Sie sind auf Seite 1von 25

Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)

EC No. SEIAA/HR/2015/308 dated 19-03-2015

CHAPTER-1

INTRODUCTION AND PROJECT DESCRIPTION

1.1 Introduction

M/s Rajiv Gandhi Charitable Trust has proposed a Eye Hospital at Sector-62, Village-
Ullahawas,, District- Gurgaon, Haryana.

The Project has been recommended by State Expert Appraisal Committee (SEAC). This Project has
obtained its Environmental Clearance from State Environment Impact Assessment Authority
(SEIAA) with the EC No. SEIAA/HR/2015/308 dated 19.03.2015. The Project has been awarded
“Gold” grading by SEAC in its meeting held on 13.08.2014 and 18.02.2015.

1.2 Project Description

Sr. No. PARTICULARS DETAILS


1 Total Plot Area 19477.70 sqmt.
2 Total Built-up Area 30704.28 sqmt.
(2 Basements+ Lower Ground floor), (Upper ground
3 No. of Blocks
Floor + Maximum 03 floors)
4 Maximum Height of the Building 21 meter
5 Total Water Requirement 375 KLD
6 Total Fresh Water Requirement 241 KLD
7 Domestic Waste water generation 149 KLD
9 Capacity of STP 175 KLD
10 Total Connect Power Requirement 1700 KVA
30.24% (24.78% tree plantation+5.225%
11 Green Area
landscaping)
12 Rain Water Harvesting Pits 6
13 Solid Waste generation 377 kg/day
14 Total Parking Space 353 ECS

1.3 Purpose of the Report

This report is submitted after every six months on or before 1st June and 1st December each year as
per the conditions stipulated in Environment Clearance Order. The Environmental assessment has
been carried out to verify:

i. That the proposed project has not any adverse effect on the project site as well as its
surrounding.
ii. That there is compliance with the conditions stipulated in the Environmental
Clearance Letter.
iii. That the Project proponent is implementing the environmental safeguards in true
spirit.
iv. The non conformity in the project with respect to the environmental implication of
the project.
v. That the project proponent is implementing the environmental pollution mitigation
measures as suggested in approved Form-1 and Form – 1A, Environmental
Management Plan and Building Plan.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
1
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

CHAPTER-2

ADHERENCE TO SPECIFIC & GENERAL CONDITIONS OF ENVIRONMENTAL CLEARANCE

PART A – SPECIFIC CONDITIONS

I. Construction Phase

S. No. Conditions of Environmental Clearance Status of Compliance


1) “Consent For Establishment” shall be obtained from CTE has already been obtained for a portion of the
Haryana state Pollution Control Board under Air and project vide NOC dated 3.12.2013 from Haryana State
Water Act and a copy shall be submitted to the Pollution Control Board. CTE for the remaining portion
SEIAA, Haryana before start of any construction has already been applied an shall be granted soon.
work at site.
CTE obtained and applied for, both are collectively
enclosed as Annexure – 1.
2) A First aid room as proposed in the project report We assure that we will provide the first aid facility
will be provided both during construction and during construction of the project.
operation phase of project.
3) Adequate drinking water and sanitary facilities Adequate drinking water & sanitary facilities will be
should be provided for construction workers at the provided for construction workers at the site. The safe
site. Provision should be made for mobile toilets. disposal of waste water and solid waste will be done
Open defecation by the laboures is strictly properly. Sanitation & hygiene will be of prime
prohibited. The safe disposal of waste water and importance.
solid wastes generated during the construction
phase should be ensured.
4) All the top soil excavated during construction Top soil will be stored for use in horticulture/landscape
activities should be stored for use in development.
horticulture/landscape development within project
site.
5) The project proponent shall ensure that the building We ensure that building material used in the
material used in the construction phase should be construction phase will be stored within the project area.
stored within the project area and disposal of It will be disposed of after taking necessary precautions
construction waste should not create any adverse for general safety and health aspects of the people.
effect on the neighboring and should be disposed of
after taking necessary precautions for general safety
and health aspects of the people .only in the
approved sites with the approval of competent
authority.
6) Construction spoils, including bituminous materials Construction spoils will be stored in a dedicated area
and other hazardous materials must not be allowed duly bounded to avoid contamination to the environment
to contamination watercourses and the dump site in proximity. Storage area will be covered by insulated
for such materials must be secured so that they lining to prevent contamination from hazardous
should not leach into groundwater and any materials like fuel of DG sets. Waste oil of the DG Set will
hazardous waste generated during construction be disposed of through authorized vendors.
phase should be disposed off as per applicable rules
and norms with necessary approval of Haryana State
Pollution Control Board.
7) The diesel generator sets to be used during Silent DG sets will be used at the project site during
construction phase should be of ultra low sulphur construction stage, with maintained noise and emission
diesel type and should conform to Environment within the permissible limits.
(Protection) Rules prescribed for air and noise
emission standard.
8) The diesel required for operating DG sets shall be The diesel will be stored in underground pits and if
stored in underground tank if required clearance quantity of diesel stored exceeds the threshold limit,
Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
2
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

