Sie sind auf Seite 1von 61

S.N Description of work No.

s
A CIVIL WORKS
1 Preparatory Works
Site clearance

Building area + 1m Clearance in each side 1


Total Site Clearance

2 EARTHWORK
2.1 Excavation
Isolated Footings (F1) 4
Lower Tie Beam 4
Total Earthwork Excavation

2.2 Earth Back filling


2.3 Earth Filling upto the Plinth with material brought from outside
1
Total Back Filling Work

3 POLYETHENE SHEET 1

4 APPROVED GRAVEL SAND (60:40) MIXTURE FILLING 1


Total Gravel Sand Mixture Filling

5 FOUNDATION BED PREPARATION WORK


5.1 Brick Soling
Isolated Footing 4
Lower Tie Beam 4
Plinth Area 1
Total Brick Soling

6 Concrete Works
6.1 Plain Cement Concrete (1:3:6)
Isolated Footing 4
Lower Tie-Beam 4
Total P.C.C. Works

6.2 Plain Cement Concrete (1:2:4)


For Plinth Area 1
Total P.C.C Works

6.3 P.C.C For R.C.C. Works


6.3.1 For Footing
Rectangular 4
Trapezoidal 4

6.3.2 For Column


Upto Plinth Level
Column C1 4

Upto First Floor Level


Column C1 4

6.3.3 For Lower Tie Beam 4


For Plinth Beam 4
For First Floor Beam 4
For Second Floor Beam

6.3.4 For Slab


For first Roof Level (Chajja) 4
For Second roof Level 4
For third Roof Level 4

6.3.4 For Sill Band


For Ground Floor level 4
For First floor Level 4
For Second Floor Level 4
Deduction 4

6.3.4 For Lintel Band 4


4
4
4
TOTAL P.C.C FOR R.C.C WORKS

7 REINFORCMENT WORKS
FOOTING (1 %)
Column (4%)
Beam (3%)
Slab(1.5%)
R.C.C. BANDS (1.5%)
TOTAL REINFORCEMENT WORKS

8 FORMWORK

8.1 FORMWORKS IN COLUMN


upto Plinth level 4
upto first floor level 4
Total Forms WorK Column
8.1 FORMWORKS IN BEAM
for tie Beam 4
for Plinth Beam 4
for Floor Beam 4
TOTAL FORMWORKS (BEAM)
8.3 FORMWORKS IN OTHER STRUCTURES (SLAB)
8.3.1 Formwork for Plain Cement Concrete(1:3:6) works

Footings
Isolated Footings (F1) 4
Lower Tie Beam 4
8.3.2 Formwork for PCC for RCC (1:1.5:3) work

Footing

Footing (F1) 4.00

Slab

Chajja 1

8.3.3 Sill Band

For Ground Floor level 4


For First floor Level 4
For Second Floor Level 4

8.3.4 Lintel Band

For Ground Floor level 4


For First floor Level 4
For Second Floor Level 4

Total Formworks
9 BRICKWORK
9.1 Below Plinth Level
Brick Work Below Plinth Level 4

TOTAL BRICKWORK BELOW PLINTH LEVEL

9.2 Brickwork Above Plinth Level


First Floor 4
Second Floor Level 4
Third floor level 4
Brickwork Above Plinth Level

Deductiom
Deduct Door (D1) 4
Deduct Opening in Second Floor 16
Deduct opening in Third Floor 4

TOTAL BRICKWORK ABOVE PLINTH LEVEL

10 FLOORING
10.1 Marble Flooring
Ground Floor 1
Total Marble Flooring

10.2 Tile Flooring

1
Total Tile Flooring

11 WATER PROOFING WORKS

11.1 Chajja 1
Total Water Proofing Works

12 PLASTERING AND CLADDING WORKS

12.1 Plaster in Outer Wall


Ground Floor 4
First Floor 4
Second Floor 4

Deduct
Door(D1) 4
Window(W1) 4
Total Plaster in Outer Wall

12.2 Internal Plaster Work


12.5 mm thick cement sand(1:4) plastering works in inner partition
walls

Ground Floor 4
First Floor 4
Second Floor 4
Door(D1) 4
Window(W1) 4
Total Internal Plaster Work
13 DOORS AND WINDOWS WORK
13.1 Window Frame
Window Chaukhats

Window (W1) 4
Total Wood Work For Window Chaukhats

Door (D1) 4
Total Wood Work For Door Chaukhats

13.2 Window Shutter

Window (W1) 4
Total Wood Work For Window Shutter

13.3 Door Shutter

Door (D1) 4
Total Wood Work For Window Shutter

14 PAINTING WORKS
14.1 Internal Plastic Emulsion Painting

Inner Walls 1
Chajja 1
Total Internal Plastic Emulsion Painting

14.2 Chapra Polish Works

Window(W1) 4
Door(D1) 4
Shutter 4
window(w1) 4
Door(D1) 4
Total Chapra Polish Works
15 PLINTH PROTECTION WORKS

All Sides 4
Length Breadth Height Quantity Units Remarks

Area
23.79 23.79
23.79 sq.m

1.83 1.83 1.50 20.09


0.91 0.535 1.00 1.95
22.04 cu.m.

8.82

5.95 0.30 1.78


10.60 cu.m

5.95 5.95
5.95 sq.m

5.95 5.95
5.95 sq.m

1.68 1.68 11.26


0.91 0.381 1.39
5.95 5.95
18.59

1.68 1.68 0.08 0.84


0.91 0.381 0.08 0.10
0.95

5.95 0.08 0.45


2.34 cu.m
1.50 1.5 0.20 1.80
1.25 0.25 1.25

0.30 0.3 1.40 0.50

0.30 0.3 3.09 1.11

2.44 0.23 0.23 0.52


2.44 0.23 0.23 0.52
2.43 0.23 0.35 0.78

4.46 0.13 0.56


3.16 0.13 0.40
2.15 0.13 0.27

2.44 0.23 0.08 0.04


2.29 0.23 0.08 0.04
1.68 0.23 0.08 0.03
-0.91 0.23 0.08 -0.02

2.44 0.23 0.08 0.04


2.29 0.23 0.08 0.04
1.68 0.23 0.08 0.03
-0.91 0.23 0.08 -0.02
7.91 cum

239.43
507.55
427.35
24.14
22.29
1220.76 Kg
1.20 1.50 7.20
1.20 3.09 3.71
10.91 Sq.m.
`
0.92 2.44 8.98
0.92 2.44 8.98
0.69 2.43 6.71
24.66 Sq.m.

6.71 0.08 2.01


3.00 0.08 0.90

6.10 0.20 4.88

9.77 9.77

2.44 0.08 0.73


2.29 0.08 0.69
1.68 0.08 0.50

2.44 0.08 0.73


2.29 0.08 0.69
1.68 0.08 0.50

21.40 sq.m.

