Bill of Quantity :

Protective Works

PART C : PROTECTIVE WORK

Item Rate Amount


Ref. to SOR Description of Item Unit Quantity
No. (Rs.) (Rs.)
C-1 Ref .Item # Filling properly the empty sausage crates with boulders
18.31, page-336 of any size & shape with hand packing after preparation of
of S.O.R of P.W bed of placement, placing the crate in position, carriage of
(Roads), 2018 boulders from road stacks with a lead upto 150m etc.
complete in all respect including stitching the rest of the crate
with wire (passage for filling boulders) after filling up the crate cum 5175.00 2092.25 108,27,394
with boulders and launching the crate in position if necessary
and as directed by the Engineer-in charge.

C-2 Ref .Item # Weaving wire mattress as directed with wire of 4mm dia and
18.30, page-336 making sausage crate of required shape after tying all
of S.O.R of P.W intersections including joining longitudinal ends, closing ends
(Roads), 2018 of sausage, carriage of wire to site of work complete in all
sqm 26910.00 201.00 54,08,910
respect as per direction of the Engineer-in-charge including
cost of supply of G.I. wire. (With 100mm x 100mm mesh.)

C-3 Ref .Item # Providing and laying Design Mix concrete for plain
18.07(a), Page- concrete work in any part of bridge (excluding bottom
333 of S.O.R of plugging) with pakur coarse aggregates of appropriate
P.W (Roads), nominal size and grading, fine aggregate (coarse sand)
2018 conforming to proper grading zone, both of approved quality
and cement, as necessary, including labour, cost and
carriage of all materials and including preparation of design cum 207.00 5111.57 10,58,095
mix, approval of the same by the Engineer-in-Charge and
cost for quality control, sampling, testing etc. all complete but
excluding cost of labour and materials for formwork &
reinforcement works.

M-15, Using concrete mixer


Over Bolder Toping
C-4 Ref .Item # Earthwork in excavation for foundation of structures upto
11.01, Page- 3 m depth as per drawing and technical specification Clause
282 of S.O.R of 1104 for Rural Roads of MORD including setting out,
P.W (Roads), construction of shoring and bracing, removal of stumps and cum 517.50 104.00 53,820
2018 other deleterious matter, dressing of sides and bottom and
backfilling with approved material.

C-5 Ref Item # Hire and labour charges for Shuttering with or without
18.05(b), page- staging upto 4.0 m height using approved stout props with
332, S.O.R of wooden planks/ply wood/steel sheet plate with required
P.W (Roads), bracing for any kind of plain or reinforced concrete works in
2018 all sorts of minor structure including culvert, box culvert, sqm 12880.00 214.00 27,56,320
crossdrain etc. The rate is inclusive of fitting, fixing and
striking out after completion of work as per specification and
direction.
Where staging is not required.
Total Protective Works : Rs. 201,04,539
Quantity Calculation :
Protective Works

Quantity Estimate of proposed Protective Work

Detailed List of Protective Work


Starting Ending
Length (m) Side Remarks
Chainage Chainage
0+000 1+143 1143.00 LHS Submerged Area
0+000 1+143 1143.00 RHS Submerged Area
1+353 1+367 14.00 RHS Submerged Area
Total Quantity = 2300.00 m

ITEM No. C-1 : Filling properly the empty sausage crates with boulders of any size & shape ……

2300.00 x (1.2+0.9) / 2 x 1.00 2415.00 cum


2300.00 x 1.20 x 1.00 2760.00 cum

Total Quantity = 5175.00 cum

ITEM No. C-2 : Weaving wire mattress as directed with wire of 4mm dia and making sausage crate ……

(Considering laping length = 0.40 m)


2 x 2300.00 x ((1.2+0.9) / 2) + 0.4 6670.00 sqm
2 x 2300.00 x 1.40 6440.00 sqm
2 x 2300.00 x 1.60 7360.00 sqm
2 x 2300.00 x 1.40 6440.00 sqm
Total Quantity = 26910.00 sqm

ITEM No. C-3 : Providing and laying Design Mix concrete for plain concrete work in any part of bridge ……

M-15, Using concrete mixer Over Bolder Toping

2300.00 x 0.90 x 0.100 207.00 cum

Total Quantity = 207.00 cum

ITEM No. C-4 : Earthwork in excavation for foundation of structures upto 3 m depth as per drawing ……

2300.00 x 1.50 x 0.15 517.50 cum

ITEM No. C-5 : Hire and labour charges for Shuttering with or without staging upto 4.0 m heigh ……
Where staging is not required.
2 x 2300.00 x 0.10 460.00 sqm
3 locations x 2 x 2300.00 x 0.90 12420.00 sqm
Total Quantity = 12880.00 sqm
Analysis of Rates :
Protective Works

ANALYSIS OF RATES FOR PROTECTIVE WORKS

ITEM No. C-1 : Filling properly the empty sausage crates with boulders of any size & shape ……

Schedule Ref .Item # 18.31, page-336 of S.O.R of P.W (Roads), 2018


Ref.: Unit : cum

Materials required =
3
Stone Boulder 1.00 m x 1661.25 = Rs. 1661.25
3
Labour rate = 431.00 per m
3
Total= 2092.25 per m
3
Total = Rs. 2092.25 per m

ITEM No. C-2 : Weaving wire mattress as directed with wire of 4mm dia and making sausage crate ……

Schedule Ref .Item # 18.30, page-336 of S.O.R of P.W (Roads), 2018


Ref.: Unit : sqm

2
Labour rate = 201.00 per m
2
Total = Rs. 201.00 per m

ITEM No. C-3 : Providing and laying Design Mix concrete for plain concrete work in any part of bridge ……
M-15, Using concrete mixer Over Bolder Toping
Schedule Ref .Item # 18.07(a), Page-333 of S.O.R of P.W (Roads), 2018
Ref.:
Unit : cum
a) Cost of Labour , T& P Machineries etc. Rs.1,406.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)

20 mm stone chips cum 0.54 1885.75 1018.31


10 mm stone chips cum 0.36 1754.75 631.71
Cement kg 350 5.873 2055.55
Total cost of material = Rs.3,705.6
Total (a+b) = Rs.5,111.57
Say , Rs.5,111.57
ITEM No. C-4 : Earthwork in excavation for foundation of structures upto 3 m depth as per drawing ……

Schedule Ref .Item # 11.01, Page-282 of S.O.R of P.W (Roads), 2018


Ref.: Unit : cum

Materials required =
3
Labour rate = 104.00 per m
3
Total = Rs. 104.00 per m

ITEM No. C-5 : Hire and labour charges for Shuttering with or without staging upto 4.0 m heigh ……
Where staging is not required.
Schedule Ref Item # 18.05(b), page-332, S.O.R of P.W (Roads), 2018
Ref.: Unit : sqm
3
Labour rate = 214.00 per m
3
Total = Rs. 214.00 per m