from chief controller of explosive shall be taken. approval of chief controller of explosives will be
obtained.
9) Ambient noise levels should conform to standards Ambient air & noise monitoring has been conducted by
both during day and night. Incremental pollution Vardan Envirolab, Gurgaon (NABL Accredited) at project
loads on the ambient air and noise quality should be site and the results shows that the noise and air pollution
closely monitored during construction phase. levels are within the prescribed limits. Lab report are
Adequate measures should be taken to reduce attached as Annexure-2
ambient air and noise level during construction
phase, so as to confirm stipulated residential
standards.
10) Fly ash should be used as building materials in the Fly ash based construction material will be used for
construction as per the provision of fly ash building construction.
notification of September 1999 and amendment as
on 27th August 2003.
11) Storm water control and its re-use as per CGWB and The recharge structures for storm water control as well
BIS standard for various applications should be as rain water harvesting are proposed for recharging of
ensured. ground water.
12) Water demand during construction phase should be Premix concrete and curing agent will be used for water
reduced by uses of premix concrete, curing agent conservation.
and other best practices.
13) In view of the severe constrains in water supply The trust has obtained water assurance from XEN HUDA
augmentation in the region and sustainability of regarding supply of water during operation phase of the
water resources, the developer will submit the NOC project. Further, an NOC from Administrator, HUDA has
from CGWA specifying water extraction quantities also been obtained for supply of treated water during
and Assurance from HUDA/utility provider construction phase of the project.
indicating source of water supply and quantity of
water with detail of impended use of water-potable
and non potable. Assurance is required for both
construction and operation stages separately. It shall
be submitted to the SEIAA and RO, MoEF,
Chandigarh before the start of construction.
14) Roof must meet prescribed requirements as per Thermal insulation of roofs shall be done as per ECBC
energy conservation building code by using norms.
appropriate thermal insulation material.
15) Opaque wall should meet prescribed requirements The walls will be constructed as per ECBC norms as
as per energy conservation building code which is applicable.
proposed to be mandatory for all air conditioned
spaces while it is desirable for non air conditioned
spaces by use of appropriate thermal insulation to
fulfill the requirement.
16) The approval of competent authority shall be Structural safety certificate from has been obtained and
obtained for structural safety of the building due to is enclosed as Annexure – 3.
earthquake, adequacy in firefighting equipment etc
as per national building code including protection No forestland is involved in the proposed site, hence
measures for light etc. If any forest land is involved clearance under FCA is not applicable.
in the proposed site, clearance under Forest
conservation act shall be taken from competent
authority.
17) The project proponent as stated in proposal shall 6 number of RWH pits will be constructed in due course
construct 06 rainwater harvesting pits for of time as per the prescribed norms.
recharging the ground water with in project
premises. Rain water harvesting pits shall be
designed to make provision for silting chamber and
removal of floating matter before entering
harvesting pit maintenance budget and person
responsible for maintenance must be provided. Care
shall also be taken that contaminated water do not

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
3
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

enter any RHW pit.


