CRONOGRAMA SEMANAL PROYECTADO COMUNIDAD DE SUCA

FECHA: 02/09/2019 a 07/09/2019

ITEM DESCRIPCION Und LUNES MARTES MIÉRCOLES JUEVES VIERNES SÁBADO

MOVIMIENTO DE TIERRAS tramo m tramo m tramo m tramo m tramo m tramo m


EXCAVACION MANUAL DE ZANJAS m3
EXCAVACION MANUAL DE ZANJAS CON MAQUINARIA m3
NIVELACION Y PERFILADO DE ZANJAS m
PREPARACION CAMA DE APOYO m
RELLENO DE ZANJA CON MATERIAL SELECCIONADO
RELLENO DE ZANJA CON MATERIAL PROPIO
SUMINISTRO E INSTALACIÒN DE TUBERIAS
TUBERIA PVC 110 mm C-7.5 SAP m
TUBERIA PVC 90 mm C-7.5 SAP m
TUBERIA PVC 75 mm C-7.5 SAP m
TUBERIA PVC 63 mm C-7.5 SAP m
TUBERIA PVC 48 mm C-10 SAP m
PRUEBA HIDRAULICA
PREPARACION PARA RUEBA HIDRAULICA m
PRUEBA HIDRAULICA DE TUBERÍAS m
SUMINISTRO E INSTALACION DE ACCESORIOS
SUM. Y COLOCACION DE ACCESORIOS PVC SAP Und
DADOS DE CONCRETO
CONCRETO f 'c=140 kg/cm2 m3
MURO SECO EN PENDIENTE
CONCRETO PARA MURO SECO f 'c=140 kg/cm2 m3
CRONOGRAMA SEMANAL PROYECTADO COMUNIDAD DE CUYPAMPA

FECHA: 09/09/2019 a 14/09/2019

ITEM DESCRIPCION Und LUNES MARTES MIÉRCOLES JUEVES VIERNES SÁBADO


MOVIMIENTO DE TIERRAS tramo m tramo m tramo m tramo m tramo m tramo m
EXCAVACION MANUAL DE ZANJAS m3
EXCAVACION MANUAL DE ZANJAS CON MAQUINARIA m3 (CC-19)-(CRP- 20 (CRP-01)-(CR 60
NIVELACION Y PERFILADO DE ZANJAS m (CC-19)-(CRP- 20 (CRP-01)-(CR 60
PREPARACION DE CAMA DE APOYO m 7-10 260 TL-(CC-19) 140 (CC-19)-(CRP- 20 (CRP-01)-(CR 100 10-11 140
RELLENO CON MATERIAL SELECCIONADO m 7-10 260 TL-(CC-19) 140 (CC-19)-(CRP- 20 (CRP-01)-(CR 100 10-11 140
RELLENO CON MATERIAL PROPIO m 7-10 260 TL-(CC-19) 140 (CC-19)-(CRP- 240 (CRP-01)-(CR 60 (CRP-01)-(CRP 300
SUMINISTRO E INSTALACIÒN DE TUBERIAS
TUBERIA PVC 160 mm C-7.5 SAP (CC-19)-(CRP- 20 (CRP-01)-(CR 40
TUBERIA PVC 110 mm C-7.5 SAP m (CRP-01)-(CR 60
TUBERIA PVC 90 mm C-7.5 SAP m 7-8 100
TUBERIA PVC 75 mm C-7.5 SAP m 8-10 220
TUBERIA PVC 90 mm C-10 SAP m
TUBERIA PVC 75 mm C-7.5 SAP m
TUBERIA PVC 63 mm C-7.5 SAP m
TUBERIA PVC 48 mm C-7.5 SAP m

PRUEBA HIDRAULICA
PREPARACION PARA RUEBA HIDRAULICA m 4-8 330 TL-(CC-19) 140 (CC-19)-(CRP- 240 (CRP-01)-(CRP 300 10-11 140
PRUEBA HIDRAULICA DE TUBERÍAS m 4-8 330 TL-(CC-19) 140 (CC-19)-(CRP- 240 (CRP-01)-(CRP 300 10-11 140
SUMINISTRO E INSTALACION DE ACCESORIOS
SUM. Y COLOCACION DE ACCESORIOS PVC SAP Und
DADOS DE CONCRETO
CONCRETO f 'c=140 kg/cm2 m3
MURO SECO EN PENDIENTE
CONCRETO PARA MURO SECO f 'c=140 kg/cm2 m3