0.91 0.23 1.52 1.28

1.28 cu.m

2.44 0.23 3.05 6.84


2.29 0.23 1.07 2.24
1.68 0.23 0.91 1.41
10.49 cu.m

0.91 0.23 2.13 -1.79


0.38 0.23 0.30 -0.42
0.38 0.23 0.60 -0.21

8.06 cu.m

Area=
5.97 5.97 sqm
5.97 sq.m

Area=
17.83 17.83 sqm
17.83 sq.m

Area=
9.77 9.77 sq.m
9.77 sq.m

2.44 2.97 28.98


2.44 0.61 5.95
2.29 0.53 4.88
39.81 Sq.m

0.91 2.13 7.80


0.61 0.38 0.93
31.07 sq.m

1.98 2.97 23.55


2.44 0.61 5.95
2.29 0.53 4.88
0.91 2.13 7.80
0.61 0.38 0.93
25.64 sq.m
1.98 0.05 0.08 0.03
0.03 Cu.m

6.40 0.05 0.13 0.16

0.19 Cu.m

0.07 0.28
0.28 Sq.m

1.95 7.80
7.80 Sq.m

25.64 25.64
9.77 9.77
35.41 Sq.m

1.25 5.00
1.42 5.68

0.07 0.28
1.95 7.80
18.76 sq.m

4.88 19.51 r.m.


2.1
EARTH WORK
Excavation
Wall Footing 4 2.82 0.65 0.8 5.87
Total Earthwork Excavation 5.87
cu.m
Bill of Quantities
Colony Temple, Kathmandu

Item
Description of Works Quantity Unit
No.

SITE CLEARANCE
Site Preparation Work including levelling ground, cutting tress, removing
away bushes, remains of old building like concrete by chipping , removing
1.0 23.79 sq.m.
loose earth, soil and brick-bats etc. Before commencement and after
completion, as per direction, specification and instruction of Site Engineer,
all complete.

EXCAVATION WORKS:
Earth work in excavation in foundation including lift up to 1.5m timbering,
pumping out water from the foundation trench, stacking the soil 1.5 m.
2.0 22.04 cu.m.
minimum from the edge of the foundation trench, back filling the excavated
soil with clean and grub of soil up to a lead of 30m. as per direction,
specification and instruction of the Site engineer, all complete.

EARTH BACK FILLING WORKS:


Supplying and filling in plinth floor and the area wherever required below
ground level and sides of the foundation and walls with the material given
3.0 10.60 cu.m.
below in layers not exceeding 150 mm thick, including well watering and
consolidation, leveling, loading, unloading and transportation etc. complete,
and as per specification, drawing and instructions of Site Engineer.

EARTH FILLING WORKS:


Bringing selected earth from outside the Site wherever available and
depositing in places as instructed by Site Engineer including filling in plinth
floor and the area wherever required in layers not exceeding 150 mm
thickness, breaking clods, watering, and consolidation by mechanical
compaction of required capacity to obtain 95 % Proctor Density all complete
as instructed. Rate shall include for excavation of earth and conveyance
4.0 235.02 cu.m.
for all distances. Block levels at the place of depositing of earth being
taken prior at minimum 5 metre grid and such levels shall be used for
calculating the quantity of earth deposited by taking final levels. The
measurements shall be at the place of deposit and not at the place of
excavation. Measurements shall be according to IS 1200 (latest issue) and
the rate shall include for loading and unloading, compaction, transportation
by all means etc. all complete.

APPROVED GRAVEL SAND ( 60:40) MIXTURE FILLING


Supplying and Providing of crushed coarse aggregates and sand in a ratio of
60:40 over the soil filling works including laying in layers of thickness not
5.0 154.62 cu.m.
exceeding 150 mm thickness including compacting to approved level, lines
and dimension all complete as per specification, drawing and instruction of
Site Engineer.
POLYTHENE SHEET
Providing and laying polythene sheets of 500 gauge in floors including
6.0 5.95 sq.m.
overlaps of 250 mm, as per specification, drawing and instruction of Site
Engineer, all complete.

DRY FLAT BRICK SOLING


Dry flat brick soling including supplying and laying chimney made Brick
7.0 (Specified/approved by an engineer) in sand bed in foundation trenches to its 18.59 sq.m.
true line & level including filling up spaces by sand as specified in all shapes,
size, at all depths,leads & locations etc. complete

PLAIN CEMENT CONCRETE (PCC)


Providing and laying machine mixed plain cement concrete of (1:3:6)
proportion using crushed coarse aggregates of 20 mm and down size in
foundation and under floors, steps, walls, platform etc. including laying in
8.0 2.34 cu.m.
layers of thickness not exceeding 150 mm and in alternative bays not
exceeding 10 sqm including setting out, mixing, compacting, curing and
finishing etc. to approved level, lines and dimension all complete as per
specification, drawing and instruction of Site Engineer.

PLAIN CEMENT CONCRETE (PCC)


Providing and laying machine mixed plain cement concrete of (1:2:4)
proportion using crushed coarse aggregates of 20 mm and down size in
foundation and under floors, steps, walls, platform etc. including laying in
layers of thickness not exceeding 150 mm and in alternative bays not
9.0 2.34 cu.m.
exceeding 10 sqm and nominal reinforcements for the floors including setting
out, mixing, compacting, curing and finishing etc. to approved level, lines and
dimension all complete as per specification, drawing and instruction of Site
Engineer.
Note : Rate is inclusive of cost of form work.

P.C.C. FOR R.C.C. WORKS


Providing and laying machine mixed plain cement concrete of M20 grades
((1:1.5:3) proportion) for R.C.C. slab, tie beam, wall, and all kinds of
10.0 R.C.C. works with cement, sand and crushed coarse aggregates of 20 mm/ 7.91 cu.m.
13 mm gauge including setting out, mixing, compacting, curing, and
finishing, etc. excluding cost of reinforcement as per specification, drawing
and instruction of Site Engineer.
TMT THERMEX STEEL REINFORCEMENT BAR (Fe-500)
Providing, straightening, cleaning, cutting, fabricating, bending and placing
TMT Thermex steel reinforcement bars and binding the bars with 18 gauge
annealed wire for tying them at each junction as per design and details for
all types of RCC elements including all waste and cut pieces, provision for
spacers, chairs, providing and placing cement mortar (1:1) cover blocks
to keep the bars in the intended position at all levels, all complete.
12.0 Note : Unless noted otherwise the measurements shall be in accordance with 1220.76 kg
IS 1200 or equivalent BS. However reinforcement shall be measured only in
lengths of bars as actually placed in position on standard weight basis, no
allowance being made in the weight for rolling margin. Authorized laps and
splices only will be measured. Chairs of any shape & profile, Spacer bar of
any shape & profile, cover block, wastage and binding wire will not be
measured and shall be included in the quoted rates. Quoted rate shall be
deemed to have considered the above stipulation.

