Beruflich Dokumente
Kultur Dokumente
REMARKS :
PREVIOUS ID PRESENT ID CUMULATIVE ID
ABBREVIATION : PIPE - P, 90 DEG ELBOW - E, 45 DEG ELBOW - E/2, EQUAL TEE - EQ-TEE, UNEQUAL TEE - UNEQ-TEE, CONCENTRIC REDUCER - CON-RED, ECCENTRIC REDUCER - ECC-RED, WELDNECK
FLANGE - WF, SLIP ON FLANGE - SF, HALF COUPLING - HC, FULL COUPLING - FC, SOCK-O-LET - S-LET, WELD-O-LET - W-LET, NIPPLE - N, MITRE - MIT , BUTT WELD - BW, SOCKET WELD - SW, FILLET WELD -
FW, MITRE WELD - MW, ATTACHMENT WELD - AW, PIPE TO PIPE BRANCH WELD - BRW, BRANCH WITH RF PAD WELD - BRPW, P TO HC/S-LET/O-LET WELD - GRBRW
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD. CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/012 R0
CLIENT
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
PROJECT
Kanpur-208022
PO NO. :
REMARKS :
PREVIOUS ID PRESENT ID CUMULATIVE ID
ABBREVIATION : PIPE - P, 90 DEG ELBOW - E, 45 DEG ELBOW - E/2, EQUAL TEE - EQ-TEE, UNEQUAL TEE - UNEQ-TEE, CONCENTRIC REDUCER - CON-RED, ECCENTRIC REDUCER - ECC-RED, WELDNECK FLANGE - WF, SLIP ON
FLANGE - SF, HALF COUPLING - HC, FULL COUPLING - FC, SOCK-O-LET - S-LET, WELD-O-LET - W-LET, NIPPLE - N, MITRE - MIT , BUTT WELD - BW, SOCKET WELD - SW, FILLET WELD - FW, MITRE WELD - MW, ATTACHMENT
WELD - AW, PIPE TO PIPE BRANCH WELD - BRW, BRANCH WITH RF PAD WELD - BRPW, P TO HC/S-LET/O-LET WELD - GRBRW
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD. CONSULTANT / TPI CLINT
DOCUMENT FORMAT NO. : HO/QA-QC&I/013 R0
CLIENT
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT
PO NO.
REPORT NO.
DYE PENETRANT TEST REPORT
DATE : :
Test Conducted on # Base Metal/Weld #Plate/Pipe Test Conducted after Root / Intemidiate / Final Weld
Cleaner
Penetrant
Developer
Line No.- Rev. No. / Joint Welder
Sl. No Observation Result
Equipment No. / Mark No. No Size Type No.
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD. CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/14 R0
DOCUMENT FORMAT NO. : HO/QA-QC&I/15 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT :
PO NO. :
REPORT NO. :
RADIOGRAPHY OFFER
DATE : :
Procedure No: IQI Type : As per Table T-233.2_ASME Sec.V
Line No. Rev. No. / Joint Welder
Sl. No Technique XR NO Remarks
Equipment No./Mark No. No Size Thk. No.
Total No. of Joints Offered Total No(s) of Joint Taken Total No(s) of Radiographs Submitted
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/33 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT :
PO NO. :
REPORT NO. :
Line No. / Isometric No. INDEX
DATE : :
TEST LOOP NO. : RUNNING METERs :
Sl. No. Line No. / Isometric No. Rev. Sl. No. P &ID No. Rev.
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/17 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT :
PO NO. :
REPORT NO. :
Mechanical CLEARANCE REPORT
DATE : :
TEST LOOP NO. : RUNNING METERs :
Sl. No. Line No. / Isometric No. Rev. Sl. No. P &ID No. Rev.
Witness / Acc
Action By Checked By
Observation By
Sl No. Items to check Observation Remarks
given by Consultant /
FLEFPL FLEFPL
TPI
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/18 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area, PROJECT :
Kanpur-208022
PO NO. :
REPORT NO. :
PUNCH LIST FOR PRESSURE TEST DATE : :
TEST LOOP NO. : RUNNING METERs :
Sl. No. P &ID No. Rev. Sl. No. P &ID No. Rev.
