JOB TITLE / AIM: HDPE Liner welding using fusion welding


JSA DATE:02 /06/2006 JSA NO./ REVISION:
SUPERVISOR/ JSA LEADER:Iqbal Zafar SCRIBE:Hernand Suyom
PARTICIPANTS : Iqbal Zafar, Shoaib
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps:
1.Mobilization of Tools & Equipment
2. Manual preparation of HDPE liner and equipment set-up
3. HDPE liner fusion welding
4. Demobilization

Alternatives Considered: N/A

Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the Hse personnel is the first response in case of
emergency

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.

File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 Mobilization of equipment Unauthorised equipment/tools brought out to Before mobilizing any equipment/tools make sure
site that the E &P Personnel got inspected the
equipment. Checklist are in equipment
Unskilled and uninducted personnel starting Ensure that all personnel prior to start the have
the job been inducted and oriented about the hazard in the
job site.
Open trench All open trench should be barricaded off when not
attended
Workers starting the job unfit to work All personnel not fit to work shall not be allowed
to work at the project site. Ensure excavation
certificate to BHP are in place
Workers starting the job without permit JSA must be in place prior to work. Ensure all the
persons take part in the tool box meeting
discussion. Persons signed at the back of JSA
Ensure gas testing are in place whenever doing
fusion welding at transition zone area
Hand Injury Ensure proper hauling of materials/get help if
required/Wear leather gloves.
2 Sleeving ss17 pipe with HDPE pipe Exposure of workers to various hazard like Ensure workers are complying with the min.
hand injury, dust, eye injury PPE req.Safety shoes, helmet, safety glass,
Dust mask.

Hand Injury Ensure proper hauling of materials/Wear hand


gloves.

Unskilled and uninducted personnel Ensure that toolbox meeting was regularly
starting the job conducted and people are aware of the job
and the hazard enclosed in the job they are
performing
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)

3 Manual Concrete Pouring Hand / Eye Injury Ensure that during the concrete pouring workers will
use gloves and safety goggles.
Improper Access A Proper access shall be made for reaching and
performing job of concrete pouring.
Heat Exertion Ensure that sufficient amount of water and shelter is
available for the workers.
Slips & Trips Ensure that Area is kept clean and tidy and all
material to be used shall be properly managed to
avoid slip & trip falls.
Un Experienced Persons Ensure that only experienced persons will perform
the job of Concrete Pouring.
Un Inspected / Improper Wheel Borrow Ensure that wheel borrow to be used shall be in good
working condition
Starting Concrete Pouring not using Rubber If a worker has to perform concrete pouring job while
Shoes standing in the wet concrete they will use rubber
shoes.
Improper tools Usage Ensure that proper and Inspected tools must be used
for the concrete pouring job.
Dust Ensure that workers shall wear dust masks in case of
dust.
Back Injury Ensure that workers shall be properly demonstrated
about the proper posture.
4 Demobilization Same as item one Same as item one