and components
xv. Utility to plan the automatic calls of the
(FP's, cables, luminaires, lamps, ballasts,
controllers, including the possibility to choose
ignitors, capacitors)
the operation to be performed, and the
ii. Management of data list by means of a tree
management of errors in the communication
structure
xvi. Remote plant override to switch the lighting
iii. Fill-in of plant and component data list from the
system on and off
tree structure or directly from the maps
xvii. Remote control of input/output relay
iv. Utility functions such as copy, cut, paste, paste
special 4 Plant management by active maps:
v. Management capacity up to 30 towns, 300 FPs i. Map management on three levels in case of a
and more than 30,000 objects with possibility to wide area or on two levels in case of
extend without limit. medium/small area
vi. Identification (object can belong to more than Up to 324 maps
one group) and without limitation in numbers
Maps in whatever graphic format (JPG, BMP,
vii. Management of groups by means a tree
WMF, TIF, GIF)
structure; data searching and selection via
appropriate filters (with logic addresses) Simple insertion of object in the map
viii. Data replicate tool to revise and modify the Facility to choose the objects to be displayed in
data list of elements the map, only one object type at a time
ix. Facility to personalize the screen and ii. Active objects which light-on because of alarms
background iii. Color light indication in the quadrants at levels
x. Control panel for easy access to the different one and two, indicating the presence of one or
program functions more objects in alarm condition inside the area
3 Communication: iv. Facility to add, delete, remove, new objects
i. Communication via serial cable or via modem directly from the map
(standard telephone PSTN, GSM, GPRS, radio v. Utility functions such as copy, cut, paste, paste
modem, TCP/IP protocol on Ethernet) special
ii. Management of 5 modems at the same time or vi. Full interactivity of the objects to open data list,
5 TCP/ IP channels. to display a mimic panel or alarms or records of
iii. Facility to configure the interface modems for maintenance activities or set-up , directly from
only incoming calls, only outgoing calls, only the map
manual calls, only automatic calls vii. Zoom function in the detailed map
iv. Full automatic management of the connections viii. Tools to navigate into the maps
(automatic disconnection only when required) ix. (As an alternative to normal maps) chart
v. Emulation in remote mode to enable all the module, to interface and interact with drawing
operations as if in front of the controller Autocad and/or shop files, with facility to import
vi. Manual connection to verify the controller state, automatically elements of chart system used
to perform a data-download, to synchronize the 5 Mimic panel application:
clock, to program the operative parameters i. Remote diagnostic identification by displaying
vii. Monitoring and recording on log files of the the operational state of the controller and
communications procedure and errors relevant components on an interactive on-line
viii. Diagnostics of communication based on the diagram
errors and faulty answers from the field, with
activation of alarm to signal the most critical
connections

