Namendra Anand
Sr. Engineer (BM/RM)
Ramagundam Super Thermal Power Station
NTPC Limited
nanand@ntpc.co.in
Ramagundam Super Thermal Power Station
NTPC Limited
Milling system maintenance is a challenge
as it requires to use all kinds of
maintenance practices to run the system
effectively….
Gear Box
PROBLEMS FACED
&
IMPROVEMENT ACTIONS TAKEN
These resulted in
reduction of premature
failure of grinding rings.
AT
Preventive Maintenance.
Predictive Maintenance.
Proactive Maintenance.
Planned maintenance
(Overhaul/Servicing)
Break Down Maintenance
Life Assessment.
OEM Recommendation
Site Experience
After SRCM, this frequency and scope have
been revised. This is mainly based on failure
modes.
Technologies in use :
Vibration analysis
Infrared thermo graphy
Motor current signature analysis
Wear debrisanalysis
Practices:
• Pre-overhaul
• During overhaul
• Post overhaul
Pre-overhaul:
• Preparing Engineering declaration of all the
units as per OPI guidelines.
• Identification of resources ( materials,
contracts & T&P).
• Review of the materials & contracts status.
• Distribution of engineering declaration to all
concerned before the start of overhaul
During overhaul:
Ensuring proper isolation of the equipments
before start of the work.
During overhaul:
• Safety survey & training to agency personnel.
• Constituting Knowledge team
• Daily review meeting
• Review of works planned & actual done.
• Feed back to all concerned.
Post-overhaul:
• Preparing executive summary
1. Daily report
2. Weekly report
3. Monthly report
4. Yearly report
5. Unit overhauling report