Beruflich Dokumente
Kultur Dokumente
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
SCOPE OF WORK:
1 General Requirements including Temporary Enclosure, Temporary Lighting and Water Facilities
and Billboard
2 Site Works including lay-out and staking, site cleaning & preparation, excavation, backfill &
compaction, soil poisoning, gravel bedding, imported earthfill and hauling of all debris/materials at site
and demolish of existing structure like concrete walls, partitions, roofing, steel materials including
concrete breaking
3 Structural Works including footing, column, beams, slab, staircase, wall footing
a. Concrete Works
b. Reinforcing Bar
c. Formworks
d. Scaffolding & Shoring
4 Masonry Works
5 Tileworks (Floor and Wall Finishes)
6 Ceiling Works
7 Fabricated Materials
8 Miscellaneous Works
9 Steel Works and Hardwares
10 Roofing and Tinnery Works
11 Plumbing Works
12 Electrical Works
13 Scaffolding Works
14 Painting Works
15 Construction of Septic Vault (1.2mx2.4m.1.6m Depth)
BILL OF MATERIALS
I. GENERAL REQUIREMENTS
II. SITEWORKS
Page 1 of 29
Clearing & Hauling of all necessary debris, waste cu.m. 15 450.00 6,750.00
materials at site
Demolish of existing structure like concrete walls, unit 1 15,000.00 15,000.00
counter, roofing, partitions, steel materials,
including concrete breaking,etc.
Direct Cost P 47,043.30
Page 2 of 29
III STRUCTURAL WORKS FOR FOOTING, WALL FOOTING,
COLUMN, BEAMS, SLAB, MAIN STAIR, ETC.
C. Formworks
Column sq.m. 76 P 308.00 P 23,408.00
Suspended Slab sq.m. 29 182.00 5,278.00
Beams sq.m. 73 275.00 20,075.00
Canopy sq.m. 5 182.00 910.00
Stair sq.m. 8 182.00 1,456.00
Material Cost P 51,127.00
Labor Cost 17,894.45
Direct Cost P 69,021.45
Page 3 of 29
Direct Cost P 69,985.35
Sub-Total III P 608,847.30
Page 4 of 29
IV. MASONRY WORKS
Laying of 150mm CHB including Mortar, Reinforcement sq.m. 130 P 928.00 P 120,640.00
& Plastering both sides (Exterior Walls)
Laying of 100mm CHB including Mortar, Reinforcement sq.m. 11 775.00 8,525.00
& Plastering both sides (Interior Walls)
Stiffiner Beams & Columns including Concreting, l.m. 17 586.00 9,962.00
Steel Bars & Formworks -
Laying of 100mm CHB including Mortar, Reinforcement sq.m. 18 586.00 10,548.00
and Plastering (Parapet Wall)
Plastering of Doors & Windows openings l.m. 66 75.00 4,950.00
Material Cost P 154,625.00
Labor Cost 54,118.75
Direct Cost P 208,743.75
Page 5 of 29
VIII. MISCELLANEOUS WORKS
A. Fixtures
Water Closet Tank Type w/ Fittings set 1 P 6,500.00 P 6,500.00
Page 6 of 29
and complete accessories
Urinal Pedestal Type w/ Fittings set 1 7,500.00 7,500.00
and complete accessories
Tissue Holder sets 1 850.00 850.00
Lavatory w/ Fittings sets 1 4,500.00 4,500.00
and complete accessories
4'x4" Floor Drain pcs 1 350.00 350.00
4"x4" Roof Drain pcs 3 450.00 1,350.00
Water Meter pc 1 2,500.00 2,500.00
Faucet (Heavy Duty) pcs 1 550.00 550.00
Material Cost P 24,100.00
Labor Cost 8,435.00
Direct Cost P 32,535.00
C. Drainage Line
Area Drain/Catch Basin (.60mx.60m) including Sets 3 P 1,450.00 P 4,350.00
CHB, cover, reinforcement, concrete topping,
etc. to complete
6"dia PVC Coupling pcs 6 120.00 720.00
Page 7 of 29
6"dia PVC Elbow pcs 6 220.00 1,320.00
6"dia PVC Pipe (S-1000) pcs 5 1,560.00 7,800.00
Material Cost P 14,190.00