18) Overexploited ground water and impending severe For conservation of water during operation phase, we
shortage of water supply in the region requires the have proposed to install Dual plumbing line and rain
developer to redraw the water and energy water harvesting system to. During construction phase,
conservation plan. Developer shall reduce the we shall use STP treated water from HUDA only. No fresh
overall footprint of the proposed development. water will be used.
Project proponent shall incorporate water efficiency
/ savings measures as well as water reuse/recycling As an energy conservation measure, we shall be use of
within 3 months and before start of construction to CFLs, TFLs and solar panels. Use of LEDs maybe
the SEIAA, Haryana and RO, MoEF, GoI, Chandigarh considered.
19) The project proponent shall provide for adequate Adequate fire safety measures and equipment as
fire safety measures and equipments as required by required by Haryana Fire Service Act 2009 and as per
Haryana Fire Service Act, 2009 and instructions instructions of local concerned departments and
issued by the local Authority/Directorate of fire authorities will be complied. Fire scheme has been
from time to time. Further the project proponent obtained. Copy enclosed as Annexure – 4.
shall take necessary permission regarding fire safety
scheme/NOC from competent Authority as required.
20) The project proponent shall obtain assurance from Assurance from DHBVN has been obtained for supply of
the DHBVN for supply of 1700 KVA of power supply power.
before the start of construction. In no case project
will be operational solely on generators without any
power supply from any external power utility.
21) Detail calculation of power load and ultimate power Application for assurance of power supply from DHBVN
load of the project shall be submitted to DHBVN was submitted and consequently assurance has been
under intimation to SEIAA Haryana before the start granted.
of the construction. Provisions shall be made for
electrical infrastructure in the project area.
22) The project proponent shall not raise any Same will be complied as per the requirement during the
construction in the natural land depression/ Nallah/ construction phase.
Water course and shall ensure that the natural flow
from the Nallah/ Water course is not obstructed.
23) The Project Proponent shall keep the plinth level of We will keep the plinth level above the level of the road
the building blocks sufficiently above the level of the to avoid flooding.
approach road to the Project as per prescribed by-
laws. Levels of the other areas in the Projects shall
also be kept suitably so as to avoid flooding.
24) Construction shall be carried out so that the density Noted. Building plans have been prepared as per the
of population does not exceed norms approved by applicable population density norms and consequently
the Director General Town and Country Department the building plans approved by TCP Haryana.
Haryana.
25) The project proponent shall submit an affidavit with Affidavit has already been submitted to SEIAA Haryana
the declaration that ground water will not be used at the time of appraisal of project for grant of EC.
for construction and only the treated water should
be used for construction.
26) The project proponent shall not cut any existing tree Noted.
in the project area and project landscaping plan shall
be modified to include the tree in the green area.
27) The project proponent shall ensure that ECBC norms ECBC norms for composite climate zone shall be met.
for composite climate zone are met. In particular
building envelope, HVAC service, water heating,
pumping, lighting and electrical infrastructure must
meet ECBC norms.
28) The project proponent shall provide 3 meter high We will provide barricade of adequate height around the
barricade around the project area, dust screen for project area. Further, water sprinklers, dust screens and
every floor above the ground, proper sprinkling and other measures to avoid the air pollution to the
covering of stored material to restrict dust and air neighboring communities due to the project will be
pollution during construction. adopted.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
4
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

