Current Status
Responsible Part (Sat 29/02/2020) Remarks
Tue 25/02/2020
Delayed by lack of
adequate resources
B&H Horticulture 85% by contractor
B&H Horticulture 100% Ongoing
Awaiting decision on
light type (solar or
Bilaad Ad-hoc 0% electrical)
B&H Horticulture 100%
B&H Horticulture 100%
Bilaad Ad-hoc 100%
Mouna Mo 100%
Mouna Mo 100%
LGN 100%
Bulwark 100%
Eric 100% reproduction
of gates by
Inspired Design 70% contractor
Mouna Mo 100%
Ola/Abel 100% Awaiting
Implementation
Goodfix 0% by conctractor
Bilaad Ad-hoc 100%
Musnat Nig. Ltd. 100%
Timeline
Wed 26/02/202 Thur 27/02/202Fri 28/02/202 Sat 29/02/202
Sun 01/03/2020
BOBOWASI PHASE 1 OUTSTANDING/O
S/N Activity
1 Screeding/painting maintenances
2 Complete installation of water pump
3 Installation of sanitary fittings, testing of water pressure/silicon appli
4 Resolution of snags on windows/nets and doors
5 Completion of kitchen sink and mixers
6 Completion of mini grid switches installations in kitchen
7 Home automation installations including door bell and chime
8 Snags on general electrical works
9 Fibre optics points termination on rack
10 External doors snags and installation of door architraeves
11 Testing and commissioning of water heaters
Responsible Par
Current Status Remarks
Wed 26/02/2020
Multiple parties 97%
Bikhranz 100%
Cachez Design 98%
Euro-Deco Design 97%
TRT/ SA Kadiri 95%
Electricians 90%
Hausba 60%
Electricians 98%
LEGEND 100% Awaiting checking and commissioning
Gladiator doors 10%
Goodfix 97%
Awaiting complete
Funergy 30% delivery of Inverters
Painter 10%
TRT Arredo 95%
Industrial cleaner 50%
Thur 27/02/2020Fri 28/02/2020Sat 29/02/2020Sun 01/03/2020