Beruflich Dokumente
Kultur Dokumente
GROUND FLOOR
COMMON AREA 1 9.00 7.00 63.00
TOILET ( HE ) 1 2.00 1.50 3.00
TOILET ( SHE ) 0 2.00 1.40 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
1 -
-
SUB-TOTAL 66.00
SECOND FLOOR
COMMON AREA 1 12.80 5.00 64.00
TOILET ( HE ) 1 2.00 1.40 2.80
TOILET ( SHE ) 1 2.00 1.40 2.80
CANOPY 1 1.60 3.30 5.28
LEDG 11 1.60 0.50 8.80
-
-
SUB-TOTAL 83.68
THIRD FLOOR
-
-
-
-
SUB-TOTAL -
FOURTH FLOOR
-
SUB-TOTAL -
ROOF DECK
ROOF SLAB -
-
-
-
-
SUB-TOTAL -
OTHER AREAS
MAIN STAIRS 20.00
FIRE EXIT STAIRS -
EAVES -
SUB-TOTAL 20.00
TOTAL AREA
w/ Allowance
Aluminum Cladding
ITEM / MARK SETS W H A
Left Portal 1 1.60 7.50 18.00
Right Portal 1 1.60 7.50 18.00
Lettering 1 34.89 1.00 51.00
Top & Bottom of Cladding 1 24.00 0.50 18.00
Canopy 1 6.75 0.50 5.00
Decorative Stone
ITEM / MARK SETS W H A
Front Elevation 0 4.33 1.43 -
Rear Side Elevation 0 2.15 1.43 -
Left Side Elevation 0 2.15 1.43 -
Right Side Elevation 0 2.15 0.83 -
TOTAL AREA -
TOTAL AREA -
concrete moulding
ITEM / MARK SETS L L
1 9.00 11.00
1 4.15 5.00
1 62.00 75.00
plastering guide
ITEM / MARK SETS L L
11 57.05 38.00
-
-
-
1 2 3 4 5 6 7 8
3 - - 63.00 - - - - -
6 - - - - - 3.00 - -
6 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
6 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
6 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
6 - - - - - - - -
3 - - - - - - - -
3 - - - - - - - -
6 - - - - - - - -
- - - - - - - -
- - 63.00 - - 3.00 - -
8 - - - - - - - 64.00
6 - - - - - 2.80 - -
6 - - - - - 2.80 - -
4 - - - 5.28 - - - -
4 - - - 8.80 - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.05
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
CEILING
Concrete Engineered CODE Water Water Green Green Painted
topping for Wood WATER Proofing Proofing Roof Roof CODE Hardiflex Finish
water planks PROOFING (CR) (Deck) Waterproofing CEILING Board
proofing
- - - - - - 1 63.00 -
- - - - - - 1 3.00 -
- - - - - - 5 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 5 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 5 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 5 - -
- - - - - - 3 - -
- - - - - - 3 - -
- - - - - - 5 - -
- - - - - - - -
- - - - - - 66.00 -
- - - - - - - -
- - 1 4.84 - - - - -
- - 1 4.84 - - - - -
- - 2 - 8.22 - - - -
- - 2 - 22.66 - - - -
- - - - - - - -
- - - - - - - -
- - 9.68 30.88 - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - -
- - - - 1 6.30 -
- - - - 1 - -
- - - - - -
- - - - - -
- - - - - -
- - - - 1 - -
- - - - - -
- - - - - -
- - - - 1 - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - 1 - -
- - - - - -
- - - - - -
- - - - 1 - -
- - - - - -
- - - - 6.30 - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - -
- - - - - -
- - - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - -
- - - - 6.30 - -
- - - - 8.00 - -
6 6
NUMBER NUMBER
OF CUTS
