Compressor Foundation Concrete Pour Plan Typical

9.6 9.6 9.6 9.6 9.6 9.6 9.6 9.6 9.6 9.6
Strip Each Cum Cum Cum Cum Cum Cum Cum Cum Cum Cum
Strip #s Strip #s Strip #s Strip #s Strip #s Strip #s Strip #s Strip #s Strip #s Strip #s
400 mm 22 25 28 34 38 42 45 47 49 50
400 mm 11 15 19 26 32 36 40 44 46 48
400 mm 7 9 13 18 24 27 33 39 41 43
400 mm 3 5 8 12 16 20 23 30 35 37
400 mm 1 2 4 6 10 14 17 21 29 31
2000 mm 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm
Foundation Strip Section
Start early morning or late evening in hot weather conditions Thermal curing required
60 Truck Trips @ 8 cum each Frequency 15 minutes 2 Pumps 60 Trips 8 Hours
GGBS concrete required Formwork System required
Vibrators 6 # Masons 4
Helpers 20 Concrete Truck
Carpenters 4

Concrete Truck 1 2 3 Concrete Truck


Pump Location Pump Location Pump Location

1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm
1000 mm

Foundation Strip Plan RCC Quantity 480 Cum

Concrete Truck 1 2 3 Concrete Truck


Pump Location Pump Location Pump Location

Concrete Truck