CADANGAN PEMBANGUNAN SEMENTARA

BAGI PEMBANGUNAN EAST COST


RAILWAY LINE (ECRL) SECTION 6 DIATAS
SEBAHAGIAN LOT 34392 (GRN14841)
MUKIM KUALA KUANTAN, DAERAH
KUANTAN, PAHANG DARULMAKMUR
TITLE : CADANGAN PEMBANGUNAN SEMENTARA BAGI PEMBANGUNAN EAST
COST RAILWAY LINE (ECRL) SECTION 6 DIATAS SEBAHAGIAN LOT 34392
(GRN14841) MUKIM KUALA KUANTAN, DAERAH KUANTAN, PAHANG
DARULMAKMUR

DISTRICT : KUANTAN

SUMMARY BILL OF QUANTITIES

BIL NO. DESCRIPTION AMOUNT (RM)

1.00 BILL NO 1 : PRELIMINARIES 8,000.00

2.00 BILL NO 2 : PAVEMENT 82,204.90

3.00 BILL NO 3 : ROAD MARKINGS 16,772.60

4.00 BILL NO 4 : TRAFFIC CONTROL PLAN 14,616.00

TOTAL AMOUNT (RM) 121,593.50


TITLE : CADANGAN PEMBANGUNAN SEMENTARA BAGI PEMBANGUNAN EAST COST RAILWAY LINE
(ECRL) SECTION 6 DIATAS SEBAHAGIAN LOT 34392 (GRN14841) MUKIM KUALA KUANTAN,
DAERAH KUANTAN, PAHANG DARULMAKMUR

DISTRICT : KUANTAN

BILL NO. 1 - PRELIMINARIES

BIL RATE AMOUNT


S.O.R. DESCRIPTION UNIT QTY
NO. (RM) (RM)

1.00 MOBILISATION AND DEMOBILISATION

Mobilisation and demobilisation of construction


LS 8,000.00
equipments, ancillaries and everything require for this work.

TOTAL AMOUNT (RM) 8,000.00


TITLE : CADANGAN PEMBANGUNAN SEMENTARA BAGI PEMBANGUNAN EAST COST RAILWAY LINE
(ECRL) SECTION 6 DIATAS SEBAHAGIAN LOT 34392 (GRN14841) MUKIM KUALA KUANTAN,
DAERAH KUANTAN, PAHANG DARULMAKMUR

DISTRICT: KUANTAN

BILL NO. 2 - PAVEMENT

RATE AMOUNT
ITEM S.O.R DESCRIPTION UNIT QTY
(RM) (RM)

1.00 Reconstruction

Cut, excavate and dispose unsuitable material other than rock to


1.0.1 m3 246.57 14.10 3,476.64
the designated dumping area within site.

1.0.2 Supply, lay , spread, level and compact sub-base materials


3
to the required formation level. m - 60.20 -

1.0.3 Supply, lay , spread, level and compact crushed aggregate


3
materials to the required formation level. m 156.16 90.60 14,148.10

1.0.4 Supply and apply bituminous prime coat uniformly including

cleaning the surface of pavement prior to application m2 821.90 1.82 1,495.86

1.0.5 Supply lay and compact asphaltic concrete binder course


3
(AC28) m 49.32 672.16 33,150.93

1.10 Resurfacing

1.1.1 Supply and apply bituminous tack coat uniformly

including cleaning the surface of pavement prior m2 821.90 1.71 1,405.45

1.1.2 Supply, lay and compact asphaltic concrete wearing

course (AC14) m3 41.10 694.11 28,527.92

TOTAL AMOUNT (RM) 82,204.90


TITLE : CADANGAN PEMBANGUNAN SEMENTARA BAGI PEMBANGUNAN EAST COST RAILWAY LINE
(ECRL) SECTION 6 DIATAS SEBAHAGIAN LOT 34392 (GRN14841) MUKIM KUALA KUANTAN,
DAERAH KUANTAN, PAHANG DARULMAKMUR

DISTRICT : KUANTAN

BILL NO. 3 - MAINTENANCE OF ROAD MARKINGS

BIL RATE AMOUNT


S.O.R. DESCRIPTION UNIT QTY
NO. (RM) (RM)

MAINTENANCE OF ROAD MARKING

1.00 Painting of New Marking

1.10 Prepare and apply 2.0mm therm-plastic pavement


markings of sizes 100mm to 150mm wide single
continuous edge line marking as specification JKR/SPJ/-
S6/BS EN 1436 m² 36.00 80.00 2,880.00
1.20 Ditto but of 150mm width single continous centre line and
lane marking.
m² 0.00 80.00 0.00
1.30 Ditto intermittent center line and lane marking of 100mm
wide. m² 0.00 80.00 0.00

1.40 Ditto but intermittent give away line of 200mm wide with
300mm length each and at 200mm gap. m² 19.20 80.00 1,536.00