OF CUTS PER COM PCS @ 1 PCS @ 1 TOTAL KG TIE WIRE
PER COM L
L (1 ) (2 ) 0
5 5 17.6 17.6 334 7.422222222
0.00 0.00 0 0 0
0.00 0.00 0 0 0
334
RSB KG W1 W2 W3 W4
VOLUME FORM
LENGTH EXCAVATION OF VOLUME OF ALONG S ALONG L 2 0.3 1 0.75 2 0.6 0.3
WORKS
CONRETE GRAVEL
58 20.3 7.25 1.45 65.50133333 117.9024 29 1 8 4 4
0 10.7 2.354 1.07 0.214 9.667093333 21.75096 5.35 0 0 0 0
23 9 2 76 140 35 4.6 28 20.8 4.8
216
388
VOLUME
AT AT FORM STIRRUPS 10
COLUMN MIDSPAN AT COLUMN AT MISPAN AT COLUMN AT MISPAN END SUPPORT CONTI. BAR OF RSB ( KG) SHORING
WORKS mm
CONRETE
37.92 18.96 37.92 37.92 18.96 1.264 3.792 138.408 1.095 13.14 352.024 62.9552 10.95
37.92 18.96 37.92 37.92 18.96 1.264 3.792 138.408 1.095 13.14 352.024 62.9552 10.95
37.92 18.96 37.92 37.92 18.96 1.264 3.792 138.408 1.095 13.14 352.024 62.9552 10.95
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0
4 40 1109 189 32.85
VOLUME
AT AT FORM STIRRUPS 10
COLUMN MIDSPAN AT COLUMN AT MISPAN AT COLUMN AT MISPAN END SUPPORT CONTI. BAR OF RSB ( KG) SHORING
WORKS mm
CONRETE
37.92 37.92 25.28 1.264 5.056 1.264 3.792 126.4 1 12 302.096 57.7808 10
37.92 37.92 25.28 1.264 5.056 1.264 3.792 126.4 1 12 302.096 57.7808 10
37.92 37.92 25.28 1.264 5.056 1.264 3.792 126.4 1 12 302.096 57.7808 10
37.92 37.92 25.28 1.264 5.056 1.264 3.792 126.4 1 12 302.096 57.7808 10
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0
4 48 1269 232 40
VOLUME
AT AT FORM STIRRUPS 10
COLUMN MIDSPAN AT COLUMN AT MISPAN AT COLUMN AT MISPAN END SUPPORT CONTI. BAR OF RSB ( KG) SHORING
WORKS mm
CONRETE
28.44 0 18.96 0 14.22 0 2.844 128.928 1.632 21.9 207.612 50.2656 10.2
28.44 0 18.96 0 14.22 0 2.844 128.928 1.632 21.9 207.612 50.2656 10.2
28.44 0 18.96 0 14.22 0 2.844 128.928 1.632 21.9 207.612 50.2656 10.2
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0
5 66 623 151 30.6
TOTAL DEDUCTION
0.3 0 0 2 2.1 0.9 2.1 0.8 2.1 0.8 2.1 0.8 2.1
4 0 4 1 1 2 2 -35.49
0 0 0 2 0 0 0 -3.78
4.8 0 32.8 18 5.8 11.6 11.6
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
Scope of Works :
1 General Requirement including temporary enclosure, lighting & water facilities and permits
2 Demolition Works of existing structures including hauling and disposal
3 Site Works including excavation, backfill and compaction, soil poisoning, gravel bedding
4 Concrete Works including concreting, reinforcements, formworks & scaffolding, and concrete stairs
5 Masonry Works
6 Metal Fabrication
7 Waterproofing Works
8 Architectural Works including floor finishes, wall finishes, ceiling finishes, roofing works, doors & windows,
painting works and miscellaneous
9 Electrical Works
10 Plumbing Works (Waterline, Drain, Waste, Vent, Dry Standpipe and Drainage System)
I GENERAL REQUIREMENTS
Temporary enclosure around the construction area unit 109.50 P 80.00 P
Temporary lighting and water facilities days 150.00 350.00
