Sie sind auf Seite 1von 9

GREATWALL BUILDERS STANDARD CONSTRUCTION DOCUMENT - C003

PROJECT WORK SCHEDULE


Week No 14 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)

PROJECT NAME:

PROPOSED 3 STOREY MIXED USE COMMERCIAL BLDG. WITH ROOFDE


LOCATION:

BACOLOD CITY
WORK DURATION AND PROGRESS MANPOWER LOADING 1 2 3 4 5 6 7 8 9 10 11 12 13
PLAN START

RELATIVE WT

MANPOWER
DIVISION OF
MARK

AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST

COMPLETE
DURATION

DURATION

FOREMAN

LABORER

PERCENT
SKILLED
ACTUAL
ACTUAL

SAFETY
ENGRS
START

TOTAL
PLAN

WORKS COST
WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

GENERAL REQUIREMENTS
A

A.1 SITE CLEARING & LAYOUT 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

A.2 STAKING ,BATTENS, BOARD U 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

A.3 TEMPORARY FACILITY 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

A.4 MOBILIZATION 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

A.5 EXCAVATION 1 10 350,000.00 0.68% 1 1 1 10 7 20 0% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%

A.6 WATER / ELECTRICITY 1 10 50,000.00 0.10% 1 1 1 10 7 20 0% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

A.6 PREPARATION OF PLANS 1 10 3,200,000.00 6.19% 1 1 1 10 7 20 0% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%

A.8 SAFETY / SECURITY 1 10 150,000.00 0.29% 1 1 1 10 7 20 0% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%

A.9 PERMITS 1 10 800,000.00 1.55% 1 1 1 10 7 20 0% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%

A.10 MISC. (ADVANCE MAT'L PURC 1 12 6,500,000.00 12.57% 1 1 1 10 7 20 0% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05%

CONCRETE WORKS
B

B.1 FOOTING 1 10 1,837,520.34 3.55% 1 1 1 10 7 20 0% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36%

B.2 COLUMNS 5 36 5,476,535.58 10.59% 1 1 1 15 10 28 0% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29%

B.3 FOOTING TIE BEAM 4 17 2,230,022.83 4.31% 1 1 1 20 15 38 0% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%

B.4 2ND FLOOR BEAM 14 10 3,322,607.54 6.42% 1 1 1 25 20 48 0% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64%

B.5 3RD FLOOR BEAM 24 10 2,622,716.04 5.07% 1 1 1 40 35 78 0% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51%

B.6 3RD FLOOR BEAM 34 10 2,622,716.04 5.07% 1 1 1 45 35 83 0% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51%

B.7 GR. FR. SLAB 16 6 1,505,002.79 2.91% 1 1 1 30 25 58 0% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48%

B.8 2ND FR SLAB 22 6 2,995,634.79 5.79% 1 1 1 30 25 58 0% 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%

B.9 3RD FR SLAB 28 6 2,995,634.79 5.79% 1 1 1 30 25 58 0% 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%

B.10 ROOF DECK SLAB 34 6 2,995,634.79 5.79% 1 1 1 30 25 58 0% 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%

MASONRY WORKS 0.00%


C

C.1 MASONRY WORKS (GR.FR.) 22 5 579,392.38 1.12% 1 1 1 25 15 43 0% 0.22% 0.22% 0.22% 0.22% 0.22%

C.2 MASONRY WORKS (2ND FR.) 27 5 2,226,360.51 4.30% 1 1 1 25 15 43 0% 0.86% 0.86% 0.86% 0.86% 0.86%

C.3 MASONRY WORKS (3RD FR) 32 5 2,261,671.19 4.37% 1 1 1 25 15 43 0% 0.87% 0.87% 0.87% 0.87% 0.87%

C.4 MASONRY WORKS (ROOFDECK 37 5 741,181.80 1.43% 1 1 1 25 15 43 0% 0.29% 0.29% 0.29% 0.29% 0.29%

PAINTING WORKS
D

D.1 PAINTING WORKS (GF) 34 3 339,755.00 0.66% 1 1 1 15 5 23 0% 0.22% 0.22% 0.22%

D.2 PAINTING WORKS (2F) 37 3 587,762.50 1.14% 1 1 1 15 5 23 0% 0.38% 0.38% 0.38%

D.3 PAINTING WORKS (3F) 40 3 677,451.50 1.31% 1 1 1 15 5 23 0% 0.44% 0.44% 0.44%

D.4 PAINTING WORKS (4F) 43 3 204,034.55 0.39% 1 1 1 15 5 23 0% 0.13% 0.13% 0.13%

ELECTRICAL WORKS 0.00%


E

E.1 ELECTRICAL WORKS (GF) 16 6 339,755.00 0.66% 1 1 1 5 3 11 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%

