Sie sind auf Seite 1von 124

(

(
..~'~

_ M,ANUAL ON
-THE PLANNING AN 0
. -DESiGN-OF
( HYDRAULIC TUNNELS
(

Publication No. 178

Central Board of Irrigation and Power


Malcha Marg, Chanakyapuri, N-ew Delhi-110021

- December 1984
(

(,
CONTENTS

1. Introduction, Classification and Scope 1-2


(
L 1 Introduclion
J.2' Classification
1.3 Scope

). Pl~·dfling and Im'cstigatioD 3-4


(
2.) General
( 2.2 Selection of tbe Alignment
2.3 Investigations
(
3. Geometric and Hydraulic Design 5-15

3.0 Geometric Design


3.1 Tunnei 'Cro'55-section
3.2 . Economic Diameter Studies
3.3 Losses in Hydraulic Tunnels ,/
3.4 Surges in Tunnels
3.5 Air-locking in Hydraulic Tunnels
(
4. Estimation of Rock Loads and Prc·ssurcs 17-24

4.0 General
4.1 Rock Pressu res
4.2 The Concept of Ground Arch and Terzaghi's Table
4.3 Other Methods of Rock Load Estimation
44 General Remarks

5. Excavation and Support Details 25-44


<. 5.0 General
5.1 Preliminary Works
5.2 Methods of Tunnelling
,, 5.3 Steps Involved in Tunnelling Operation
! 5.4. Sequence of Operations for Construction of Tunnels
- l 5,5 Tunnel Supports

-
~
,I
5.6 Rock Bolting and Shotcreting

6, Tunnel Lining 45-61

6.0 General
6.1 Concr~te Lining
6.2 Steel Lining

7. tunnel Grouting 63-66

7.0 General
-- ! 7.1 Types of Grouting
7.2 Process of Groutiog
7,3 Maintenance and Upkeep of Grouting Equipment
8. Tunnel Portals and Plugs

8.0 General
8.1 Tunnel Portals
8.2 Tunnel Plugs

9. Special Problems in Thnnelling 73-

9.0 General
I 9,1 Tunnelling'in Firm Ground
I- 9.2 Tunnelling Through Soft and Running Ground
: 9.3 Tunnelling Through Soft Water Bearing Strata
9.4 Tunnelling Through Squeezing Ground
9.5 Tunnelling Through Swelling Strata
9.6 Conversion to Circular Sections
9.7 Tunnelling Methods by Use of Machines
9.8 Excavation of Vertical Shafts
9.9'. Excavation of Inclined Tunnels

]0. Recent Advances in Tunnelling 87-10...

10.0 General
10.1 Rock Bolts
10.2 Shotcrete in Rock Tunnelling
10.3 Tunnel Design Criteria Using C.S.l.R and N ..G .I. Classification
. ~ .. " 10.4 Design of Tunnel Supports Using New Austrian Tunnelling
Method

