JOB TITLE / AIM: JSA for Cathodic Protection for Oily Water Line
JSA DATE: 13/08/2006 JSA NO./ REVISION:
SUPERVISOR/ JSA LEADER: Ali Jan, M. Usman SCRIBE: Imran Shahbaz.
PARTICIPANTS: Zaheer, Mir Ahmad, Niaz Ahmad, Shahid Jamal, Ali Azhar, Mohammad Jamil.
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps:
1. Mobilization of Equipment & Workers.
2. Mixing of Bentonite &Gypsum
3. Shuttering for mixture of Bentonite & Gypsum
4. Installation and laying of Anode Ribbon (including Bentonite&gypsum)
5. Backfilling in Trench.
6. Demobilization.

Alternatives Considered: N/A

Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE, S: First aid kit must be present at the area and the Hse personnel is the first response in case of
emergency

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 Mobilization of equipment Unauthorised equipment/tools brought out to Before mobilizing any equipment/tools make sure
site that the E &P Personnel got inspected the
equipment. Checklist are in equipment
Unskilled and uninducted personnel starting Ensure that all personnel prior to start the have
the job been inducted and oriented about the hazard in the
job site. Only trained personnel shall do the
Cathodic Protection activity.

Workers starting the job unfit to work All personnel must be undergone fitness for work
assessment thru Del Doctor.
Workers starting the job without permit JSA must be in place prior to work. Permit shall be
obtained from BHP Operations. Ensure that all the
persons take part in the toolbox meeting
discussion. & They are fully aware of job hazards.
Hand Injury Ensure proper hauling of materials/get help if
required/Wear hand gloves. Ensure trolley are
secured with stable support
Back Injury Ensure Proper posture and positioning.
Miscommunication. Ensure stand by radio is on job site for all the
times.
Ensure that area to be secured and barricaded with
Cathodic Protection sign board in place.

2 Mixing of Bentonite & gypsum Unauthorised person Ensure that all workers have been informed when
the cathodic protection will be conducted properly
lit and barricaded by a barrier.
Dust Ensure that workers are wearing dust mask while
doing the job.
It is advised that the cathodic protection to be
SIMOPS
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
conducted at break time hours to minimized the
SIMOPS or personnel interface.
Chemical inhalation Ensure that MSDS of Gypsum & Bentonite is
Eye& skin Irritation provided and available at the doctor’s clinic and
site.
Ensure that workers are wearing hand gloves &
eye protection.
Eyewash must be available at the clinic and
washbasin in case of eye irritation must be present
in the area.

Back Injury Ensure workers are following the correct procedure


of positioning and lifting. Get help if required.
Ensure that workers are oriented about the job and
no one allowed to work alone.
Ensure That Workers are fully aware of the
Snake Bite presence of Snake in the area. No killing of snake.
Ensure that workers accessing the right walkway
Tripping hazard and watch your steps.
Other worker shall not involve in the job or shall
not come closer to the area.

Ensure o works shall perform during strong wind


Strong wind
and workers shall stay in safe area.

3. Shuttering for mixture of Bentonite Unauthorised person Ensure that all workers have been informed when
& gypsum the cathodic protection will be conducted properly
lit and barricaded by a barrier.
Inhalation of gypsum.
Eye & skin Irritation Ensure that MSDS is provided and available at the
doctor’s clinic.
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
Ensure that workers are wearing hand gloves &
eye protection.
Eyewash must be available at the clinic and
washbasin in case of eye irritation must be present
in the are.
Ensure workers are following the correct procedure
Back injury
of positioning and lifting. Get help if required.

Ensure that workers accessing the right walkway


Tripping hazards and watch your steps.

Ensure that all workers have been informed when


4. Installation and laying of Anode Unauthorised person the cathodic protection will be conducted properly
ribbon (including Bentonite & lit and barricaded by a barrier & no body shall
gypsum) involve who is not related to the job.
Ensure that MSDS is available at the site and the
Inhalation of gypsum workers and participants are aware of the Chemical
Eye & skin Irritation. reaction.
Ensure workers are complying with the min, PPE
Backfilling in trench req , Safety shoes, helmet, safety glass, dust mask.
5. Exposure of workers to various hazard like
And other PPE’s as the req, of Job.
hand injury, dust, eye injury

Ensure that signboard was in place/ensure that


Hidden Services Underground
underground services properly marked and
determined the depth.
Any excavation deeper than 4ft must be bench or
Cave – in slope. Area must be hard barricaded.
Ensure potable water/sufficient shelter is available
Heat Stress/Exhaustion each area where workers are doing the job.

Ensure that workers are fully aware from the


JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
Snake bite. presence of snake in the area.

Area with excavation /holes to be barricaded and


Excavated holes/openings covered.
Ensure that workers accessing the right walkway.
Tripping Hazards

6. Poor Housekeeping Ensure that the area was properly housekeep.


Demobilization.
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)