Beruflich Dokumente
Kultur Dokumente
This specification has been revised as indicated below and described in the revision record on the following
page. Please destroy all previous revisions.
A 9/14/2010 P. D. Quinn 4
0 11/09/2010 P. D. Quinn R. C. Merrick 14
1 3/31/2011 R. C. Merrick C. Dwyer 14
Lead Engineer
Engineering Manager:
Client Approval:
Record of Revisions
TABLE OF CONTENTS
1.0 GENERAL
1.1 Summary
A. Scope of Specification
1. This specification provides guidelines for design of piping tie-ins, selection of tie-in
methods, and control and coordination of piping tie-ins for the purpose of planning
and safely performing tie-in work.
2. Wherever a difference exists between this specification and the drawings, the
drawings shall govern. No deviation shall be made from this specification without
written authorization from Marafiq.
B. Related Specifications
D. Supplied by Owner
In cases when Marafiq will perform connections to existing piping or equipment, the tie-
in point shall be the interface point between the Marafiq supplied piping and Contractor's
scope piping.
E. Terminology
4. Hazardous Substances: Included, but are not limited to, those substances that are
explosive, combustible, toxic, or corrosive.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Page 6 of 14
Revision 1
6. Confined Space: An enclosure with known or potential hazards and restricted means
of entrance and exit.
1.2 References
The publications listed below form part of this specification. Each publication forming part of this
specification shall be the latest revision and addendum in effect on the date this specification is issued
for construction unless noted otherwise. Except as modified by the requirements specified herein or the
details of the drawings, Work included in this specification shall conform to the applicable provisions
of these publications.
E. Government Requirements
Where fabrication and design criteria in this specification are affected by Kingdom of
Saudi Arabia or Royal Commission requirements, this specification shall be modified as
necessary to ensure compliance.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Page 7 of 14
Revision 1
A. Design Requirements
1. Piping tie-ins shall be approved by Contractor Lead Piping Engineer and Marafiq
Representative before any work can be done to existing piping by Construction
Personnel or Contractor.
2. A piping tie-in method for each tie-in shall be established before any tie-in work can
be started.
3. Tie-in methods shall be grouped in the following procedures, and the procedures
strictly adhered to during piping tie-in work:
4. Procedures may also be submitted to the Marafiq Lead Piping Engineer for approval
(refer to Section 1.4, of this specification). However, no deviation from the minimum
guidelines and safety considerations specified in this specification shall be permitted.
Tie-in points shall be identified on the P&IDs (Piping and Instrumentation Diagrams) and
piping drawings with the Marafiq tie-in symbol and numbering system as defined on the
P&ID legend key sheet.
1. P&IDs
a. Locate and tag tie-in points during the development of flow diagrams.
b. Show sufficient detail of existing piping to identify the point of tie-in.
a. Tie-in points shall be indicated in the piping plans, taking into consideration
clearances required to perform tie-in work.
b. Field survey of tie-in location shall be done, and it is recommended early during
design.
3. Isometric Drawings
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Page 8 of 14
Revision 1
f. For ductile iron lines, tapping saddle, or sleeve specification and the exact
outside radius (R) of the line as measured at the point of pressure tapping.
h. Test fluid and pressures for testing nozzles, valve, adapter, and reinforcing pad
(if reinforcing is specified), and special instructions for removal of test fluid and
cleaning the nozzle, if required to prevent product contamination.
k. The minimum clear, full-round valve opening required (allow for 3 mm [1/8 of
an inch] clearance in diameter) and the specific valve meeting this requirement.
A piping tie-in list shall be prepared and issued for use by Construction / Contractor.
Completed tie-ins shall be initialed and dated on the tie-in list by authorized personnel
responsible for performing tie-ins, Contractor personnel on site, and Marafiq.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Page 9 of 14
Revision 1
1.4 Submittals
A. It is mandatory that in advance of any hot tap work, the following items should be
prepared and submitted to Marafiq for approval:
4. Health, safety, fire protection, and other appropriate instructions, including Marafiq
or User requirements
B. Alternate cold tap procedures may be submitted for Marafiq approval. Otherwise, the
cold tap procedures specified herein shall be adhered to.