Billboard unit 1.00 3,669.30
Sub-Total I P
II DEMOLITION WORKS
Demolition of existing Structure unit 1.00 P 150,000.00 P
Hauling and clearing of demolished materials unit 10.00 3,500.00
Sub-Total II P
Page 17 of 53
Wall footing m³ 23.00 561.61
Septic tank m³ 13.36 561.61
Backfill and Compaction m³ 42.00 453.00
Sub-Total 1-4 P
Page 18 of 53
Soil Poisoning / Termite Proofing m² 109.50 P 69.00 P
Gravel Bedding and compaction (Ordinary Gravel) 15.00
Footings m³ 1.00 900.00
Septic tank m³ 1.00 900.00
Wall Footing m³ 2.00 900.00
Slab on Grade m³ 16.25 900.00
Materials Cost P
Labor Cost
Sub-Total 5-6 P
Sub-Total A P
Sub-Total III P
IV CONCRETE WORKS
A Concreting (RMC @ 28 Days)
Column Footings, 3000 psi, 3/4" Gravel m³ 4.00 P 4,000.00 P
Columns, 3000 psi, 3/4" Gravel m³ 9.00 4,000.00
Wall Footings, 3000 psi, 3/4" Gravel m³ 9.00 4,000.00
Beams/Roof Beam, 3000 psi, 3/4" Gravel m³ 18.00 4,000.00
Slabs-on-fill, 3000 psi, 3/4" Gravel m³ 17.00 4,000.00
(including concrete topping)
Suspended Slabs, 3000 psi, 3/4" Gravel m³ 11.00 4,000.00
(including concrete topping)
Ramp, 3000 psi, 3/4" Gravel m³ 2.00 4,000.00
(including concrete topping)
Septic Tank ( Slab, Floorings) 3000 psi, 3/4" Gravel m³ 4.00 4,000.00
(including concrete topping)
Materials Cost P
Labor Cost
Sub-Total A P
B Reinforcing Bars
Grade 40
Wall Footings kgs 216.00 39.00
Suspended slab kgs 2,846.00 39.00
Slabs-on-fill kgs 429.00 39.00
Stirrups ( Columns & Beams ) kgs 1,694.00 39.00
Septic Tank kgs 452.00 39.00
Grade 60
Column Footings kgs 334.00 39.00
Columns kgs 2,086.00 39.00
Beams kgs 2,378.00 39.00
G.I. Tie Wire kgs 388.00 80.00
Materials Cost P
Labor Cost
Page 19 of 53
Sub-Total B P
Page 20 of 53
C Formworks & Scaffoldings
Formworks
Columns m² 160.00 P 308.00 P
Beams m² 470.00 275.00
Suspended slab m² 200.00 182.00
Suspended slab ( Septic Tank ) m² 10.00 182.00
Scaffoldings / Shoring
Columns lm 95.00 575.00
Beams m² 80.00 154.00
Roof BEam m² 80.00 154.00
Suspended Slab m² 105.00 131.00
Suspended slab ( Septic Tank ) m² 10.00 131.00
Materials Cost P
Labor Cost
Sub-Total C P
Sub-Total IV P
V MASONRY WORKS
Laying of 150mm CHB, including mortar, m² 599.00 P 659.00 P
and reinforcement
Laying of 100mm CHB, including mortar, m² 114.00 460.00
and reinforcement
Laying of 150mm CHB, including mortar and m² 26.00 586.00
reinforcement, Septic Tank
Stiffener Beams and Columns including concreting, lm 24.00 330.00
reinforcement and formworks
Plastering of CHB Walls m² 1,426.00 171.00
Plastering of Door and Window Openings lm 138.00 257.00
Materials Cost P
Labor Cost
Sub-Total V P
Materials Cost P
Labor Cost
Sub-Total VII P
VII STEEL WORKS
Construction of Steel Trussed including plates,
Page 21 of 53
bolts, connectors and accessories, painted finish
TRUSS 1
2 x2 x 1/4 Angle Bars pcs 71.00 P 1,132.00
2 X 4 Metal C Purlins pcs 50.00 650.00