♦ 15- 34♦
ii. Display of the state of equipment in real time xiii. Print out of log messages
mode (when on-line) or by records (from 8 Maintenance module
database)
i. Automatic elaboration of programmed
iii. Identification by color code of alarms and
maintenance plan, according to user's needs
operational state of: breakers, limit switches,
and settable parameters
contactors, relays etc…
ii. Facility to customize maintenance operations
iv. Display of all measures done by the local
iii. Print out of plan of activities
control module (voltage, current, power, power
iv. Recording of failures and unplanned activities
factor etc.)
v. Recording of real activity done
v. Manual override commands, in ON-LINE mode,
vi. Management of historical data
controlled directly from the mimic panel
6 Events and data analysis: 15.14.5 RCM Hardware
i. Events shall be able to be programmed in four
1 Personal computers shall be latest models and have
priority levels:
the following features:
Table, to display the events with predefined
i. Processor: Intel 2.0Ghz or over
customizable filters for each PC
ii. RAM memory: 1 GB
Bar graph for the analysis of the types of iii. Multi-serial with 5 ports COM (or in alternative
events and the objects involved USB hub with converters) (if not used by TCP/IP)
Events in cases of: override controls, iv. Parallel port
communication problems, automatic call v. Printer with continuous paper form
results, etc. vi. Double HD with indicative capacity 40GB each
Management of an appropriate printer for one (IDE or SCSI; same type)
recording alarms vii. If the HD is SCSI type, the controller must be
ii. Each alarm/event shall able to be configured to SCSI U/160.
send a message via SMS or e-mail viii. Color video card that grants a definition of
iii. Display of data of the plant (measures, monthly 1024x765 at least.
measures, alarms) through tables, graphs, ix. Minimum video memory card 32 Mb
active mimic panel of the selected unit x. Compatible back-up system
iv. Table to display data with predefined 2 Operative system shall be as stated below or as
customizable filters for each PC selected by the Concerned Authority:
v. Creation of customizable graphs for the analysis i. MS Windows 2000® Professional or Windows
of the most interested values XP® Professional, or latest system (up-to-date)
vi. Availability of different types of graphs (line, complete.
steps, cake, etc.)
3 Modems shall be:
7 Working parameters of controllers
i. Modem standard for wired telephone line
i. Data replicate tool, to revise and modify the (PSTN)
parameters of controllers ii. Modem GSM for SMS alarms
ii. Facility to transfer and read each parameter iii. Modem GSM/GPRS for SMS alarm
iii. Automatic control of errors during the
parameter transfer 15.14.6 Method of Measurement
iv. Facility to program in automatic mode each
controller or groups of them 1 The public lighting management and control system
v. Tool for automatic calculation of switch-on shall be measured by the number of completed feeder
hours of the plant, depending on astronomical pillars controlled by the PLMCS, installed and
clock parameters (for season and for year) commissioned. The rate per feeder pillar shall include for
vi. Print out of data list and the groups of objects the remote control and management software and
vii. Print out of all related tables (streets, supports, hardware, and any transmission/ communication media
lamps) between the feeder pillar and the control center. Rates are
viii. Table and graph print out, with filters, of events deemed to include for all work, including design supply,
ix. Table and graph print out, with filters, of transportation and installation, testing and commissioning
measures and instruction of the Concerned Authority’s personnel in
x. Table and graph print out, with filters, of operation of the system.
monthly data
xi. Report of the energy (theoretical, actual and 15.14.7 Basis of Payment
saving)
1 The amount of completed and accepted work
xii. Detailed print out of the working parameters of
measured as provided for above, will be paid for at the
the controllers
unit rate for PLMCS powered and controlled feeder pillar

