Beruflich Dokumente
Kultur Dokumente
Thumb Rules For Civil Engineers is essential for any civil engineer, Site engineer
or civil supervisor. They play a crucial role while taking quick decisions on site.
Thumb rules help you in finding out the solution using a simple mathematical
formula and make smart decisions whenever needed. But, while using these
thumb rules, you must remember that the thumb rule never gives the exact or
accurate results, you just have used them for approximate results.
There are numbers of thumb Rules For Civil Engineers which we used in
construction work. So, following are some most frequently used Thumb rules on
Construction site.
The Thumb rule method is an approximate & comparing method. In thumb rules
and the units are not the same when we compare to get the results. So, ignore
units while performing thumb rule.
Thumb rule for estimating the Concrete Volume with respect to the
area:
So, for the plan area of 800 Sq. m. area the total volume of concrete required
Thumb rule for Steel quantity required for Slab, Beams, Footings &
Columns:
Steel required in residential buildings = 4.5 Kgs – 4.75 Kgs / Sq. Ft.
Example:
How to calculate the steel quantity of slab having the Length, width, and depth
of the slab is 5m x 4m x 0.15m
= 3m3
As per the guidelines are given in B N Dutta reference book the steel quantity of
slab is 1% of the total volume of concrete utilized.
Components of Shuttering:-
Suppose, The shuttering Ply has a length, width & depth of 2.44 x 1.22 x 0.012
If work requires 25 Ply sheets, the total quantity of Battens are 19.82 x 25 = 495
Battens
(or)
Example :
If, total area of shuttering is 15 m2, then Shuttering oil Consumption = 0.065 x
15 = 0.975.
Thumb rule for Cement required in Brickwork, Cement Masonry & Plastering
work in construction:
Example..
= 0.025 * 7850*1
= 196.25. Kg
Thumb rules based on day by day practice & experience in construction field…
my senior engineer tell me in case of immediate/ urgency we use this rule..many times it
helpful…
1. For M20(1:1.5:3)
8.4 bag cement, 0.84 m3 CA, 0.42m3 sand.
Thumb rule requirement of standard materials and standard calculation in high raised
building
Steel =3 to 5 kg / sft
Cement =.5bags/ sft
RMC =.05 m3/sft
Block =12.5 nos /sqm
Electrical cast = Rs 133/sft
Plumbing cost = Rs 126/sft
Fire fighting cost = Rs 40/sft
External development = Rs 94.5/sft
Civil works-Structure = RS 751.25/sft
Finishing works = RS 467.50/sft
200 mm in cm 1:6 =0.124Bags /sqm
200 mm in cm 1:4 =0.206 bags/sqm
150 mm in cm 1:6 =0.093 bags/sqm
150mm in cm 1:4 =0.144 bags/sqm
100 mm in cm 1:4 =0.103 bags/sqm
Ceiling plastering =0.11 bags/sqm
Wall plastering =0.09 bags/sqm
Rough plastering =0.09 bags/sqm
Duct plastering =0.09 bags/sqm
External plastering =0.175 bags/sqm
lathen plastering =0.55 bags/sqm
stucco plaster =0.175 bags/sqm
100 mm plaster band =0.012 bags/rmt
pcc 1: 4: 8 =3.4 bags/cum
pcc 1:5:10 =2.52 bags/cum
pcc 1:3:6 =4.2 bags/cum
pcc 1:2:4 =6.02 bags/cum
230 mm brick =0.876 bags/cum
115 mm brick work =0.218 bags/cum
vdf 100 mm thick =0.82 bags/sqm
granolithic flooring =40 mm 0.35 bags/sqm
granolithic flooring =20 mm 0.28 bags/sqm
anti-skid =0.28 bags/sqm
ceramic =0.28 bags/sqm
vertified tile flooring =0.28 bags/sqm
vertified tile dado =0.27 bags/sqm
cerami dado =0.27 bags/sqm
marble flooring =0.3 bags/sqm
100 mm ht marble skerting =0.027 bags/rmt
marble glading =0.27 bags/sqm
terracota tle flooring =0.3 bags/sqm
mangalore tile =0.3 bags/sqm
Door frame fixing =0.17 bags/sqm
water proofing for sunken slab =0.23 bags/sqm
water proofing for walls =0.23 bags/sqm
water proofing for balcony/toilets =0.65 bags/sqm
Anti terminate treatment chemical Name is chloropyrifoc 20% . Diluting5 Lit of
Chemical with 95 Lit of water and usage is 7.5 Sqm Per liter {Diluted} .To Provide 1”
Dia hole And Deep1Foot
Labour Productivity thump rule :-
Brick work
1 Women Mazdoor
1 Women Mazdoor
1 Women Mazdoor
1 Women Mazdoor
1 Women Mazdoor
1 Women Mazdoor
1 Women Mazdoor
Carpenter 1 Skilled
1 Un skilled 4 Sqm
1 UN skilled 200Kg
1M Mazdoor 10 Sqm
Paint
External Painting
Ace-Low quality
Apex-Medium Quality
3. Decreased by 1%, then the slump value will be decreased about 12.5 mm.
4. Decreased by 1%, then the durability of the concrete will be reduced by 10%.
The following are some of the rules of thumb which will be useful to achieve
economy:
By minimizing the floor-to-floor height, the cost associated with mechanical services, stairs,
exterior building cladding can be significantly reduced.
The cost of formwork may be very high and is not given due consideration by the designers.
The cost can be reduced when the framing system is used repetitively (10 or more times) on
a structure.
This can be achieved by varying the amount of reinforcing steel and the concrete strength
within the column. This will allow for a single column form and will minimize the number of
variations to meet beam or slab forms.
Adopt uniform column layout
Uniform column layout results in simple formwork, which can be used repetitively from
floor-to-floor. Similarly, regular shaped buildings will be more economical than irregularly
shaped buildings with L- or T-shaped columns.
The saving in formwork and shoring costs will exceed any additional costs for concrete and
reinforcing steel. This will also provide a uniform ceiling elevation and minimize mechanical
service installation difficulties.
The high strength may reduce the column size or the amount of reinforcing steel required
for the column.
This will allow for earlier form stripping and will reduce total construction time.
Heavily reinforced columns and beams can be very congested with rebar, which prevents
the proper placement of the concrete. SSC maximizes concrete flowability without harmful
segregation and dramatically minimize honeycombing and air pockets.
The use of local aggregates and recycled materials in concrete makes it a 'green' product,
which is requested by environmentally responsible owners.
For a single structural member, the number of different sizes of bars should be kept to a
minimum.
Use the largest bar size that satisfies the design considerations
Use larger size bars in columns and smaller size bars in slabs. Larger diameter bars reduce
the number of bars that must be placed and minimize installation costs.
Bent bars increase fabrication costs and require greater storage area and sorting time on
the job site.
Avoid congestion of steel