(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 2 of 9
PSCJ Job No. JI-2025
TABLE OF CONTENTS
1. GENERAL 3
1.1 SCOPE 3
1.2 ABBREBIATION 3
1.3 DETAIL OF THE PROJECT 3
1.4 DEFINITION 3
2. REFERENCES 3
3. LOCATION 4
4. EQUIPMENTS 4
5. MATERIAL 4
6. RESOURCES 4
7. KEY PERSONNEL 5
8. SAFETY 5
9. PROCEDURE
9.1 EXCAVATION 6
9.2 DEWATERING 7
9.3 BACKFILL & COMPACTION 7
9.4 BACK FILLING INSIDE MANHOLES AND PITS 8
9.5 GRADING AND LEVELLING 8
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 3 of 9
PSCJ Job No. JI-2025
1.0 GENERAL
1.1 SCOPE
The scope of this method statement is to define the procedure that will be followed
for the Deep Excavation for foundations and all underground utilities including
pipelines.
1.2 ABBREBIATION
1.4 DEFINITION
2.0 REFERENCES
2.1.1 Project variation for site preparation and earthworks
DEP-34.11.00.11.Gen P6000CFP-000PV
2.1.2 HSE guidelines for contractor - HSE-TSSA-05-1118
2.1.3 Safe work practice on excavation and civil works-SHE-TSSE-07-
2013.
2.1.4 Safe work practice work permit system and Risk Assessement-
HSE-TSSA-06-2029
2.1.5 SH&E training procedure-SHE-TSTR-05-1501.
2.1.6 IFC Drawings
2.1.7 Pip cvs02100-Site preparation, Excavation
2.1.8 ASTM D1556/ ASTM D1557/ ASTM D698/ ASTM C136
ASTM D4253/ ASTM D4254/ ASTM D422/ ASTM D1146
ASTM D4318
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 4 of 9
PSCJ Job No. JI-2025
3.0 LOCATION
3.1 Location of Deep Excavation works is applicable to all CFP project's areas.
4.0 EQUIPMENT
Depending on the size of the area, site conditions and accessibility, some / all of the
following equipment shall be used as applicable for:
4.1 Excavation:
1. Shovel Loaders with minimum of 2m³ buckets.
2. Bucket excavators or backhoes starting from 400mm wide bucket size.
3. Rock breakers of capacity starting from 0.75 tons.
4. Tipper trucks capacity between 14 and 32m³.
5. Dozers.
6. Electrical Drill Machine (Hilti Machine).
7. Hand tools such as hand shovel, pick axe, etc…
8. Survey equipment.
9. Jack hammer.
4.2 Backfill:
1. Shovel loaders or backhoe loaders.
2. Grader.
3. Plate compactors.
4. Different sizes of double drum roller.
5. 10 Ton vibratory steel rollers.
6. Pneumatic type rollers.
7. Hand tampers.
8. Excavator or backhoe.
9. Diesel operated dewatering pumps 6" discharge.
10. Electric submersible pump.
11. Diesel Ø2", Ø3" & Ø4" dewatering pumps.
12. Tipper Trucks.
13. Bobcat
14. Soil Test Equipment
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 5 of 9
PSCJ Job No. JI-2025
5.0 MATERIAL
5.1 Material to be used for backfilling is the classified structural fill material as per
approved MAR.
add: the corresponding DEP reference
6.0 RESOURCES
6.1 Manpower allocated to this job will be as follows:
Civil superintendent
- Civil supervisor
- Heavy duty operators and drivers.
- Charge hands.
- Test Technicians.
- Laborers.
- Flagmen
8.0 SAFETY
8.1 All equipment shall be KNPC safety certified and in good working condition.
8.2 All personnel involved in this task shall wear safety helmets, safety boots,
gloves, safety glasses and hearing protection, coverall, and have a water
bottle in addition to goggles and dust mask that will required in
windy conditions.
8.6 All involved personnel shall have received the required safety induction and
other appropriate trainings.
8.7 Generated dust (by wind and/or equipment operation), shall be controlled by
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 6 of 9
PSCJ Job No. JI-2025
9.0 PROCEDURE
9.1 Deep Excavation ( full open cut method )
9.1.3 Composite drawing- Cable detectors that can detect both live and dead
cable are to be used.
9.1.5 Excavation shall be carried out in accordance with the lines, level and
profiles shown on the engineering drawings. Generally open cut
excavation will be applied.
9.1.6 Rock breakers will be used in hard Strata where Sheer teeth bucket
excavations and / or shovel loaders are inefficient.
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 7 of 9
PSCJ Job No. JI-2025
9.1.11 The Full open cut method can be further distinguished into the
slope full open cut method and the cantilever method. As figure 1
shows, the slope method does not use retaining walls or struts.
Instead , the construction site is excavated with sloped sides .since
there is no strut to obstruct excavation
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 8 of 9
PSCJ Job No. JI-2025
……….
• Prevent the sides and the ends from collapsing by battering them to a safe angle or
supporting them with timber, sheeting or proprietary support systems.
• Do not go into unsupported excavations.
• Never work ahead of the support.
MS-1146-041
Kuwait National Petroleum Company
(K.S.C) P6012MAB.000.51.1.M321
Clean Fuels Project
Method Statement for
REV. OA, 29-April-2015
KNPC Contract No. CFP/EPC/0054-MAB1 Deep Excavation Page 9 of 9
PSCJ Job No. JI-2025
trenches can be dangerous. You may need to provide support if the work involves
bending or kneeling in the trench.
• Position of Cranes, set back from edge of excavations
MS-1146-041