♦ 15- 35♦
stated in the Bill of Quantities, which rate shall be full specified, all earthing materials and components shall be
compensation for supplying materials, installation, testing of copper.
and putting into operation, for labor, equipment, tools,
supplies, earthing, training, and other items of work 15.15.3 Construction Requirements
necessary for the completion of the system(s) to the
1 Exposed non-current carrying metallic parts of each
satisfaction of the Concerned Authority, as specified.
electrical installation and the neutral point of the
distribution system shall be earthed. The earthing of the
15.14.8 Items in the Bill of Quantities
distribution system shall be made at the neutral point of
i PLMCS installation at each feeder pillar the transformers.
and all related communication and central 2 A separate 50mm x 6mm high conductivity earth bar
control facilities. (nr) shall be mounted on porcelain connectors in each
substation and feeder pillar housing. The bar shall be pre-
drilled with a minimum distance of 75mm between holes
15.15 Earthing
and connected as follows:
i. Insulated cable:
15.15.1 Description
a. Transformer neutral
1 This Sub-section describes requirements for b. Earth mat
supplying, installing, and testing earthing connections in ii. Bare cable:
electrical installations, including transformer neutral a. Switchgear frame earth
earthing, main earthing terminals or bars, exposed b. Transformer frame earth
conductive parts of electrical equipment, extraneous
3 The insulated cable shall be green–yellow striped
conductive parts, and standby generator neutral earthing
50mm² single core PVC fixed at regular intervals with non-
where installed.
magnetic insulating cleats and terminated with suitably
2 The Contractor shall carry out work in accordance sized lugs. The bare conductors shall be 35mm x 6mm or
with the following: 50mm² high conductivity copper tape or conductor fixed at
BS 7671 chapter 54 (seventeenth edition) regular intervals with purpose made brass saddles.
or IEC 60364-5-54 (2004) 4 Each sub-station and feeder pillar earth mat shall
3 Prior to ordering materials, the Contractor shall have two 16mm diameter copper covered steel earth rods
submit data for the Engineer’s approval including, but not of 2.5m length, connected together and to the earth bar.
limited to, manufacturer’s catalogues for earth rods, Each rod shall be housed inside a concrete inspection box
connecting clamps, earthing conductors, protective recessed into the ground and fitted with a removable
conductors, bonding conductors, connectors and other metal lid with the inscription ’Earthing Rod’. An earth
accessories, exothermic welding kits and tools etc,, and resistance test shall be carried out on the earth bar at each
samples of conductors as requested. sub-station and feeder pillar. Three readings shall be
obtained on each of the two earth paths connected
4 The Contractor shall submit drawings for approval by
individually and in parallel. The results shall be tabulated
the Engineer, including, but not limited to the following:
and submitted to the Engineer for approval.
i. exact location of earth pits, rods and details of
5 The earth bar shall be labeled and the connections
installation and connections
identified. The insulated earthing cables for high mast and
ii. exact routing of buried earthing conductors with
lighting column circuits shall be earthed at the low voltage
indication of cross-section, depth of laying and
supply position at the earth bar.
covering
iii. cross sectional area of all earthing ,protective 6 At the masts and each last column on a circuit,
and bonding conductors earthing shall be by connecting the earthing bolt to a
iv. layout and details of earthing provisions at 16mm diameter copper covered steel rod of 2.5 m length
substations, switchgear, distribution minimum, driven into the ground adjacent to the mast or
panelboards etc., indicating fittings used, column to achieve the required resistance (1 ohm
insulation, plates and markings, passage and maximum). Bonding is to be by means of a 16mm2
routing of earthing conductors, conduit, sleeves, stranded bare copper conductor. Each mast and column
grooves, niches etc. giving sizes and shall be bonded to the earthing cable. Where the supply
dimensions of component parts. cable is looped into the column the earthing cable shall
not be cut. The final column in each distribution circuit
15.15.2 Materials shall be bonded to a separate earth rod.
7 The earthing system at sign lighting installations
1 Fittings, plant, equipment, ducts and cables used for
shall be as specified for masts and columns.
each earthing installation shall be as specified in other
pertinent Clauses of this Section 15. Unless otherwise 8 Connections between rods and earthing tape or
cables shall be made by the ’Cadweld’ process to produce

♦ 15- 36♦
a fused joint. Bolted connections may be used for 15.16 Labeling, Testing and
removable items of equipment only. Commissioning
9 Protective conductors shall not be formed by conduit,
trunking, ducting or the like. Where armored cable is 15.16.1 Description
specified and armor is steel, it may be used as a protective
conductor, if approved and if not otherwise shown on the 1 This Sub-section describes requirements for labeling,
Drawings. In general a protective conductor shall be run testing and commissioning of electrical and
together with the lighting power circuit unless otherwise communication systems installations and equipment. The
waived by the concerned authority. work is supplementary to the work specified in the
respective parts of this Section 15.
10 Connection of every earthing conductor to earthing
electrode and every bonding conductor to extraneous
15.16.2 Materials
conducting parts shall be labeled in accordance with the
applicable regulations, as follows: 1 Labels shall be manufactured from sheet aluminum,
‘SAFETY ELECTRICAL CONNECTION - DO NOT REMOVE’. plastics or other approved non-corrosive inert material.
Text shall be die-stamped, engraved, painted or printed
15.15.4 Earth Resistance Test with a legible life expectancy of 20 years. Finished labels
shall be permanently bonded, screwed, riveted, bolted or
1 Earth resistance tests shall be made by the wire-locked to the part as appropriate.
Contractor on the earthing system, separating and
reconnecting each earth connection. 15.16.3 Construction Requirements
2 If it is indicated that soil treatment or other corrective
measures are required to lower the ground resistance 15.16.3.1 Labeling
values, the Contractor shall submit proposals for
1 The Contractor shall submit for approval a
corrective measures to the Engineer for approval prior to
comprehensive labeling and marking plan before work is
working on such measures.
started. This shall include all factory labeled items as well
3 The electrical resistance of the earthing circuit (ECC) as field labeling.
together with the resistance of the earthing leads,
2 Plant and equipment not labeled to the Engineer's
measured from the connection with earth electrode to any
approval by the manufacturer shall be labeled by the
other position in the complete installation, shall not
Contractor on the Site.
exceed one ohm.
3 Equipment labels shall be simply and clearly written
5 Earth resistance test shall be performed as the
in black on white or white on black in English and Arabic,
Engineer’s requirements. The earth resistance of each
in accordance with the schematic diagram on the
electrode shall be measured by means of resistance
installation drawings. Warning labels shall be red on
bridge instrument and results recorded.
white or white on red lettering a minimum 15mm in height