FORMWORK (COLUMN)
Formwork, centering and shuttering with waterproof plywood for column
structure, works of any shape, size and at any level with necessary mild steel
13.0 propping, scaffolding, staging, supporting, cutting holes for utilization works, 10.91 sq.m.
etc. including providing final surface in correct line, level, cleaning the
surface and applying form oil and removal of forms all complete as per
specification, drawing and instruction of Site Engineer.

FORMWORK (BEAM)
Formwork, centering and shuttering with waterproof plywood for beam
structure, works of any shape, size and at any level with necessary mild steel
14.0 propping, scaffolding, staging, supporting, cutting holes for utilization works, 24.66 sq.m.
etc. including providing final surface in correct line, level, cleaning the
surface and applying form oil and removal of forms all complete as per
specification, drawing and instruction of Site Engineer.

FORMWORK (SLAB)
Formwork, centering and shuttering with waterproof plywood for all kinds
of R.C.C. and P.C.C, works of any shape, size and at any level with necessary
15.0 mild steel propping, scaffolding, staging, supporting, cutting holes for 9.77 sq.m.
utilization works, etc. including providing final surface in correct line, level,
cleaning the surface and applying form oil and removal of forms all complete
as per specification, drawing and instruction of Site Engineer.

BRICKWORK IN FOUNDATION
Brickwork in cement sand mortar (1:6) in foundation up to plinth level
with approved quality first class chimney burnt bricks, in perfect line and
16.0 level including soaking bricks in water, provision for recesses, openings, 1.28 cu.m.
toothings, packing the joints and curing the work in all types and thickness of
wall as per specification, drawing and instruction of Site Engineer, all
complete.
BRICKWORK IN SUPERSTRUCTURE
CHIMNEY MADE BRICKWORK
Brickwork in cement sand mortar (1:6) above plinth level with
17.0 approved quality first class chimney burnt bricks in perfect line and level 8.06 cu.m.
including cost of scaffolding, soaking bricks in water, packing the joints,
raking the joints and curing the work in all types and thickness of wall as per
specification, drawing and instruction of Site Engineer, all complete.

IPS FLOORING
50mm thick IPS flooring in floors in 1:2:4 (1cement: 2coarse sand:
18.0 4graded stone aggregate 10mm nominal size) and 3mm thick fine cement 151.93 sq.m.
punning all complete as per specification, drawing and instruction of Site
Engineer.

NON-SLIP CERAMIC TILE FLOORING


Providing and laying 8 mm thick non slip ceramic tiles of approved
colour, shade and size on floor in perfect line and level on 20 mm thick
19.0 334.60 sq.m.
base cement sand mortar (1:4) and jointed with white cement slurry
mixed with pigment to match the shade of the tile complete as per
specification, drawing and instruction of Site Engineer.

MARBLE FLOORING
Providing and laying 16 mm thick Rajasthan marble of approved quality
and shade, laid over base cement sand mortar (1:4) of 20 mm
20.0 5.97 sq.m.
thickness as per approved pattern/design, including grinding and polishing
to smooth finished glazed floor surface, all complete as per specification,
drawing and instruction of Site Engineer.

GLAZED CERAMIC WALL TILES


Providing and laying 8 mm thick glazed ceramic tiles of approved
shade, size and pattern on wall in perfect line and level on 20 mm thick
21.0 17.83 sq.m.
base cement sand mortar (1:4) and jointed with cement slurry mixed with
pigment to match the shade of the tile including adhesive chemical all
complete as per specification, drawing and instruction of Site Engineer.

WATER PROOFING WORKS


Providing and applying integral crystalline water proofing treatment to
slabs and walls, upto 300 mm height above the finished floor level, of toilets,
terraces, balconies etc with two coats of pure acrylic based cementitious
waterproofing membrane, sealing all joints, corners, junction of pipes and
masonry with epoxy putty including pressure grouting to the base slab at any
depth, height and level by injecting high strength polymeric cementitious
grout admixed with new generation polycarboxylic based hyperplasticizer and
22.0 9.77 sq.m.
microsilica and superplasticizing cum shrinkage compensating admixture.
Rate shall include for preparation of surface by removing all loose mortar and
laitance, oil, grease etc. and washing the surface with water to get neat
surface, curing, waterproofing chemicals, wastage, conveyance, tools and
plants, mixing device and gauge, nozzles etc. complete as per manufacturer's
specification and instruction of Site Engineer.
Note : The Contractor must provide written guarantee for 10 years against
any defect and leakage for waterproofing works on any surface.
CEMENT PLASTER SKIRTING WITH PUNNING
Providing and laying skirting of 150 mm height laid on 12 mm thick
23.0 cement sand mortar (1:4) including moulding, finishing to match the 5.95 r.m.
respective flooring, all complete as per specification, drawing and instruction
of Site Engineer.

MARBLE SKIRTING
Providing and laying skirting of 150 mm height laid on 12 mm thick
24.0 cement sand mortar (1:4) of 16mm thick Rajasthani Marble including 36.04 sq.m.
moulding, finishing to match the respective flooring, all complete as per
specification, drawing and instruction of Site Engineer.

TILE SKIRTING
Providing and laying skirting of 150 mm height laid on 12 mm thick
cement sand mortar (1:4) of 15mm thick Kazzaria, somany or
25.0 187.75 sq.m.
equivalent tiles including moulding, finishing to match the respective
flooring, all complete as per specification, drawing and instruction of Site
Engineer.

CEMENT PLASTER (1:4) (20 MM THICK) EXTERNAL


Providing and applying cement sand plaster on walls, ceilings, skirting etc. of
good finishing, including raking the joints, cleaning and wetting the surface,
and curing the works , including alkali resisting fibre reinforcement to
26.0 551.92 sq.m.
minimize cracks in plaster, all complete including necessary single or multiple
stage scaffolding at all heights.
Rate shall include for providing drip courses/moulds/grooves/bands of any
size and shape, as instructed.

CEMENT PLASTER (1:4) (12.5 MM THICK) INTERNAL


Providing and applying cement sand plaster on walls, ceilings, skirting etc. of
good finishing, including raking the joints, cleaning and wetting the surface,
27.0 25.64 sq.m.
and curing the works , including alkali resisting fibre reinforcement to
minimize cracks in plaster, all complete including necessary single or multiple
stage scaffolding at all heights.