50mm gI Pipe pcs 10.00 2,300.00
2 x 10 x 6mm Structural Steel Tubular (Fire-Exit Main Frame ) kg 1,017.00 54.00
2 x 6 x 6mm Structural Steel Tubular ( Fire Exit Thread ) kg 700.00 54.00
Page 22 of 53
16mm Square Bar kg 354.00 54.00
12mm Round Bar pcs 654.00 54.00
Miscellaneous and Consumables
Epoxy Primer gal 10.00 950.00
Quick Dry Enamel gal 10.00 630.00
Welding Machine rentals days 35.00 350.00
Welding Rod kg 15.00 100.00
Materials Cost P
Labor Cost
Sub-Total VII P
B Wall Finishes
400mm x 400mm Ceramic Wall Tiles m² 93.12 P 1,000.00 P
downspout cladding, painted finish
PVC Plastering Guide lm 138.00 150.00
Stoneworks m² 15.00 2,500.00
Materials Cost P
Labor Cost
Sub-Total B P
C Ceiling Finishes
6" thk Ficem Board on Metal frame m² 304.00 850.00
Materials Cost P
Labor Cost
Sub-Total C P
Page 23 of 53
D3 - 0.8 m x 2.1 m Panel Door sets 1.00 12,000.00
D4 - 0.8 m x 2.1 m PVC Door with Louver sets 2.00 6,500.00
D5 - 0.6 m x 2.1 m PVC Door with Louver sets 2.00 4,500.00
Windows including accessories
W1 - 2.0 m x 0.30 m Clear glass on powder sets 2.00 3,900.00
coated aluminum frame
W2 - 1.0 m x 0.75 m Clear glass on powder sets 4.00 4,875.00
coated aluminum frame
W3 - 2.0 m x 0.8 m Clear glass on powder sets 4.00 10,400.00
coated aluminum frame
W4- 0.3 m x 0.3 m Clear glass on powder sets 4.00 585.00
coated aluminum frame
Page 24 of 53
Hardware accessories
Door Hinges pcs 30.00 100.00
Door Knobs / handles pcs 10.00 1,000.00
Materials Cost P
Labor Cost
Sub-Total E P
E Roofing Works
Rib Type Long Span Roofing m² 130.00 P 560.00
End Flashing pcs 16.00 560.00
Gutter pcs 5.00 560.00
Ridge Cap pcs 0.00 560.00
Heat Insulation m² 130.00 150.00
Tekscrew pcs 500.00 3.50
Silicon Sealant pcs 10.00 200.00
Vulcaseal pcs 10.00 200.00
Materials Cost P
Labor Cost
Sub-Total E P
F Painting Works
Semi-Gloss Latex Paint Finish (exterior & Exterior masonry walls m² 1,426.00 P 160.00 P
walls, stairs and slab soffit)
Latex Paint Finish (ceiling for Ficem board) m² 304.00 160.00
Painting of Doors and jambs m² 8.00 250.00
Materials Cost P
Labor Cost
Sub-Total F P
Page 25 of 53
IX ELECTRICAL WORKS
A Lighting and Power System
1 Roughing-ins
1/2"Ø x 3m PVC Pipe pcs 80.00 P 80.00 P
1/2"Ø PVC Adaptor pcs 51.00 5.00
1/2"Ø PVC Locknut pcs 18.00 5.00
2" x 4" Utility Box pcs 27.00 28.00
4" x 4" Junction Box with cover pcs 10.00 36.00
2 Wires and Cables
3.5mm² THHN Copper Wire rolls 8.00 3,550.00
3 Wiring Devices & Lighting Fixtures
Duplex C.O. with ground pcs 17.00 335.00
2 x 36 W FL Tube in 14" x 24" Louver Fixtures pcs 16.00 2,500.00
Pinlight pcs 9.00 650.00
Single Pole Switch w/ Plate & Cover pcs 6.00 120.00
Three Pole Switch w/ Plate & Cover pcs 3.00 240.00
Three way Switch w/ plate & cover pcs 1.00 350.00
4 Miscellaneous & Consumables \
400cc PVC Solvent Cement cans 5.00 230.00
Hacksaw Blade pcs 3.00 60.00