29) The project proponent shall construct a A sedimentation filtration system has been proposed in
sedimentation basin in the lower level of the project the water recharge system.
site to trap pollutant and other wastes during rains.
30) The project proponent shall provide proper Rasta of Rasta of adequate width and strength will be provided
proper width and proper strength for each project before the start of the construction.
before the start of construction.
31) The project proponent shall ensure that the U-value The U- value and solar heat gain coefficient shall be as
of the glass is less than 3.177 and maximum solar per applicable norms.
heat gain coefficient is 0.25 for vertical fenestration.
32) The project proponent shall adequately control Adequate measures will be provided during the
construction dust like silica dust, non-silica dust, and construction of the project to control the dust particles
wood dust. Such dusts shall not spread outside the to spread outside the project area. Respiratory protective
project premises. The project proponent shall equipment will be provided to the workers keeping their
provide respiratory protective equipment to all health in mind.
construction workers.
33) The project proponent shall obtain permission of Permission from Mines & Geology Department for the
Mines & Geology , Department for excavation of soil excavation of soil has already been obtained. Refer
before the start of construction. Annexure-5
34) The project proponent shall seek specific prior We will take necessary permission/connection from
approval from concerned local Authority/ HUDA HUDA for the integration of storm water drainage and
regarding provision of storm drainage and sewerage sewerage system with the external source in due course
system including their integration with external of time. These connections are not necessary to be
services of HUDA/ Local Authorities beside other obtained prior construction.
required services before taking up any construction
activity.
35) The site for solid waste management plant be A waste management site has been proposed within the
earmarked on the layout plan and the detailed project premises. Map indicating the same is enclosed as
project for setting up the solid waste management Annexure – 6.
plant shall be submitted to the Authority within one
month.
36) The project proponent shall discharge excess of Attempt will be made to re-use the excess treated water
treated waste water /storm water in the public within the project site for horticulture and flushing
drainage system and shall seek permission of HUDA purpose. However, if any quantity of treated water still
before the start of construction. remains, the same shall be discharged in the public sewer
after taking prior permission and sewer connection from
HUDA.

Similarly, attempt will be made to use the storm water in


rain water harvesting pits. However, excess storm water
shall be discharged in the public sewer after taking prior
permission and sewer connection from HUDA.

However, this permission is not required before start of


construction.
37) The project proponent shall use treated water for Revised water balance diagram is not required since our
HVAC make up / DG Cooling instead of fresh water proposal (Form 1, 1A and Conceptual Plan) submitted to
and shall submit revised water balance diagram the authority for appraisal of EC already consisted of
before the start of construction. water balance diagram in which treated water was
being used for HVAC makeup and DG Cooling.
38) The project proponent shall provide sound We will use adequate measures for sound reduction
reduction technique during day time. including use of silent DG sets and development of green
to ensure the noise within prescribed limits.
39) The project proponent shall dispose off Bio-Medical Noted. Bio-medical waste will be disposed off as per Bio-
waste as per Bio Medical (Management & Handling) Medical waste as per Bio Medical (Management &
Rules, 1998. Handling) Rules, 1998 during operation phase of the
project.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
5
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

40) The project proponent is responsible for compliance We agree that we are responsible for the compliance of
of all conditions in Environmental Clearance letter all conditions given in Environmental Clearance Letter of
and project proponent can not absolve the project.
himself/herself of the responsibility by shifted it to
any contractor engaged by project proponent.
41) Vertical fenestration shall not exceed 40 % of total Noted. The vertical fenestration will not exceed more
wall area. than 40 % of the wall area.
42) The project proponent shall not install any tube well We agree that we will not extract ground water by any
without permission of CGWB. means without the permission of Central Ground Water
Authority.
43) The project proponent shall not dispose off any solid Any type of liquid and solid waste will never be disposed
or liquid waste in the Nallah. off in the Nallah.