WOODEN FRAMES
Providing and fixing door, window and ventilator frames using first
class kiln seasoned and preservative treated sal wood, to shape and
profile as shown in the drawings with mitred joints including providing and
fixing necessary MS hold fasts ( 20 X 6 mm) 300 mm long, 3 nos at each side,
28.0 0.19 cu.m.
and concrete (1:2:4) block grouting for fixing the holdfast and anchor
fasteners/ coach screws Frames must be erected in absolute plumb and level
as per drawing, specification and instruction of Site Engineer.
Note : Rate shall include cost of application of two coats bitumen emulsion at
masonry/concrete faces.
WOODEN SOLID CORE DOOR
Providing and fixing 38 mm thick flush door shutters single leaf of solid
core of water proof and termite resistant block board type bonded
with phenol formaldehyde synthetic resin thermo pressed, with both
side teak , wooden beadings and 8 mm thick teak wood external lipping, as
per drawing. The construction procedure of the shutter should be as per IS
2202. The shutter shall be shop prepared for taking mortice lock or latches
29.0 7.80 sq.m.
suitable lock block of wood may be provided for fixing the hardware. All the
four edges of the door shutter shall be square. The shutter shall be free from
twist or warp in its plane and of required size etc. complete as instructed.
Rate shall include necessary approved hardwares such as S.S.hinges with
S.S.screws, locks, door closer, silver coloured lever type handles, aldrops and
latches, door stopper etc., all complete and application of chapra polish, as
instructed.

30.0 Window Shutter Work 0.28 sq.m.

PAINTING WORKS (WEATHER COAT PAINT)


Providing and applying two coats of weather coat paint of approved
brand and colour on the external facade with one coat of primer including
31.0 preparation of surface through cleaning as per specification and making good 551.92 sq.m.
all small holes of nails, open joints and minor defects of every kind after
application of primer coat as per specification and instruction of Site
Engineer.

PAINTING WORKS ( PLASTIC EMULSION PAINT)


Providing and applying two coats of plastic emulsion paint of approved
brand and colour with one coat of primer including preparation of surface
32.0 1884.18 sq.m.
through cleaning as per specification and making good all small holes of
nails, open joints and minor defects of every kind after application of primer
coat as per specification and instruction of Site Engineer.

WALL PUTTY WORKS


Providing and applying wall putty of Birla, JK or equivalent over cement
33.0 plaster surface in perfect line and level in wall and ceiling. The surface shall 1884.18 sq.m.
be made smooth by rubbing with sand paper. The corners shall be curbed to
avoid sharp edge as per instruction Site Engineer.

PAINTING WORKS (CHAPRA POLISH)


Providing and applying two coats of CHAPRA polish of approved brand
and colour to the wooden surfaces with one coat of primer including
34.0 preparation of surface through cleaning as per specification and making good 18.76 sq.m.
all small holes of nails, open joints and minor defects of every kind after
application of primer coat as per specification and instruction of Site
Engineer.
PAINTING WORKS (ENAMEL PAINT)
Providing and applying two coats of enamel paint of approved brand and
colour to the plastered, metal and wooden surfaces with one coat of primer
35.0 including preparation of surface through cleaning as per specification and 18.76 sq.m.
making good all small holes of nails, open joints and minor defects of every
kind after application of primer coat as per specification and instruction of
Site Engineer.

RAILING WORKS
Providing and fixing railing in staircase of 1000 mm height, consisting
36.0 of 50 mm dia stainless steel pipes (1.5 mm thick) balustrades with 10mm 32.51 r.m.
thick toughned glass and 50 mm dia stainless steel pipes (1.5 mm thick)
hand rail, as per drawing and instruction of Site Engineer, all complete.

APRON WORKS
Providing apron works around the building with precast RCC slab sized
1000 X 1000 X 75 of M15 grade (1:2:4) cast with polypropylene fibre
@ 1 kg per bag of cement, laid with a nominal slope, over a stone dust
bed of 100 mm thickness including necessary excavation wherever
necessary and pointing the joints with 12.5 mm thick cement mortar
37.0 19.51 r.m.
(1:3), laying 12.5 mm thick screeding (1:4) and cement sand punning
(1:1), necessary form work and 8 mm dia TMT reinforcement bars spaced at
200 mm centres both ways in single layer. Rate shall include for providing
necessary form work, excavation, refilling, consolidation and compaction of
filled earth, pointing, screeding, punning, curing and reinforcement all
complete, as per drawing and instruction of Site Engineer.

TOTAL COST
Rate (NRs.) Amount (Nrs.)

51.75 1,231.13

710.70 15,663.83

433.03 4,590.31

433.03 101,770.43

3,203.96 495,386.77
162.04 963.78

1,128.02 20,970.81

14,012.74 32,825.15

19,523.28 45,733.72

19,523.28 154,377.36
128.26 156,573.63

1,694.47 18,483.28

1,168.13 28,803.82

898.04 8,773.86

15,674.98 20,094.34
16,407.07 132,320.87

946.87 143,857.78

2,837.11 949,296.03

5,305.79 31,676.34

2,837.11 50,585.62

814.20 7,954.73
946.87 5,631.93

5,305.79 191,199.32

2,837.11 532,666.85

564.71 311,673.90

436.18 11,183.25

315,781.78 59,912.88
15,915.75 124,142.87

10,987.08 3,032.43

256.27 141,438.59

330.41 622,548.81

247.53 466,384.53

201.02 3,770.33
328.46 6,160.52

1,207.50 39,255.83

5,838.65 113,890.06

5,054,825.71
Rate Analysis
Colony Temple, Kathmandu

Site Clearance and grass cutting, root digging, breaking sods, clearing ground
1.0 and carrying away from site

S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)

A Labour
Unskilled MD 0.06 750.0 45.00
B Material
Nil
C Equipment

D Subtotal (A+B+C) 45.00


E Contractor's Overhead@ 15% 0f(D) 6.75
Total(D+E) 51.75
Rate per 1 m2 51.75
Rate per 1 sqft 4.81

2.0 Earthwork excavation(Manual excavation)in Gravel mixed soil in foundation


including stacking the soil 1 m from the edge of the foundation and 30m hauling
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Unskilled MD 0.8 750.0 600.00
B Material
Nil
C Equipment
@ 3% of (A) LS 1 18.00
ty Three Thousands Two Hundred and One Rupees and Eighty Three Paisa.Subtotal (A+B+C) 618.00
E Contractor's Overhead@ 15% 0f(D) 92.70
Total(D+E) 710.70
Rate per 1 m3 710.70
Rate per 1 cft 20.12

3.0 Earthwork in filling by laying 15-15 cm layer soil with spraying water and
compacted by labour
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Unskilled MD 0.5 750.0 375.00
B Material
water ltr 5 0.31 1.55
C Equipment

D Subtotal (A+B+C) 376.55


E Contractor's Overhead@ 15% 0f(D) 56.48
Total(D+E) 433.03
Rate per 1 m3 433.03
Rate per 1 cft 12.26
4.0 Earthwork in filling by laying 15-15 cm layer soil with spraying water and
compacted by labour (soil brought from outside)
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Unskilled MD 0.5 750.0 375.00
B Material
Soil m3 1.5 318.6 477.90
water ltr 5 0.31 1.55
C Equipment

