ID Task Task Name Duration Start Finish

Sep '19 Oct '19 Nov '19


Mode 15 22 29 6 13 20 27 3 10 17 24
1 Software Development Cycle 189 days Tue 10/1/19 Fri 6/19/20

2 Provisioning of Fully Functional Hardware 6 days Tue 10/1/19 Tue 10/8/19

3 Installation of Basic Software Architecture 6 days Tue 10/1/19 Tue 10/8/19

4 Imparting Training to Users 10 days Wed 10/9/19 Tue 10/22/19


5 Development & Implementation Phase 160 days Tue 10/1/19 Mon 5/11/20
6 Payroll Module 20 days Tue 10/1/19 Mon 10/28/19
7 Leave Administration 20 days Tue 10/29/19Mon 11/25/19
8 SUBLO Tickets for Employees 20 days Tue 11/26/19Mon 12/23/19
9 TADA Claim process 20 days Tue 12/24/19Mon 1/20/20
10 Probation assessment 20 days Tue 1/21/20 Mon 2/17/20
11 Performance Appraisals 20 days Tue 2/18/20 Mon 3/16/20
12 Job Portal 20 days Tue 3/17/20 Mon 4/13/20
13 ESS / MSS 20 days Tue 4/14/20 Mon 5/11/20
14 Quality Control 15 days Tue 5/12/20 Mon 6/1/20
15 Installation and Deployment of Final Product 6 days Tue 6/2/20 Tue 6/9/20
16 Acceptance Test 2 days Wed 6/10/20 Thu 6/11/20
17 Comprehensive Training of Users 6 days Fri 6/12/20 Fri 6/19/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SereneAir HRIS
Summary Manual Summary Rollup Progress
Date: Tue 10/1/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
Dec '19 Jan '20 Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20
24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SereneAir HRIS
Summary Manual Summary Rollup Progress
Date: Tue 10/1/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2

Das könnte Ihnen auch gefallen