E.2 ELECTRICAL WORKS (2F) 22 6 587,762.50 1.14% 1 1 1 5 3 11 0% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%

E.3 ELECTRICAL WORKS (3F) 28 6 330,687.50 0.64% 1 1 1 5 3 11 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%

E.4 ELECTRICAL WORKS (RD) 34 6 55,737.50 0.11% 1 1 1 5 3 11 0% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%

E.5 PANELS / BREAKERS / FEEDER 40 10 850,000.00 1.64% 1 1 1 5 3 11 0% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%

PLUMBING WORKS
F

F.1 PLUMBING WORKS (GF) 16 6 120,000.00 0.23% 1 1 1 5 3 11 0% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%

F.2 PLUMBING WORKS (2F) 22 6 450,000.00 0.87% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

F.3 PLUMBING WORKS (3F) 28 6 350,000.00 0.68% 1 1 1 5 3 11 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%

F.4 PLUMBING WORKS (4F) 34 6 75,000.00 0.14% 1 1 1 5 3 11 0% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%

F.5 PUMPS/TANKS/STF 40 10 750,000.00 1.45% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

ROOFING AND STEEL


G

G.1 ROOFING AND STEEL WORKS 40 6 350,000.00 0.68% 1 1 1 3 2 8 0% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%

TOTAL PROJECT COST ### 100.00%

Monthly 2.32% 2.32% 2.32% 2.57% 2.87% 2.87% 2.87% 2.87% 2.87% 2.87% 1.59% 1.59% 0.55% 1.19% 1.19% 1.82% 1.82% 1.82% 1.82% 1.82% 1.57% 2.46% 2.46% 2.32% 2.32% 2.32% 2.96% 2.85% 2.85% 2.85% 2.85% 2.86% 2.86% 2.90% 2.90% 2.90% 2.47% 2.47% 2.47% 1.95% 1.65% 1.37% 1.06% 0.55% 0.55% 0.31% 0.31% 0.31% 0.31% 0.00% 0.00% 0.00% 0.00%

PERCENTAGE ACCOMPLISHMENT
Progressive / Commulative 2.32% 4.64% 6.96% 9.54% 12.40% 15.27% 18.14% 21.01% 23.88% 26.74% 28.34% 29.93% 30.48% 31.67% 32.86% 34.68% 36.51% 38.33% 40.15% 41.98% 43.55% 46.01% 48.47% 50.79% 53.11% 55.44% 58.40% 61.25% 64.09% 66.94% 69.79% 72.65% 75.51% 78.41% 81.31% 84.21% 86.68% 89.16% 91.63% 93.58% 95.23% 96.60% 97.66% 98.21% 98.76% 99.07% 99.38% 99.69% 100.00% 100.00% 100.00% 100.00% 100.00%

Yearly 21,714,682.43 30,015,895.03


BILLING AMOUNT
Progressive / Commulative 21,714,682.43 51,730,577.46

GREAT WALL BUILDERS OF VISAYAS INC. FOR COMPANY USE ONLY


PROJECT NAME:
PROPOSED 3 STOREY MIXED USE COMMERCIAL BLDG. WITH ROOFDECK
LOCATION:
BACOLOD CITY

WEEK NO.
MARK

WORK
DIVISION OF WORKS PROGRESS &
RELATIVE
WEIGHT

GENERAL REQUIREMENTS
A

A.1 SITE CLEARING & LAYOUT 0.10% 14


A.2 STAKING ,BATTENS, BOARD UP 0.10% 14
A.3 TEMPORARY FACILITY 0.10% 14
A.4 MOBILIZATION 0.10% 14
A.5 EXCAVATION 0.68% 14
A.6 WATER / ELECTRICITY 0.10% 14
A.6 PREPARATION OF PLANS 6.19% 14
A.8 SAFETY / SECURITY 0.29% 14
A.9 PERMITS 1.55% 14
A.10 MISC. (ADVANCE MAT'L PURCHASE) 12.57% 14
CONCRETE WORKS
B

