Government of Nepal

Ministry of Physical Infrastructure Development


Infrastructure Directorate
Water Supply Irrigation and Energy Development Office
Karnali Province
khalanga,Jajarkot

Quantity Estimate

Name of Works:Construction of Aqueduct


Location:Jajarkot
S.N Particular Nos. Length Breadth Height Quantity Units Remarks
1 Earthwork in Excavation for foundtion
a. Abutment part 2 3.70 2.90 7.99 171.46
b Peir 1 2.20 2.90 0.60 3.82
c For gabion works 1 6.00 6.00 0.13 4.60
Sub total 179.88 m3
2 Back filling in structure part 2/3 of excavtion Qty. 118.72 m3
Sub total 118.72 m3
3 PCC (1:3:6) M10
a Abutment part 2 3.70 2.90 0.10 2.14
b Peir 1 2.20 2.90 0.10 0.63
Sub total 2.77 m3
4 PCC for RCC (1:1.5:3) (M20)
A for Raft
a Raft of abutment 2 3.50 2.70 0.75 14.17
b Peir Raft 1 2.00 2.70 0.50 2.70
B for stem
a Abutment part 2 2.15 0.55 7.14 16.88
b Peir 1 2.20 0.55 7.14 8.63
C Aqueduct
a Aqueduct Beam 2 22.95 0.25 1.15 13.19
b Slab 1 22.95 0.60 0.25 3.44
D U/S & D/S canal
a Wall 2*2 3.00 0.15 1.05 1.89
b bed 2*1 3.00 0.60 0.15 0.54
Sub total 61.44 m3

Estimated By: Checked By: Approved By:


Government of Nepal
Ministry of Physical Infrastructure Development
Infrastructure Directorate
Water Supply Irrigation and Energy Development Office
Karnali Province
khalanga,Jajarkot

Quantity Estimate

Name of Works:Construction of Aqueduct


Location:Jajarkot
S.N Particular Nos. Length Breadth Height Quantity Units Remarks
5 Formwork
A for Raft
a Raft of abutment 2 12.40 0.75 18.60
b Peir Raft 1 9.40 0.50 4.70
B for stem
a Abutment part 2 5.40 7.14 77.11
b Peir 1 4.97 7.14 35.48
C Aqueduct
a Aqueduct Beam 2 46.40 0.90 83.52
b Slab 1 22.95 0.60 13.77
D U/S & D/S canal
a Wall 2*2 3.00 1.05 12.60
b bed 2*1 3.00 0.60 3.60
Sub total 249.38 m2
6 Reinforcement
A Abutment raft
a 16 mm dia main bar @ 200mm c/c
raft top & bottom 56 3.70 1.58 kg/m 327.37 kg 17
b 12 mm dia dist. bar @ 200mm c/c
raft top & bottom 72 2.90 0.89 kg/m 185.83 kg
B Abutment stem
a 16 mm dia main bar @ 200mm c/c Outer & inner vertical 44 8.80 1.58 kg/m 611.77 kg
b 12 mm dia dist. bar @ 200mm c/c 160 2.35 0.89 kg/m 334.64 kg
C Peir raft
a 12 mm dia main bar @ 150mm c/c
raft top & bottom 36 2.20 1.58 kg/m 125.13 kg
b 12 mm dia dist. bar @ 150mm c/c
raft top & bottom 28 2.90 0.89 kg/m 72.26 kg
D Peir stem KG of steel d2/162
a 20 mm dia main bar @ 150mm c/c Outer & inner vertical 34 7.79 2.47 kg/m 654.20 kg
b 12 mm dia dist. bar @ 200mm c/c 37 5.27 0.89 kg/m 173.54 kg
E Aqueduct Beam
a 20 mm dia main bar, Botto &top 12 23.60 2.46 kg/m 696.67 kg 2.4691358
b 12 mm dia dist. bar @ 200mm c/c 24 23.00 0.89 kg/m 491.28 kg
c 8 mm dia. stirrups bar @ 200mm c/c 232 2.75 0.39 kg/m 248.82 kg
F Aqueduct Slab
a 12 mm dia main bar,@200mm c/c Bottom & top 232 1.10 0.89 kg/m 227.12 kg

Estimated By: Checked By: Approved By:


Government of Nepal
Ministry of Physical Infrastructure Development
Infrastructure Directorate
Water Supply Irrigation and Energy Development Office
Karnali Province
khalanga,Jajarkot

Quantity Estimate

Name of Works:Construction of Aqueduct


Location:Jajarkot
S.N Particular Nos. Length Breadth Height Quantity Units Remarks
b 10mm dia dist. bar @ 200mm c/c 8 23.30 0.62 kg/m 115.56 kg
G U/S & D/S canal

Estimated By: Checked By: Approved By:


Government of Nepal
Ministry of Physical Infrastructure Development
Infrastructure Directorate
Water Supply Irrigation and Energy Development Office
Karnali Province
khalanga,Jajarkot

Quantity Estimate

Name of Works:Construction of Aqueduct


Location:Jajarkot
S.N Particular Nos. Length Breadth Height Quantity Units Remarks
a 12 mm dia main U bar @200mm c/c 32 2.80 0.89 kg/m 79.74 kg
b 10mm dia dist. bar @ 200mm c/c 30 2.90 0.62 kg/m 53.94 kg
Total reinforcement (main & distribution bar) 4752.89 kg
4.75 tons
7 12 3.00 1.00 1.00 36.00 m3
Providing and fabricating gabion crates of more than 0.5m
height mesh size with 100 mm x 120 mm hexagonal mess and
heavy coated including rolling, cutting, weaving filling of
creates with broken stones etc including lead 10m lift 1.5m , all
complete (mesh wire 10 SWG, binding wire 12 SWG and
Selvedge wire 7 SWG)