1.40 Ditto but continuos stop line of 300mm wide. m² 80.00 0.00

1.50 Prepare and apply Transverse yellow thermoplastic of m² 76.80 142.00 10,905.60
5.0mm thick 600mm wide as specified in specification
JKR/SPJ/2012-S6/BS EN 1436.
1.60 Ditto 300mm width chevron hatching for merging /
diverging traffic and cross hatching. m² 10.50 86.00 903.00

1.70 Ditto pavement direction arrow. m² 5.48 100.00 548.00

TOTAL AMOUNT (RM) 16,772.60


TITLE : CADANGAN PEMBANGUNAN SEMENTARA BAGI PEMBANGUNAN EAST COST RAILWAY LINE
(ECRL) SECTION 6 DIATAS SEBAHAGIAN LOT 34392 (GRN14841) MUKIM KUALA KUANTAN,
DAERAH KUANTAN, PAHANG DARULMAKMUR

DISTRICT : KUANTAN

BILL NO. 4 - TRAFFIC CONTROL PLAN (TCP)

BIL RATE AMOUNT


S.O.R. DESCRIPTION UNIT QTY
NO. (RM) (RM)

MAINTENANCE OF SIGN

1.00 Schedule Of Day Work Rate

No per
1.10 Temporary Signboard 126.00 16.00 2,016.00
day
9 Nos x 14 day = 126

No per
1.20 New Jersey Plastic Barrier 2,800.00 3.50 9,800.00
day

200 Nos x 14 day = 2800

No per
1.30 Blinkers 700.00 4.00 2,800.00
day
50 Nos x 14 day = 700

TOTAL AMOUNT (RM) 14,616.00


RECONTRUCTION
section Length width Thickness Milling cut & Exc sand c/run Prime Coat AC28 Tack Coat AC 14 TONNE
Item
Start End (M) (M) (M) ( M²) ( M³) ( M³) ( M3) ( M²) ( M³) ( M²) ( M³) ( MT)
Bounds
(a) (b) (a)x(b)x(c) (a)x(b)x(c) (a)x(b)x(c) (a)x(b) (a)x(b)x(c) (a)x(b) (a)x(b)x(c) ( a ) x ( b ) x ( c ) x 2.3
(c) (a)x(b)

RECON 1 20.00 1.58 0.30 9.45


20.00 1.58 0.00 0.00
20.00 1.58 0.19 5.99
20.00 1.58 0.06 31.50 1.89
20.00 1.58 0.05 31.50 1.58

RECON 2 20.00 3.15 0.30 18.90


20.00 3.15 0.00 0.00
20.00 3.15 0.19 11.97
20.00 3.15 0.06 63.00 3.78
20.00 3.15 0.05 63.00 3.15

RECON 3 30.00 11.56 0.30 104.04


30.00 11.56 0.00 0.00
30.00 11.56 0.19 65.89
30.00 11.56 0.06 346.80 20.81
30.00 11.56 0.05 346.80 17.34

RECON 4 30.00 4.22 0.30 37.98


30.00 4.22 0.00 0.00
30.00 4.22 0.19 24.05
30.00 4.22 0.06 126.60 7.60
30.00 4.22 0.05 126.60 6.33

RECON 5 40.00 3.65 0.30 43.80


40.00 3.65 0.00 0.00
40.00 3.65 0.19 27.74
40.00 3.65 0.06 146.00 8.76
40.00 3.65 0.05 146.00 7.30

RECON 6 60.00 1.80 0.30 32.40


60.00 1.80 0.00 0.00
60.00 1.80 0.19 20.52
60.00 1.80 0.06 108.00 6.48
60.00 1.80 0.05 108.00 5.40
PROPOSED QUANTITIES 0.00 246.57 0.00 156.16 821.90 49.32 821.90 41.10
ROADMARKING
Section Roadmarking Total Quantity
Item Edge Lane marking Double Yellow Arrow Stop Hatching Edge Lane marking Double Yellow Arrow Stop Hatching
Start End
Line Inter 4.5m Inter 2.7m Inter 0.3m Line bar Double Line Chevron Line Line Bar (m2) Line Chevron
(m) 100mm 100mm 200mm Straight Line (m2) (Gx3.49) (m2) (m2)
( no ) ( no ) ( no ) (m) Turning (m) (m) (m2) (m2) (m2) (m2) (m2) (Fx0.3) (Gx2.07) (Hx0.1) ( I x0.15)
(A) (B) (C) (D) (E) (F) (Nos) (G) (H) (I) (Ax0.15) (Bx4.5x0.1) (Cx2.7x0.1) (Dx0.3x0.2) (Ex0.1x2) (Fx0.6) (Gx1.37) (Hx0.3) ( I x0.3)

1 70.00 10.50
2 130.00 19.50
3 20.00 3.00
4 20.00 3.00
5 320.00 19.20
6 4 5.48
7 35.00 10.50
8 128.00 76.80

36.00 19.20 76.80 5.48 10.50