15.15.5 Method of Measurement 4 Each item of plant, including individual parts of a


package sub-station or control panel, shall be labeled on
1 Earthing shall be measured by the number of the exterior of the respective casings.
completed sets of earthing rods supplied, installed, and
5 Lighting columns and masts shall be fitted with
tested. The interconnecting work within the circuit shall
identification labels of black lettering 50mm high on a
not be measured separately.
white background. The labels shall be attached to the
columns by means of galvanized nuts and bolts positioned,
15.15.6 Basis of Payment just above the access openings and facing approaching
1 The amount of completed and accepted work traffic.
measured as provided for above will be paid for at the unit 6 Control switchgear labels shall indicate the voltage,
rate stated in the Bill of-Quantities which rate shall be full current rating and phase color, together with the
compensation for supplying, installing, testing, manufacturer's distinguishing mark. A separate label shall
transportation, putting into operation and for materials, state the service controlled by the switch.
labor, equipment, tools, supplies and other items
7 Switchgear, distribution boards and apparatus shall
necessary for the proper completion of the work as
be included in an overall identification scheme and labeled
specified.
accordingly.
8 ’Danger High Voltage’ labels in English and Arabic
15.15.7 Items in the Bill of Quantities
with red lettering and electrical flash shall be fixed to the
i. Twin rod earthing installation (location) (nr) doors of each sub-station and switch station and be clearly
ii. Single rod earthing installation (location) (nr) visible from the fence access gates.
9 The interior of each item of electrical equipment shall
indicate the phases by means of colored plastic sleeving
or discs.

