Beruflich Dokumente
Kultur Dokumente
PROJECT NAME:
BACOLOD CITY
WORK DURATION AND PROGRESS MANPOWER LOADING 1 2 3 4 5 6 7 8 9 10 11 12 13
PLAN START
RELATIVE WT
MANPOWER
DIVISION OF
MARK
AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST
COMPLETE
DURATION
DURATION
FOREMAN
LABORER
PERCENT
SKILLED
ACTUAL
ACTUAL
SAFETY
ENGRS
START
TOTAL
PLAN
WORKS COST
WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
GENERAL REQUIREMENTS
A
A.1 SITE CLEARING & LAYOUT 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
A.2 STAKING ,BATTENS, BOARD U 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
A.3 TEMPORARY FACILITY 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
A.4 MOBILIZATION 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
A.5 EXCAVATION 1 10 350,000.00 0.68% 1 1 1 10 7 20 0% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
A.6 WATER / ELECTRICITY 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
A.6 PREPARATION OF PLANS 1 10 3,200,000.00 6.19% 1 1 1 10 7 20 0% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%
A.8 SAFETY / SECURITY 1 10 150,000.00 0.29% 1 1 1 10 7 20 0% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
A.9 PERMITS 1 10 800,000.00 1.55% 1 1 1 10 7 20 0% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
A.10 MISC. (ADVANCE MAT'L PURC 1 12 6,500,000.00 12.57% 1 1 1 10 7 20 0% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05%
CONCRETE WORKS
B
B.1 FOOTING 1 10 1,837,520.34 3.55% 1 1 1 10 7 20 0% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36%
B.2 COLUMNS 5 36 5,476,535.58 10.59% 1 1 1 15 10 28 0% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29%
B.3 FOOTING TIE BEAM 4 17 2,230,022.83 4.31% 1 1 1 20 15 38 0% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%
B.4 2ND FLOOR BEAM 14 10 3,322,607.54 6.42% 1 1 1 25 20 48 0% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64%
B.5 3RD FLOOR BEAM 24 10 2,622,716.04 5.07% 1 1 1 40 35 78 0% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51%
B.6 3RD FLOOR BEAM 34 10 2,622,716.04 5.07% 1 1 1 45 35 83 0% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51%
B.7 GR. FR. SLAB 16 6 1,505,002.79 2.91% 1 1 1 30 25 58 0% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48%
B.8 2ND FR SLAB 22 6 2,995,634.79 5.79% 1 1 1 30 25 58 0% 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%
B.9 3RD FR SLAB 28 6 2,995,634.79 5.79% 1 1 1 30 25 58 0% 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%
B.10 ROOF DECK SLAB 34 6 2,995,634.79 5.79% 1 1 1 30 25 58 0% 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%
C.1 MASONRY WORKS (GR.FR.) 22 5 579,392.38 1.12% 1 1 1 25 15 43 0% 0.22% 0.22% 0.22% 0.22% 0.22%
C.2 MASONRY WORKS (2ND FR.) 27 5 2,226,360.51 4.30% 1 1 1 25 15 43 0% 0.86% 0.86% 0.86% 0.86% 0.86%
C.3 MASONRY WORKS (3RD FR) 32 5 2,261,671.19 4.37% 1 1 1 25 15 43 0% 0.87% 0.87% 0.87% 0.87% 0.87%
C.4 MASONRY WORKS (ROOFDECK 37 5 741,181.80 1.43% 1 1 1 25 15 43 0% 0.29% 0.29% 0.29% 0.29% 0.29%
PAINTING WORKS
D
E.1 ELECTRICAL WORKS (GF) 16 6 339,755.00 0.66% 1 1 1 5 3 11 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
E.2 ELECTRICAL WORKS (2F) 22 6 587,762.50 1.14% 1 1 1 5 3 11 0% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