Electrical tape rolls 5.00 35.00
16mmØ x 3000mm Grounding Rod set 1.00 2,400.00
GI Tie Wire kgs 15.00 65.00
Rubber Tape rolls 3.00 190.00
Paint Brush pcs 2.00 45.00
Masking tape rolls 5.00 35.00
Eyebolt pcs 1.00 478.00
Red Oxide Primer liters 1.00 350.00
Service Entrance set 1.00 27,000.00
Materials Cost P
Labor Cost
Sub-Total 1 - 4 P
X PLUMBING WORKS
A Drain, Waste & Vent
1 PVC Pipe
PVC Pipe, 75 Ø x 3 mts pcs 8.00 630.00
PVC Pipe, 50 Ø x 3 mts pcs 10.00 420.00
Page 26 of 53
2 PVC Fittings
2.1 Wye
Wye, 75 Ø x 75 Ø pcs 5.00 130.00
Wye, 75 Ø x 50 Ø pcs 4.00 130.00
Wye, 50 Ø x 50 Ø pcs 10.00 50.00
2.2 Tee
Tee, 75 Ø x 50 Ø pcs 5.00 130.00
Tee, 50 Ø x 50 Ø pcs 10.00 50.00
Page 27 of 53
2.3 1/4 Bend
1/4 Bend 75 Ø pcs 3.00 70.00
1/4 Bend 50 Ø pcs 3.00 40.00
2.4 1/8 Bend
1/8 Bend 75 Ø pcs 3.00 60.00
1/8 Bend 50 Ø pcs 3.00 30.00
2.5 Reducer
Reducer, 75 Ø x 50 Ø pcs 2.00 50.00
2.7 Cleanout
Cleanout 75 Ø pcs 1.00 50.00
Cleanout 50 Ø pcs 30.00
2.8 P-Trap
P-Trap, 50 Ø pcs 1.00 150.00
B Waterline
1 PPR Pipe, PN 16
PPR Pipe, 20 Ø x 4m pcs 20.00 620.00
2 PPR Fittings
2.1 Tee Equal
Tee Equal, 20 Ø x 20Ø pcs 10.00 70.00
2.2 Unequal Tee
Unequal Tee, 20 Ø x 20 Ø pcs 5.00 70.00
2.3 Reducer
2.4 90° Elbow
90° Elbow, 20 Ø pcs 3.00 60.00
2.5 Female Threaded Tee
Coupling, 20 Ø pcs 3.00 40.00
2.9 Male Adaptor
Gate Valve PPR, 20 Ø pcs 2.00 830.00
Material Cost P
Labor Cost
Sub-Total A - B P
Page 28 of 53
14 Expansion Bolt with Shield, 1/2" Ø x 2" pcs 7.00 60.00
15 Metal Drill Bit, 1/2" Ø pcs 7.00 80.00
Materials Cost P
Labor Cost
Sub-Total C P
Sub-Total X
Page 29 of 53
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
SUMMARY
I GENERAL REQUIREMENTS P
II DEMOLITION WORKS
III SITE WORKS
IV CONCRETE WORKS
V MASONRY WORKS
VI THERMAL AND MOISTURE PROTECTION
VII STEEL WORKS
VIII ARCHITECTURAL WORKS
IX ELECTRICAL WORKS
X PLUMBING WORKS
TOTAL DIRECT COST P
OCM
PROFIT
FIRE PERMIT FEES
ELECTRICAL & SANITARY PERMIT FEES
VAT
PROJECT COST P
Submitted by:
Page 30 of 53
Recommending Approval:
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved:
JOSELITO B. CABUNGCAL
City Engineer
Page 31 of 53
NG AT
TOTAL
COST
8,760.00
52,500.00
3,669.30
64,929.30
150,000.00
35,000.00
185,000.00
9,547.37
Page 32 of 53
12,917.03
7,500.86
19,026.00
48,991.26
Page 33 of 53
7,555.50
900.00
900.00
1,800.00
14,625.00
25,780.50
9,023.18
34,803.68
83,794.94
83,794.94
16,000.00
36,000.00
36,000.00
72,000.00
68,000.00
-
44,000.00
-
8,000.00
-
16,000.00
-
296,000.00
103,600.00
399,600.00
8,424.00
110,994.00
16,731.00
66,066.00
17,628.00
13,026.00
81,354.00
92,742.00
31,040.00
438,005.00
153,301.75
Page 34 of 53
591,306.75
Page 35 of 53
49,280.00
129,250.00
36,400.00
1,820.00
54,625.00
12,320.00
12,320.00
13,755.00
1,310.00
311,080.00
108,878.00
419,958.00
1,410,864.75
394,741.00
52,440.00
15,236.00
7,920.00
243,846.00
35,466.00
749,649.00
262,377.15
1,012,026.15