Annexures 105-116

Annexure I
Annexure II
Annexure III
Anne"xure IV

Bibliography 117-118

'I

i
I
I'
.--

CHAPTER I

INTRODUCTION, CLASSIFICATION AND SCOPE

r
1.1 Introduction (2) Highway Tunnels
(3) Navigation Tunnels
Tunnels can be defined as underground passages made
without removing the overlying rock or soil. (B) Conveyance Tunnels:
( Even in ancient times underground structures present- 0) Hydroelectric power station tunnels-these sball
ed a challenge to man. Apart from natural caves, tunnels be referred to as "Hydraulic Tunnels" in all
driven to undermine fQr-tifications constituted an ·impor- further discussions .
... ...... tant and effective m~ns in !ncicm· warfare. Second to (2) Water Supply Tunnels
military purposes was the extraction of valuable mineral (3) Sewer Tunnels
resources from the hidden depths. Besides military and (4) Transportation tunnels in industrial plants.
mining purposes, the earliest uses of tunnels included
store houses, tombs, temples etc. More recent applica· Hydraulic tunnels can be further sub-divided inro the
tions are rout~s for roads, railways. canals, hydro-electric following categories ;.
power and water supply schemes.
(I) Pressure Tunnels
Through recent progress made in the field ofmechani· (2) free ftowing Tunnels
cal engineering equipments 'like pneumatic drills, im- (3) Free flowing·cum-pressure tunnels
proved drill bits, improvement in the quality and strength
of modern explosiv~s,..aQvent of sophjsticated clearance 1.2.2 Depending on their 'shape, tunnels rna): be classi-
machinery, highly' successful application of electrical fied as :
power for }jghting and ventilation, introducrion of new
techniques for supponing the tunnel, like the iJs~ of steel (l) D-shaped
ribs, precast and cast-in-situ concrete lining, cast iron (2) Horse-shoe shaped
lining in conjunction with pressure grouting, shotcreling (3) Circular shaped
( (4) Elliptical shaped
and rock bolting, and the applicarion of various forms of
shield for driving tunnels through water bearing strata (5) Square or rectangular shaped
etc.,· speed of construction has been greatly increased and The selection of the tunnel cross-section is influenced
danger to workmen has been drastically reduced. Tunnell- by:
ing has become much more simpler, safer and faster than
what it was, say fifty years ago. ~1an's ever increasing (l)"The clearances specified in view of the vehicles and
need for energy has opened up new possibilities of deve- materials lransportcd in the tunnel,
loping power through run·of-the-river schemes in difficult (2) Geological conditions,
and mountainous terrains where a major part of the (3) The method of driving the tunnel, and
water conductor system is in tbe tunnels. Most of the (4) The material and strength of tun.Del lining.
geologically competent sites have already been explored The first step in the design of a tunnel is the determi-
and presently man is facing the coallenge of making nation of the cross-section required for the trouble free
tunnels in difficult and unpredictable mountains. As such operation. For the mucking and hauling equipment rhat
it becomes more important to learn about the lates~ will be used during construction, the cJearaoce of tunnels
techniques in planning, desjgn and execution of tunnelling in which rail tracks are to be provided for· mucking
( operations. should be so designed that it should be at least 30 to
In this manual, the above three aspects in relatio~ to 40 cm larger than the clearance required for the open
hydraulic tunnels have been discussed in derails. line. This is to provide additional safety against con-
structional in-accuracies and deformation of l~e section
1.2 Classification due to rock pressure and presence of water. While deter-
minioo the size of the section, space required for veotila-
Tunnels may be classified according to their purpose, tion d~cts, compressed air pipes, supply cables for lighting.
shape and supporting arrangements. . power safety equipment etc. should be kept in mind.
1.2:J Dependjng on their purpose the following two The type of geological environment in whic~ the tunnel
malO groups of tunnels. may be distinguished: is to be constructed has got a considerable IOfluence on
(A) Traffic Tunnels: the shape of the cross-section. In hard .and infa~t rock,
tunnel sections excavated with an ar'ched roof may serve.
(l) Railway Tunnels In loose and weak rocks. a relatively considerable lateral
th·rust may be expected. The greater the magnitude of the lin'ed" tunnels. lftbe rock conditions are favoura'-
latera] pressure, the more advantageous a circular cross- the tunnel is required to be used for a short pet-
section would be. In such cases, selection has to be limit- time, e.g., a diversion tunnel constructed for the COP
ed either to a circular section or a borse-shoe shaped tion of a dam, the tunnel may be left unlined. H<r_
section. Economy of both the sections should be carefully . in mnst cases, hydraulic tunnels are invariably line~
studied before recommending either of it. cement concrete- (Plain Or reinforced) or shotcrch._
The method of construction must be chosen in accord- draulic tunneh: discharging silt-lad den water undt
ance with the prevailing site conditions, but may be in- velocities. (e.g., silt flushing tunnels) are requiret
fluenced by the availability of equipment, machinery and steel-lined. _.
material~. 1.2.4 Lastly, tunnels may also be classified based
Conventional tunnelling methods are suitable for driv- supporting arrangements. Under excellent rock ('-
ing horse-shoe and fiat arched sections, and arc less tions, the tunnels may be left unsupported. Oepf
economical for cir.:uJar sections. upon the type of supports, tunnels may be cJassifi{"'~
The shield method is restricted to circular sections only. (i) Tunnels supported by R.S.J. sections.
The free face method can be used for cross-secUons of (ii) Tunnels supported by Rock bolts.
any desired shape. (iii) Tunnels supported by Shotcrete.
The material used for tunnel ·lining also. influences tbe (iv) Tunnels supported by a combination of (j"--
shape of the cross-sections, si~e materia.ls capable of and (iii).
resisting eompres~,e: stre~e~:'?-QJY are limited to strue.,.
tures composed orafc.he'S such a:s horse-shoe, circular and 1.3 Scope
dliptical sections. Materi"als capab~e 'of resisting tensile
and bending stresses alike (RCC, Steel etc.) can be used This manual deals with the planning, design "'1
for lining sections of any desired shape. e;~ecution of Hydraulic tunnels used for Power H(.~""
1.2.3 Tunnels may also be c1assi6ed a~ "lined" or ('un- and Diversion works only.

2
CHAPTER 2

f PLANNING AND INVESTIGATION


(

2.1 General (ii) Presence of methane gas,


(iii) Presence of jointed rock acquifers confined by im-
The planning and investigation of Hydraullc Tunnels pervious strata which might lead to heavy inflow
shall include the selection of its alignment and the geo- of water.
logical competence along the alignment: selected. (iv) Squ'eezing rock conditions.

