BOM:--

1.BOM usage:IMG --Production--Basic data--Bill of materials--General data--BOM


Usage--Define BOM Usage

2.Define Default Values for item status :-Set the default value for items in BOM.
IMG--Production--Basic data--Bill of materials--General data--BOM usage--Define
default values for the item status

3.Creation of BOM for Material type ROH should not be allowed.


IMG--Production--Basic data--Bill of materials-- General data--Define allowed
material type for BOM header ex: ROH -

Note :-When a new bill of material is created, the system checks the
material type as follows:� Non-generic entries are checked first. The generic
entries are checked afterwards.

4.BOM Status :-BOM status is used to define whether the BOM can be used by any
application area or not.BOM status defines whether The BOM is active or inactive.
IMG--Production--Basic data--Bill of materials-- General data--Define BOM status
5.This configuration setting enables to define item category. IMG--Production--
Basic data--Bill of materials-- Item data--Define item category
6.Define allowed material type for BOM items:
This configuration setting enables to control the item type which can be entered as
a component in the BOM.
Ex:--It is required to restrict FERT material to be the member of the BOM.
IMG--Production--Basic data--Bill of materials-- Item data--Define allowed material
type for BOM items
7.Define Explosion types:
IMG--Production--Basic data--Bill of materials--Item data--Define Explosion types.

8.Define Order of Priority:


This configuration setting enables to define order of priority for Bill Of Material
to be selected during MRP and production or process order creation. IMG--
Production--Basic data--Bill of materials-- Alternative determination--Define order
of priority for BOM usage.

9.Define Application:
This configuration setting enables to define BOM Application.BOM application
controls use of BOM in a specific area.
Areas like MRP run, cost estimate calculation etc.. will use the BOM of its own
respective BOM application.
IMG--Production--Basic data--Bill of materials--Alternative determination--Define
Applications

10.Define Alternative Determination for Multiple BOM :


IMG--Production--Basic data--Bill of materials--Alternative determination--Define
alternativedetermination for multiple BOM.

11.Define User-specific setting:


This configuration setting enables to configure the parameters specific to the
user.
IMG--Production--Basic data--Bill of materials-- Define user-specific settings

Work center :--

1. Define Work center Category: ex:Machine, processing unit, labor


IMG--Production--Basic data--Work center-- General Data --Define work center
category.

2.Define field selection :


This configuration setting enables to make the field in work center master data as
Mandatory
Optional
Highlight
Hide
scenario:-Make field person responsible for work center category 0007 as mandatory
field.
IMG--Production--Basic data--Work center-- General Data --Define field selection.

3.Define Task List usage:


This configuration setting enables to define the task list usage to the work
center.Usage of work center specific to the task list (i.e. only in the
master recipe or Routing) can be defined to restrict its usage.
IMG--Production--Basic data--Work center-- General Data --Define task list usage.

4.Define Parameters:
This configuration setting enables to define Parameter (activities) for
formula.Parameter is one of the required settings to calculate the conversion cost
incurred in the Work center during manufacturing.
IMG--Production--Basic data--Work center-- General Data --Standard Value--Define
Parameters.

5.Define Standard Value:This configuration setting enables to define the standard


value key.Standard value key is very essential to capture the cost incurred in the
work center.
Standard value key will contain the activities. One standard value key can contain
up to six activities. Each activity refers to the cost.One work center can have
only one standard value key
IMG--Production--Basic data--Work center-- General Data --Standard Value--Define
standard value key.
6.Determine Person ResponsibleThis configuration setting enables to define the
person responsible for work center.
IMG--Production--Basic data--Work center-- General Data --Determine person
responsible
7. Define Control Key:
IMG--Production--Basic data--Work center-- Routing Data-- Define control key

Capacity Planning:--

Define Capacity Category:


Capacity category will differentiate the type of capacity used in
the work center.
Capacities can be
� Machine
� Labor
� Processing unit
Capacity category and capacity details are assigned to the work center.
IMG--Production--Basic data--Work center-- Capacity Planning-- Define capacity
category
Determine Capacity Planner:
Capacity planner is the person who is responsible to plan and schedule the
specified capacity.
IMG--Production--Basic data--Work center-- Capacity Planning-- Determine capacity
planner

Define Shift Sequence:


Shift sequence is used to define the specific working pattern.I.e. weekly holidays,
number of shift and working hours of each shift.Work center capacity
is calculated from its working hours defined in the capacity header details of the
work center.
IMG--Production--Basic data--Work center-- Capacity Planning-- Available capacity--
Define shift sequence
Define Formula Parameters for Work centers:
Formulas are to be defined to calculate
Cost
Capacity requirements
Schedule the operation
Formula parameter will be used in the formulas. Formulas are
used in the work center capacity view, scheduling view and
costing view to
Calculate capacity
Schedule the operation
Calculate the activity cost.
IMG--Production--Basic data--Work center-- Capacity Planning-- Work center
formulas-- Define formula parameter for work center
Define Formula for Work centers:
Formulas are used in
� Calculate capacity requirement
� Schedule the start and end of the operation
� Calculate the cost
Formulas will be assigned in the work center capacity view,
scheduling view and in costing view.
IMG--Production--Basic data--Work center-- Capacity Planning-- Work center
formulas-- Define formula parameter for work center

Define Factory calendar:

Factory calendar will contain the entire working day and holiday details for a
specific plant.Factory calendar will be attached to the capacity header.Factory
calendar will be referred while scheduling the
operations.IMG--General settings -- Maintain Calendar
Note:-Factory calendar will be defined directly in the client. It will not be
captured and transported through Transport Management.

Define Default Capacity:


By defining the default capacity, for work center and resource,if the capacity is
not defined, system will consider this default capacity detail.
IMG--Production--Basic data--Work center-- Capacity Planning-- Define default
capacity

Define Work center screen sequence:

Screen sequence setting controls the sequence of appearance of screen while


creating the work center master data.
IMG--Production--Basic data--Work center-- Setup work center screen sequence
Routing :---

Define standard value description in operation over view :


IMG--Production--Basic data--Routing-- Control data-- Define standard value
description in operation over view

Define Routing Status:


IMG--Production--Basic data--Routing-- General data-- Define routing statuses

Define Task List usage:


Task list usage defines the specific purpose of routing.There are four important
usage of Routing.
� Production usage
� Costing only
� Sales and Distribution
� Universal ( all purpose)IMG--Production--Basic data--Routing-- General data--
Define routing usage
Define Reduction Strategy :
Reduction strategy defines the sequence of compressing the time or duration to meet
the production dates.Reduction strategy can reduce the following times which are
involved in scheduling.
� Queue time
� Move time
� Over lapping
� SplitIMG--Production--Basic data--Routing-- Operation data-- Define reduction
strategy

Define User Fields :


User field can be used in the operation heading in the task list to define your own
reference data.Maximum of six fields can be defined through the user field.
IMG--Production--Basic data--Routing-- Operation data-- Define user fields
Define Routing Selection Automatic :
IMG--Production--Basic data--Routing-- Routing selection-- Select automatically