Beruflich Dokumente
Kultur Dokumente
BUSINESS CASE: Based on the quantity, the planned quantities will be distributed. The percentage of STATUS: Tested
completion will aggregate to the higher level based on the costing. The Progress analysis
report will provide a comparison of the actual progress of the project based on work.
EXPECTED All the Phase 4 (Progress) activities have been carried out. RUN DATE: Aug 17 2016
RESULTS:
SETUP DATA
Page 1 of 8
PROJECT SYSTEM TEST SCENARIOS
TRANSACTIONAL STEPS
No BUSINESS PROCESS TRANS. CODE INPUT DATA / SPECIAL OUTPUT DATA / RESULT TESTER / OK /
. STEPS INFORMATION TEAM ERROR
1 Maintain Measurement CN22 1. Network: 1000060 Measurement method Riyaz, OK
method for Network activity 2. Click on select all maintained Ansari,
3. Click of details Malini
4. Go to progress tab
5. Maintain plan and actual
Measurement method for
progress version 100, i.e
EACH/PIECE
6. Click on next and repeat
the process.
2 Plan SKF for Network CN22 1. Network: 1000060 SKF Quantity Maintained Riyaz, OK
Activity 2. Click on select all Ansari,
3. Click of details Malini
4. Go to SKF tab
5. Click on append row
6. Enter SKF: QTYEA
7. Enter SKF QTY = 100
8. Click next and repeated
process from 5 to 7.
3 View Plan and actual SKF S_ALR_870135 1. Project: EGC-011602 SKF report displayed Riyaz, OK
48 2. Controlling Area: 1000 Ansari,
3. Plan Version: 0 Malini
Page 2 of 8
PROJECT SYSTEM TEST SCENARIOS
No BUSINESS PROCESS TRANS. CODE INPUT DATA / SPECIAL OUTPUT DATA / RESULT TESTER / OK /
. STEPS INFORMATION TEAM ERROR
4. Fiscal Year: 2016
4 Post Actual SKF KB31N 1. CO Area: 1000 Actual SKF posted and Riyaz, OK
2. Doc. Date: Today document is posted under Ansari,
3. Postg date: Today document number Malini
4. Screen variant: 200000148
WBS/Network
5. Rec. Network: 1000020
6. ReCo: 0008,0020,0022
(Activity Number)
7. StatKF: QTYEA
8. Total Qty: 40,100,500
9. Press enter and save
5 Plan and Actual SKF data S_ALR_870135 1. Project: EGC-011602 Plan and actual SKF Riyaz, OK
48 2. Controlling Area: 1000 displayed Ansari,
3. Plan version: 0 Malini
4. Fiscal Year: 2016
6 Calculate Progress Analysis CNE1 1. Project Definition: EGC- Progress Updated Riyaz, OK
011602 Ansari,
2. With hierarchy: Ticked Malini
3. With Orders: Ticked
4. Progress Version: 0
5. To period: 12 2016
6. Test run: Unticked
7. Execute or F8
Page 3 of 8
PROJECT SYSTEM TEST SCENARIOS
No BUSINESS PROCESS TRANS. CODE INPUT DATA / SPECIAL OUTPUT DATA / RESULT TESTER / OK /
. STEPS INFORMATION TEAM ERROR
Evaluate Progress Analysis CNE5 SAPPS_EV0001 Ansari,
2. Project: EGC-011602 Malini
3. Execute
Test Completion Results: Passed: Failed: Corrected, re-tested, and passed
Comments:
Page 4 of 8
PROJECT SYSTEM TEST SCENARIOS
Page 5 of 8
PROJECT SYSTEM TEST SCENARIOS
Page 6 of 8
PROJECT SYSTEM TEST SCENARIOS
Page 7 of 8
PROJECT SYSTEM TEST SCENARIOS
Page 8 of 8