2.3 Ioyestigations
2.2 Selection of th'e AJig.menl -- .... "

( The investigations for selecting tbe route or alignment


While selecting the alignr~ent the following points of tunnels are done by means o( selective drilling and by
should be considered: making drifts and test tunnels to obtain as much in-
(i) 1/ should be the Shoriest Possible: This would formation as possible of the geological conditions pre-
ensure minimum losses and shall be economically vailing at the site.
cheapest. The mbst important phase of preliminary work in
(ii) 1/ should be Straight as far as Possible: Introduc- tunnelling is the careful exploration of geological con-,
tion of bends in tbe alignment shall involve losses ditions.
at all sucq J:>e~ds and th.e cost of lunnelling.wol\ld The purpose of geological explorations are as belo\\'" :
also increa~e.¥
(iii) It should be Easi/yAccessible: An easy access near (i) The deterJ1.lination of the origin and actual cell-
the entrance and exit to the tunnel becomes essen- dition of rock.
tial for tbe construction faciIitv. (ii) The collection of hydrological data and information
(iv) Careful selection of enrrv and -exit' locations with on underground g'lses and soil temperatures.
minimum -length and depth of approach cuttings (iii) The determination of physical, mechanical amI
and no weathered, loo~e fractured layers slope strength properties of rock along the proposed line
( towards ponals. of the tunnel, and
(iv) Determination of geological features which may
"However~ it is not always possible to foHow a straight affect tbe magnitude of rock pressures to be anti-
ahgnm~nt because of the follo\ving parameters affecting cipated along the proposed locations.
the deSign of hydraulic tunnels'
Explorations should be ex. tended to determine;
(i) Topography: There may nct b.: sufficient vertical
and/or lateral cover. - (;)Top cover,
(ii) Geological Sec/ion along the Alignment: It may (ii)Quality of subsurface rock.
show certain difficult strata through which tbe pro- (iii)Surface drainage conditions,
cess of tunnelling may be cumbersome and un- (iv) Position, type and volume of water and gases con-
economical. tained in subsurface rock,
(iii) Ground and/or Rock Water Loads along the tunnel (v) The physical properties and resistance to tunnelling
alignment may be excessive tbus increasing tbe Offered by the rock encountered.
( . overalj cost of the tunnel. Drilling provides us with valuable information for de-
(IV) !?~ck Jlfechanics Properties: The in-situ stresses, lineating geological profile all along the proposed align-
JOWl pattern. shear strength. unconfirmed com-
ment and also gives information about rock conditions,
pressive strength. shear modulus of deformation pattern of joints. presence of weak zo"nes, extent of rock
etc. may not be favourable along a· particular cover etc. which are very important parameters for as-
alignment. " certaining the stability of the 'tunnels and the types of
(v) Creep or Tectonic Movement along the Tunnel: The construction problems likely to be met with during
tunnel may be passing through active faults or line-
tunnelling operations.
aments which could cause collapse of the tunnel."
From the drilling data, the ground water levels and
In addition to the above, certain other parameters may Rock Quality Designation (RQD) can be obtained. RQD
a.'so affect the tunnel alignment because of tbe construe· is defined as the percentage of core samples longer tban
tlOD difficulties. These arc: . 10 cm recovered during drilling and is indicative of the
(i) Rock temperatures, rock characteristics and tunnelling conditions.
l
The investigations should also be Carried out to getber tain advance information about tunnelling conditionS.~;
additional information for determining the support con- Studies were.carried out to obtain rock properties liJr
ditions. stand up time etc. These are: Uniaxial and Point shear modulus, deformation modulus, behaviour of rock-::'<!
load compressive strength of rocks; spacing of joints; on formation of cavity, activity of thrust planes, measure'- -.
condition of joints; ground water conditions and orienta~ ment of creep etc. Tests were also carned out in expert _
tion of joints. Beiniawskie defined a classification system mental logging sections. Tbe results obtained "from tbese -
wherein different ratings are given for the above factors investigations proved to be of tremendous help in th ~
and tbe final rating for the panicular rock mass could be proper planning and execution of the. tunnelling opera- .
arrived at. This classification system bas been discussed tions. ,
in details in Cbapter 10. However. test tunnel section or drift can be justified~
The sequence of geological e'xpJorations referring to only in case it is supported by properly planned instru· .
tunnel constructions may be carried out in the following mentation programme. Tbe minimum programme sball':i
order: include:
(i) Investigation of general cbaracter prior to planning.
This sbould be done by tborougb field reconnaiss- (j) Closure measurements from boreboles,
ance on foot and sball include tbe bibliograpbical (ii) Stress mea~url~ID:ents-both in·situ stresses as weJl ;~_
and statistical survey of morpbology, petrograpby, as stresses In JOlOg,
stratigrapby and hydrology of tbe environment. (iii) Detailed geological logging, -.J!
(iv) Seismological observations from an observatory
(ii) Detailed geotechnical (Subsurface) investigation . located at the site.
parallel to planning but prior to construction. This (v) Installation of deformation gauges, and
would furnish information regarding pbysical (vi) Rock pressure measurements from Pressure Cells.
strength. chemical properties of rock to be pene.-
trated as well as their condjtion. The above listed measurements sbould also be supple-
(iii) Geologjcal investigations'should be continued dur- mented by angular and levelling measurements of pillars
ing construction. not only in the interest of check- constructed on the surface at typical location. J~:
ing design data but also for ascertaining whether The site of tbe test drifts may also be selected with a
tbe drilling method adopted .is correct or needs to view to use the same for future construction require- ~
be modified. ments of ad its. ~
One of the most -important items for investigations is Recently the underground construction Research
the determination of in-situ ·stresses. The in-situ stresses Council set up by tbe American Society of Civil Engineers
t
have a marked effect on tunnelling conditions. The vari- and National Sciences Academy of U.S.A. bas strongly
ous methods presently available for determining the in- . recommended such investigation and instrumentation
situ stresses can be obtained from any standard text book programmes wherever feasible particularly where new
. on Rock Mechanics. construction and supporting techniques-are contempla-
Pre-construction stage test tunnels or drifts can assist ted. It may be worthwhile to mention here tbat proper
designs and result in substantial economy. In India. at and systematic investigations and instrumentation could
Khodri Project, a test drift was driven 400 metres long give lot of information before band which could go in a .~ -
with cross drifts to intersect the intra-thrust zones to ob- long way to solve many oftbe varied tunnelling problems.