II. Operation Phase

S. No. Conditions of Environmental Clearance Status of Compliance


a) “Consent to operate” shall be obtained from CTO will be obtained before the commencement of operation
Haryana State Pollution Control Board under air phase.
and water act and a copy shall be submitted to the
SEIAA, Haryana.
b) The Sewage Treatment Plant (STP) should be STP of adequate capacity and latest technology will be
installed for the treatment of sewage generated to installed before operational phase. An adequacy report from
be prescribed standards including odour and an independent expert will be obtained and submitted to
treated effluent will be recycled to achieve zero SEIAA Haryana after installation of STP.
discharge. The installation of STP should be
certified by an independent expert and a report in
this regard should be submitted to SEIAA, Haryana
before the project is commissioned for operation.
Tertiary treatment of waste water is mandatory.
The project proponent shall remove not only ortho-
phosphorus but total phosphorus to the extent of
less than 2mg/litre in tertiary treated waste water.
Discharge of treated sewage shall confirm to the
norms and standards of HSPCB, Panchkula. The
project proponent shall implement such STP
technology which does not require filter backwash.
c) Separation of black and grey water should be done Separation of black and grey water would be done by use of
by use of dual plumbing line. Treatment of 100% dual plumbing line.
grey water by decentralized treatment should be
done ensuring that the re-circulated water should
have BOD maximum 10 mg/litre and the recycled
water will be used for flushing, gardening and DG
set cooling etc to achieve zero exit discharge.
d) For disinfections of treated waste water ultra We will use the ultra violet radiation or ozonization for
violation radiation or ozonization should be used. disinfection of treated waste water
e) Diesel power generating sets proposed as source of All DG sets to be used will be of “enclosed type” to prevent
backup power for lifts, common areas illumination noise and will conform to rules made under Environment
and for domestic use should be of enclosed type and (Protection) Act 1986, prescribed for air and noise emission
confirm to the rule made under Environment standards. Adequate stack height as per CPCB norms will be
Protection Act, 1986. The location of DG sets should provided. Ultra low sulfur content diesel would be used.
be in the basement as promised by the project
proponent with appropriate stack height i.e above
the roof level as per the CPCB norms. The diesel
used for DG should be low sulphur content
(maximum 0.05% sulphur), instead of low sulphur

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
6
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

S. No. Conditions of Environmental Clearance Status of Compliance

diesel.
f) Ambient Noise level should be controlled to ensure Yes we will monitor the noise level at the proposed eye
that it does not exceed the prescribed standards hospital in the operational phase and take all necessary
both within and at the boundary of Proposed steps to keep noise in permissible limit.
Commercial Complex.
g) The project proponent as stated in the proposal We will maintain 30.24 % area under greenery. The plants
should maintain at least 30.24% as green cover area of native and locally available varieties will be used.
for tree plantation especially all around the
periphery of the project site and on the road sides
preferably with local species so as to provide
protection against particulates and noise. The open
space inside the plot should be preferably
landscaped and covered with vegetation/grass.
Herbs & shrubs. Only locally available species shall
be used.
h) The project proponent shall strive to minimize Efficient irrigation system, use of native species of plants,
water in irrigation by minimizing the grass area, mulching and xeriscaping will be encouraged in the project
using native verity, xeriscaping and mulching, premises to minimize the water consumption.
utilizing efficient irrigation system, scheduling
irrigation only after checking evaporation data.
i) Rain water harvesting for runoff and surface runoff, All measures for rain water harvesting will be implemented
as plan submitted should be implemented. Before during the operation phase. The ground water levels and Its
recharging the surface runoff, pretreatment must be quality will be monitored regularly in consultation with the
done to remove suspended matter, oil and greases. Central Ground Water Authority. Oil & Grease trap will be
The bore well for rain water recharging should be provided to remove oil and grease from the surface run off
kept at least 5 mts. above the highest ground water and suspended matter will be removed in a settling tank
table. Care shall be taken that contaminated water before its utilization for rainwater harvesting.
do not entry any RWH pit. The project proponed
shall avoid rain water harvesting of first 10 minutes
of rain fall. Roof top of the building shall be without
any toxic materials or paints which can contaminate
rain water. Wire mess and filter should be used
wherever required.
j) The project proponent shall ensure that ground Ground water will not be extracted. However, regular
water is not contaminated due to leached of spoiled monitoring of water quality as provided by HUDA will be
organic material. The ground water level and its done during the operation phase.
quantity should be monitored regularly in
consultation with Central Ground Water Authority.
k) A report on energy conservation measures The project is designed to meet the needs of a hot and humid
conforming to energy conservations norms finalize climatic zone.
by bureau of energy efficiency should be prepared The roofs will be thermally insulated.
incorporating details about building materials &
technology, “R & U factors etc” and submit to IA The walls will be opaque
division of environment and forest department,
Haryana in three months time. The glass to be used in the building will be of adequate U-
value and have reflective surface.
l) Energy conservation measures like installation of For conservation of water during operation phase, we have
LED for the lighting the area outside the building proposed to install Dual plumbing line and rain water
should be integral part of the projects design and harvesting system to. During construction phase, we shall
should be in place before project commissioning. use STP treated water from HUDA only. No fresh water will
Use of solar panels must be adapted to the be used.
maximum energy conversion.
As an energy conservation measure, we shall be use of CFLs,
TFLs and solar panels. Use of LEDs maybe considered.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
7
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