B.1 FOOTING 3.55% 14


B.2 COLUMNS 2.94% 14
B.3 FOOTING TIE BEAM 2.79% 14
B.4 2ND FLOOR BEAM 0.64% 14
B.5 3RD FLOOR BEAM 0.00% 14
B.6 3RD FLOOR BEAM 0.00% 14
B.7 GR. FR. SLAB 0.00% 14
B.8 2ND FR SLAB 0.00% 14
B.9 3RD FR SLAB 0.00% 14
B.10 ROOF DECK SLAB 0.00% 14
MASONRY WORKS
C

C.1 MASONRY WORKS (GR.FR.) 0.00% 14


C.2 MASONRY WORKS (2ND FR.) 0.00% 14
C.3 MASONRY WORKS (3RD FR) 0.00% 14
C.4 MASONRY WORKS (ROOFDECK) 0.00% 14
PAINTING WORKS
D

D.1 PAINTING WORKS (GF) 0.00% 14


D.2 PAINTING WORKS (2F) 0.00% 14
D.3 PAINTING WORKS (3F) 0.00% 14
D.4 PAINTING WORKS (4F) 0.00% 14
ELECTRICAL WORKS
E

E.1 ELECTRICAL WORKS (GF) 0.00% 14


E.2 ELECTRICAL WORKS (2F) 0.00% 14
E.3 ELECTRICAL WORKS (3F) 0.00% 14
E.4 ELECTRICAL WORKS (RD) 0.00% 14
E.5 PANELS / BREAKERS / FEEDERS 0.00% 14
PLUMBING WORKS
F

F.1 PLUMBING WORKS (GF) 0.00% 14


F.2 PLUMBING WORKS (2F) 0.00% 14
F.3 PLUMBING WORKS (3F) 0.00% 14
F.4 PLUMBING WORKS (4F) 0.00% 14
F.5 PUMPS/TANKS/STF 0.00% 14
ROOFING AND STEEL
G

G.1 ROOFING AND STEEL WORKS 0.00% 14

TOTAL WORK PERCENTAGE PROGRESS 31.67%


AS OF NOV. 13, 2018
WEEK NO, 14
ITH ROOFDECK
GREATWALL BUILDERS STANDARD CONSTRUCTION DOCUMENT - C003

PROJECT WORK SCHEDULE


Week No 14 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)

PROJECT NAME:

PROPOSED 3 STOREY MIXED USE COMMERCIAL BLDG. WITH ROOFDE


LOCATION:

BACOLOD CITY
WORK DURATION AND PROGRESS MANPOWER LOADING 1 2 3 4 5 6 7 8 9 10 11 12 13
PLAN START

RELATIVE WT

MANPOWER
DIVISION OF
MARK

AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST

COMPLETE
DURATION

DURATION

FOREMAN

LABORER

PERCENT
SKILLED
ACTUAL
ACTUAL

SAFETY
ENGRS
START

TOTAL
PLAN

WORKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

A CONCRETE WORKS

A.1 FOOTING 1 10 1,837,520.34 4.54% 1 1 1 10 7 20 0% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45%

A.2 COLUMNS 5 36 5,476,535.58 13.53% 1 1 1 15 10 28 0% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38%

A.3 FOOTING TIE BEAM 7 14 2,230,022.83 5.51% 1 1 1 20 15 38 0% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39%

A.4 2ND FLOOR BEAM 14 10 3,322,607.54 8.21% 1 1 1 25 20 48 0% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82% 0.82%

A.5 3RD FLOOR BEAM 24 10 2,622,716.04 6.48% 1 1 1 40 35 78 0% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65%

A.6 3RD FLOOR BEAM 34 10 2,622,716.04 6.48% 1 1 1 45 35 83 0% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65%