~
"
-
CHAPTER 3

GEOMETRIC AND HYDRAULIC DESIGN

...
· t;'1.0 Geometric Design sure but does not ·have goqd quality of rock and/or
adequate rock cover around it~ circular section is consi-
..f;::~,i,,'·T,·After the final alignment of the tunnel has been chosen dered to be most suitable,
',f'~ ~J~y carrying out detafled planning and investigations,.tbe
.~~_-~~"D.ext step for the designer. is tp choose an appropnate 3.1. 2 D-.shaped Section
~r-,- geometric section of tbe tunn~l. For doing thj~ the judge- D-sbaped section is found to be suitable in tunnels
'. 'ment of tbe designer. is required for makmg a fioal located in good quality, intact sedimentary rocks and
( ~:'''' choice of a section considering tbe prevailing site condt- massive external igneous, bard. compacted. metamorphic
~?t:-. ti'ons. No general recommendations can be made to. fit rocks where tbe external pressures due to rock and water
"; '·;1» each and every individual case but a few important are not very large and where the lining is not designed
·!·.. ::~~nd widely used geometrical sections for bydraulil; to carry any external or internal pressures. The main
-:~;~t_tunnels are discussed below: advantages of tbis section over horse-shoe section are the
.' .. - Tbe following shapes are generally used for bydraulic added width of the invert which gives more working noor
t~·~:-::-·tuDnels : space in the tunnel during driving and flatter invert which
helps to eliminate the tendency of wet concrete to slump
:tiC:~· (a) Circular section and draw awa~ from the tunnel sides. Tbe added invert
'.;\,~'? (b) D-sbaped secti"n width also perrnits the use of concurrent lining of· the
'~::;:~3~~ (c) Horse·shoe section tunnel wbich may not be possible for circular and horse-
~:{~.~2_f (0) Modified hors~-shoe section shoe tunnels of the same dimensions.
'-':-i~~i~~'i Sometimes' egg-shaped and eggilipse sections are also
· .·~,7!~'!il)scd. 3.1.3 Horse-shoe and Modified Horse·shoe Sec/ions
( ";~'~f"''''
~.~~~,~:;-, These sections are a compromise between circular and
· -~.": ~l .Tunnel Cross-Section D-shapcd sections. These sections are structurally strong
( J,,=' r to withstand external rock and water pressures. Where
::Cross-section of a tunne! depends 00 tbe following a moderately good rock is available and the tunnel has
( ctors: to resist internal pressures also, these sections are found
to be most suitable. Where advantages of a flatter invert
Geological conditions. prevailing along the align- are required for con~tructioDal ease, modified horse-shoe
menl, sections are advantageous. These modified borse-shoe
Hydraulic requirements. sections also afford easy.change over to circular sections
{iii) Structural considerations, and with minimum additional cost in rea~hes where rock
(iv)-- Functional requirements. quality is poor or rock cover is inadequate.
·il-A·- final cboice of tbe section is made by carefully figure 3.1 sbows tbe geometrical properties of circular,
.ctutinizing the above four factors. ·However. Once a .' D-shaped. horse-shoe and modified horse-shoe sections
_.;.... '. ~ction has been adopted. it is not binding on the part respectively.
~)~;r.the designer to stick to the same section throughout
'. -~Jength of the tunnel. There are many instances where 3.2 Economic Diameter Studies
~:Sections have been modified during the course of
Q,p$truction of the q.mncl. Such contingencies should, Having finalised the alignment and the- geometrjc
owever, be avoided as far as possible so as to fulfil tbe shape of tbe tunnel, tbe next step is to work out t be
QotractuaJ obligations. economic djam·eter .of tbe tunnel. The following factors
~the general requirements and design parameters for should be considered while working out tbe economic
~.few widely used shaped are discussed below: diameter:
•• >
I'i
1.1 Circular Section (a) Velocity requirements,
(b) Head loss in tunnel,
'The circular section is most suitable from structural (c) Interest on capital cost of tunnel,
.nsideratioDs. However. it is difficult for excavation, (d) Annual Maimenance cbarges,
~icularly where the cross-sectional area is small. In a (e) Whetber lined or unlined, and
;~e where. the tunnel is subjected to high internal pres- (0 Cost of gates and tbeir boists.
- - - - - - - - -. .
-J