7,034.73
6,800.00
13,834.73
4,842.16
18,676.89
Page 36 of 53
80,372.00
32,500.00
23,000.00
54,918.00
37,800.00
Page 37 of 53
19,116.00
35,316.00
9,500.00
6,300.00
12,250.00
1,500.00
312,572.00
109,400.20
421,972.20
26,006.40
438,177.60
4,030.99
7,500.00
475,714.99
166,500.25
642,215.24
93,120.00
-
20,700.00
37,500.00
151,320.00
52,962.00
204,282.00
258,400.00
258,400.00
90,440.00
348,840.00
109,200.00
15,000.00
Page 38 of 53
12,000.00
13,000.00
9,000.00
7,800.00
19,500.00
41,600.00
2,340.00
Page 39 of 53
3,000.00
10,000.00
242,440.00
48,488.00
290,928.00
72,800.00
8,960.00
2,800.00
-
19,500.00
1,750.00
2,000.00
2,000.00
109,810.00
38,433.50
148,243.50
228,160.00
48,640.00
2,000.00
278,800.00
97,580.00
376,380.00
15,000.00
15,000.00
10,000.00
11,200.00
245,000.00
133,920.00
71,400.00
501,520.00
175,532.00
677,052.00
2,687,940.74
Page 40 of 53
6,400.00
255.00
90.00
756.00
360.00
28,400.00
5,695.00
40,000.00
5,850.00
720.00
720.00
350.00
1,150.00
180.00
175.00
2,400.00
975.00
570.00
90.00
175.00
478.00
350.00
27,000.00
123,139.00
43,098.65
166,237.65
8,000.00
8,000.00
2,800.00
10,800.00
177,037.65
5,040.00
4,200.00
Page 41 of 53
650.00
520.00
500.00
650.00
500.00
Page 42 of 53
210.00
120.00
180.00
90.00
100.00
50.00
-
150.00
12,400.00
700.00
350.00
180.00
120.00
1,660.00
28,370.00
9,929.50
38,299.50
26,000.00
13,000.00
18,000.00
20,000.00
23,100.00
1,150.00
35.00
360.00
200.00
3,600.00
280.00
900.00
Page 43 of 53
420.00
560.00
107,605.00
37,661.75
145,266.75
183,566.25
Page 44 of 53
64,929.30
185,000.00
83,794.94
1,410,864.75
1,012,026.15
18,676.89
421,972.20
2,687,940.74
177,037.65
183,566.25
6,245,808.86
562,122.80
499,664.71
7,681.46
400.00
365,783.89
7,681,461.72
rogrammer
Page 45 of 53
Page 46 of 53
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
AGENCY ESTIMATE
TOTAL 7,681,461.72
Amount in Words:
SEVEN MILLION SIX HUNDRED EIGHTY ONE THOUSAND FOUR HUNDRED SIXTY ONE PESOS
AND SEVENTY TWO CENTAVOS ONLY
Note:
Recommending Approval :
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved:
JOSELITO B. CABUNGCAL
City Engineer
TA
Item
DESCRIPTION
No. 5 10 15 20 25 30 35 40
I GENERAL REQUIREMENTS
II DEMOLITION WORKS
III SITE WORKS
IV CONCRETE WORKS
V MASONRY WORKS
VI THERMAL AND MOISTURE PROTECTION
VII STEEL WORKS
VIII ARCHITECTURAL WORKS
IX ELECTRICAL WORKS
X PLUMBING WORKS
WORK SCHEDULE
NO. OF CALENDAR DAYS
40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120
Recommending Approval:
Approved by:
JOSELITO B. CABUNGCAL
City Engineer
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
Recommending Approval:
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved by:
JOSELITO B. CABUNGCAL
City Engineer
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
Recommending Approval:
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved by:
JOSELITO B. CABUNGCAL
City Engineer