The construction of the project will be started with the mobilization of personnel, materials and
equipments/tools necessary for the first month of construction activities. A temporary facilities will be
constructed for material storage, site office and sleeping quarters.
Item No. 1046(2)a1 CHB Non Load Bearing (including reinforcing steel), 100 mm
CHB will be laid plumb, level and all cells filled with mortar following the mixture indicated on the
technical specifications and up to the desired elevation. CHB reinforcement will be as indicated on
drawings.
Item No. 1046(2)a2 CHB Non Load Bearing (including reinforcing steel), 150 mm
CHB will be laid plumb, level and all cells filled with mortar following the mixture indicated on the
technical specifications and up to the desired elevation. CHB reinforcement will be as indicated on
drawings.
Item No. 1010(1) Frames (Jambs, Sills, Head, Transoms and Mullions)
This item will be installed plumbed, leveled and to the elevations specified on drawings.
Item No. 1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated Type, above 0.427mm
Roof sheets will be installed by personnel skilled to do the work observing proper anchorage.
Item No. 1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, gauge 26)
Ridge roll will be installed by personnel skilled to do the work observing proper anchorage.
Item No. 1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, gauge 26)
Flashing will be installed by personnel skilled to do the work observing proper anchorage.
There will be general cleaning of the project site before the turn-over of the project.
Submitted by:
DANTE C. TAN
Proprietor/Manager
DEACONS TEMPLE CONSTRUCTION AND SUPPLY
Steel Works
Materials, dimensions, locations and elevations of GI railings will be as indicated on drawings.
Only skilled personnel will be allowed to do the same. All welded joints will be fully welded and
smoothened by edger.
Electrical Works
All materials to be installed will be brand new and will conform to the specifications. Only
skilled personnel using proper tools and equipment will be employed during the entire duration
of installation work. All workmanship will be of the best practices of the trade involved.
Painting
Surfaces that will receive paint will be prepared properly. Surfaces will be sanded smooth and
dusted before painting.
There will be general cleaning of the project site before the turn-over of the project.
Submitted by:
NOEL T. LATORRE
Proprietor/Manager
LATORRE BUILDERS AND CONSTRUCTION
Shoulder
Shoulder will be placed and compacted after the PCCP has been cured.
There will be general cleaning of the project site before the turn over of the project.
Submitted by:
NOEL T. LATORRE
Proprietor/Manager
LATORRE BUILDERS AND CONSTRUCTION
Form Works and False Works -False works will be constructed to withstand the load it will
carry. Form works will be constructed true to line, level and properly braced or tied together to
maintain the correct position and shapes of the concrete members. Forms will be constructed
sufficiently to prevent bulging and seepage of water. Forms will not be removed without
permission from the ESSU project Engineers and Inspectors.
Reinforced Concrete Works – Reinforcement will be accurately placed and secured against
displacement. Sizes location and spacing of steel reinforcement will be as indicated on drawings
or schedule of steel reinforcements. No concrete will be poured into forms without an approved
pouring request.
Masonry Works – CHB will be laid plumb, level and all cells filled with mortar following the
mixture indicated on the technical specifications. Laying of CHB will be done after the columns
are sufficiently cured.
Roof Structure –Roof structure will be installed when the roof beams are cured sufficiently
enough to carry the proposed loads following the details on the drawings and the technical
specifications.
Slab on Fill –Fill material will be thoroughly compacted before the pouring of concrete slab.
Materials and elevation of the slab on fill will be as indicated on the technical specifications and
drawings.
Doors and Windows – Doors and windows will conform to the sizes, designs and kind of
materials shown on the schedule of doors and windows and it will be plumb and level.
There will be cleaning of project site before the turn over of the project.
Submitted by:
CONSTRUCTION METHODS
The construction of the project will be started with the mobilization of personnel, materials and
equipments/tools necessary for the first two weeks of construction activities. A temporary
facilities will be constructed for material storage, site office and sleeping quarters.
Form Works and False Works -False works will be constructed to withstand the load it will
carry. Form works will be constructed true to line, level and properly braced or tied together to
maintain the correct position and shapes of the concrete members. Forms will be constructed
sufficiently to prevent bulging and seepage of water. Forms will not be removed without
permission from the ESSU project Engineers and Inspectors.
Reinforced Concrete Works – Reinforcement will be accurately placed and secured against
displacement. Sizes location and spacing of steel reinforcement will be as indicated on drawings
or schedule of steel reinforcements. No concrete will be poured into forms without an approved
pouring request.
Masonry Works
CHB will be laid plumb, level and all cells filled with mortar following the mixture indicated on
the technical specifications. CHB reinforcement will be as indicated on drawings.
Roof Framing & Roofing
Roof framing will be installed when roof beams have already been cured with anchorage as
indicated on drawings. GI sheets will be fastened by umbrella head GI nails at every other
corrugation.
Plumbing Works
We will ensure that all plumbing installation will be air and water tight, in correct slope and with
vents properly provided.
Slab on Fill
Base course will be thoroughly compacted before any concrete is poured. Concrete mixture will
be as indicated on the technical specifications with slump height of not more than 75mm.
Partition
Aluminum partitions will be installed by skilled personnel from glass/aluminum suppliers. This
item of work will be undertaken by sub-contractor.
Tile Works
Tile works will be laid plumb, level and true to line. It will be laid using tile adhesive following
the technical specifications on the Bid Documents.