Permissible velocity in a concrete lined tunnel is -of Darcy-Waisbach formula:


the order of 6 mjsec. Higher yelocities are allowed for
steel-lined tunnels. For diversion tunnels and tunnel IL
hf~-X--
V' (
spillways tbere is no limitation on the maximum per- D 2g
missible velocity provided that the lining (or the surface, where hr= head losss 'due to friction in ro,
if the tunnel is unlined) is adequate to withstand the f = friction coefficient,
velocities which would occur. The maxinlum permissible L ~ length of tunnel in m.
velocity· shall be limited to approximately 3 mjsec in the D = Diameter of tunnel in ill,
case oftuonels conveying suspended abrasive materials. V= Velocity of water in the tunnel in m/s and
Thus, for making economic diameter studies, a per- g = acceleration due to gravity in m/sec 2.
missible velocity is assumed in the tunnel and losSes are
calculated as detailed in para 3.3. An example for work- The friction coefficient f depends upon the Reynolds ~
ing on the economic diamete-r of a tunnel is given in number and the relative roughness K,jD where K, i5 the
Annexure 1. equivalent sand grain roughness and its. value depends
upon the surface characteristics. For new concrete lined
tunnels using steel forms the va1ue of K1 varies from Y
3.3 Losses in Hydraulic Tunnels 0.015 mm to 0.18 mm. For welded steel-lined tunnels,
the value of K, ranges from 0.05 mm to 0.1 mm.
Following are tbe tYfles g.f.losses generally occurring Because of fluctuations in tbe load demand. the wr~.
in a .hydraulic tunnel : -,
bines keep an accepting or rejecting water. This causes
(a) Friction Loss the flow in the water conductor system to be turbulent.
(b) Trash Rack Loss For turbulent flow and in the range of Reynolds Dumber
(c) Entrance Loss between 3000 to 10000 (normally expected in concrete
(d) Transition Loss lined and steel-lined tunnels), the friction factor f is
(e) Bend and Junction Loss calculated by using the formula:
(f) Gate Loss
I I
(g) Exit Loss
Jf=2.010~:O 2£.+1.74.
Fach of tbe aboye,losses ar~ discu~ssed in detail belQ.w :
wher< 1= friction factor (for use in Darcy formula)
3.3.1 Friction Loss
For tunnels flO\ving full friction may be calculated E·= re Ialive . h ness. = K,
· roug D
either by using Manning's formula or Darc)' \Vaisbach
formula: For unlined tunnels. the value of I depends upon the·
Manning's For.IDula : variation in cross-sectional area obtained in'the fit:id.
The frictiomil los5 factor may be estimated by measuring-
V2N'-L
cross-sectional areas at intervals and determininJ2 the
hr= R~f3 J
value of I by the following formula: -
where llf= head loss due to friction in ill,
1~0.00257 8
v= velocitv of water in the tunnel in m!s
L = length of the tunnel in rD, .
wbere
R= ··
fa d·IUS ( W·
h y d rau IIe Area·
d )' In
. m.
eue penmeter . A99 = area corresponding to 99 percent freq ueney,
N= Rugosity coefficient. and
~or concrete lined tunnels the value of rugosity-coeffi- A I = area c?rrespondiog to I percent frequency
Clent N varies from 0.012 to 0.018.
For tunnels of non-circular section, the diameter iJ in
For unlined tunnels. the value of N depends upon Darcy's formula shall be replaced by 4R where R is tbe
tbe nature of rock and the quality of trimming. Recom- hydraulic mean radius (A!P). The Darcy'sformula sball
mended values of lVfor various rock surface cond·itions thus read as follows:
are given below:
h·=~-/ LV'
Surface CharaCTeristics Vallie 01 N , ,
8aR
Minimum Maximum For tunnels flowing partly full. the head loss du" to fric-
Very rough tIOn will be calculat~d by usin o Mannino's formula oiven
0.04 0.06 earlier. ~::..::>
Surface trimmed 0.025 0.035
Surface [rimmed and
invert concreted 0.02 0.03
3.3.2 Trash Rack Loss
- - - - - - - - - - - _ .------_. Tunnel- openings are provided with (rash racks at the

6
~
t
t . take to prevent the entry:of tloating debris into' the Where D is rhe venical height of the tunnel down-
~~nnel. Where ma.ximuDl 1055 values are des-ired, it is stream from tbe entjaoce.
t sual to assume 50 percent of the rack area as clogged. The above three types of entrance transitions are
~his would result in twice the velocity through the trash shown in Figure 3.2.
t rack. Since the 1<:>55 varies .dj~ec[ly as tb~ square ?f tbe Entrance ioss <hall be computed by the following
velocity, it is desIrable to lImIt tbe velocIty a~ ~he mtake formula:
to about 1 ill per second for the· WOfst condlttOl1s. For
maximum trash rack losses, tbe -racks may not be consi- V'
he=Ke ?
dered clogged when computing the head loss or the loss -g
may be neglected altogether. The trash rack loss sball where h~ = head loss at entqmce,
be computed by using the following formula: . Ke = loss coefficient for entrance.
V' V ~ velocity of flow
1t,=Kt - g= acceleration due to gravity.
2g
where ht trash rack bead loss, The value of the K e for circular bell mouth en~rance
varies from 0.04· to 0.10 with an' average value 01'0.05 ~1nd
:0:

)(, = loss coefficient for trash rack,


that for square bell mouth entrances varies from 0.07 10
= 1.45-0.45 .0!
~~':' .:. at
_ (0a,.0
)'
0.20 with an average value of 0.J6.