D Subtotal (A+B+C) 854.45


E Contractor's Overhead@ 15% 0f(D) 128.17
Total(D+E) 982.62
Rate per 1 m 3
982.62
Rate per 1 cft 27.82

5.0 Providing and Laying one layer of 500 gauge polythene sheet all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0.6 1030.0 618.00
Unskilled MD 0.6 750.0 450.00
B Material
500 Gauge Polythene Sheet m2 11 31.0 341.00
C Equipment
Nil
D Subtotal (A+B+C) 1409.00
E Contractor's Overhead@ 15% 0f(D) 211.35
Total(D+E) 1620.35
Rate per 1 m 2
162.04
Rate per 1 sqft 15.05

6.0 Dry Flat Brick Soling


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0.5 1030.0 515.00
Unskilled MD 1.0 750.0 750.00
B Material
Brick Nos 420 14.9 6262.20

River Sand m3 0.71 3213.6 2281.68


C Equipment
Nil
D Subtotal (A+B+C) 9808.88
E Contractor's Overhead@ 15% 0f(D) 1471.33
Total(D+E) 11280.21
Rate per 1 m2 1128.02
Rate per 1 sqft 104.80
7.0 Providing and laying gravel sand
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0 1030.0 0.00
Unskilled MD 0.75 750.0 562.50
B Material
Gravel m³ 1.1 2021.41 2223.55
C Equipment
Nil
D Subtotal (A+B+C) 2786.05
E Contractor's Overhead@ 15% 0f(D) 417.91
Total(D+E) 3203.96
Rate per 1 m³ 3203.96
Rate per 1cft 90.73

P.C.C. in 1:3:6 (M10)work for levelling in ground with approved quality of cement
8.0 and sand and crushed stone aggregate including mixing,laying,curing etc all as
per instruction and specification all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 1 1030.0 1030.00
Unskilled MD 4 750.0 3000.00
B Material
Cement MT 0.22 16500.0 3630.00
River Sand m 3
0.47 3213.6 1510.41
Crushed agg.40mm down m 3
0.65 3354.9 2180.68
Crushed agg.20mm down m 3
0.24 3319.6 796.70
water ltr 120 0.31 37.20
C Equipment
Nil
D Subtotal (A+B+C) 12184.99
E Contractor's Overhead@ 15% 0f(D) 1827.75
Total(D+E+F) 14012.74
Rate per 1cft 396.80

P.C.C. in 1:2:4 (M15)work for levelling in ground with approved quality of cement
9.0 and sand and crushed stone aggregate including mixing,laying,curing etc all as
per instruction and specification all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 1 1030.0 1030.00
Unskilled MD 4 750.0 3000.00
B Material
Cement MT 0.32 16500.0 5280.00
River Sand m 3
0.445 3213.6 1430.07
Crushed agg.40mm down m 3
0.52 3354.9 1744.54
Crushed agg.20mm down m3 0.22 3319.6 730.31
Crushed agg.10mm down m3 0.11 3319.6 365.15
water ltr 150 0.31 46.50
C Equipment
Nil
D Subtotal (A+B+C) 13626.57
E Contractor's Overhead@ 15% 0f(D) 2043.99
Total(D+E) 15670.56
Rate per 1cft 443.74

P.C.C. in 1:1.5:3 (M20) work for levelling in ground with approved quality of
10.0 cement and sand and crushed stone aggregate including mixing,laying,curing etc
all as per instruction and specification all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0.8 1030.0 824.00
Unskilled MD 7 750.0 5250.00
B Material
Cement MT 0.4 16500.0 6600.00
River Sand m 3
0.425 3213.6 1365.79
Crushed agg.40mm down m 3
0.57 3354.9 1912.29
Crushed agg.20mm down m 3
0.29 3319.6 962.68
Water ltr 200 0.31 62.00
C Equipment
Nil
D Subtotal (A+B+C) 16976.76
E Contractor's Overhead@ 15% 0f(D) 2546.51
Total(D+E) 19523.28
Rate per 1cft
P.C.C. in 1:1:2 (M25) work for levelling in ground with approved quality of 552.84
11.0 cement and sand and crushed stone aggregate including mixing,laying,curing etc
all as per instruction and specification all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0.8 1030.0 824.00
Unskilled MD 7 750.0 5250.00
B Material
Cement MT 0.61 16500.0 10065.00
River Sand m3 0.425 3213.6 1365.79
Crushed agg.40mm down m3 0.64 3354.9 2147.13
Crushed agg.20mm down m 3
0.21 3319.6 697.11
Water ltr 300 0.31 93.00
C Equipment
Nil
D Subtotal (A+B+C) 20442.04
E Contractor's Overhead@ 15% 0f(D) 3066.31
Total(D+E) 23508.34
Rate per 1cft 665.68

Cutting, bending & placing of reinforcement bars in position as shown in the


12.0
drawings and binding by GI wire for RCC works with 30 m lead all complete
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled md 0.012 1030.0 12.36
A.

Unskilled md 0.012 750.0 9.00


B. Material:
Reinforcement bar (Fe 415) Kg 1.05 85.0 89.25
Binding wire Kg 0.01 92.0 0.92
C. Equipment:
Nil
D. Subtotal (A+B+C) 111.53
E. Contractor's Overhead @ 15% of (D) 16.73
Total (D+E) 128.26
\ Rate per 1 Kg 128.26

13.0 Plywood formworks with steel adjustable pipe props for floor and slab
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled md 17.200 1030.0 17716.00
Unskilled md 25.700 750.0 19275.00
B. Material:
19mm board m2 16.50 1496.2 24687.03

Local wood m3 0.23 22071.7 5076.48


Iron pipes (NMB50-M) No. 4.40 1940.0 8536.00
Iron nails Kg 25.00 112.0 2800.00
C. Equipment:
Nil
D. Subtotal (A+B+C) 78090.51
E. Contractor's Overhead @ 15% of (D) 11713.58
Total (D+E) 89804.09
\ Rate per 1 sq m 898.04
Rate per 1 sqft 83.43

19mm plywood formworks for beam including materials and removing with
14.0
transpotation upto 30m.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled md 2.670 1030.0 2750.10
Unskilled md 4.000 750.0 3000.00
B. Material:
ply board m2 1.65 1496.2 2468.70
local wood cum 0.04 22071.7 882.87
steel prop no. 0.40 1940.0 776.00
nails Kg 2.50 112.0 280.00
C. Subtotal (A+B) 10157.67
D. Contractor's Overhead @ 15% of (C) 1523.65
Total (C+D) 11681.32
\ Rate per 1 sq m 1168.13
Rate per 1 sqft 108.52