A.7 GR. FR. SLAB 16 6 1,505,002.79 3.72% 1 1 1 30 25 58 0% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%

A.8 2ND FR SLAB 22 6 2,995,634.79 7.40% 1 1 1 30 25 58 0% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%

A.9 3RD FR SLAB 28 6 2,995,634.79 7.40% 1 1 1 30 25 58 0% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%

A.10 ROOF DECK SLAB 34 6 2,995,634.79 7.40% 1 1 1 30 25 58 0% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%

B MASONRY WORKS

B.1 MASONRY WORKS (GR.FR.) 22 5 579,392.38 1.43% 1 1 1 25 15 43 0% 0.29% 0.29% 0.29% 0.29% 0.29%

B.2 MASONRY WORKS (2ND FR.) 27 5 2,226,360.51 5.50% 1 1 1 25 15 43 0% 1.10% 1.10% 1.10% 1.10% 1.10%

B.3 MASONRY WORKS (3RD FR) 32 5 2,261,671.19 5.59% 1 1 1 25 15 43 0% 1.12% 1.12% 1.12% 1.12% 1.12%

B.4 MASONRY WORKS (ROOFDECK 37 5 741,181.80 1.83% 1 1 1 25 15 43 0% 0.37% 0.37% 0.37% 0.37% 0.37%

C PAINTING WORKS

C.1 PAINTING WORKS (GF) 34 3 339,755.00 0.84% 1 1 1 15 5 23 0% 0.28% 0.28% 0.28%

C.2 PAINTING WORKS (2F) 37 3 587,762.50 1.45% 1 1 1 15 5 23 0% 0.48% 0.48% 0.48%

C.3 PAINTING WORKS (3F) 40 3 677,451.50 1.67% 1 1 1 15 5 23 0% 0.56% 0.56% 0.56%

C.4 PAINTING WORKS (4F) 43 3 204,034.55 0.50% 1 1 1 15 5 23 0% 0.17% 0.17% 0.17%

D ELECTRICAL WORKS

D.1 ELECTRICAL WORKS (GF) 16 6 339,755.00 0.84% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

D.2 ELECTRICAL WORKS (2F) 22 6 587,762.50 1.45% 1 1 1 5 3 11 0% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24%

D.3 ELECTRICAL WORKS (3F) 28 6 330,687.50 0.82% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

D.4 ELECTRICAL WORKS (RD) 34 6 55,737.50 0.14% 1 1 1 5 3 11 0% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%

D.5 PANELS / BREAKERS / FEEDER 40 10 850,000.00 2.10% 1 1 1 5 3 11 0% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%

E PLUMBING WORKS

E.1 PLUMBING WORKS (GF) 16 6 120,000.00 0.30% 1 1 1 5 3 11 0% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%

E.2 PLUMBING WORKS (2F) 22 6 450,000.00 1.11% 1 1 1 5 3 11 0% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%

E.3 PLUMBING WORKS (3F) 28 6 350,000.00 0.86% 1 1 1 5 3 11 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

E.4 PLUMBING WORKS (4F) 34 6 75,000.00 0.19% 1 1 1 5 3 11 0% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%

E.5 PUMPS/TANKS/STF 40 10 750,000.00 1.85% 1 1 1 5 3 11 0% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%

F ROOFING AND STEEL

F.1 ROOFING AND STEEL WORKS 40 6 350,000.00 0.86% 1 1 1 3 2 8 0% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

TOTAL PROJECT COST ### 100.00%

Monthly 0.45% 0.45% 0.45% 0.45% 0.83% 0.83% 1.22% 1.22% 1.22% 1.22% 0.77% 0.77% 0.77% 1.59% 1.59% 2.40% 2.40% 2.40% 2.40% 2.40% 2.01% 3.14% 3.14% 2.97% 2.97% 2.97% 3.78% 3.64% 3.64% 3.64% 3.64% 3.65% 3.65% 3.71% 3.71% 3.71% 3.16% 3.16% 3.16% 2.49% 2.11% 1.75% 1.36% 0.71% 0.71% 0.40% 0.40% 0.40% 0.40% 0.00% 0.00% 0.00% 0.00%