Sub total 36.00 m3


8 Site clearance works 1 1.00 job

Estimated By: Checked By: Approved By:


Government of Nepal
Ministry of Physical Infrastructure Development
Infrastructure Directorate
Water Supply Irrigation and Energy Development Office
Karnali Province
khalanga,Jajarkot

ABSTRACT OF COST
Name of Works:Construction of Aqueduct
Location:Jajarkot

S.No. Description Unit Quantity Rate Amount Remarks


A Civil Works
A.1 Earthwork in excavation for foundations of canal,
drains, Structures etc in all types of soil in all
condition & disposal of excavated soil upto 200 m.
m3 179.88 1,058.64 190,428.16
A.2 Backfilling works for structure m3 118.72 533.55 63,343.48
A.3 Supply, bending, binding and placing of
reinforcement as per instruction Kg 4.75 21,229.35 100,900.76
A.4 Supply & placing of Form work as per instruction
m2 249.38 1,200.21 299,307.12
A.5 Supply & placing of concrete (1:3:6) M10 as per
instruction m3 2.77 33,942.48 94,020.66
A.6 Supply & placing of concrete (1:1.5:3) M20 for RCC
works as per instruction m3 61.44 46,305.34 2,845,000.08
A-7
Providing and fabricating gabion crates of more than
0.5m height mesh size with 100 mm x 120 mm
hexagonal mess and heavy coated including rolling,
cutting, weaving filling of creates with broken stones
etc including lead 10m lift 1.5m , all complete (mesh
wire 10 SWG, binding wire 12 SWG and Selvedge
wire 7 SWG)
m3 36.00 7,305.72 263,005.92
A-8 Site clearance works Job 1.00 LS 15,000.00
Sub Total of A
3,871,006.18
Contingency @ 5% 193550.31
VAT @ 13 % of (A) 503230.80
Grand Total 4,567,787.29
ITEM (I) Fabrication of gabion boxes including rolling , cutting and weaving
A. Hexagonal Mesh Size - 100 mm. X 120mm.
UNIT a. 2 X 1 X 1
Mesh wire 10 SWG. And Selvedge wire 8 SWG
S.N. 44.1 B (ii) Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.39 m-day 950.00 370.50 370.50
Unskilled 0.20 m-day 715.00 143.00 143.00
Constructio Mesh Wire 23.43 kg. 95.00 2225.85 2225.85
Materials Selvedge wi 2.88 kg. 95.00 273.60 273.60
Actual Rate 3012.95
Overhead @ 15 % 451.94
Sub Total 3464.89
Rate per m³ 1732.45
(ii) Assembling of wire crates/gabion/revetment and placing them in position including
stretching, binding them together and tying down lids.
a) 2x1x1
UNIT box
Ref: 44.2 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Unskilled 0.09 m-day 715.00 64.35 64.35
Constructio Binding Wir 0.95 Kg. 95.00 90.25 90.25
Materials
Actual Rate 154.60
Overhead @ 15 % 23.19
Sub Total 177.79
Rate per m³ 88.90

(iii) Packing and filling of gabion crates with rubble stones.


UNIT Cu m.
S.N. 45 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.5 m-day 950.00 475.00 475
Unskilled 1.50 m-day 715.00 1072.50 1072.5
Constructio Boulder 1.10 cu.m. 2981.00 3279.10 3279.10
material
Actual Rate 4826.60
Overhead @ 15 % 723.99
Sub Total 5550.59
Total per cu.m. 7371.93
ate per m³ for total gabion works 7371.93

ITEM (I) Fabrication of gabion boxes including rolling , cutting and weaving
A. Hexagonal Mesh Size - 100 mm. X 120mm.
UNIT b. 3 X 1 X 1
Mesh wire 10 SWG. And Selvedge wire 8 SWG
S.N. 44.1 B (ii) Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.57 m-day 950.00 541.50 541.50
Unskilled 0.28 m-day 715.00 200.20 200.20
Constructio Mesh Wire 34.08 kg. 95.00 3237.60 3237.60
Materials Selvedge wi 4.03 kg. 95.00 382.85 382.85
Actual Rate 4362.15
Overhead @ 15 % 654.32
Sub Total 5016.47
Rate per m³ 1672.16

(ii) Assembling of wire crates/gabion/revetment and placing them in position including


stretching, binding them together and tying down lids.
b) 3x1x1
UNIT box
Ref: 44.2 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Unskilled 0.13 m-day 715.00 92.95 92.95
Constructio Binding Wir 1.30 Kg. 95.00 123.50 123.50
Materials
Actual Rate 216.45
Overhead @ 15 % 32.47
Sub Total 248.92
Rate per m³ 82.97
(iii) Packing and filling of gabion crates with rubble stones.
UNIT Cu m.
S.N. 45 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.5 m-day 950.00 475.00 475
Unskilled 1.50 m-day 715.00 1072.50 1072.5
Constructio Boulder 1.10 cu.m. 2981.00 3279.10 3279.10
material
Actual Rate 4826.60
Overhead @ 15 % 723.99
Sub Total 5550.59
Total per cu.m. 5550.59
Total Gabion works per cu.m. 7305.72
ate per m³ for total gabion works 7305.72