Beruflich Dokumente
Kultur Dokumente
METHOD STATEMENT
FOR CHEMICAL CLEANING
Issue Purpose For Reference
Contents
1 INTRODUCTION .........................................................................................................................3
2 SCOPE OF APPLICATION ..........................................................................................................3
3 HSE.............................................................................................................................................3
4 METHOD ....................................................................................................................................3
4.1 Degreasing ............................................................................................................................3
4.2 Soda Boil-out .........................................................................................................................4
4.3 Acid Cleaning .......................................................................................................................4
5 PRECAUTION.............................................................................................................................4
6 DETAILS FOR IMPLEMENTATION ...............................................................................................5
6.1 Planning.................................................................................................................................5
6.2 Preparation............................................................................................................................7
6.3 Execution...............................................................................................................................7
6.3.1 Degreasing ........................................................................................................................8
6.3.2 Soda Boil-out ......................................................................................................................9
6.3.3 Acid Cleaning .................................................................................................................. 10
7 ACCEPTANCE CRITERIA ......................................................................................................... 11
8 POST WORK.............................................................................................................................11
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
1 INTRODUCTION
This document describes the general requirements for carrying out chemical cleaning applied to
pipes and equipment of the plant’s SUS Tank.
The purpose of chemical cleaning is to remove contaminants that may impair plant operations
caused by foaming and poor heat exchange and may eventually cause damage and loss of
production.
For a newly constructed pipes and equipment, it is assumed that they contain remaining oils,
preservatives and mill scale left over during manufacturing.
2 SCOPE OF APPLICATION
All systems will be subjected to chemical cleaning by degreasing with heat-up. For the
purpose of minimizing or eliminating the effect of foaming and loss of heat exchange
during start-up and normal operation.
All systems will be subjected to chemical cleaning by soda boil-out with heat-up to
remove dirt, grease and mill scales.
All systems will be subjected to chemical cleaning with acid cleaning to remove internal
mill scales from pipes that may damage reciprocating compressor valve discs and linings
and equipment.
3 HSE
The following HSE risks are inherent in chemical cleaning:
Material Safety Data Sheet shall be available for chemicals being used. All the
precautions and safety measures mentioned must be respected and implemented as
applicable.
Disposal of chemicals has to be carried out in an environmental manner.
Appropriate personal protective equipment (PPE) shall be worn or used. Verify that
adequate PPE is available for chemical handling acid gear such as chemical gloves,
face shield, goggles, respirator, etc.
The area will be barricaded and unnecessary personnel will be asked to leave the
affected area.
Safety shower and eye washer shall be provided (Temporary or Permanent)
Spill containment kit available
4 METHOD
4.1 Degreasing
Degreasing is carried out using cleaning agent such as sodium hydroxide. The chemical will be
prepared in accordance with Vendor/Licensor’s instruction/recommendation, as agreed to by
Employer.
Degreasing of Amine circuit shall be carried out following the steps below:
(1) Manual cleaning
(2) Washing and circulation operation
(3) Preparation and filling of chemicals
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
(4) Degreasing
(5) Rinsing and circulation
(6) Inspection
(7) Effluent disposal
(8) Re-assembly
(9) Preservation (if required)
5 PRECAUTION
The following precautions must be paid when chemical cleaning is conducted.
Chemical cleaning area must be roped-off and warning signs to be displayed in the
area.
The internal of vessels, columns and pipes will be flushed, air blown or manually cleaned
as pre-cleaning for degreasing/soda boil-out/acid cleaning prior to chemical cleaning.
Prior to inject chemicals into the system, entire system shall be temporarily boxed up and
tightness tested with water.
All level gauges and other instruments that can be damaged by alkaline solutions or
acid solutions must be removed or positively isolated.
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
Required control loops and indicators that will be required for operation during chemical
cleaning will be functionally tested prior to operation.
The use of hydrofluoric acid is not permitted and austenitic stainless steel items shall not
come in contact with hydrochloric acid, acid solutions containing more than 2ppm
chloride or other liquids containing more than 100ppm chloride.
Suitable water shall be used for water circulation, chemical cleaning and rinsing to
prevent pipes and equipment from damage.
Steam generators may be fired when alkaline degreasing but acid solutions must be
heated external to the equipment.
2. Water quality
The type of water service used for chemical cleaning shall be clearly mentioned on detailed
procedure. Suitable water shall be used for water circulation, chemical cleaning and rinsing to
prevent pipes and equipment from damage.
3. Chemicals
The typical chemical components for chemical cleaning are as below. It may be changed as
per Vendor/Licensor or Chemical cleaning specialist recommendation, as agreed to by
Employer.
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
phosphate 0.5%
Nonionic detergent 0.01%
Acid pickle: Citric acid
Ammonia 3%
Suitable inhibitor To pH 3 to 3.5 To be
advised
5. The timing of chemical cleaning will follow the Mechanical Completion Split of Responsibilities
3550-8710-PR-0001. The timing of soda boil out may be before or during the refractory dry-out,
operational test and/or mechanical run-in test. The planned timing of each item is mentioned
in the item lists (Attachment-1).
6. Circulation cleaning will be applied to all systems in listed in Attachment-1. Heat will be applied
during the circulation.
7. For system where no pumps are available to circulate the system, natural circulation of liquid
due to application of heat will be applied or use of pumping facility by subcontractor. This
method is applicable to Soda boil-out.
6.2 Preparation
1. Availability of necessary utilities must be checked/confirmed
Electricity
Instrument Air and Plant Air
Water (potable and utility)
Cold condensate water
Boiler Feed Water
Fuel Gas
Nitrogen
2. Remove the following and upon completion, reinstate them.
Some parts, made of non-ferrous metal, of equipment/piping/valve/instrument, which
may be deteriorated by alkaline or acid solution.