Ceiling
Ceiling joist will be installed level with sufficient anchorage, fasteners and hangers. Ceiling
boards will be fastened with nails of not more than 4” in distances both directions.
Painting
Surfaces that will receive paint will be prepared properly. Surfaces will be sanded smooth and
dusted before painting.
There will be general cleaning of the project site before the turn over of the project.
Submitted by:
NOEL T. LATORRE
Proprietor
LATORRE BUILDERS AND CONSTRUCTION
CONSTRUCTION METHODS
Name of Project: Construction of 1 – Unit, 2 – Classroom Building
The construction of the project will be started with the mobilization of personnel, materials and
equipments/tools necessary for the first two weeks of construction activities. A temporary
facilities will be constructed for material storage, site office and sleeping quarters.
Scaffolding Works/Formworks -False works will be constructed to withstand the load it will
carry. Form works will be constructed true to line, level and properly braced or tied together to
maintain the correct position and shapes of the concrete members. Forms will be constructed
sufficiently to prevent bulging and seepage of water. Forms will not be removed without
permission from the ESSU project Engineers and Inspectors.
Plastering Works
Surface to receive cement plaster will be cleaned of all projections, dust, loose particles, grease
and bond breakers. All surfaces to be plastered will be wetted thoroughly with clean water to
produce a uniformly moist condition. Brown coat mix will be applied with sufficient pressure to
fill the grooved and to prevent air pockets. Finish coat will be floated to a true and even surface
and troweled in a manner that will force the mixture to penetrate into the brown coat. Surfaces
applied with finish coat will then be smooth with paper or foam to remove trowel marks and
blemishes.
Filling Works
Fill materials will be placed in layers not exceeding 150mm in thickness, and each layer will be
thoroughly compacted.
Electrical Works
All materials to be installed will be brand new and will conform to the specifications. Only
skilled personnel using proper tools and equipment will be employed during the entire duration
of installation work. All workmanship will be of the best practices of the trade involved.
Submitted by:
NOEL T. LATORRE
Proprietor
LATORRE BUILDERS AND CONSTRUCTION
CONSTRUCTION METHODS
The construction of the project will be started with the mobilization of personnel, materials and
equipments/tools necessary for the first two weeks of construction activities. A temporary facilities will
be constructed for material storage, site office and sleeping quarters.
Concreting of Yard
Base material shall be thoroughly compacted before the concreting of yard. Concrete will be machine
mixed.
Tile Works
Tile works will be laid plumb, level and true to line. It will be laid using tile adhesive following the
technical specifications on the Bid Documents. Tile works will be done after ceiling works had been
finished.
Ceiling Works
Ceiling joist will be installed level with sufficient anchorage, fasteners and hangers. Ceiling boards will
be fastened with nails of not more than 4” in distances both directions. Sufficient falsework will be
provided for this item of work.
Plumbing Works
We will ensure that all plumbing installation will be air and water tight, in correct slope and with vents
properly provided.
GI Railings
Materials, dimensions, locations and elevations of GI railings will be as indicated on drawings.
Only skilled personnel will be allowed to do the same. All welded joints will be fully welded and
smoothened by edger.
Painting Works
Surfaces that will receive paint will be prepared properly. Surfaces will be sanded smooth and dusted
before painting. Painting will be in three coats.
Submitted by:
NOEL T. LATORRE
Proprietor
LATORRE BUILDERS AND CONSTRUCTION
CONSTRUCTION METHODS
The construction of the project will be started with the mobilization of personnel, materials and
equipments/tools necessary for the first two weeks of construction activities. A temporary facilities will
be constructed for material storage, site office and sleeping quarters.
Submitted by:
NOEL T. LATORRE
Proprietor
LATORRE BUILDERS AND CONSTRUCTION
CONSTRUCTION METHODS
The construction of the project will be started with the mobilization of personnel, materials and
equipments/tools necessary for the first two weeks of construction activities. A temporary facilities will
be constructed for material storage, site office and sleeping quarters.
Plumbing Works
We will ensure that all plumbing installation will be air and water tight, in correct slope and with vents
properly provided.
Tile Works
Tile works will be laid plumb, level and true to line. It will be laid using tile adhesive following the
technical specifications on the Bid Documents.
Electrical Works
All materials to be installed will be brand new and will conform to the specifications. Only skilled
personnel using proper tools and equipment will be employed during the entire duration of installation
work. All workmanship will be of the best practices of the trade involved.
Submitted by:
NOEL T. LATORRE
Proprietor
LATORRE BUILDERS AND CONSTRUCTION
Ceiling Works
Ceiling joist will be installed level with sufficient anchorage, fasteners and hangers. Ceiling boards will
be fastened with nails of not more than 4” in distances both directions. Sufficient falsework will be
provided for this item of work.
Plumbing Works
We will ensure that all plumbing installation will be air and water tight, in correct slope and with vents
properly provided.
GI Railings
Materials, dimensions, locations and elevations of GI railings will be as indicated on drawings.
Only skilled personnel will be allowed to do the same. All welded joints will be fully welded and
smoothened by edger.
Painting Works
Surfaces that will receive paint will be prepared properly. Surfaces will be sanded smooth and dusted
before painting. Painting will be in three coats.
Submitted by:
NOEL T. LATORRE
Proprietor
LATORRE BUILDERS AND CONSTRUCTION