♦ 15- 37♦
10 Circuit lists shall be mounted on the inside of appropriate and have current calibration certificates issued
distribution board lids or doors. The list shall comprise a by an approved laboratory.
printed sheet heat-sealed into a semi-rigid clear plastic 4 Advance notice shall be given to the Engineer of the
cover. testing program proposed together with a list of the
11 Power cable cores shall be identified at their equipment to be used.
terminations by colored sheaths of the heat or chemically 5 The Contractor shall re-test any item that fails. No
shrinkable type to indicate the respective phases and repeat test shall be carried out until the cause of failure
neutral. Where the core insulation is suitably colored has been identified and removed.
during manufacture the colored sleeve may be omitted. 6 After satisfactory completion of the tests the
12 Local switches, switch-fuses, isolators, lighting Contractor shall obtain authorization from the Engineer
fittings, and similar accessories shall carry engraved and the Concerned Authority to connect the power supply
identification plates to indicate the circuit number and to the installation.
phase to which the accessory is connected.
13 Medium voltage cables shall be clearly labeled 15.16.4 Method of Measurement and Basis of
'DANGER HIGH VOLTAGE' in English and Arabic every 2m Payment
of exposed length. 1 No separate measurement shall be made and no
14 Prior to final testing the Contractor shall obtain the separate payment made for work of labeling, testing and
Engineer's approval that the labeling is intact over the Site commissioning of the electrical and telecommunication
and that circuit markers have been fitted wherever cables installations. The cost of this work is deemed to be
emerge from the duct system or enter a building. included in the unit rates for the respective items stated in
the Bill of Quantities.
15.16.3.2 Testing and Commissioning
15.17 Civil Works for Electrical and
1 Testing of the installations shall be carried out in
Telecommunication Installations
accordance with the relevant regulations and standards
after completion of the work. The tests shall be carried
out to the satisfaction of the Engineer and the concerned
15.17.1 Description
authority. Manufacturer’s test certificates shall be included 1 This Sub-section describes requirements for civil
in the documented results submitted for approval. work, including excavation, concrete, building work, and
2 Tests shall comprise the following: duct work, associated with the electrical and telecoms
- Insulation resistance on MV equipment installations.
including busbars, bushings, through
insulators and feeder terminations, using a 15.17.2 Materials
5000 V megger, between phases, and between 1 Backfill material for excavations shall be as specified
phase and earth, with control and protection in Section 2, Sub-section 2.7 of these Specifications.
circuits, lamps and similar components
2 Concrete for column and pole bases, equipment
disconnected.
foundations and other structures shall be Class 30 as
- Insulation resistance on every cable and specified in Sub-section 5.1. Reinforcement for concrete
insulator, power, control and relay circuit of the shall be mild steel in accordance with Section 5, Sub-
LV systems, using appropriate megger range; section 5.2 of these Specifications.
500 V for installations rated below 500 V and
3 Anchor bolts shall be as specified and shown on the
1000 V for installations rated up to 1000 V, in
Drawings and as instructed by the Engineer.
accordance with the IEE Wiring Regulations
(BS 7671) Subsection 612. Minimum standard shall be ASTM F1554, Grade 55,
minimum thread length of 10 inches, galvanized for a
- HV test, using power frequency HV test set, to
minimum of 12 inches on the threaded end to the
80% of IEC withstand voltage ( 2.5 rated
requirements of ASTM A153. Each is to be supplied with
voltage) for one-minute, between phases and
too hexagonal nuts and two flat washers, all to be hooked
phase to earth for each MV switchgear and
end on the embedded side.
transformer, disconnected.
4 Buildings to house switchgear for the medium
- MV cable tests as Sub-section 15.7, Paragraph
voltage switching station shall be as shown on the
15.7.3.2.
Drawings. They shall have adequate space for the
- Any other tests required by the concerned concerned Authority’s equipment. If buildings are not
authority standards, unless waived in writing defined on the Drawings, they shall be constructed of
by the Concerned Authority, conventional materials with concrete foundations and
3 The test and measuring apparatus provided by the floor, blockwork walls, rendered internally and externally,
Contractor to carry out the testing shall be sealed as and suitable waterproof roof. Doors shall be painted steel,