To ensure that the proper precautions are taken before and during tie-in work, the following safety
precautions shall be taken into consideration:
A. Safety Precautions
1. Piping systems that have held hazardous substances shall be prepared before tie-in
work, in accordance with ANSI / AWS F4.1 and this specification.
3. Only qualified personnel are allowed to perform tie-in work. Qualified personnel are
designated by Contractor and Marafiq, in writing, as capable (by education or
specialized training, or both) of anticipating, recognizing, and evaluating employee
exposure to hazardous substances or other unsafe conditions. These personnel should
be capable of specifying the necessary control or protective action, or both, for
worker safety.
5. Welding Precautions
a. Welding shall not be performed on compressed air lines or air receivers under
pressure.
b. Welding shall not be performed on piping operating above its rated working
pressure.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Page 10 of 14
Revision 1
d. No welding shall be performed in tanks and vessels above their liquid level.
6. Hot tapping of lines or vessels containing the following services is not permitted
unless written approval from Construction Contractor and Marafiq is obtained:
7. Hot tapping shall not be done on piping with cladding or linings such as glass, lead,
refractory, plastic, and strip lining.
8. Hot tapping shall not be done in piping requiring PWHT (Post Weld Heat
Treatment).
10. To ensure that hot tapping will be performed under safe conditions, a checklist is
attached for consideration. Refer to Attachment 03.
11. For work above and below grade, or in congested areas, provide for easy personnel
exit. To ensure that excavations are safe for entry and hot line work, tests for
presence of flammable and toxic material shall be made. If either of these are
present, an air mover or some other positive means of ventilation shall be provided.
Air breathing equipment must be used to protect personnel from toxic atmospheres
or vapors emitted as a result of welding or penetrations into lines. Refer to Section
1.6, of this specification, for site conditions.
A. Existing Conditions
1. Tie-in work performed in Refineries, Gas Plants, and Petrochemical Plants shall be
in accordance with API Publication 2009.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Page 11 of 14
Revision 1
2. Tie-in work locations shall be analyzed for the appropriate safeguards and types of
personal protective equipment available if needed. Factors that require consideration
are as follows:
a. The work location must be gas free, and precautions should be taken to prevent
ignition of flammable or combustible materials.
b. Before welding or cutting is performed above or near oily surfaces, the area
should be flushed with water, steam cleaned, or covered with clean dirt or sand,
or other precautions should be taken.
c. Tie-in work should not be permitted while adjacent equipment that contains
flammable liquid or vapor is being opened, disassembled, steamed, ventilated, or
flushed of sediment.
Plant shutdown schedule should be requested from Marafiq in order to prioritize and
schedule tie-in activities (such as drawing issue, material purchase, and material
delivery).
2.0 PRODUCTS
A. Components
1. Valves, packing, gaskets, and other piping components shall be in accordance with
Piping Engineering Specification MQ-SP-P-5002.
B. Nozzle Reinforcement
C. Branch Connections
1. Special branch reinforcing may be required for hot tapping to prevent buckling of
header during pressure testing of the branch connectors.
1. Valves must have clear, full, round openings at least 3 mm (1/8 of an inch) greater in
diameter than the specified drill or cutter OD.
2. Regular port (not tilted port or venturi port) gate valve with the same DN (Nominal
Diameter) or NPS (Nominal Pipe Size) and rating as the branch connection shall be
specified, except as follows:
a. Ball valves may be used if port opening and material specifications are
adequate.
b. Corporation plug cocks (DN 20 [NPS ¾]]) may be used in water service if the
line being tapped is ductile iron or steel, Schedule 40, and DN 100 (NPS 4) or
larger.
3. For valve sizes DN 50 (NPS 2) and smaller (other than full port type), it may be
necessary to use a drill diameter 1 size smaller than that specified in order to clear
the valve seat rings. This decision must be made in the field after the valve has been
selected since inside dimensions of the smaller valves vary widely with manufacturer
and style.
A. Hot Tapping
1. Some pipe systems may be unsuitable for hot tapping because the metallurgy or
thickness of metal requires stress relieving, which normally cannot be done while the
system is in service. Special treatment is required for high tensile strength alloy
steels, and special welding electrodes must be used. Hot tap fitting and weld rod
metallurgy must be compatible with piping to be welded.