Labor Cost 4,966.50
Direct Cost P 19,156.50
Sub-Total XI P 93,082.50
Roughing-ins
20mmØ x 3m PVC Pipe pcs 38 P 80.00 P 3,040.00
20mmØ PVC Adaptor w/ Locknut pcs 76 18.00 1,368.00
PVC Clip pcs 76 5.00 380.00
25mmØ x 10m RSC Pipe pcs 5 262.00 1,310.00
25mmØ x 10m RSC Adaptor w/ Locknut pcs 10 65.00 650.00
25mmØ Malleable Iron Clamp pcs 5 60.00 300.00
3/4"Ø x 8' Grounding rod w/ connector pair 1 1,380.00 1,380.00
Wires
3.5mm² THHN Wire rolls 3 4,110.00 12,330.00
8.0mm² THHN Wire mtrs 10 75.00 750.00
14.0mm² THHN Wire mtrs 10 108.00 1,080.00
Page 8 of 29
Miscellaneous and Consumables
Electrical Tape roll 5 58.00 290.00
Masking Tape roll 1 50.00 50.00
#16 GI Tie Wire kg 1 80.00 80.00
400cc Solvent Cement cans 3 418.00 1,254.00
100cc Solvent Cement cans 2 139.00 278.00
4" Paint Brush pcs 1 70.00 70.00
QDE Paint (Silver Gray) lit 1 250.00 250.00
Red Oxide Paint (Metal Primer) lit 1 185.00 185.00
Hacksaw blade pcs 2 67.00 134.00
Hangers, clips. screws and other accessories unit 1 1,000.00 1,000.00
for electrical fixtures
XIII. SCAFFOLDING
a. Earthworks
b. Materials
Page 9 of 29
12mmdiax6m def bar kgs 145 65.00 9,425.00
10mmdiax6m def bar kgs 94 65.00 6,110.00
#16 GI Tie Wire kls 4 80.00 320.00
Formworks (Slab) sq.m. 3 182.00 546.00
Formworks (Column) sq.m. 3 308.00 924.00
Sanitary Tee 4"dia pcs 3 220.00 660.00
Materials Cost P 35,125.00
Labor Cost 12,293.75
Direct Cost P 47,418.75
Sub-Total 50,226.80
Page 10 of 29
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
SUMMARY OF COST
I. GENERAL REQUIREMENTS P 53,669.30
II. SITEWORKS 53,762.25
STRUCTURAL WORKS FOR FOOTING, WALL FOOTING,
III 608,847.30
COLUMN, BEAMS, SLAB, MAIN STAIR, ETC.
IV. MASONRY WORKS 208,743.75
V. TILE WORKS (Floor and Wall Finishes) 127,210.50
VI. CEILING WORKS 74,587.50
VII. FABRICATED MATERIALS 192,870.00
VIII. MISCELLANEOUS WORKS 301,725.00
IX. STEEL WORKS 91,183.05
X. ROOFING AND TINNERY WORKS 69,822.00
XI. PLUMBING WORKS 93,082.50
XII. ELECTRICAL WORKS 128,559.15
XIII. SCAFFOLDING 16,560.00
XIV. PAINTING WORKS 99,063.00
XV. SEPTIC VAULT (1.2mx2.4mx1.6m depht) 50,226.80
Total Direct Cost P 2,169,912.10
OCM 325,486.82
PROFIT 216,991.21
FIRE PERMIT FEE 2,851.26
SANITARY AND ELECTRICAL PERMIT FEES 400.00
VAT 135,619.51
Total Project Cost P 2,851,260.89
Prepared by: Checked by:
NASARIO F. CAMPOSANO
Electrical Engineer / Programmer
Submitted by:
Page 11 of 29
Recommending Approval:
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved:
JOSELITO B. CABUNGCAL
City Engineer
Page 12 of 29
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
AGENCY ESTIMATE
T O TAL 2,851,260.89
Amount in Words:
TWO MILLION EIGHT HUNDRED FIFTY ONE THOUSAND TWO HUNDRED SIXTY PESOS
AND EIGHTY NINE CENTAVOS ONLY
Note:
Recommending Approval :
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Ap p r o ve d :
JOSELITO B. CABUNGCAL
City Engineer
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5 Floor, QC Civic Center Building “B”
th
PROJECT NAME : PROPOSED CONSTRUCTION OF TWO (2)-STOREY BOY SCOUT SUB-OFFICE AT RAMON MAGSAYSAY ELEMENTARY SCHOOL
LOCATION : BARANGAY LOURDES, DISTRICT 1, QUEZON CITY
DURATION: 150 CALENDAR DAYS
WORK SCHEDULE
I GENERAL REQUIREMENTS
II SITE WORKS
STRUCTURAL WORKS FOR FOOTING,
III WALL FOOTING, COLUMN, BEAMS, SLAB,
MAIN STAIR, ETC.
