SCHEDULE

Start time : 0:00


INFORMATION
Tank Foundation and Bundwall Works
PT. TRIPATRA ENGINEERS & DAILY PROGRESS REPORT Schedule Duration: WORKING TIME Finish Time : 18:00
CONSTRUCTORS Date : 21 Juli 2019
Time Lapsed: Total time : 10

DOC. NO : 9750-AJG-DPR-001
MANPOWER STATUS PROGRESS STATUS TODAY ACTIVITY

ATTENDANCE WORKING ACHIEVEMENT


SR. NO DESCRIPTION
SR. NO MANPOWER SR. NO DESCRIPTION OF WORK UNIT QTY
HOUR
QTY STATUS PREV. DAY TODAY ACCUM % PROG
Normal OT 1 Rebar Fabrication
INDIRECT WORKER 11 110 FABRICATION AREA 2 Excavation Tank T 001, T 018, T 019
1 Project Manager 0 0 1 PHT Rebar Fabrication SET 889 701 22 723 81% 3 Cutting Pile Tank T 001, T 018, T 019
2 Site Manager 0 0 2 Rebar Fabrication Tank T-005 TON 64,483 64,483 0,000 64,483 100% 4 Rebar Installation Tank T 005
3 Superintendant 0 0 3 Rebar Fabrication Tank T-003 TON 83,542 83,542 0,000 83,542 100%
4 Supervisor 1 10 3 Rebar Fabrication Tank T-006 TON 39,353 39,353 0,000 39,353 100%
5 Logistic 1 10
6 Engineering 2 20 TANK FOUNDATION
7 Admin 1 10 A. FOUNDATION TANK T-005
8 Surveyor 1 10 1 Excavation M3 305,938 305,938 0 305,938 100%
9 HR/GA 1 10 2 Cutting Pile EA 80 80 0 80 100%
10 Safety 3 30 3 PHT EA 80 80 0 80 100%
11 QC 1 10 4 Lean Concrete M3 35,357 35,357 0 35,357 100% TOMORROW ACTIVITY
5 Rebar Installation TON 64,483 32,242 6,448 38,690 60%
SR. NO DESCRIPTION
DIRECT WORKER 60 600 6 Forwmork Installation M2 64,240 0 0 0 0%
1 Foreman 2 20 7 Pouring Concrete M3 468,160 0 0 0 0% 1 Rebar Fabrication
2 Rebar Man 27 270 1 off 8 Anchor Box Setting EA 32 0 0 0 0% 2 Excavation Tank T 001, T 018, T 019
3 Carpenter 7 70 9 Backfilling M3 37,966 0 0 0 0% 3 Cutting Pile Tank T 001, T 018, T 019
4 Mason 7 70 4 Rebar Installation Tank T 005
5 Skill Labor 0 0 B. FOUNDATION TANK T-002
6 Operator 4 40 1 off 1 Excavation M3 507,898 507,898 0 507,898 100%
7 Rigger 2 20 2 Cutting Pile EA 178 178 0 178 100%
8 Helper 7 70 1 off 3 PHT EA 178 0 0 0 0%
9 Driver 3 30 4 Lean Concrete M3 59,754 0 0 0 0%
10 Mechanic 1 10 5 Rebar Installation TON 112,455 0 0 0 0%
6 Forwmork Installation M2 84,040 0 0 0 0%
TOTAL 71 710 0 7 Pouring Concrete M3 801,790 0 0 0 0%
8 Anchor Box Setting EA 40 0 0 0 0% CONCERN/POTENTIAL DELAY
9 Backfilling M3 49,280 0 0 0 0%
SR. NO DESCRIPTION

C. FOUNDATION TANK T-001 1 Rainy


1 Excavation M3 507,898 197,120 24,640 221,760 44%
MAIN EQUIPMENT STATUS 2 Cutting Pile EA 174 66 28 94 54%
3 PHT EA 174 0 0 0 0%
SR. NO EQUIPMENT/TOOL UNIT QTY HOUR STATUS
4 Lean Concrete M3 59,754 0 0 0 0%
1 Bar Bending EA 2 20 good 5 Rebar Installation TON 112,455 0 0 0 0%
2 Bar Cutter EA 2 20 good 6 Forwmork Installation M2 84,040 0 0 0 0%
3 Concrete Vibrator EA 5 50 good 7 Pouring Concrete M3 801,790 0 0 0 0%
4 Truck Crane EA 1 10 good 8 Anchor Box Setting EA 40 0 0 0 0%
5 Crane 35 Ton EA 1 10 good 9 Backfilling M3 49,280 0 0 0 0%
6 Excavator PC 75 EA 1 10 good
7 Excavator PC 200 EA 1 10 good D. FOUNDATION TANK T-018
8 Dump Truck EA 2 20 good 1 Excavation M3 20,114 20,114 0,000 20,114 100% PROJECT PHOTOGRAPH
9 Stamper EA 2 20 good 2 Cutting Pile EA 6 5 0 5 83%
10 Light Vehicle EA 2 20 good 3 PHT EA 6 0 0 0 0%
11 Generator Set 150 kVA EA 1 10 good 4 Lean Concrete M3 2,210 0 0 0 0%
12 Fuel Storage Tangk (3000 L) EA 1 10 good 5 Rebar Installation TON 2,646 0 0 0 0%
6 Forwmork Installation M2 15,400 0 0 0 0%
7 Pouring Concrete M3 26,158 0 0 0 0%
8 Anchor Box Setting EA 8 0 0 0 0%
9 Backfilling M3 4,714 0 0 0 0%

MATERIAL RECEIVED E. FOUNDATION TANK T-018


SR. NO DESCRIPTION UNIT QTY REMARKS 1 Excavation M3 20,114 20,114 0,000 20,114 100%
2 Cutting Pile EA 6 5 0 5 83%
1 Rebar Material D25 Ea 6393 3 PHT EA 6 0 0 0 0%
2 Rebar Material D13 Ea 400 4 Lean Concrete M3 2,210 0 0 0 0%
3 Rebar Material P10 Ea 1500 5 Rebar Installation TON 2,646 0 0 0 0%
4 Rebar Material D19 Ea 3348 6 Forwmork Installation M2 15,400 0 0 0 0%
5 Rebar Material D16 Ea 372 7 Pouring Concrete M3 26,158 0 0 0 0%
6 Rebar Material D10 Ea 1075 8 Anchor Box Setting EA 8 0 0 0 0%
7 Plywood Ea 720 9 Backfilling M3 4,714 0 0 0 0%
8 Hollow 6 m Ea 387
9 Hollow 3 m Ea 100 INSTRUCTION/APPROVAL GIVEN BY MAIN CONTRACTOR
Hollow 2 m Ea 50
SR. NO DESCRIPTION

WEATHER STATUS

SR. NO
WEATHER
REMARKS Acknowledge by, Checked by, Prepared by,
TIME CONDITION Construction Manager Construction Engineer Project Control
1 06.00 - 08.00 A PT. TPEC PT. TPEC PT. ALHAS JAYA GROUP
2 08.00 - 10.00 A
3 10.00 - 12.00 D
4 12.00 - 14.00 B
5 14.00 - 16.00 A
6 16.00 - 18.00 A
7 18.00 - 20.00 A
Remarks: A = Clear; B = Cloudy; C = Drizzle; D = Rainy; E = Heavy Rain. (………………….) (………………….) (………………….)