E.3 ELECTRICAL WORKS (3F) 28 6 330,687.50 0.64% 1 1 1 5 3 11 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
E.4 ELECTRICAL WORKS (RD) 34 6 55,737.50 0.11% 1 1 1 5 3 11 0% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
E.5 PANELS / BREAKERS / FEEDER 40 10 850,000.00 1.64% 1 1 1 5 3 11 0% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%
PLUMBING WORKS
F
F.1 PLUMBING WORKS (GF) 16 6 120,000.00 0.23% 1 1 1 5 3 11 0% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
F.2 PLUMBING WORKS (2F) 22 6 450,000.00 0.87% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
F.3 PLUMBING WORKS (3F) 28 6 350,000.00 0.68% 1 1 1 5 3 11 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
F.4 PLUMBING WORKS (4F) 34 6 75,000.00 0.14% 1 1 1 5 3 11 0% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
F.5 PUMPS/TANKS/STF 40 10 750,000.00 1.45% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
G.1 ROOFING AND STEEL WORKS 40 6 350,000.00 0.68% 1 1 1 3 2 8 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Monthly 2.32% 2.32% 2.32% 2.57% 2.87% 2.87% 2.87% 2.87% 2.87% 2.87% 1.59% 1.59% 0.55% 1.19% 1.19% 1.82% 1.82% 1.82% 1.82% 1.82% 1.57% 2.46% 2.46% 2.32% 2.32% 2.32% 2.96% 2.85% 2.85% 2.85% 2.85% 2.86% 2.86% 2.90% 2.90% 2.90% 2.47% 2.47% 2.47% 1.95% 1.65% 1.37% 1.06% 0.55% 0.55% 0.31% 0.31% 0.31% 0.31% 0.00% 0.00% 0.00% 0.00%
PERCENTAGE ACCOMPLISHMENT
Progressive / Commulative 2.32% 4.64% 6.96% 9.54% 12.40% 15.27% 18.14% 21.01% 23.88% 26.74% 28.34% 29.93% 30.48% 31.67% 32.86% 34.68% 36.51% 38.33% 40.15% 41.98% 43.55% 46.01% 48.47% 50.79% 53.11% 55.44% 58.40% 61.25% 64.09% 66.94% 69.79% 72.65% 75.51% 78.41% 81.31% 84.21% 86.68% 89.16% 91.63% 93.58% 95.23% 96.60% 97.66% 98.21% 98.76% 99.07% 99.38% 99.69% 100.00% 100.00% 100.00% 100.00% 100.00%
WEEK NO.
MARK
WORK
DIVISION OF WORKS PROGRESS &
RELATIVE
WEIGHT
GENERAL REQUIREMENTS
A
PROJECT NAME:
BACOLOD CITY
WORK DURATION AND PROGRESS MANPOWER LOADING 1 2 3 4 5 6 7 8 9 10 11 12 13
PLAN START
RELATIVE WT
MANPOWER
DIVISION OF
MARK
AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST
COMPLETE
DURATION
DURATION
FOREMAN
LABORER
PERCENT
SKILLED
ACTUAL
ACTUAL
SAFETY
ENGRS
START
TOTAL
PLAN
WORKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
A CONCRETE WORKS
A.1 FOOTING 1 10 1,837,520.34 4.54% 1 1 1 10 7 20 0% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45%
A.2 COLUMNS 5 36 5,476,535.58 13.53% 1 1 1 15 10 28 0% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38%
A.3 FOOTING TIE BEAM 7 14 2,230,022.83 5.51% 1 1 1 20 15 38 0% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39%
A.4 2ND FLOOR BEAM 14 10 3,322,607.54 8.21% 1 1 1 25 20 48 0% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82%
A.5 3RD FLOOR BEAM 24 10 2,622,716.04 6.48% 1 1 1 40 35 78 0% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65%
A.6 3RD FLOOR BEAM 34 10 2,622,716.04 6.48% 1 1 1 45 35 83 0% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65%
A.7 GR. FR. SLAB 16 6 1,505,002.79 3.72% 1 1 1 30 25 58 0% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%
A.8 2ND FR SLAB 22 6 2,995,634.79 7.40% 1 1 1 30 25 58 0% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%
