Retrofit schedule for QDR Bath & Chemical Bath of WD0, Retrofit Schedule of WD1 Sep.

Sep. 13, 2013 JY Jeong


Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
Description Remark
Day1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
● P/O
- Purchase Order ●
● System Inspection
- Inspection engineer Arrival at RST
- Hardware Measuring & Meeting
- Software Monitoring & Meeting

● Hardware Design
- QDR Bath & Chemical Bath
- Circulation Unit

● Software Design
- P & ID Review
- System Process Review
- Software & Electronic Modification Design

● Parts Delivery for QDR retrofit


- QDR Bath with N2 Bubbling manufacturing
- Plumbing Parts for QDR retrofit preparation
- Shipment to RST

● Retrofit for QDR Baths for WD0 at site


- PLEX Engineer arrival at RST ●
- Disassemble of current parts
- Parts arrival at RST ●
- QDR Bath Setting ● 7 days expected
- Plumbing Parts connection
- Software Modification
- Electric Wiring Modificaiton
- Auto Running Test & Debugging

● Parts Delivery for Chemical Bath retrofit


- chemical Bath for Detergent and SC2
- Plumbing Parts for Chemical retrofit preparation
- Circulation Unit manufacturing
- Shipment to RST

● Retrofit for QDR Baths dfor WD0 at site


- Disassemble of current parts
- Parts arrival at RST ●
- Chemical Bath Setting ●
7 days expected
- Plumbing Parts connection
- Software Modification
- Electric Wiring and Modification
- Auto Running Test & Debuggig

● Parts Delivery for WD1 retrofit


- Parts Preparation
- Shipmetn for RST

● Retrofit for QDR Baths dfor WD0 at site


- Disassemble of current parts
- Parts arrival at RST ●
7 days expected
- Chemical Bath Setting ●
- Plumbing Parts connection
- Auto Running Test & Debuggig