19mm plywood formworks for column including materials,erection,nailing,


15.0
removing with transpotation upto 30m.(formwork on 2m dia column)
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled md 1.570 1030.0 1617.10
Unskilled md 2.360 750.0 1770.00
B. Material:
ply board m2 0.69 1496.2 1032.37
local wood cum 0.02 22071.7 441.43
steel prop no. 0.54 1940.0 1047.60
nails Kg 2.50 112.0 280.00
C. Subtotal (A+B) 6188.50
D. Contractor's Overhead @ 15% of (C) 928.27
Total (C+D) 7116.77
\ Rate per 1 sq m 1694.47
Rate per 1 sqft 157.42

16.0 Mean Rate of formwork


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
Qty.Column / Shear Wall 1694.47
Qty.Beam 1168.13
Qty. slab 898.04
Total 3760.64
Mean rate of formwork per sqm 1253.55

Note:Wood re-use upto 6 times with 25% salvage value (1.6875x1.1x0.7516=0.2


:Ply re-use upto 6 times with 10% salvage value(100x1.1x0.9/6=16.5)
:Pipe re-use upto 15 times with 25% salvage value(88/15x0.75=4.4)

Good quality local chimney made Brickwork in 1:6 C/S mortar above ground floor
17.0 in perfect line level finished including wetting the bricks,racking the joints and
curing the work for at least 7 days all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 1.5 1030.0 1545.00
Unskilled MD 2.2 750.0 1650.00
Unskilled MD 0.7 750.0 525.00
B Material
Cement MT 0.07 16500.0 1155.00
Sand m 3
0.28 3213.6 899.82
Brick Nos 560 14.9 8349.60
water ltr 100 0.3 31.00
C Equipment
3% of A LS 1 111.60
D Subtotal (A+B+C) 14267.02
E Contractor's Overhead @15% of (D) 2140.05
Total(D+E) 16407.07
Rate per 1 m3
16407.07
Rate per 1cft 464.60
Good quality local chimney made Brickwork in 1:6 C/S mortar above ground floor
18.0 in perfect line level finished including wetting the bricks,racking the joints and
curing the work for at least 7 days all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 1.5 1030.0 1545.00
Unskilled MD 2.2 750.0 1650.00
B Material
Cement MT 0.07 16500.0 1155.00
Sand m 3
0.28 3213.6 899.82
Brick Nos 560 14.9 8349.60
water ltr 100 0.3 31.00
C Equipment
Nil
D Subtotal (A+B+C) 13630.42
E Contractor's Overhead @15% of (D) 2044.56
Total(D+E) 15674.98
Rate per 1 m3
15674.98
Rate per 1 sqft 1456.25

19.0 Sal wood work for chaukhats.


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled MD 34.00 1030.0 35020.00
Unskilled MD 3.40 750.0 2550.00
B. Material:
Sal wood m³ 1.10 204825.1 225307.57
Hold Fast Nos. 92.00 125.00 11500.00
Screw Nos. 184.00 1.17 215.28
C. Subtotal 274592.85
D. Contractor's Overhead @ 15% of (C) 41188.93
Total (C+D) 315781.78
\ Rate per m3 315781.78
Rate per 1cft 8941.94

20.0 Sal Wood Work for Door Shutter

S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)


A. Labour
Skillled MD 10.00 1,030.00 10,300.00
Unskilled MD 1.00 750.00 750.00
B. Material:
Sal wood m3 0.084 204,825.07 17,205.31
100 mm hinge Nos. 6.00 28.00 168.00
150 mm Tower Bolt Nos. 1.00 67.00 67.00
300 mm Tower Bolt Nos. 1.00 107.00 107.00
300 mm locking set Nos. 1.00 260.0 260.00
Handle (brass) 10" Nos. 2.00 150.0 300.00
Screws LS 1.00 100.0 100.00
C. Subtotal 29257.31
D. Contractor's Overhead @ 15% of (C) 4388.60
Total (C+D) 33645.90
\ Rate per m2 15915.75
Rate per 1 sqft 1478.62

Sal Wood Work for window Shutter (38x75 mm wooden frame) with 5mm thick
21.0
clear glass all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour
Skillled MD 9.00 1,030.00 9,270.00
Unskilled MD 0.90 750.00 675.00
B. Material:
Sal wood m3 0.049 204,825.07 10,036.43
5mm thick clear glass m2 1.09 807.29 879.95
75 mm hinge Nos. 8.00 15.00 120.00
100 mm Tower Bolt Nos. 4.00 40.00 160.00
Handle (simple) Nos. 2.00 32.0 64.00
Screws LS 100.00
C. Subtotal 21305.38
D. Contractor's Overhead @ 15% of (C) 3195.81
Total (C+D) 24501.18
\ Rate per m2 10987.08
Rate per 1 sqft 1020.73

22.0 UPVC DOOR AND SHUTTER (Frame 60x60, Sash 60x104 white colour)
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Construction Materials with labour charg sq.m 1.00 8328.0 8328.00
D. Subtotal (A+B+C) 8328.00
E. Contractor's Overhead @ 15% of (D) 1249.20
Total (D+E) 9577.20
\ Rate per sq.m 9577.20
Rate per 1 sqft 889.75

23.0 Providing and Laying 50mm screed (1:2:4) on Floor


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 1.25 1030.0 1287.50
Unskilled MD 2.5 750.0 1875.00
B Material
Cement MT 0.17 16500.0 2805.00
Sand m3 0.23 3213.6 739.14
Aggregate-20mm m3 0.46 3319.6 1527.01
C Equipment
Nil
D Subtotal (A+B+C) 8233.64
E Contractor's Overhead @15% of (D) 1235.05
Total(D+E) 9468.69
Rate per 1 m2 946.87
Rate per 1 sqft 87.97

Providing & Laying Porcelein Glazed/Non Glazed tile (Floor/Wall of Kazzaria,


24.0
Somany or equivalent) in 1:4 C/S
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 13.00 1,030.00 13,390.00
Unskilled MD 4.50 750.00 3,375.00
B Material
Porcelein glazed/non-glazed (kazzaria,
somany or equivalent)tile m2 11.00 581.25 6,393.76
Cement MT 0.056 16,500.00 924.00
Sand m3 0.152 3,213.63 488.47
White Cement kg 3.228 30.75 99.26
C Equipment
Nil
D Subtotal (A+B+C) 24,670.50
E Contractor's Overhead @15% of (D) 3,700.57
Total(D+E) 28,371.07
Rate per 1 m2
2,837.11
Rate per 1 sqft 263.58

25.0 16mm thick marble on 20mm thick mortar & polishing all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled MD 2.00 1,030.00 2,060.00
Unskilled MD 8.00 750.00 6,000.00
B. Material:
Cement MT 0.130 16500.0 2145.00
Sand m3 0.183 3213.6 588.10
White Cement MT 0.089 30750.0 2736.75
16mm thick Marble m2 11.000 1980.6 21786.15
Oxalic acid kg 0.370 118.0 43.66
Wax polish kg 0.118 345.0 40.71
Terpentine Oil ltr 0.538 208.0 111.90
Carbondum stoe LS 500.00