♦ 15- 38♦
lockable, and complete with ventilation louvers and sand 3 When cables cross road, paved area or other services
traps. Foundations and floors shall incorporate trenches or are buried in slab, they shall be laid in protective ducts
and ducts for cables and bases for equipment. of adequate size. The duct/ conduit ends after installation
5 Cable ducts shall be uPVC Schedule 40, UL listed, or of cable shall be plugged to make them watertight by
equivalent standard as specified or shown on the means of bituminized hessian or equivalent material.
Drawings. Minimum requirements shall be non-sparking 4 Cables shall be laid without sharp bends or kinks,
type, suitable for direct burial in ground, minimum tensile and if within 500mm of drainage ware, shall be contained
strength 500 kg/cm2, impact strength 5 kg/cm2, supplied in in a duct.
standard 6 m lengths. 5 Slack shall be left in cables for which purpose the cut
6 Unless otherwise indicated on the Drawings, lengths of cables shall allow about 3% more in the
columns 8m through 16m shall incorporate a cast measured length between terminations (Engineer will
aluminium breakaway transformer base and electrical verify the lengths of cables). At junction boxes, ample
breakaway quick disconnect. The base shall be designed slack shall be left to prevent straining of cable joints due to
and constructed so that when used with the size and settlement of cable trench.
weight of the column, the assembly shall meet the 6 Cables shall be pulled in uPVC ducts or conduits with
requirements of AASHTO Standard Specifications for care, preferably without the use of any lubricant. Where
Structural Supports for Highway Signs, Luminaires and necessary, and after approval of the Engineer, the cable
Traffic Signals. manufacturer’s recommended lubricant shall be used. Use
7 Transformer base and column combination shall be of any kind of oil or soap will not be permitted.
designed, fabricated and tested to withstand the wind 7 Sharp bends or tees shall not be allowed. At road
loads described in Clause 15.1.9, and Paragraph 15.8.2.1. crossings the duct shall have a bedding and surround of
8 The transformer base shall meet the following concrete Class 30 and shall be laid at 800 mm below road
standards: surface or as shown on drawings and directed by the
ASTM B108 alloy 5G70-T6 or alloy 356-T6 for the base Engineer.
ASTM A-325 for the bolts, ASTM A-563 Grade A for the 8 Prior to backfilling at duct location, the following
nuts, both galvanized to ASTM A-153. shall be completed:
i. Placement of the approved type of draw cord in
15.17.3 Construction Requirements each duct section
ii. Capping ducts at both ends
15.17.3.1 Bases for Poles and Equipment
iii. Recording the coordinates of both ends
1. Excavations for foundations shall be carried out in 9 Where ducts rest over rocky soil, a layer of 200 mm
accordance with Sub-section 2.7. Foundations located on dune sand shall be spread, compacted and rammed in
old backfill shall have the ground bearing material re- order to create proper bedding for the duct. In water-
compacted to the Engineer’s requirements. The sides of logged or unstable soil, a concrete base 200mm thick shall
excavations for foundations that will be subject to uplift or be laid, followed by 100mm layer of dune sand on top of
lateral forces shall be compacted and approved before any the concrete as a base for the duct.
concrete is poured.
10 Spare ducts shall be provided wherever ducts are
2. The position of anchor bolts in the concrete bases used for MV or LV cable routing. 30% spare ducts or at
shall be set by means of templates. The top of foundation least one duct per run, whichever is greater, shall be
bases shall be horizontal to a tolerance ±0.25mm across provided.
the width of an individual base.
11 Cables, whether installed in bare ground or in uPVC
Where shown on the Drawings duct stubs 300mm long ducts or conduits shall not be bent to a radius less than
and to the diameter shown shall be provided in the that recommended by the cable manufacturers.
structural concrete. uPVC ducts shall be cast into lighting
i. Install cables as indicated, according to
column, mast and feeder pillar bases to run the incoming
manufacturer's written instructions.
and outgoing power cables.
ii. Use manufacturer-approved pulling compound
15.17.3.2 Cable Trenches and Ducts or lubricant where approved; compound used
must not deteriorate conductor or insulation.
1 The depth of low voltage cable trench excavation Do not exceed manufacturer's recommended
shall provide a minimum cover to the cable of 500mm in maximum pulling tensions and sidewall
open ground and sidewalks. pressure values.
2 Cables shall be ducted where they run under or cross iii. Use pulling means, including fish tape, cable,
below roads and shall not be at less than 800mm deep, rope, and basket-weave wire/cable grips, that
with a concrete cover of 100mm all around. Duct ends will not damage cables or raceways. Do not use
shall extend minimum 600mm beyond road structure or rope hitches for pulling attachment to cable.
embankment where ducts cross the road iv. Install exposed cables, parallel and
perpendicular to surfaces of exposed structural

