PROJECT: Sison Residence (2 Storey with Veranda & Carpark)
LOCATION: B 24, L 7, Nuvista San Jose - CSJDM Bulacan
DATE: 22-Feb-20 DURATION: Feb 17, 2020 - Feb 22, 2020
I. SCOPE OF WORK
• Concrete Pouring for Wall footings
• Fabrication of Steel Bars • Concrete pouring of Columns and CHB Laying • Installation of 2nd Floor Beams
II. DOCUMENTATION:
A. Anticipated Activities for the upcoming week
• Formworks and Rebar Installation for Slab 2nd Floor
• Installation of 2nd Floor Beams • Leveling of Ground III. STATEMENT OF ACCOMPLISHMENTS Actual Progress Remaining tasks THIS ACC. WT REMAIN DESCRIPTION QTY U PREV. U U ACT. (%) WEEK (%) (%) A. EARTHWORKS Excavation works 277.20 m² m² 277.2 m² 7.99% 7.99% 0.00% Compaction And Backfilling 166.32 m² m² 142.32 m² 4.79% 4.10% 0.69% B. STRUCTURAL WORKS Foundation Reinforced Concrete footing 48.00 m² m² 48 m² 1.38% 1.38% 0.00% Reinforced Concrete Column on grade 30.00 m³ m² 27.1 m² 0.86% 0.78% 0.08% Reinforced Concrete Wall Footing 83.32 m² m² 83.32 m² 2.40% 2.40% 0.00% Demolition of Walls for Extension 33.00 m² m² 27.3 m² 0.95% 0.79% 0.16% Ground floor Reinforced Concrete Slab 35.81 m² m² m² 1.03% 0.00% 1.03% Reinforced Concrete slab for Garage 38.49 m² m² m² 1.11% 0.00% 1.11% Reinforced Concrete column (Perimeter) 68.40 60.4 1.97% 1.74% Reinforced Concrete column 21.60 m² m² 21.6 m² 0.62% 0.62% 0.00% Reinforced Concrete beams and girder 89.64 m² m² 67.87 m² 2.58% 1.96% 0.63% Second Floor Reinforced Concrete Slab (Including Balcony) 30.30 m² m² m² 0.87% 0.00% 0.87% Reinforced Concrete column 43.20 m² m² m² 1.24% 0.00% 1.24% Reinforced Concrete Roof beams and girder 16.67 m² m² m² 0.48% 0.00% 0.48% C. ARCHITECTURAL WORKS i MASONRY WORKS Exterior Walls (CHB Laying) 227.40 m² m² 205.55 m² 6.55% 5.92% 0.63% Interior Walls (CHB Laying) 128.00 m² m² 50.1 m² 3.69% 1.44% 2.24% Plastering and Wall Finish (Exterior) 454.80 m² m² m² 13.10% 0.00% 13.10% Plastering and Wall Finish (Interior) 256.00 m² m² m² 7.38% 0.00% 7.38% ii CEILING WORKS Ground floor Ceiling Works Joists and Boards 72.00 m² m² m² 2.07% 0.00% 2.07% Second Floor Ceiling Works Joists and Boards 66.00 m² m² m² 1.90% 0.00% 1.90% iv ROOFING WORKS Truss Installation 12.19 m² m² m² 0.35% 0.00% 0.35% Roofing sheets and Tinsmithing 19.17 m² m² m² 0.55% 0.00% 0.55% v DOORS AND WINDOWS Ground floor Installation of Doors and Windows 33.20 m² m² m² 0.96% 0.00% 0.96% vi PAINTING WORKS Painting/Finishing works at Exterior 454.80 m² m² m² 13.10% 0.00% 13.10% Painting/Finishing works at Interior 256.00 m² m² m² 7.38% 0.00% 7.38% Painting/Finishing at Ceiling Area 138.00 m² m² m² 3.98% 0.00% 3.98% vii TILING/CLADDING WORKS Ground floor Installation of Floor tiles 72.00 m² m² m² 2.07% 0.00% 2.07% Installation of countertop at kitchen 0.99 m² m² m² 0.03% 0.00% 0.03% Second Floor Installation of Floor tiles 66.00 m² m² m² 1.90% 0.00% 1.90% Installation of Floor tiles at veranda 18.60 m² m² m² 0.54% 0.00% 0.54% D. ELECTRICAL/PLUMBING Ground floor Electrical Installation 60.58 m² m² 29.87 m² 1.75% 0.86% 0.88% Plumbing Installation 60.58 m² m² 29.87 m² 1.75% 0.86% 0.88% Second Floor Electrical Installation 92.26 m² m² m² 2.66% 0.00% 2.66% 3470.51 0.00 1070.5 100.00% 30.85% 68.92%