CONSTRUCTION SCHEDULE OF PROPOSED ONE STORY RESIDENTIAL HOUSE

ID WBS Task Task Name Duration Start Finish Predecessors Dec '19 Jan '20 Feb '20
Mode 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23
0 XSTRUC-1 PROPOSED ONE STOREY 75 days 24 Nov '19 06 Feb '20
RESIDENTIAL HOUSE
1 XSTRUC-1001 KEY DATES 75 days 24 Nov '19 06 Feb '20
2 XSTRUC-1001.01 Start Date 0 days 24 Nov '19 24 Nov '19 24/11
3 XSTRUC-1001.02 Finish Date 0 days 06 Feb '20 06 Feb '20 7FF 06/02
4 XSTRUC-1002 PRELIMINARIES 75 days 24 Nov '19 06 Feb '20
5 XSTRUC-1002.01 Mobilization 2 days 24 Nov '19 25 Nov '19 2 Mobilization
6 XSTRUC-1002.02 General Requirements 0 days 24 Nov '19 24 Nov '19 5SS 24/11
7 XSTRUC-1002.03 Demobilization 2 days 05 Feb '20 06 Feb '20 65FF Demobilization
8 XSTRUC-1003 ENGINEERING 73 days 26 Nov '19 06 Feb '20
9 XSTRUC-1003.01 Shop Drawings 6 days 26 Nov '19 01 Dec '19 5 Shop Drawings
10 XSTRUC-1003.02 As-built drawing 6 days 01 Feb '20 06 Feb '20 65FF As-built drawing
11 XSTRUC-1004 CONSTRUCTION PHASE 75 days 24 Nov '19 06 Feb '20
12 XSTRUC-1004.01 02 Site Works/Earthworks 21 days 27 Nov '19 17 Dec '19
13 XSTRUC-1004.01.1 Site Preparation & Setting out 3 days 02 Dec '19 04 Dec '19 9 Site Preparation & Setting out
14 XSTRUC-1004.01.2 Excavation for foundation 5 days 05 Dec '19 09 Dec '19 13 Excavation for foundation
15 XSTRUC-1004.01.3 Excavation for grade beam 2 days 10 Dec '19 11 Dec '19 14 Excavation for grade beam
16 XSTRUC-1004.01.4 Backfilling around foundation 3 days 14 Dec '19 16 Dec '19 22 Backfilling around foundation
17 XSTRUC-1004.01.5 Backfilling around gradebeam 1 day 27 Nov '19 27 Nov '19 23 Backfilling around gradebeam
18 XSTRUC-1004.01.6 Gravel bedding under slab on 1 day 17 Dec '19 17 Dec '19 33 Gravel bedding under slab on grade
grade
19 XSTRUC-1004.02 03 Concrete Works 28 days 24 Nov '19 21 Dec '19
20 XSTRUC-1004.02.1 Substructure 28 days 24 Nov '19 21 Dec '19
21 XSTRUC-1004.02.1.1 Foundation 3 days 10 Dec '19 12 Dec '19 14 Foundation
22 XSTRUC-1004.02.1.2 Column Neck 1 day 13 Dec '19 13 Dec '19 21 Column Neck
23 XSTRUC-1004.02.1.3 Grade Beam 3 days 24 Nov '19 26 Nov '19 Grade Beam
24 XSTRUC-1004.02.1.4 Slab on grade 4 days 18 Dec '19 21 Dec '19 18 Slab on grade
25 XSTRUC-1004.02.2 Superstructure 9 days 28 Nov '19 06 Dec '19
26 XSTRUC-1004.02.2.1 Column 3 days 28 Nov '19 30 Nov '19 17 Column
27 XSTRUC-1004.02.2.2 Beam 6 days 01 Dec '19 06 Dec '19 26 Beam
28 XSTRUC-1004.03 04 Masonry Works 22 days 22 Dec '19 12 Jan '20
29 XSTRUC-1004.03.1 Laying of CHB 13 days 22 Dec '19 03 Jan '20 24 Laying of CHB
30 XSTRUC-1004.03.2 Plastering Works 18 days 26 Dec '19 12 Jan '20 29SS+4 days Plastering Works
31 XSTRUC-1004.04 05 Metal Works 7 days 10 Dec '19 16 Dec '19
32 XSTRUC-1004.04.1 Structural Steel 5 days 10 Dec '19 14 Dec '19 27FS+3 days Structural Steel
33 XSTRUC-1004.04.2 Roofing 3 days 14 Dec '19 16 Dec '19 32SS+4 days Roofing
34 XSTRUC-1004.05 06 Doors & Window 21 days 13 Jan '20 02 Feb '20
35 XSTRUC-1004.05.1 Doors 21 days 13 Jan '20 02 Feb '20
36 XSTRUC-1004.05.1.1 Installation of door jamb 2 days 13 Jan '20 14 Jan '20 30 Installation of door jamb
37 XSTRUC-1004.05.1.2 Installation of doors & 2 days 01 Feb '20 02 Feb '20 36,42 Installation of doors & hardwares
hardwares
38 XSTRUC-1004.05.2 Windows 2 days 13 Jan '20 14 Jan '20
39 XSTRUC-1004.05.2.1 Installation of windows 2 days 13 Jan '20 14 Jan '20 30 Installation of windows
40 XSTRUC-1004.06 07 Finishes 35 days 03 Jan '20 06 Feb '20
41 XSTRUC-1004.06.1 Floor Finishes 8 days 24 Jan '20 31 Jan '20
42 XSTRUC-1004.06.1.1 Ceramic Floor Tiles 8 days 24 Jan '20 31 Jan '20 48 Ceramic Floor Tiles
43 XSTRUC-1004.06.2 Wall Finishes 35 days 03 Jan '20 06 Feb '20
44 XSTRUC-1004.06.2.1 Ceramic Wall Tiles 4 days 04 Jan '20 07 Jan '20 29 Ceramic Wall Tiles
45 XSTRUC-1004.06.2.2 Painting works for wall 12 days 03 Jan '20 14 Jan '20 30SS+8 days Painting works for wall
46 XSTRUC-1004.06.2.3 Touch up painting 6 days 01 Feb '20 06 Feb '20 45,37SS,39 Touch up painting
47 XSTRUC-1004.06.3 Ceiling Finishes 11 days 13 Jan '20 23 Jan '20
48 XSTRUC-1004.06.3.1 Ceiling work 11 days 13 Jan '20 23 Jan '20 30 Ceiling work
49 XSTRUC-1004.06.3.2 Painting works for ceiling 2 days 13 Jan '20 14 Jan '20 48SS Painting works for ceiling
50 XSTRUC-1004.07 08 Electrical Work 47 days 22 Dec '19 06 Feb '20
51 XSTRUC-1004.07.1 Installation of 1st Fix 2 days 22 Dec '19 23 Dec '19 29SS Installation of 1st Fix (Conduiting)
(Conduiting)
52 XSTRUC-1004.07.2 2nd Fix (Cabling/Wiring) 4 days 20 Jan '20 23 Jan '20 48FF,30FF,51,53,45 2nd Fix (Cabling/Wiring)
53 XSTRUC-1004.07.3 Installation of Panel 1 day 15 Jan '20 15 Jan '20 45 Installation of Panel
54 XSTRUC-1004.07.4 Installation of Final Fix (Lighting 2 days 05 Feb '20 06 Feb '20 48,52,46FF,49 Installation of Final Fix (Lighting Fixture & Power devices)
Fixture & Power devices)