♦ 15- 39♦
members, and follow surface contours where the number and size of duct, including all bends,
possible. couplings and bushings. Concrete encasement shall not
v. Install direct-buried cables on leveled and be measured for direct payment but shall be considered as
tamped 100-mm bed of clean sand at bottom of subsidiary item, the cost of which will be deemed to be
trench. Separate cables crossing other cables included in rates for the duct.
or piping from those items by a minimum of 9 Cable markers, drawpits, handholes and manholes,
100 mm of tamped earth. shall be measured by detail shown on drawings, and
vi. Install permanent markers at ends of cable runs, number completed including all civil work and finishing
changes in direction, and buried splices. work.
vii. Install ‘buried cable’ warning tape 305 mm
above cables. 15.17.5 Basis of Payment
viii. Cable identification/route markers shall be
erected at 25m maximum spacing throughout 1 The quantity of completed and accepted work
the entire length of the cable trench route and at measured as provided for above will be paid for at the unit
each bend or intersection. Refer to MEW rates for the items stated in the Bill of Quantities, which
Standard OES 2 for all details. rates shall be full compensation for supplying all materials,
ix. In manholes, hand-holes, pull boxes, drawpits, formwork, construction, installation, testing and putting
junction boxes, and cable vaults, train cables into service, and for labor, equipment, tools, supplies,
around walls by the longest route from entry to transportation, and other work items necessary for the
exit and support cables at intervals adequate to proper completion of the work as specified.
prevent sag.
x. Seal around cables passing through fire-rated 15.17.6 Items in the Bill of Quantities
elements using approved fire-stopping material.
i Building for medium voltage intake
xi. Identify cables according to Section 15.16-
Labelling, Testing and Commissioning. switching station (reference drawing
and detail) (nr.)
15.17.4 Method of Measurement ii Concrete foundation for package
1 Buildings for the medium voltage switching stations substation (reference drawing
shall be measured by the number of the constructed block and detail) (nr.)
work buildings, including foundations, concrete roof,
iii Building for package
fence, and all necessary related civil works.
medium voltage switching station
2 Bases for package substations shall be measured by
the number of concrete foundations including fence and (reference drawing and detail) (nr.)
other builder’s works, as per the approved related shop iv H type concrete foundation for
drawings. 33kV/low voltage pole mounted
3 Buildings for package medium voltage switching transformer station (reference
stations shall be measured by the number of the
drawing and detail) (nr.)
constructed block work buildings, including foundations,
concrete roof, fence, and all necessary related civil works. v H type concrete foundation for

4 Bases for the 33kV/11kV pole mounted transformer 11kV/low voltage pole mounted
station shall be measured by the concrete base H type transformer station (reference
construction for 11m poles, to the detail of Concerned drawing and detail) (nr.)
Authority, including all related civil works.
vi Concrete base for feeder pillar
5 Bases for the feeder pillars shall be measured by the
(ref.dwg) (nr.)
number of concrete bases, including incoming and
outgoing ducts for cables and other builders work. vii Trench for low voltage cable for:

6 Trenches for directly buried cables shall be measured - one cable (lin.m)
by linear meter completed, including concrete tile, - two cables (lin.m)
warning tape and excavation and backfilling to levels and - three cables (lin.m)
dimensions as specified in the Drawings.
viii Trench for medium voltage cable for:
7 Bases for lighting columns/high masts shall be
- one cable (lin.m)
measured separately each by the number of concrete base
and other related civil works, including all related civil - two cables (lin.m)
work as the column detail approved. ix Lighting column concrete foundation
8 uPVC ducts shall be measured in linear meters of (Type, ref. dwg) (nr.)
multiple duct run installed in trench or in concrete x High mast concrete foundation
encasement, completed and accepted with reference to
(Type, ref. dwg) (nr.)

♦ 15- 40♦
xi uPVC duct (size and nr) (lin.m)
xii uPVC duct, in concrete encasement
(size and nr) (lin.m)
xiii Cable marker as per MEW details (nr.)
xiv Manhole (type, dimension, ref. dwg) (nr.)
xv Handhole or drawpit (type,
dimension, ref. dwg) (nr.)
xvi Cast aluminium breakaway transformer
base for column (height) (details,
ref. dwg) (nr.)

♦ 15- 41♦

Das könnte Ihnen auch gefallen