3.3.4 Transitioll Loss


G" ~ ne~ area tb;~ugh the trash "rack bars,
( a, = gross area" of tbe opening' In a hydraulic tunnel transitions are often required Cit
V= Velocity of water in net area, and the intake, junctiC'ns with de~silting chambers, gate
g = acceleration due to gravity. galleries, surge shafts etc. and at outlets. All these tran-
sitions cause head loss in tunnels. To minimise the head
loss: and to avoid cavitation tendencies alon o the tunnel
3.3.3 Entrance Loss surfaces. the transitions should be gradual./;) Transition.;
To minimise th~ head losses and to avoid zones where can either be for contraction or for expansion.
cavitation pressures may develop, the entrance to a pres- For contractions, the maximum- convergent dngle
sure tunnel should be steam-lined to provide a gradual should not exceed that given by the relationship
and smooth changes in ftl?w. For best efficiency th.e shape
of the entrance should stimulate tbat of a jet discharg- I
in~ !nto ai.r and should guide and support the jet with tan·x = Ti
mlDlmum mterference until it is contracted to the tunnel
dimensions. where IX = ~mgle of the tunnel wall surface with resp..:~ct
( For a circ:uJar tunnel tbe bell-mouth entrance shape . to Its centre line,
may be approximated by an elliptical entrance curve . V
given by tb~ equation: U=2.n arbltrar.y parameter=----=-
,/gD
Xl _ yl _

(0.5D)' + (0. I 5D)2 - J Vend D = average of the velocitie, and diameters '.:it tbe
beginning and end of the transitions. and
where x and yare the coordinate axes and D is the g = acceleration due to gravity,
tunnel diameter at the end of entrance transition. For
bead race tunnels sjnce a gate is essential at the entrance Expansions should be more gradual than contractions
the opening shall be either rectangular or square. Fa; because of the danger of cavitation where sharp changes
such an opening the elliptical curve for the entrance in the side walls occur. Expansion angle should be based
shall be approximated by tlie equation: upon the following relationship:

x:! T tan a; =
I
2U
D' + (6~33i:i)' ~I
. Where D is the vertical height of the tunnel for defin- The notations are the same as giH'n for contrilc,ions .
mg the top and bottom curves and is also the horizontal It has been noticed that head loss increase"s rapidlv
width of the tunnel for defining the side curves. in the case of expansions where the angle a; exceeds J 0;-".
Hence, for r.ll hydraulic tunnels and for pressure tunnel..
. For.a rectangular entrance with the bQttom placed
in particular. angle 0: must be limited to 10°. .
even With the upstream floor and with curved side piers
at each side of the entrance openings, both the boltom \Vhere a circular tunnel flowing partly full discharoes
and side contractions will take place at the top of the into a chute or channel, the tr'3mition from the circular
openJDg. For such a case, the top curve may be obtained section to tbe one with flat bottom rnav be made either
from the equation: . within the tunnel itself or in the optm channel down-
stream from the tunnel portal. The length of the transi·
;\:2 y~ tion for exit velocities of upto 6 m/sec may be obtained
D' + (O.67D)' by using the relationship:

7
L= 2VD . Gate Loss: If t.he entrance to a tunnel is designer
3 properly the velocity of flow'would be approx. 1m/sec.......
In such a case no gate loss need be considered. How·
where L = length of transition in fi, ever, there will be head loss due to the gate groove and-
v= exit velocity in m/sec, the same sball be given by :
D = tunnel diameter in m.
V'
For expanding transitions. the head loss is given by tbe hg=Kg2
. g
following formula:

h'~K'(~:-~n
where hg = gate head loss in m,
Kg = loss coefficient for gate,
V = velocity of flow in m/sec, and
where hi = head loss in expanding transition in m, g=acceleration due to gravity in m/sec2 •
V, = average velocity in m/sec at the beginning of
transition . The value of Kg can be assumed to be 0.10. For partly
V2 = average velocity in m/sec at the erd of tran- open gates, the value of Kg will depend upon the top -
sition contractions and it varies from 0.20 to 0.10.
g = acceleraHon due to gravity in m/sec2
K e = loss coefficient for expansion 3.3.7 Exit Loss
Where no recovery of velocity head will occur, such as
= 3.50 (tan ;)\'22 '. . .,. where the release from a pressure tunnel discharges freely
or is submerged or supported on downstream floor, the
IX = angle of tbe tunnel wall surface with respect velocity bead loss coefficient K ex shall be taken as unity. --!