2. The base metal thickness must provide support for the new connection and the hot
tap machine or be properly reinforced to provide such support. Generally, a
minimum base metal thickness of 5 mm (3/16 of an inch) is recommended for hot
tapping. A minimum base metal thinner than 5 mm (3/16 of an inch) shall not be hot
tapped without written authorization from Engineering Contractor and Marafiq.
3. The base metal must be free of lamination, hydrogen attack, or stress corrosion
cracking. There must be no other imperfections that would prevent a solid weld from
being made.
A. The hot tap machine shall be of the proper size and rating to accommodate the required
pipe branch connection.
B. Hot tapping machines have a maximum working pressure and temperature rating which
shall not be exceeded. The machine may be powered by hand, hydraulic fluids, or
pneumatic drives. Electric motor drives are prohibited.
C. The hot tap machine shall have an accurate means by which to indicate the travel distance
of the pilot bit and cutter.
D. The design shall include the specification for gaskets, tapping valve, and bolts. Hot tap
fitting length must accommodate the machine. Sufficient clearance for operation of the
machine must be provided.
E. Before hot tapping is attempted, the machine, cutter, and pilot bit shall be carefully
inspected to ensure that all are in satisfactory condition.
3.0 EXECUTION
3.1 Preparation
Tie-in work shall not start until the following criteria have been met:
B. Each tie-in point must have a tapping-type listed on the tie-in list.
A. Tie-in work shall be done in accordance with referenced procedures in this specification's
Attachment section, and Piping Engineering Specification MQ-SP-P-5004.
4. Installation
5. Quality Control
4.0 ATTACHMENTS
4.1 Attachment 01: Cold Tap Procedure in Conjunction with Total Plant Shutdown
4.2 Attachment 02: Cold Tap Procedure in Conjunction with System Shutdown or Isolation of
Pipe
4.3 Attachment 03: Hot Tap and Stoppling Procedure - Minimum Guidelines
End of Specification
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Attachment 01 - Page 1 of 1
Revision 1
b. Tie-in points shall be clearly marked with tie-in point numbers identical to tie-in list.
c. Tie-ins shall be done in sequence with a schedule previously prepared by Engineering Contractor
and Marafiq to ensure tie-ins can be completed during plant shutdown.
d. Special considerations shall be given to any tie-in work done on piping which has contained
hazardous substances (refer to ANSI/AWS F4.1.).
e. Each tie-in work area shall be prepared in accordance with Section 1.6.A, before tie-in work is
performed.
b. Valves in the line should be closed and locked out. The pipe should be disconnected and drained.
The open end of the pipe sections not being worked on should be blanked off.
4. Installation
Installation of new piping systems shall be done in accordance with Piping Engineering Specification MQ-
SP-P-5004. Welding shall be done in accordance with Piping Engineering Specification MQ-SP-P-5029.
5. Quality Control
After the tie-in work is completed, it shall be checked in accordance with the existing plant safety criteria
and the appropriate construction QC (Quality Control) practices.
b. Tie-in points shall be clearly marked with tie-in point numbers identical to tie-in list.
c. Tie-ins shall be done in sequence with a schedule previously prepared by Engineering Contractor
and Marafiq to ensure tie-ins can be completed during plant shutdown.
d. Special considerations shall be given to any tie-in work done on piping which has contained
hazardous substances (refer to ANSI/AWS F4.1.).
e. Each tie-in work area shall be prepared in accordance with Section 1.6.A, before tie-in work is
performed.
b. Valves in the line should be closed and locked out. The pipe should be disconnected and drained.
The open end of the pipe sections not being worked on should be blanked off.
4. Installation
Installation of new piping systems shall be done in accordance with Piping Engineering Specification MQ-
SP-P-5004. Welding shall be done in accordance with Piping Engineering Specification MQ-SP-P-5029.
5. Quality Control
After the tie-in work is completed, it shall be checked in accordance with the existing plant safety criteria
and the appropriate construction QC (Quality Control) practices.
