Beruflich Dokumente
Kultur Dokumente
WSM
ROAD WORKS VERSION
PEPL/WSM/0.1/2016
DEFINITION:
The part of a road intended for the movements of vehicles, in contrast to the pavement or verge.
PEPL/WSM/0.1/2016 1
Road works activity comprises of following steps
PEPL/WSM/0.1/2016 2
a. Water Bound Macadam road:
Water bound macadam (WBM) roads are constructed as follows:
b. Bituminous road:
Bituminous road are constructed as follows:
Preparation of surface
Fixing of forms
Mixing and laying of concrete
Compaction and finishing
Curing
Opening to traffic
PEPL/WSM/0.1/2016 3
2. BEFORE ROAD WORKS:
PEPL/WSM/0.1/2016 4
The compacted soil should be able to take up the loads as per design.
After completion of sub-grade work, all the underground utilities, ducts, culverts, etc
should be installed.
Road crossing drain pipes & other crossing utilities are executed after sub-grade
compaction, because there may high chances of this utilities getting damaged during
compaction of sub-grade, if laid prior to compaction and moreover the crossing
utilities pipe will be almost at the sub-grade level.
Electrical, sewage/water line, which crosses the alignment of the road, should be
completed as per requirement.
The water lines should be above the sewage lines with proper separation layer between
the two lines.
In the required places sub grade material should be placed in layers of not more than
150mm height and it should be compacted. Up to the desired level sub grade filling has
to be done.
A layer of granular sub base (GSB) should be laid in a maximum thickness of 150mm
(after compaction) per layer and compacted to the required level.
After spreading the granular sub base, it should be watered.
By using the single drum roller compaction to be done.
The aggregates should be slightly wet during this process (5% to 7% moisture
content).
While laying the granular sub-base, the camber and profile of the road has to be
maintained as per the GFC drawings.
Upon the completion of the GSB layer, gutters & Kerb stone are fixed to line and level
as per the GFC drawings, before laying the wet mix macadam.
Wet Mix Macadam (WMM) consisting of graded and granular, material which is
premixed with water, is laid in one or more layers not exceeding 150mm each (after
compaction).
WMM levelled with a grader and compacted with vibrating soil compactor.
PEPL/WSM/0.1/2016 5
3.1 ASPHALTIC FINISH (BITUMINOUS FINISH):
PEPL/WSM/0.1/2016 6
3.2 CONCRETE FINISH:
A separation membrane shall be used between the concrete slab and the sub base.
Separation membrane shall be impermeable plastic sheeting 125 microns thick laid flat
without creases.
The location and type of joint is provided as per the drawings.
JOINTS:
PEPL/WSM/0.1/2016 7
Expansion Joint:
The dowel bars are adequate and are as per required length and diameter
Expansion joints are commonly spaced at distances equal to 24 to 30 times the road thickness.
Joint spacing that is greater than 15 feet require the use of load transfer devices (dowels or
diamond plates
Dowel bars are typically 32 to 38 mm (1.25 to 1.5 inches) in diameter, 460 mm (18 inches)
long and spaced 305 mm (12 inches) apart.
Expansion joints on each side of the longitudinal joint shall be in line with each other
and of the same type and width.
The filler board shall be positioned vertically with the prefabricated joint assemblies
along the line of the joint within the tolerances
The adjacent sides shall be completely separated from each other by providing joint
filler board. Space around the dowel bars, between the sub-base and the filler board
shall be packed with a suitable compressible material to block the flow of cement
slurry
Expansion joints shall be placed whenever concreting is completed after a day’s work
or is suspended for more than 30 minutes. These joints shall be provided at the regular
location of contraction joints using dowel bar
Expansion joints shall consist of a joint filler board and dowel bars as detailed in the
drawings.
All transverse joints in surface slabs shall be sealed using sealants. Joints shall not be
sealed before 14 days after construction.
Contraction Joints:
The Contraction joints are using dowel bars and they are made as butt type joints.
Dowel bars are typically 32 to 38 mm (1.25 to 1.5 inches) in diameter, 460 mm (18
inches) long and spaced 305 mm (12 inches) apart.
The Contraction joints should be cut as soon as the concrete undergoing initial
hardening is hard enough to bear the load of sawing machine without causing damage
to the slab.
Contraction joints shall consist of a mechanical sawn joint groove, 3 to 5 mm wide and
1/4 to 1/3 depth of the slab ± 5 mm or as stipulated in the drawings.
PEPL/WSM/0.1/2016 8
Longitudinal Joints (Warping joint)
Tie bars are provided at the longitudinal joints as per dimensions and spacing shown in
the drawing
Longitudinal differential vertical movement between the slabs is prevented by fixing
mild steel tie bars of generally 12mm in diameter.
The Longitudinal joints shall be cut as soon as the concrete has undergone initial
hardening and is hard enough to take the load of joint sawing machine without causing
damage to the slab
The longitudinal joints shall be saw cut as per details of the joints shown in the
drawing. The groove may be cut after the final set of the concrete. Joints should be
sawn to at least 1/3 the depth of the slab ± 5 mm as indicated in the drawing
PEPL/WSM/0.1/2016 9
3.3. PAVING:
The materials used for the base construction consists of graded granular material or
lean mixed concrete, constructed and compacted in layers not exceeding 225mm.
The sub-base surface should have reasonable slope and fails. Compaction should be
carried by mechanical vibrating compactors to specified CBR. It is a must to use
proper kerbing before beginning to lay paving segments.
PEPL/WSM/0.1/2016 10
3.3.3 LAYING COURSE (SAND BEDDING):
These materials consist of 6mm D/S natural sand. Thickness of laying course should
be between 25 and 50mm.
In certain areas, like around the manholes, it is suggested to use lean cement mortar
(one part of cement to ten part parts of sand) instead of plain sand.
Once the pavers are laid, dry, coarse and clean sand should be used to fill the paver
joints.
The sand can be brushed or broomed into the joints.
A vibrating compactor should help to complete the job efficiently.
4. KERBS:
PEPL/WSM/0.1/2016 11
5. AFTER ROAD WORKS:
After completion of the road construction, the pavement marking, fixing of road signs,
markers, reflectors, convex mirrors, painting of kerb stones, should be done.
The walking area next to the road has to be done.
Poles for street lights, signals and other signage’s should be installed and all electrical
works should be done.
PEPL/WSM/0.1/2016 12
17. IRC: SP: 21-1979- Manual on Landscaping of Roads
18. IRC: SP: 53-2002 -Guidelines on Use of Polymer and Rubber Modified Bitumen in Road
Construction (First Revision)
7. STAGES OF CHECKING:
PEPL/WSM/0.1/2016 13