Priority : (A) Needed for Pressure test, (B) Needed for Commissioning, (C) Needed for Start-Up, (D) Needed for Plant Acceptance
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/16 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area, PROJECT :
Kanpur-208022
PO NO. :
REPORT NO. :
RADIOGRAPHY INTERPRETATION REPORT
DATE : :
Technique : SFD :
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/19 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area, PROJECT :
Kanpur-208022
PO NO. :
REPORT NO. :
NDT CLEARANCE REPORT FOR PIPING DATE : :
TEST LOOP NO. : RUNNING METERs :
Sl. No. Line No. / Isometric No. Rev. Sl. No. P &ID No. Rev.
Witness / Acc
Action By Checked By
Observat Observation By
Sl No. Items to check Remarks
ion given by Consultant /
FLEFPL FLEFPL
TPI
Remarks :
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/20 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area, PROJECT :
Kanpur-208022 PO NO. :
REPORT NO. :
LINE HISTORY SHEET DATE : :
TEST LOOP NO. : RUNNING METERs : TEST MEDIUM : TEST PRESSURE : Kg / cm2
MC CLEARANCE REPORT : NDT CLEARANCE REPORT :
GAD NO. : P & ID NO. : REV. :
Joint Descriptions Inspection Reports
Root Cover D.P.T. Rep. Date RT. Rep.
Thk. / Weld Pipe Fit-up Visual Remarks
Sl. No. Line No. Rev. Sheet Jt.No Size SJ / FJ Date Date Welder Welder
Ratting Type Class Rep. Rep. Root Final Root Final Rep No. Date
No. No.
1
10
11
12
13
14
15
16
17
18
19
20
Note :
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/21 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT :
PO NO. :
REPORT NO. :
PIPING FLUSHING REPORT DATE : :
TEST LOOP NO. : RUNNING METERs :
Sl. No. P &ID No. Rev. Sl. No. P &ID No. Rev.
Others :
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/22 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT :
PO NO. :
Test Duration : Hrs. #Test Starting Time : AM / PM, #Test Ending Time : AM / PM
Pressure Gauge No. Range Calibration Calibration Calibration Certificate No. Physical Condition
( Kg / cm2 ) Date Due Date
Others
Activity Date Time Remarks
Water filling & venting started at
Water filling completed
Venting completed
Test pressure reached at
Test completed at
Water drained
Temporary blinds removed
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/23 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P) LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area,
Kanpur-208022 PROJECT :
PO NO. :
PRESSURE TEST REPORT REPORT NO. :
(PNEUMATIC TEST) DATE :
TEST LOOP NO. : RUNNING-METERs :
Sl. No. Line No. / Isometric No. Rev. Sl. No. P &ID No. Rev.
Test Duration : Hrs. #Test Starting Time : AM / PM, #Test Ending Time : AM / PM
Pressure Gauge No. Range Calibration Calibration Calibration Certificate No. Physical Condition
( Kg / cm2 ) Date Due Date
Others
Activity Date Time Remarks
Test medium (Air) filling started at
Test medium (Air) filling completed
Test pressure reached at
Water - Soap solution Check / Inspection start at
Inspection / Test completed at
Test medium released
Temporary blinds removed
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT
DOCUMENT FORMAT NO. : HO/QA-QC&I/24 R0
CLIENT :
FLUIDLINE ENGINEERS & FABRICATORS (P)
LTD. CONSULTANT :
C-51, Udyog Kunj, Road No. 12, Site V, Panki Industrial Area, PROJECT :
Kanpur-208022 PO NO. :
BOX-UP REPORT :
REPORT NO.
DATE : :
TEST LOOP NO. : RUNNING METERs :
Sl. No. Line No. / Isometric No Rev. Sl. No. P &ID No. Rev.
Checked Witness /
Observat Action By
Observat By Acc By
Sl No. Items to check ion given Remarks
ion Consulta
by FLEFPL FLEFPL
nt / TPI
A.1 Flushing and internal cleaning done properly
All temporary spools and blinds removed from
A.2
the test loop
Check valve(s) , Control valve(s) , Safety
A.3 valve(s) Instruments , Rupture disc , Orifice
plate(s) etc installed properly
Signature
Name
Date
Authority FLUID LINE ENG. & FAB. PVT. LTD CONSULTANT / TPI CLIENT