Permanent instrumentations which could be affected by contact with alkaline or acid
solution.
3. Isolation valves connected to instruments except for pressure measurements should be tight
closed where the instrumentation is not utilized during chemical cleaning.
4. Install strainer elements for line strainer and pump suction strainers as per marked-up P&ID, if
required.
5. Piping including temporary piping and blind should be lined up based on detail procedure.
6. An aqueous solution of chemical should be available.
7. Waste water treatment
During chemical cleaning, disposal of waste water to comply with the Effluent Discharge Norms
as specified in the Environmental Design Basis (S-000-1240-0111V).
6.3 Execution
As mentioned in paragraph 6.1, 6.2 and 6.3 of present procedure, the following proposed work
sequences are described below:
NOTE: This proposed work sequence is the typical sequence for chemical cleaning. It may be
changed as per Vendor/Licensor or Chemical cleaning specialist recommendation, as agreed to
by Employer
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
6.3.1 Degreasing
(1) Manual Cleaning
As much as possible, interior of vessel must be checked and wiped cleaned by hand to
remove any excess oil or grease. As for piping, it is understood that piping are water flushed
or air blown earlier before water circulation. The timing of manual cleaning is during vessel
internal inspection before box-up. It should be agreed that the purpose of degreasing is
to dissolve grease and oil inside pipes and vessels, therefore, the re-opening of any vessel
is not required since final box-up and permanent gasket is used. The result of oil residue
analysis should be sufficient to judge the chemical results.
(4) Degreasing
Cold circulation will be established after filling the chemicals to stabilize level and make-
up. Gradual heat-up will be established up to a target temperature between 80 – 90degC.
The circulation shall be kept for approximately 2 hours at 80-90degC. The criteria of
degreasing shall be depending on the advice of Vendor/Licensor. In case they do not
provide, Contractor and Employer has to agree on what criteria should be applied.
(7) Re-assembly
All dismantled permanent pipes to be re-assembled as per P&ID.
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
(6) Re-assembly
All dismantled permanent pipes to be re-assembled as per P&ID.
(7) Preservation (if required)
Protect the system until start-up. Fill system with potable water with 0.5 % of sodium nitrite
to expel all air and keep filled. Drain before start-up.
Chemical preparation and mixing will be described in detail during the developing of
detail procedure for each system.
The amount of chemical required for its system will be determined after confirming the
estimated volume of solution to be poured into the system or circuit subjected for chemical
cleaning. The detailed procedure shall mention in detail the list of chemicals and the
corresponding requirement/amount to be purchased and delivered to site.
(5) Degreasing (depend on the conditions of pipes/equipment, if too much oil then it need
this step)
The pipes need to be inspected and the decision to degrease it depends on the amount
of oils inside pipes. It may not necessary if it has negligible oil quantity in the surface.
The circulation shall be kept for approximately 2 hours at 80-90 deg C. The criteria of
degreasing shall be depending on the advice of Vendor/Licensor. In case that they do
not provide it, Contractor and Employer has to agree on what criteria should be applied.
(6) Rinsing and circulation
After completion of Degreasing or the oil-laden solution should be drained.
Rinsing is carried out by filling the system with suitable water and circulation is conducted.
This will be repeated until pH of water is less than 8.5. For system where circulating pump is
not available filling up to full level and draining to be carried out until pH of water is less
than 8.5.
(7) Acid cleaning/Neutralization/Passivation
Filling and circulating at 0.2 to 0.3 m/sec for several hours until acceptance criteria are
achieved but for not less than 4 hours. During acid cleaning, samples of solution shall be
taken frequently, at agreed intervals, and checked for ferric iron, total ion and acid
strength. If solution strength drops below 1%, add ammoniated citric acid to raise
concentration to at least 2%. If iron content and acid strength stabilized, acid cleaning is
Employer Doc. No.
PK ENGINEERING CO., LTD Rev. 0
deemed to be complete. Drain and flush system with water until pH of outlet water is higher
than 7 or equal to the pH of the inlet water.
If lower than pH of 7, fill system with potable water, circulate and heat to 60 deg C. Inject
citric acid solution to give 0.5 % concentration, circulate for 30 minutes and then add
ammonia to give a pH of 9.5. Then, add sodium nitrite to give 1% concentration and
continue circulation for a further 4 hours. Drain and rinse system with ammoniated water.
(8) Air blowing
Air blow the system using dry-air to completely remove remaining liquid to keep the system
dry
(9) Effluent Disposal
Disposal of waste water to comply with the Effluent Discharge Norms as specified in the
Environmental Design Basis (S-000-1240-0111V).
(10) Re-assembly
All dismantled permanent pipes to be re-assembled as per P&ID.
(11) Preservation (if required)
The surface of pipes and vessel is bared and free to react with free oxygen, therefore, if
system is to be out of service for longer period, it must be purged to dryness and nitrogen
is introduced to keep the system blanketed as required.
7 ACCEPTANCE CRITERIA
Licensor and Vendor’s criteria shall be followed. In case these criteria are not available, Contractor
and Employer have to agree on acceptance cleanliness.
Judgment for completion shall be done by Contractor and Employer.
8 POST WORK
1. After completion of chemical cleaning, all rotary equipment are switched off, de-energized
(locked-out) and preserved until the succeeding operation.
2. Used filters in washing and circulation operation shall be cleaned after draining and rinsing of
system.
3. Upon completion of chemical cleaning, remove temporary pipes/equipment etc. and resume
the whole system as per P&ID.
4. In case it takes longer time to put online the system nitrogen blanketing or other means of
preservation and preventing corrosion shall be applied. Vendor detailed procedure shall be
applied.