Each hot or stopple tap shall be evaluated on its own merits considering operating conditions, line contents, piping
materials, and location. The following requirements shall be met:
a. Hot taps shall not be made in equipment while it is operating at temperatures below the metal transition
temperatures.
b. For hot taps that will be made at low temperatures below 5 °C (40 degrees F), special preheat, welding, and
post-heat procedures may be required.
c. Hot taps shall not be specified for equipment handling amine (MEA and DEA) or caustic, if operating
conditions would require stress relief.
d. Hot taps shall not be specified for equipment or lines containing flammables below atmospheric pressure or
containing a mixture within the flammable range and operating at any pressure.
e. Hot taps shall be avoided or special precautions specified when air-hardening alloys are involved.
f. Hot tapping of equipment containing hydrogen is permissible provided the equipment had not operated
above the Nelson curve limits. (Refer to API 941.)
g. When equipment containing hydrogen sulfide or other toxic materials is to be hot tapped, special safety
precautions (if any) for these materials shall be specified.
h. If equipment handling ethylene, butadiene, or acetylene is to be hot tapped, special precautions must be
taken to maintain circulation and prevent overheating and thermal decomposition (with possible explosion)
of the contents.
i. Do not hot tap pressurized piping or pressure vessels at locations where fluid flow does not exist.
j. Hot tapping of storage tanks shall not be specified except at locations on the shell where the liquid level can
be maintained at least 1 m above the highest point of welding during welding operations.
k. Do not hot tap equipment upstream of rotating machinery unless facilities exist that will prevent cuttings
and droppings from reaching the machinery.
l. Bolt-on connections shall be used for hot tapping cast iron equipment.
m. Hot tapping of reinforced concrete pressure piping (or other internally lined equipment) is allowed;
however, special tapping materials, equipment, and techniques are required.
Design of hot tap connections shall be in accordance with the applicable codes and standards.
a. Allow sufficient clearance to install connections and operate the tapping or plugging equipment.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Attachment 03 - Page 2 of 3
Revision 1
b. Locate connections so that welding is performed at least 600 mm (24 inches) from flanges, threaded
connections, and riveted joints, whenever possible. This should prevent leaks from developing in those
joints.
The nozzle length must be determined for the particular tapping machine that will be used so as to ensure a complete
cut through the equipment wall. In addition, for flanged nozzles, the length should be adequate to permit removal of
flange bolts. When practicable, the face-to-center line dimension of flanged nozzles for perpendicular connections
to pipelines should be the same as the corresponding dimensions for a welding tee and welding neck flange of the
same size and rating as the tapped line.
a. Hot tap connections for size-to-size connections shall be a full encirclement saddle a minimum width of 75
mm (3 inches) and 6 mm (1/4 of an inch) minimum thickness.
b. Hot tap connections for other than size-to-size shall be one of the following:
c. Hot tapping connections for cast iron pipelines shall be full-encirclement, bolt-on saddle.
d. Stoppling connections shall be full-encirclement type fitting equal to T. D. Williamson's Stopple Fitting.
Connections shall be designed to prevent buckling of the surface being tapped due to application of test pressure to
the inside of the branch connection. An acceptable method for calculating the buckling pressures in externally
loaded cylinders is given in R. J. Roark, Formulas for Stress and Strain, Fourth Edition, Page 354, Item S(34).
The minimum hot tapping nozzle and valve size specified shall be DN 25 (NPS 1).
Heating or purging of the tapping or stoppling connection shall be specified if the equipment contents will be solid
at ambient temperatures.
Power and Water Utility Co. for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-P-5018
Project Name: Date: 31 Mar 2011
Contract Number: Attachment 03 - Page 3 of 3
Revision 1
Testing
The tapping or stoppling connections, reinforcing pad, valve, machine, and joints shall be pressure tested prior to
tapping the line.
Hydrostatic test shall be specified for equipment operating between 5 °C and 93 °C, unless other special conditions
require a different test medium. For other temperatures, air, nitrogen, or another inert gas shall be specified.
Test pressure for the valve, nozzles, and reinforcing pad (if required) shall be as follows:
b. For piping and pressure vessels, test pressure shall be calculated according to the applicable code and shall
be based on the most severe combination of design pressure and temperature (not the operating conditions),
since operating conditions may change from time to time.