to its centre line. Head loss at the exit would be calculated by using the
formula:
For contractions, the head loss shall be computed using . V2 I
the following formula: hex = KU,2g ,1
h,=K, (~;-m where h~x = exit head loss in ill,
Kt:x. = loss coefficient for exit, 1
where Ire = head loss in
contracting transition in m. V = exit velocity in m/sec;
g= acceleration due to gravity in mjsec 2 . '1
V 2 = velocity in contracted section in m/sec.
VI = velocity in. normal section in m/sec,
g = acceleration due lO gravity in rn/sec 2, 3.4 Surges in Tunnels 1
K c = loss coefficient rOf contraction.
The value of Kc varies from 0.1 to 0.5. For gradual
Water hammer is created in long closed tunnels by the
sudden closure of the turbine gates. The water h·ammer
l
contractions where the flare angle does not exceed 10° pressure provides the necessary force to retard the flow
the value of K, shall be taken as 0.1. in tunnel when load is rejected by the turbine. For very 1
long tun"nels, the water hammer corresponding to normal
3.3.5 Bend and Junction Loss operation of the turbine may be very great and may l
Bends and junctions in bydraulic tunnels are unavoid- require extra ordinary strength of the tunnel to with-
able owing to their functional and constructional require- stand it and tbe violent flUCTuations of pressure in the }
ments. These bends and junctions also cause loss of tunnel may seriously interfere with proper turbine regu-
head which must also be computed. lation. Similarly, for sudden opening of the gates, the
Bend Loss; Bend Joss depends upon the relative resulting negative water hammer, or reduction of pres- l
roughness Ks/D· and rid ratio, where Ks is the absolute sure, provides the necessary force to accelerate the water
roughness, D is the diameter of tbe tunnel and" r is the and is correspondingly objectionable for very long
radius of tbe bend. The- head loss due to bend is given tunnels.
by: The simplest means of eliminating the positive and
negative water hammer pressures is to provide a surge
V' tank at the lower end of the tunnel. The steady state
h.~fV,-
2g water level in the surge tank fluctuates up and down as
knowing lhe values of K,ID and rid, the value of K. for the turbine rejects or accepts the load. With the help of
90" bends may be Obtained from Figure 3.3 and that for digital computers it is very convenient to calculate the
bends with deflection angles other tban 90° from maximum and minimum pressures. occurring all along
Figure 3.4. the length of the tunnel. The tunnel should be designed
to withstand the maximum excess pressure that is likely
to occur. Similarly. it is very essential to determine the
3.3.6 Junction alld Branching Loss. sub· normal pressures in the surge tank for sudden accep-
"Head los~ at the· tunnel junctions and branching can tance of the .load. Care should be taken that the pres- "

be obtained from Figures 3.5 and 3.6 respectively. sure in the tunnel never becomes neg~tive as, under

8
sl1<;h conditions. the tunnel is likely ,to collapse. For The presence of air in a pressure tunnel can be a
head race tunnels flowing full, maximum pressures occur source of grave damage as detaUed below:
at the time of load rejection while minimum pressure (a) The localization of an air pocket at the high point
can be expected at the time of load acceptance. However. iri a tunnel or at a cbange in slope which occasions
for tail race tunnels flowing full, minimum pressures exist a marked loss of head and dimunition of discharge.
at the time of sudden load rejection whereas maximum (b) The slipping of a pocket of air in a tunnel and its
pressures may occur at the time of load acceptance. rapid elimination by an air vent can cause a \vater
Hence, to meet the safety requirements of a tail race hammer.
tunnel, a surge tank may be provided downstream of
tbe power bouse also.
(c) The supply of a mixture or air and water to a tur-
bine affects its operation by a drop in output and
efficiency thus adYersely affecting the operation of
3.5 Air Locking in H)'draulic Tunnels generator.
The following steps are recommended to prevent the
Air may enter and accumulate in a tunnel by the entry of air in a tuonel :
following measures: (a) Intakes should be designed properly. A shallow
intake is likely to cause air being sucked in.
(a) During filling,· air may be trapped along the crown (b) Throughout the length of tunnel the velocity should
at high points or at changes in cross-sectional size remain constant or increase towards tbe outlet end.
or shape. (c) Panial gate openings resulting in hydraulic jumps
(b) Air may b~entrained at intake either by vortex should be avoided. (
action or by means of bydraulic jump associated (d) Traps of pockets along high points and crown
witb gate opening, and should be avoided.
(cl Air dissolved in the flowing water may come out (e) Thorough and careful surge analysis sbould be
of solution as a result of decrease in pressure along carried out to sec that at no point on the tunnel
the tunnel. section, negative pressures are developed.

!
.i•
1
~ 1
J

i

~l
~;j

~\g~
{,
--,)'~
'Ie 5

\
- -
,, ) ; , (
,...
l.i" Ji
- II ) , j' (
....

~~~_t$f*:W_~tI'aCc'-
. .' .
1;:;~}:.h~ -_,:::~'.,
.V"" ~.::.....-~~_....~,..•. " )

PAY- LINE PAY - LINE

_L"'N'''O'
-- ~ M.lN. EXCAVATION

Q/ \','a ))(.O
--.

CIRCULAR D- ,SHAPED HORSE - SHOE

A = 0.7854 02 A= 0·005 0'2 A= OdS203 D'

.... P = 3· 1416 0 P = 3·58 0 P = 3' 2157 D

r =!o.P = 0, 25 0 r= ~= 0·2528 D r =
.A
1> =0'25311 D