C. Equipment:
Labour for Polishing MD 13.50 750.0 10125.00
D. Subtotal (A+B+C) 46137.27
E. Contractor's Overhead @ 15% of (D) 6920.59
Total (D+E) 53057.86
\ Rate per 1 sq m 5305.79
Rate per 1 sqft 492.92
26.0 16mm thick granite on 20mm thick (1:2 C/S) mortar & polishing all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled MD 2.00 1,030.00 2,060.00
Unskilled MD 8.00 750.00 6,000.00
B. Material:
Cement MT 0.130 16500.0 2145.00
Sand m3 0.183 3213.6 588.10
White Cement MT 0.089 30750.0 2736.75
16mm thick Granite m2 11.000 3788.9 41677.86
Oxalic acid kg 0.370 118.0 43.66
Wax polish kg 0.118 345.0 40.71
Terpentine Oil ltr 0.538 208.0 111.90
Carbondum stoe LS 500.00

C. Equipment:
Labour for polishing MD 13.50 750.0 10125.00
D. Subtotal (A+B+C) 66028.98
E. Contractor's Overhead @ 15% of (D) 9904.35
Total (D+E) 75933.33
\ Rate per 1 sq m 7593.33
Rate per 1 sqft 705.44

12.5 mm thick plastering for levelling surface,1:4 cement sand mortar other than
27.0
ceiling
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 12 1030.0 12360.00
Unskilled MD 16 750.0 12000.00
B Material
Cement MT 0.538 16500.0 8877.00
Sand m 3
1.46 3213.6 4691.91
C Equipment
Nil
D Subtotal (A+B+C) 37928.91
E Contractor's Overhead @15% of (D) 5689.34
Total(D+E) 43618.24
Rate per 1 m2 436.18
Rate per 1 sqft 40.52

28.0 12.5 mm thick plastering for levelling surface,1:3 cement sand mortar on ceiling
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 15 1030.0 15450.00
Unskilled MD 20 750.0 15000.00
B Material
Cement MT 0.625 16500.0 10312.50
Sand m3 1.28 3213.6 4113.45
C Equipment
Nil
D Subtotal (A+B+C) 44875.95
E Contractor's Overhead @15% of (D) 6731.39
Total(D+E) 51607.35
Rate per 1 m
2
516.07
Rate per 1 sqft 47.94

20 mm thick plastering for levelling surface,1:4 cement sand mortar on outer


29.0
side
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 14 1030.0 14420.00
Unskilled MD 19 750.0 14250.00
B Material
Cement MT 0.81 16500.0 13365.00
Sand m 3
2.2 3213.6 7070.00
C Equipment
Nil
D Subtotal (A+B+C) 49105.00
E Contractor's Overhead @15% of (D) 7365.75
Total(D+E) 56470.75
Rate per 1 m
2
564.71
Rate per 1 sqft 52.46

Colouring with Two coats of plastic emulsion paint with one coat primer to give
30.0 uniform colouring after rendering the surface on wall,ceiling,column,beam,etc as
per specification and instruction all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 12 1030.0 12360.00
Unskilled MD 8 750.0 6000.00
B Material
Emulsion Paint LT 16 511.0 8176.00
Primer LT 8.1 271.0 2195.10
C Equipment
Nil
D Subtotal (A+B+C) 28731.10
E Contractor's Overhead @15% of (D) 4309.67
Total(D+E) 33040.77
Rate per 100 m 2
33040.77
Rate per 1 m
2
330.41
Rate per 1 sqft 30.70

2 coats of apex paint(weather coat) of approved colour with one coat primer to
31.0 give uniform coloring after rendering the surface on wall,column etc over
properly cleaned surface all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 5.8 1030.0 5974.00
Unskilled MD 5.8 750.0 4350.00
B Material
Apex paint LT 16 612.0 9792.00
Primer LT 8 271.0 2168.00
C Equipment
Nil
D Subtotal (A+B+C) 22284.00
E Contractor's Overhead @15% of (D) 3342.60
Total(D+E) 25626.60
Rate per 100 m 2
25626.60
Rate per 1 m
2
256.27
Rate per 1 sqft 23.81

2 coats of ready made enamel paint of approved colour over 1 coats of primer
32.0
Painting over properly sanded wooden surface all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 12 1030.0 12360.00
Unskilled MD 8 750.0 6000.00
B Material
Primer LT 8.1 254.0 2057.40
Enamel paint LT 16 509.0 8144.00
C Equipment
Nil
D Subtotal (A+B+C) 28561.40
E Contractor's Overhead @15% of (D) 4284.21
Total(D+E) 32845.61
Rate per 100 m2 32845.61
Rate per 1 m
2
328.46
Rate per 1 sqft 30.51

33.0 Providing and Applying 3 coats of chopra polish all complete


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 10 1030.0 10300.00
Unskilled MD 5 750.0 3750.00
B Material
Chopra Kg 2 1280.0 2560.00
Spirit Ltr. 10 87.0 870.00
C Equipment
Nil
D Subtotal (A+B+C) 17480.00
E Contractor's Overhead @15% of (D) 2622.00
Total(D+E) 20102.00
Rate per 1 m
2
201.02
Rate per 1 sqft 18.68
Providing and applying 2 mm thick white putty plaster on wall & ceiling all
34.0
complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 1.0 1030.0 1030.00
Unskilled MD 1.0 750.0 750.00
B Material
White putty kg 10.64 35.0 372.40
C Equipment
Nil
D Subtotal (A+B+C) 2152.40
E Contractor's Overhead @15% of (D) 322.86
Total(D+E) 2475.26
Rate per 1 m2 247.53
Rate per 1 sqft 23.00

35.0 Providing and Fixing 50 mm thick stainless steel pipe railing all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Construction Materials with labour charg rm 1.00 1050.0 1050.00
D. Subtotal (A+B+C) 1050.00
E. Contractor's Overhead @ 15% of (D) 157.50
Total (D+E) 1207.50
\ Rate per rm 1207.50
Rate per 1 rft 368.05

Providing and fixing Spiral Staircase using 4" dia MS Pipe post, angle and Flat on
36.0
steps all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Construction Materials with labour charg rft 1.00 2874.92 2874.92
D. Subtotal (A+B+C) 2874.92
E. Contractor's Overhead @ 15% of (D) 431.24
Total (D+E) 3306.16
\ Rate per rm 10844.20

37.0 Application of Integral Waterproofing Additive


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
Labour:
A. Skilled MD 1.00 1,030.00 1,030.00
-
Unskilled MD 3.00 750.00 2,250.00
B. Material: -
Integral Waterprofing Additive Kg 11.00 300.00 3,300.00
Accessories 1.00 500.00 500.00

