PROJECT: Sison Residence (2 Storey with Veranda & Carpark)

LOCATION: B 24, L 7, Nuvista San Jose - CSJDM Bulacan


DATE: 22-Feb-20
DURATION: Feb 17, 2020 - Feb 22, 2020

I. SCOPE OF WORK

• Concrete Pouring for Wall footings


• Fabrication of Steel Bars
• Concrete pouring of Columns and CHB Laying
• Installation of 2nd Floor Beams

II. DOCUMENTATION:

A. Anticipated Activities for the upcoming week

• Formworks and Rebar Installation for Slab 2nd Floor


• Installation of 2nd Floor Beams
• Leveling of Ground
III. STATEMENT OF ACCOMPLISHMENTS Actual Progress
Remaining tasks
THIS ACC. WT REMAIN
DESCRIPTION QTY U PREV. U U ACT. (%)
WEEK (%) (%)
A. EARTHWORKS
Excavation works 277.20 m² m² 277.2 m² 7.99% 7.99% 0.00%
Compaction And Backfilling 166.32 m² m² 142.32 m² 4.79% 4.10% 0.69%
B. STRUCTURAL WORKS
Foundation
Reinforced Concrete footing 48.00 m² m² 48 m² 1.38% 1.38% 0.00%
Reinforced Concrete Column on grade 30.00 m³ m² 27.1 m² 0.86% 0.78% 0.08%
Reinforced Concrete Wall Footing 83.32 m² m² 83.32 m² 2.40% 2.40% 0.00%
Demolition of Walls for Extension 33.00 m² m² 27.3 m² 0.95% 0.79% 0.16%
Ground floor
Reinforced Concrete Slab 35.81 m² m² m² 1.03% 0.00% 1.03%
Reinforced Concrete slab for Garage 38.49 m² m² m² 1.11% 0.00% 1.11%
Reinforced Concrete column (Perimeter) 68.40 60.4 1.97% 1.74%
Reinforced Concrete column 21.60 m² m² 21.6 m² 0.62% 0.62% 0.00%
Reinforced Concrete beams and girder 89.64 m² m² 67.87 m² 2.58% 1.96% 0.63%
Second Floor
Reinforced Concrete Slab (Including Balcony) 30.30 m² m² m² 0.87% 0.00% 0.87%
Reinforced Concrete column 43.20 m² m² m² 1.24% 0.00% 1.24%
Reinforced Concrete Roof beams and girder 16.67 m² m² m² 0.48% 0.00% 0.48%
C. ARCHITECTURAL WORKS
i MASONRY WORKS
Exterior Walls (CHB Laying) 227.40 m² m² 205.55 m² 6.55% 5.92% 0.63%
Interior Walls (CHB Laying) 128.00 m² m² 50.1 m² 3.69% 1.44% 2.24%
Plastering and Wall Finish (Exterior) 454.80 m² m² m² 13.10% 0.00% 13.10%
Plastering and Wall Finish (Interior) 256.00 m² m² m² 7.38% 0.00% 7.38%
ii CEILING WORKS
Ground floor
Ceiling Works Joists and Boards 72.00 m² m² m² 2.07% 0.00% 2.07%
Second Floor
Ceiling Works Joists and Boards 66.00 m² m² m² 1.90% 0.00% 1.90%
iv ROOFING WORKS
Truss Installation 12.19 m² m² m² 0.35% 0.00% 0.35%
Roofing sheets and Tinsmithing 19.17 m² m² m² 0.55% 0.00% 0.55%
v DOORS AND WINDOWS
Ground floor
Installation of Doors and Windows 33.20 m² m² m² 0.96% 0.00% 0.96%
vi PAINTING WORKS
Painting/Finishing works at Exterior 454.80 m² m² m² 13.10% 0.00% 13.10%
Painting/Finishing works at Interior 256.00 m² m² m² 7.38% 0.00% 7.38%
Painting/Finishing at Ceiling Area 138.00 m² m² m² 3.98% 0.00% 3.98%
vii TILING/CLADDING WORKS
Ground floor
Installation of Floor tiles 72.00 m² m² m² 2.07% 0.00% 2.07%
Installation of countertop at kitchen 0.99 m² m² m² 0.03% 0.00% 0.03%
Second Floor
Installation of Floor tiles 66.00 m² m² m² 1.90% 0.00% 1.90%
Installation of Floor tiles at veranda 18.60 m² m² m² 0.54% 0.00% 0.54%
D. ELECTRICAL/PLUMBING
Ground floor
Electrical Installation 60.58 m² m² 29.87 m² 1.75% 0.86% 0.88%
Plumbing Installation 60.58 m² m² 29.87 m² 1.75% 0.86% 0.88%
Second Floor
Electrical Installation 92.26 m² m² m² 2.66% 0.00% 2.66%
3470.51 0.00 1070.5 100.00% 30.85% 68.92%

IV. CONSTRUCTION UPDATES

A. Accomplishment photos
Excavation for Footings