~~~e;;;--PAY- LINE
t:>·~~MIN.EXCAVATION LINE

r = 0,01l7580 R
R = RADIUS OF HYDRULICALLY EOUIVALEN T CIRCLE
AREA OF SECTION = 3.253 572 r 2
PERIMETRE OF SECTION = 0',426 334 r
HYDRAULIC RA O,.US ~0·50l5287r

A = 0·780 7715 r
8 = 1.561 553 r
9 = 31°_ 22~ Ot 1/

8
I• •I
MODIFIED HORSE - SHOE
CII':. '-::I:. I I':. CI""\~A I:" TOIl"" ODf""'\OCDTI t:"c
~ XZ yZ =1
X2 y2 ----"
0'
+ 10·3301 l
0·'0 fO.;Q'i:' +1O"'Oilf"

,I
I
I
I
t
I
I

o
I'l
t

'"Z
..
o
...:,".
o

...~
-'

I,
o"
,, o
~
,
-------, I o
o I
I'l
I •. 0'50 I I'l
I

_____ J
I o
CIRCULAR TUNNEL WITH BELLMOUTH INTAKE
1• 0 t I
f-"
N RECTANGULAR OR SQUARE QPENING
I• 0 • I 2yZ
_ _ _ _ _ _ _ _ _ -,/r----::=_- X +
[)2 1O·670t2
=1

...o
'o"

...o
'"

RECTANGULAR OR SauARE OP£NING WITH BOTTOM AND SIDE FIG· 32 TYPES OF TRANSITIONS
CONTRACTIONS SUPPRESSED

~.~,!~;.)'~,~!,\~,~I!;'t'~T'~'~
, .~
.. . ~ ~ ~
, ~I \ -, . liIof.I ~. ""l!
,(")12--------------------- I

-' o
FIG. 3-3 HEAD LOSS COEFFICIENT FOR 90 BENDS
0·6

+ y2
0·5 t -
\ - ~ -0. hf = K 29
11 \ / ·x
III
\ <
II ~50D
0,4
1\
~'- Y

t
K 0.3
II
\ \

,'\
\\ \ \ j
I
I
1\
\, f"-.! i
\' " "- I
~ "- ..........
0·2 0,0020) .
:~ "
-- ---
' ' . ' ............
-.: " , ~- O· 0015 K.
. ~ :: ......
I~
r-
- ----- --- ~

- -
f--
00010
0.0005
--
0
0·1 SMOOTH
..
'-

°'°0 1
------
2 3 4 5 6 7 8 9 10
r
o
.j<MINIMUM STRAIGHT LENGTH

FIG. 3·4 HEAD LOSS COEFFICIENT FOR BENDS OTHER THAN 90o

- L
;

1
I
,
o 7·5 /5 22·5 30 37·5 45 52·5 60 67·5 75 82.5 gO

I ---,J:.. 0 _ _....._

I .j< MINIMUM STRAIGHT LENGT-H

I.
I
I 3

,i
- I
I

---------------
-'c., ,.
o
'.'
~O'o
~q VD
, ,
"'0,
'b.'o , "-hf
- 2
~
,, HEAD LOSS AT JUNCTION (hfl'Ki

WHERE

,I
l
K IS RESISTANCE COEFFICIENT, AND -'-

q6,Vb ,D b ANDq,V,D ARE DISCHARGE. AVERAGE VELOCITY AND-

DIAMETER OF AUXILIARY AND COMBINED PIPES RESPECTIVELY.


,
! ....
A

ANGLE OF Qb/q=O'3 q b/q:::t O·~ qt>!q=O.7 qt>!q:I.O-


~~ ~~ , '" , A~_~
CONVERGENCE
SHARP ROUNDED SHARP ROUNDED SHARP ROUNDED SHARP ROUNIUD
IJ IN DEGRE-ES EDGED EDGED EOGED
EDGED

(I) (2 ) (3) (4) I~ l (6) (7) (B) ( Il )

Db:0·580 Db:D. ~:()'~BD ~:0.58DDtf0..s8DD~0.58D ~:D Db: 0

50 Vb :0.IlV-V :0.3V Vb: 1.5V Vb<I.~V Vb :2.0V V b :2.0V Vb: V Vb: V


{ b
K :0.475 K: 0·33 K:O·637 K:0.553 K:0.715 K :0.15~~ K:0·1545 K: 0.~3

{
Db:0'~8D Dtr0.~8D l\,:0.5BOCVO.580 ~:D ~:D Db:D Db: 0
45 V-b:O.IlV V b :O.9V Vb:I~V- V-b:1.5V V-b:0.7V- Vb:0.7V- Vh:V- V-b: V-
K: 0.2 K :0.2 K:O.42~ K:0.425 K=0540 K:O.52~ K:O.38 K:0.38

NOTE - THESE VALUES ARE BASED ON THE EXPERIMENTS CONDUCTED AT THE HYDRAULIC LABORATORY
OF THE TECHNICAL UNIVERSITY OF. MUN-ICH, GERMANY, FOR MOST EFFICIENT CASE.

I.

Das könnte Ihnen auch gefallen