IV MASONRY WORKS
XIII. SCAFFOLDING
Prepared by: Checked & Submitted by: Recommending Approval: Approved by:
Recommending Approval:
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved by:
JOSELITO B. CABUNGCAL
City Engineer
for items
104, 105,
106
ROSARIO
Republika ng Pilipinas
Lungsod ng Quezon
TANGGAPAN NG INHINYERYA
5th Floor, QC Civic Center Building “B”
Telephone Nos. 988-4242 Local 8538
Manpower No.
1 Project Manager 1
2 Project Engineer 1
3 Materials Engineer 1
4 Foreman 1
5 Skilled Worker 4
6 Driver 1
Recommending Approval:
MENANDRO G. VALDEZ
OIC, Planning & Programming Division
Approved by:
JOSELITO B. CABUNGCAL
City Engineer
25
24
ROSARIO
PROGRAM OF WORK AND DETAILED ESTIMATE FOR THE PROPOSED
CONSTRUCTION OF TWO (2)-STOREY BOY SCOUT SUB-OFFICE AT RAMON MAGSAYSAY ELEMENTARY SCHOOL
LOCATED AT BARANGAY LOURDES, DISTRICT 1, QUEZON CITY
TAKE OFF
I. GENERAL REQUIREMENTS
II. SITEWORKS
C. Formworks
Column sq.m. 76
Suspended Slab sq.m. 29
Beams sq.m. 73
Canopy sq.m. 5
Stair sq.m. 8
A. Fixtures
Water Closet Tank Type w/ Fittings set 1
and complete accessories
Urinal Pedestal Type w/ Fittings set 1
and complete accessories
Tissue Holder sets 1
Lavatory w/ Fittings sets 1
and complete accessories
4'x4" Floor Drain pcs 1
4"x4" Roof Drain pcs 3
Water Meter pc 1
Faucet (Heavy Duty) pcs 1
C. Drainage Line
Area Drain/Catch Basin (.60mx.60m) including Sets 3
CHB, cover, reinforcement, concrete topping,
etc. to complete
6"dia PVC Coupling pcs 6
6"dia PVC Elbow pcs 6
6"dia PVC Pipe (S-1000) pcs 5
Roughing-ins
20mmØ x 3m PVC Pipe pcs 38
20mmØ PVC Adaptor w/ Locknut pcs 76
PVC Clip pcs 76
25mmØ x 10m RSC Pipe pcs 5
25mmØ x 10m RSC Adaptor w/ Locknut pcs 10
25mmØ Malleable Iron Clamp pcs 5
3/4"Ø x 8' Grounding rod w/ connector pair 1
Wires
3.5mm² THHN Wire rolls 3
8.0mm² THHN Wire mtrs 10
14.0mm² THHN Wire mtrs 10
XIII. SCAFFOLDING
J PAINTING WORKS
a. Earthworks
Excavation cu.m. 5
b. Materials