PERCENTAGE ACCOMPLISHMENT
Progressive / Commulative 0.45% 0.91% 1.36% 1.82% 2.65% 3.48% 4.70% 5.92% 7.14% 8.37% 9.14% 9.91% 10.68% 12.27% 13.86% 16.26% 18.65% 21.05% 23.45% 25.85% 27.86% 31.00% 34.14% 37.11% 40.08% 43.06% 46.84% 50.48% 54.11% 57.75% 61.39% 65.04% 68.70% 72.41% 76.11% 79.82% 82.98% 86.14% 89.31% 91.79% 93.90% 95.65% 97.00% 97.71% 98.42% 98.81% 99.21% 99.60% 100.00% 100.00% 100.00% 100.00% 100.00%

Yearly 10,464,682.43 30,015,895.03


BILLING AMOUNT
Progressive / Commulative 10,464,682.43 40,480,577.46

GREAT WALL BUILDERS OF VISAYAS INC. FOR COMPANY USE ONLY


NOAHS ARCHITECTS
STANDARD CONSTRUCTION DOCUMENT - C003

NOAH'S ARCHITECTS
The First Builders

No. 8 Calle Oro St., Capitol Hts. 3, Villamonte, Bacolod City


Tel No: (034)-7048995

PROJECT WORK SCHEDULE Week No 4 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)

PROJECT NAME:

PROPOSED 2 STOREY RESIDENCE


LOCATION:

VERDANA

NUMBER OF WEEKS 1 2 3 4 5

DIVISION OF WORKS PLAN


START
PLAN
DURATION
COST ACTUAL
START
ACTUAL
DURATION
PERCENT
WEIGHT
PERCENT
COMPLETE
AUGUST
WEEKS
SEPTEMBER
WEEKS
OCTOBER
WEEKS
NOVEMBER
WEEKS
DECEMBER
WEEKS
WEEK NO WEEKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 PREPARATION OF PLANS PHP 1,149,268.50 0%


2 3 0.2102
2 MASONRY WORKS PHP 778,572.00 0%
6 6 0.1424
3 FORMS AND SCAFFOLDS PHP 176,600.25 0%
5 4 0.0323
4 STAKING AND LAYOUT PHP 125,752.50 0%
5 3 0.023
5 CARPENTRY WORKS PHP 333,517.50 0%
11 4 0.061
6 DOORS AND WINDOWS PHP 708,041.25 0%
12 5 0.1295
7 METAL WORKS PHP 110,990.25 0%
9 4 0.0203
8 ROOFING INSTALLATION PHP 208,311.75 0%
10 4 0.0381
9 FINISHING WORKS PHP 485,514.00 0%
13 6 0.0888
10 ELECTRICAL WORKS PHP 504,650.25 0%
8 6 0.0923
11 PLUMBING WORKS PHP 368,509.50 0%
8 3 0.0674
12 PAINTING WORKS PHP 517,772.25 0%
13 6 0.0947
TOTAL PHP 5,467,500.00 0 0 1.00

Prepared By:

AR. JUN ADRIAN E. CARAIG


Architect
United Architect's of the Philippines
PRC NO 33469
VALIDITY NOV. 4, 2021

Approved By:

ZAYCO LAND
Owner

NOAHS ARCHITECTS FOR COMPANY USE ONLY


GREATWALL BUILDERS STANDARD CONSTRUCTION DOCUMENT - C003

NOAH'S ARCHITECTS
The First Builders

No. 8 Calle Oro St., Capitol Hts. 3, Villamonte, Bacolod City


Tel No: (034)-7048995

PROJECT WORK SCHEDULE NOVEMBER 25 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)

PROJECT NAME:

PROPOSED 2 STOREY RESIDENCE


LOCATION:

VERDANA

NUMBER OF WEEKS NOVEMBER DECEMBER 7 8 9 10 11 12 13


PLAN PLAN ACTUAL ACTUAL PERCENT WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER
DIVISION OF WORKS START (DATE) DURATION(DAYS)
COST
START DURATION COMPLETE NOV 11-16 NOV 18-23 NOV 25-30 DEC 2-7 DEC 9-14 DEC 16-21 WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS WEEKS
M T W TH F S M T W TH F S M T W TH F S M T W TH F S M T W TH F S M T W TH F S
11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 2 3 4 5 6 7 9 10 11 12 13 14 16 17 18 19 20 21 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