55 XSTRUC-1004.08 09 Plumbing/Sanitary and Waste 55 days 10 Dec '19 02 Feb '20


Drainage System
56 XSTRUC-1004.08.1 Plumbing/Sanitary 55 days 10 Dec '19 02 Feb '20
57 XSTRUC-1004.08.1.1 Roughing-ins 2 days 18 Dec '19 19 Dec '19 24SS Roughing-ins
58 XSTRUC-1004.08.1.2 Piping Work & fitting 4 days 31 Dec '19 03 Jan '20 57,29FF,60 Piping Work & fitting
59 XSTRUC-1004.08.1.3 Installation of 2 days 01 Feb '20 02 Feb '20 58,42,44 Installation of Plumbing/Sanitary Fixture and Accessories
Plumbing/Sanitary Fixture and
Accessories
60 XSTRUC-1004.08.1.4 Construction of Septic Tank 5 days 10 Dec '19 14 Dec '19 27FS+3 days Construction of Septic Tank
61 XSTRUC-1004.08.2 Waste Water System 6 days 09 Jan '20 14 Jan '20
62 XSTRUC-1004.08.2.1 Fabrication & Installation of 4 days 09 Jan '20 12 Jan '20 33,30FF Fabrication & Installation of G.I. Gutter
G.I. Gutter
63 XSTRUC-1004.08.2.2 Fixing of downspout 2 days 13 Jan '20 14 Jan '20 62 Fixing of downspout
64 XSTRUC-1005 Hand-over to owner 0 days 06 Feb '20 06 Feb '20 06/02
65 XSTRUC-1005.01 Hand-over to owner 0 days 06 Feb '20 06 Feb '20 63,59,54,46 06/02

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: PROPOSED ONE STORE
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: 22 Nov '19
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

Page 1