Beruflich Dokumente
Kultur Dokumente
Contractor
Project
Title
A 1 of 9
Doc. No.:
METHOD STATEMENT FOR Rev. No.
STEEL PIPING INSTALLATION A
Page 2 of 9
Revision Record
TABLE OF CONTENTS
Doc. No.:
METHOD STATEMENT FOR Rev. No.
STEEL PIPING INSTALLATION A
Page 3 of 9
1. GENERAL............................................................................................ 4
2. PURPOSE............................................................................................ 4
3. WORK SCOPE.................................................................................... 4
4. REFERENCES..................................................................................... 4
5. RESPONSIBILITY................................................................................ 5
6. WORK SEQUENCE............................................................................. 5
9. SAFETY............................................................................................... 8
Doc. No.:
METHOD STATEMENT FOR Rev. No.
STEEL PIPING INSTALLATION A
Page 4 of 9
1. GENERAL
The proposed project consists of one (1) combined cycle power block (2+2+1), comprising
of two (2) gas turbine and generators (GTGs), two (2) fired heat recovery steam generators
(HRSGs) & one (1) steam turbine and generator (STG), and Balance of Plant (BOP)
equipment.
The Power Plant will be equipped with GT capable of firing on natural gas. The exhaust gas
from the GT is fed to a HRSG, which is designed as a horizontal triple pressure, natural
circulation HRSG with re-heater. The HRSG will be supplied with supplemental firing for
meeting the load demand.
The ST will be a reheat condensing turbine. The exhaust steam is condensed in a water-
cooled condenser with mechanical draft wet cooling tower using river water from the River.
The GT, ST and Generator will be of a multi shaft configuration, with a separate Generator
for GT’s and ST.
2. PURPOSE
3. WORK SCOPE
The scope of work covered in this Method Statement is as follows;
3.1 Perform fabrication, erection, and field installation of steel piping as indicated the
related drawing and specification.
3.2 Checking elevation, leveling and alignment, where required
3.3 Any field touch up painting of pipe, and support
4. REFERENCES
All the Work must be performed according to the following as listed and the most relevant
codes & standards with good practices.
5. RESPONSIBILITIES
5.1 Joint Operation QA/QC Manager is responsible for the implementation of all required
control activities and shall ensure that the procedure is established related with this
particular job.
5.2 Joint Operation QA/QC Engineer shall execute all required quality activities such as
inspection and test in coordination with the Owner’s representative to obtain necessary
approval, and responsible for preparing all necessary check list and documents
required for carrying activities.
5.3 Piping Engineer shall ensure that the job is performed according to the latest
revision drawings and inform any problems, mismatches discovered at field to the
Piping Manager. Piping engineer is responsible for incorporating all safety
procedures, work permit requirements and all related quality control procedures.
Piping engineer shall coordinate the whole job of all other related departments
towards the end of the activity.
5.4 HSE Engineer with his team shall ensure that the work will be implemented properly
and
effectively enough to maintain safety requirement on site and train persons as
necessary.
6. WORK SEQUENCES
6.1 General
6.1.1 The work area shall be cleared of any obstacle, dust, cement or inappropriate
tools.
6.1.2 All topographical bench marks shall be marked prior to the commencement of
work.
6.1.3 Extreme care should be taken to prevent any damage during lifting to its
location.
6.1.4 A sequence and work process that includes cleanliness inspections and a
deficiency correction shall be implemented, that maintains cleanliness and that
minimize the need for cleaning activities.
6.1.5 Where conflict exists between this document and drawings and/or specification,
the report will be issued to clarify and resolve it.
6.6 WELDING
6.6.1 Welding shall be performed in accordance with the approved welding
standards and procedures
6.6.2 Welding shall be tested and qualified by QA/QC department prior to
commencement of welding.
6.6.3 No welding shall be done if there are impacts of any rain, snow, sleet, or high
wind in the working area. However, welding work shall be done provided
that suitable protection is installed
6.6.4 Welding bead shall be carefully laid to avoid undercut, pin hole, slag
inclusion, crater, imperfect penetration, etc.
6.6.5 Welding rod shall be properly selected according to the kind of the steel to be
welded
6.6.6 Grounding wire shall be firmly fastened by screw or clamp to the material to be
welded, at the position as near as possible to the welded part
6.6.7 Spatter, slag, etc. of welded part shall be thoroughly removed
6.6.8 Jigs (bridges or clamps) shall be provided in minimum number necessary for
setting up
6.6.9 Jigs (bridges or clamps) shall be used made of material which quality is the
same as or better than the base material
6.6.10 In a fit-up, select welding rod of appropriate diameter for a tack welding so as
to fit the root opening
6.6.11 Before welding first layer, both ends of tack welding bead shall be
sharpened with grinder in order to allow complete fusion
Doc. No.:
METHOD STATEMENT FOR Rev. No.
STEEL PIPING INSTALLATION A
Page 8 of 9
6.6.12 Bridges shall be removed after welding. To ensure parent material shall
not be damaged while removing
6.6.13 Repair
Unacceptable discontinuities shall be completely removed by chipping,
gouging, grinding, or other methods (for the type of material being repaired)
to clean. Repairs to correct weld defects shall be made using the same
WPS used for the original weld or other previously authorized WPS. The
repaired area shall be re-examined using the same examination method
and procedure by which the defect was originally detected
7.1.3 The completed inspection records for the installation of rotating equipment will
be maintained as a Quality documents.
7.1.4 All inspection, measuring and test equipment shall be identified with a suitable
number or tag to show the calibration status. The calibration records shall be
easily traceable to the device.
7.1.5 Before witnessing the inspection, test equipment identification tags shall be
checked and verified that the test equipment has been properly kept and
calibrated.
9. SAFETY
9.1 The safety program as defined the Health, Safety and Environment Plan shall be
implemented on a day to day basis.
Doc. No.:
METHOD STATEMENT FOR Rev. No.
STEEL PIPING INSTALLATION A
Page 9 of 9
9.2 It is required that site manager and all superintendent clearly communicate HSE
expectations at all project meeting and demonstrate a personal commitment to follow
the HSE policy at all time.
9.3 The unsafe work practice and conditions in the work place shall be immediately
identified and eliminated through the use of analytical techniques such as the risk
assessment.
9.4 Build a team safety mentality where each worker contributes to the effort and each
superintendent is fully aware of the capabilities and limitations of their team.
9.5 All tool and equipment shall be used in accordance with the manufacturer’s
recommendations, required tool guards in place, and maintained in good working
order.
9.6 Where appropriate, all employees shall require to wear eye, ear, head & face, foot
protection outfit.
9.7 Work areas shall be kept clear and unobstructed at all times. Scaffold shall be
developed and modified under the proper supervision.
9.8 All personnel shall wear safety harness / lanyard system if they work at heights where
the fall exposure is more than 6 feet or 2 m.
9.9 All certificates and permits related the particular job shall be kept at site for verification.