C. Subtotal 7080.00
D. Contractor's Overhead @ 15% of (C) 1062.00
Total (C+D) 8142.00
\ Rate per m² 814.20
Rate per 1 sqft 75.64
38.0 Plinth Protection works
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
Excavation m3 0.075 710.7 53.30
100 mm thick Stone Dust m3 0.008 1,449.31 11.59
-
Re-bar KG 4.800 128.26 615.65
Formwork m2 0.225 13,493.08 3,035.94
PCC (1:2:4) m3 0.075 15,670.56 1,175.29
Screeding m2 1.000 946.87 946.87

Total 5838.65
\ Rate per 1rm 5838.65
Rate per 1 rft 1,779.62

39.0 100 mm tile skirting on 12mm thick mortar (1:6)


S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
Labour:
A. Skilled MD 0.15 1,030.00 154.50
-
Unskilled MD 0.10 750.00 75.00
B. Material: -
Cement MT 0.001 16,500.00 16.50
Sand M3 0.003 3,213.63 9.64
Tile (Kazzaria, somany or equivalent) m2 0.11 581.25 63.94
Epoxy, Grout, Pigment LS 50.00
C. Subtotal 369.58
D. Contractor's Overhead @ 15% of (C) 55.44
Total (C+D) 425.02
\ Rate per m 425.02
Rate per 1ft 129.54

16mm thick marble skirting on 12.5mm thick mortar (1:3) & polishing all
40.0
complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A. Labour:
Skilled MD 14.00 1,030.00 14,420.00
Unskilled MD 12.00 750.00 9,000.00
B. Material:
Cement MT 0.063 16500.0 1039.50
Sand m3 0.128 3213.6 411.35
16mm thick Marble m2 11.000 1980.6 21786.15
Oxalic acid kg 0.370 118.0 43.66
Wax polish kg 0.118 345.0 40.71
Terpentine Oil ltr 0.538 208.0 111.90
Carbondum stoe LS 500.00

C. Equipment:
D. Subtotal (A+B+C) 47353.27
E. Contractor's Overhead @ 15% of (D) 7102.99
Total (D+E) 54456.27
\ Rate per 1 sq m 5445.63
Rate per 1 sqft 505.92
Unit: 1 m2

Remarks

Unit: 1 m3
Remarks

Unit: 1 m3
Remarks
Unit: 1 m3
Remarks

Unit: 10 m2
Remarks

Unit: 10 m2
Remarks
Unit: 1 m³
Remarks

Unit: 1 m3
Remarks

Unit: 1 m3
Remarks
Unit: 1 m3
Remarks

Unit: 1 m3
Remarks

Unit: 1 Kg
Remarks
Unit: 100 m2
Remarks

use for 6
times

Unit: 10 m2
Remarks

Unit: 4.20
m2
Remarks

Remarks

Unit:1m3
Remarks
Unit:1m3

Remarks

Unit: 1 m³
Remarks

Unit: 2.114
m2
Remarks
Unit: 2.23 m2
Remarks

Unit: 1m2
Remarks

Unit:10 m2
Remarks
Unit:10 m2
Remarks

Unit: 10 sq m
Remarks
Unit: 10 sq m
Remarks

Unit:100 m2
Remarks

Unit:100 m2
Remarks
Unit:100 m2
Remarks

Unit:100 m2
Remarks

Unit:100 m2
Remarks
Unit:100 m2
Remarks

Unit:100 m2
Remarks
Unit:10 m2
Remarks

Unit: 1 rm
Remarks

Unit: 1 rm
Remarks

Unit: 10 m²
Remarks
Unit: 1 rm
Remarks

Unit: 1 Rm
Remarks

Unit: 10 sq m
Remarks
Abstract of Cost
Colony Temple, Kathmandu

Item
Description of Works Unit Quantity Rate (NRs.)
No.

1.0 SITE CLEARANCE sq.m. 23.79 51.75


2.0 EXCAVATION WORKS: cu.m. 22.04 710.70
3.0 EARTH BACK FILLING WORKS: cu.m. 10.60 433.03
EARTH FILLING WORKS:(Earth brought from
4.0 cu.m. 10.60 982.62
outside)
7.0 POLYTHENE SHEET sq.m. 5.95 162.04
8.0 DRY FLAT BRICK SOLING sq.m. 18.59 1,128.02
9.0 PLAIN CEMENT CONCRETE (PCC) 1:3:6 cu.m. 2.34 14,012.74
10.0 PLAIN CEMENT CONCRETE (PCC) 1:2:4 cu.m. 2.34 15,670.56
11.0 P.C.C. FOR R.C.C. WORKS (1:1.5:3) cu.m. 7.91 19,523.28
TMT THERMEX STEEL REINFORCEMENT BAR (Fe-
12.0 kg 1220.76 128.26
500)
13.0 FORMWORK (COLUMN) sq.m. 10.91 1,694.47
13.0 FORMWORK (BEAM) sq.m. 24.66 1,168.13
13.0 FORMWORK (SLAB) sq.m. 9.77 898.04
14.0 BRICKWORK IN FOUNDATION (1:6) cu.m. 1.28 15,674.98
15.0 BRICKWORK IN SUPERSTRUCTURE (1:6) cu.m. 8.06 16,407.07
18.0 TILE FLOORING sq.m. 17.83 2,837.11
19.7 MARBLE FLOORING sq.m. 5.97 5,305.79
22.7 WATER PROOFING WORKS sq.m. 9.77 814.20
CEMENT PLASTER (1:4) (20 MM THICK) External
28.7 sq.m. 39.81 564.71
Plaster
CEMENT PLASTER (1:4) (12.5 MM THICK) Internal
30.2 sq.m. 25.64 436.18
Plaster
31.7 DOOR/WINDOW FRAMES cu.m. 0.19 315,781.78
33.2 DOOR SHUTTER sq.m. 7.80 15,915.75
34.7 WINDOW SHUTTER sq.m. 0.28 10,987.08
37.7 PAINTING WORKS ( PLASTIC EMULSION PAINT) sq.m. 18.76 330.41
40.7 PAINTING WORKS (CHAPRA POLISH) sq.m. 18.76 201.02
45.2 PLINTH PROTECTION WORK r.m. 19.51 5,838.65
TOTAL COST
Amount (Nrs.)

1,231.13 0.11%
15,663.83 1.45%
4,590.31 0.43%
10,416.13 0.97%
963.78 0.09%
20,970.81 1.95%
32,825.15 3.05%
36,708.64 3.41%
154,377.36 14.33%
156,573.63 14.53%
18,483.28 1.72%
28,803.82 2.67%
8,773.86 0.81%
20,094.34 1.86%
132,320.87 12.28%
50,585.62 4.69%
31,676.34 2.94%
7,954.73 0.74%
22,478.35 2.09%

11,183.25 1.04%
59,912.88 5.56%
124,142.87 11.52%
3,032.43 0.28%
6,197.13 0.58%
3,770.33 0.35%
113,890.06 10.57%
1,077,620.94

Das könnte Ihnen auch gefallen