1 MOBILIZATION, TEMPORARY FACILITIES #DIV/0!


12 1
STEELWORKS BENDING & INSTALLING BARS
6
STAKING/CLEARING
2 1
BELOW GRADE (STRUCTURAL)

2 FOUNDATION EXCAVATION 133%


11 3 11 4
ANTI-TERMITE TREATMENT

INSTALLATION - FOOTINGS/MATTINGS/COLUMNS

CONCRETING - FOOTINGS (16 UNITS)

SCAFFOLDINGS AND FORMWORKS - FOR 1ST LIFT OF COLUMN

CONCRETING - COLUMNS - 1ST LIFT

EXCAVATION- FOOTING TIE BEAM

EXCAVATION- ZOCALO

SCAFFOLDINGS AND FORMWORKS -FTB/ZWF

CONCRETING - FTB/ZWF

VERTICAL BARS FOR CHB LAYING

BACKFILL

ABOVE NATURAL GRADE (STRUCTURAL)

3 SCAFFOLDINGS AND FORMWORKS - FOR 2ND LIFT OF COLUMN 0%


1 1
4 CONCRETING - COLUMNS - 2ND LIFT 0%
1 1
5 CHB LAYING - EXTERIOR (6") #DIV/0!

CHB LAYING - INTERIOR (4")

6 MASONRY-ROUGH CHB #DIV/0!

7 PLUMBING ROUGHING IN, PVC PIPES, FITTINGS #DIV/0!

8 INSTALL PLUMBING FIXTURES, SINK, WATER CLOSET, LAV #DIV/0!

9 ROUGH CARPENTRY JOISTS, STUDDINGS, ROOF TRUSSES #DIV/0!

10 ARCHITECTURAL FINISHES, DOORS, WINDOWS, CLOSETS #DIV/0!

11 MASONRY FINISHES, PLASTERING, TILING #DIV/0!

12 ROOFING - LONG SPAN, GUTTERS, DOWNSPOUTS #DIV/0!

13 ELECTRICAL ROUGHING IN, PVC PIPES, FITTINGS #DIV/0!

GREAT WALL BUILDERS OF VISAYAS INC. FOR COMPANY USE ONLY


GREATWALL BUILDERS STANDARD CONSTRUCTION DOCUMENT - C003

14 ELECTRIC WIRES AND FIXTURES #DIV/0!

15 FIRE ALARM, TELEPHONE, DATA, CCTV #DIV/0!

16 MECHANICAL WORKS, SPRINKLERS, CONVEYOR #DIV/0!

17 PAINTING, EXTERIOR AND INTERIOR #DIV/0!

GREAT WALL BUILDERS OF VISAYAS INC. FOR COMPANY USE ONLY


Project Planner Period Highlight:5 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)

PLAN PLAN ACTUAL ACTUAL PERCENT


ACTIVITY START DURATION START DURATION COMPLETE PERIODS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
Activity 01 1 5 1 4 25%
Activity 02 1 6 1 6 100%
Activity 03 2 4 2 5 35%
Activity 04 4 8 4 6 10%
Activity 05 4 2 4 8 85%
Activity 06 4 3 4 6 85%
Activity 07 5 4 5 3 50%
Activity 08 5 2 5 5 60%
Activity 09 5 2 5 6 75%
Activity 10 6 5 6 7 100%
Activity 11 6 1 5 8 60%
Activity 12 9 3 9 3 0%
Activity 13 9 6 9 7 50%
Activity 14 9 3 9 1 0%
Activity 15 9 4 8 5 1%
Activity 16 10 5 10 3 80%
Activity 17 11 2 11 5 0%
Activity 18 12 6 12 7 0%
Activity 19 12 1 12 5 0%
Activity 20 14 5 14 6 0%
Activity 21 14 8 14 2 44%
Activity 22 14 7 14 3 0%
Activity 23 15 4 15 8 12%
Activity 24 15 5 15 3 5%
Activity 25 15 8 15 5 0%
Activity 26 16 28 16 30 50%

Das könnte Ihnen auch gefallen