Protective Works
C-2 Ref .Item # Weaving wire mattress as directed with wire of 4mm dia and
18.30, page-336 making sausage crate of required shape after tying all
of S.O.R of P.W intersections including joining longitudinal ends, closing ends
(Roads), 2018 of sausage, carriage of wire to site of work complete in all
sqm 26910.00 201.00 54,08,910
respect as per direction of the Engineer-in-charge including
cost of supply of G.I. wire. (With 100mm x 100mm mesh.)
C-3 Ref .Item # Providing and laying Design Mix concrete for plain
18.07(a), Page- concrete work in any part of bridge (excluding bottom
333 of S.O.R of plugging) with pakur coarse aggregates of appropriate
P.W (Roads), nominal size and grading, fine aggregate (coarse sand)
2018 conforming to proper grading zone, both of approved quality
and cement, as necessary, including labour, cost and
carriage of all materials and including preparation of design cum 207.00 5111.57 10,58,095
mix, approval of the same by the Engineer-in-Charge and
cost for quality control, sampling, testing etc. all complete but
excluding cost of labour and materials for formwork &
reinforcement works.
C-5 Ref Item # Hire and labour charges for Shuttering with or without
18.05(b), page- staging upto 4.0 m height using approved stout props with
332, S.O.R of wooden planks/ply wood/steel sheet plate with required
P.W (Roads), bracing for any kind of plain or reinforced concrete works in
2018 all sorts of minor structure including culvert, box culvert, sqm 12880.00 214.00 27,56,320
crossdrain etc. The rate is inclusive of fitting, fixing and
striking out after completion of work as per specification and
direction.
Where staging is not required.
Total Protective Works : Rs. 201,04,539
Quantity Calculation :
Protective Works
ITEM No. C-1 : Filling properly the empty sausage crates with boulders of any size & shape ……
ITEM No. C-2 : Weaving wire mattress as directed with wire of 4mm dia and making sausage crate ……
ITEM No. C-3 : Providing and laying Design Mix concrete for plain concrete work in any part of bridge ……
ITEM No. C-4 : Earthwork in excavation for foundation of structures upto 3 m depth as per drawing ……
ITEM No. C-5 : Hire and labour charges for Shuttering with or without staging upto 4.0 m heigh ……
Where staging is not required.
2 x 2300.00 x 0.10 460.00 sqm
3 locations x 2 x 2300.00 x 0.90 12420.00 sqm
Total Quantity = 12880.00 sqm
Analysis of Rates :
Protective Works
ITEM No. C-1 : Filling properly the empty sausage crates with boulders of any size & shape ……
Materials required =
3
Stone Boulder 1.00 m x 1661.25 = Rs. 1661.25
3
Labour rate = 431.00 per m
3
Total= 2092.25 per m
3
Total = Rs. 2092.25 per m
ITEM No. C-2 : Weaving wire mattress as directed with wire of 4mm dia and making sausage crate ……
2
Labour rate = 201.00 per m
2
Total = Rs. 201.00 per m
ITEM No. C-3 : Providing and laying Design Mix concrete for plain concrete work in any part of bridge ……
M-15, Using concrete mixer Over Bolder Toping
Schedule Ref .Item # 18.07(a), Page-333 of S.O.R of P.W (Roads), 2018
Ref.:
Unit : cum
a) Cost of Labour , T& P Machineries etc. Rs.1,406.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
Materials required =
3
Labour rate = 104.00 per m
3
Total = Rs. 104.00 per m
ITEM No. C-5 : Hire and labour charges for Shuttering with or without staging upto 4.0 m heigh ……
Where staging is not required.
Schedule Ref Item # 18.05(b), page-332, S.O.R of P.W (Roads), 2018
Ref.: Unit : sqm
3
Labour rate = 214.00 per m
3
Total = Rs. 214.00 per m