A.9 3RD FR SLAB 28 6 2,995,634.79 7.40% 1 1 1 30 25 58 0% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%
A.10 ROOF DECK SLAB 34 6 2,995,634.79 7.40% 1 1 1 30 25 58 0% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%
B MASONRY WORKS
B.1 MASONRY WORKS (GR.FR.) 22 5 579,392.38 1.43% 1 1 1 25 15 43 0% 0.29% 0.29% 0.29% 0.29% 0.29%
B.2 MASONRY WORKS (2ND FR.) 27 5 2,226,360.51 5.50% 1 1 1 25 15 43 0% 1.10% 1.10% 1.10% 1.10% 1.10%
B.3 MASONRY WORKS (3RD FR) 32 5 2,261,671.19 5.59% 1 1 1 25 15 43 0% 1.12% 1.12% 1.12% 1.12% 1.12%
B.4 MASONRY WORKS (ROOFDECK 37 5 741,181.80 1.83% 1 1 1 25 15 43 0% 0.37% 0.37% 0.37% 0.37% 0.37%
C PAINTING WORKS
D ELECTRICAL WORKS
D.1 ELECTRICAL WORKS (GF) 16 6 339,755.00 0.84% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
D.2 ELECTRICAL WORKS (2F) 22 6 587,762.50 1.45% 1 1 1 5 3 11 0% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24%
D.3 ELECTRICAL WORKS (3F) 28 6 330,687.50 0.82% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
D.4 ELECTRICAL WORKS (RD) 34 6 55,737.50 0.14% 1 1 1 5 3 11 0% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
D.5 PANELS / BREAKERS / FEEDER 40 10 850,000.00 2.10% 1 1 1 5 3 11 0% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
E PLUMBING WORKS
E.1 PLUMBING WORKS (GF) 16 6 120,000.00 0.30% 1 1 1 5 3 11 0% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%
E.2 PLUMBING WORKS (2F) 22 6 450,000.00 1.11% 1 1 1 5 3 11 0% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
E.3 PLUMBING WORKS (3F) 28 6 350,000.00 0.86% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
E.4 PLUMBING WORKS (4F) 34 6 75,000.00 0.19% 1 1 1 5 3 11 0% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
E.5 PUMPS/TANKS/STF 40 10 750,000.00 1.85% 1 1 1 5 3 11 0% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
F.1 ROOFING AND STEEL WORKS 40 6 350,000.00 0.86% 1 1 1 3 2 8 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
Monthly 0.45% 0.45% 0.45% 0.45% 0.83% 0.83% 1.22% 1.22% 1.22% 1.22% 0.77% 0.77% 0.77% 1.59% 1.59% 2.40% 2.40% 2.40% 2.40% 2.40% 2.01% 3.14% 3.14% 2.97% 2.97% 2.97% 3.78% 3.64% 3.64% 3.64% 3.64% 3.65% 3.65% 3.71% 3.71% 3.71% 3.16% 3.16% 3.16% 2.49% 2.11% 1.75% 1.36% 0.71% 0.71% 0.40% 0.40% 0.40% 0.40% 0.00% 0.00% 0.00% 0.00%
PERCENTAGE ACCOMPLISHMENT
Progressive / Commulative 0.45% 0.91% 1.36% 1.82% 2.65% 3.48% 4.70% 5.92% 7.14% 8.37% 9.14% 9.91% 10.68% 12.27% 13.86% 16.26% 18.65% 21.05% 23.45% 25.85% 27.86% 31.00% 34.14% 37.11% 40.08% 43.06% 46.84% 50.48% 54.11% 57.75% 61.39% 65.04% 68.70% 72.41% 76.11% 79.82% 82.98% 86.14% 89.31% 91.79% 93.90% 95.65% 97.00% 97.71% 98.42% 98.81% 99.21% 99.60% 100.00% 100.00% 100.00% 100.00% 100.00%
NOAH'S ARCHITECTS
The First Builders
PROJECT WORK SCHEDULE Week No 4 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
PROJECT NAME:
VERDANA
NUMBER OF WEEKS 1 2 3 4 5
Prepared By:
Approved By:
ZAYCO LAND
Owner
NOAH'S ARCHITECTS
The First Builders
PROJECT WORK SCHEDULE NOVEMBER 25 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
PROJECT NAME:
VERDANA
INSTALLATION - FOOTINGS/MATTINGS/COLUMNS
EXCAVATION- ZOCALO
CONCRETING - FTB/ZWF
BACKFILL