S. No. Conditions of Environmental Clearance Status of Compliance

m) The project proponent shall use zero ozone Yes we will use zero ozone depleting potential materials in
depleting potential material in the insulation, insulation refrigeration air conditioning and adhesive, also
refrigeration, air-conditioning and adhesive. The provide halon free fire suppression system in construction as
project proponent shall also provide halon free fire well as operation phase.
suppression system.
n) The solid waste generated should be properly Yes, the solid waste will be collected & segregated. The
collected and segregated as per requirements of composting of biodegradable waste and non-bio-degradable
MSW rules, 2000. The biodegradable waste should solid waste would be disposed off to municipal landfill sites
be composted by vermin-composting at the site ear after recovering recyclable waste..
marked with in the project area and dry/inert solid
waste should be disposed off to the approved sites
for land filling after recovering recyclable materials.
o) The provision of the solar water heating system Solar panels for hot water generation are proposed to install
shall be as per the norms specified by HAREDA and in the project area once the construction of the project is
shall be made operational in each building block. finished to conserve the energy and to comply with the
norms issued by Haryana Government.
p) The traffic plan and the parking plan proposed by The traffic and parking plan has been proposed as per the
the PP should be adhered to meticulously with bylaws of the region. MoEF norms, norms of National
further scope of additional parking for future Building Code and DTCP, Haryana laws have been strictly
requirement. There should be no traffic congestion adhered to while preparation of the plans. Same shall be
near the entry and exit points from the road implemented during the operation phase.
adjoining the proposed project site. Parking should
be fully internalized and no public space should be
used.
q) Operation and maintenance of STP, solid waste Maintenance of STP will be done regularly. The waste
management and electrical infrastructure, pollution generated in the project will be collected, segregated,
control measures shall be ensured even after the transported and treated as per HWM Rules. The E- waste
completion of sale. and hazardous waste 0will be disposed off properly. All the
measures will be taken to avoid pollution in the premises.
r) Different type of wastes should be disposed off as Different type of wastes will be disposed off as per provisions
per provisions of municipal solid waste, biomedical of municipal solid waste, biomedical waste, hazardous
waste, hazardous waste, e waste, battery shall be waste, e-waste, batteries & plastic rule made under
disposed off as per existing E waste Management Environment Protection Act, 1986.
rules 2011 and batteries management rules 2001.
The project proponent should maintain a collection
center for e waste and it should be disposed of to
only registered and authorized dismantler/recycler.
s) Standards for discharge of environmental pollutants The standards for discharge depicted in Environmental
as enshrined in various schedules of environmental Protection Rules will be met.
protection rules 1986 shall be strictly complied
with.
t) The project proponent shall make provision for The guard pod will be provided as per the requirement of the
guard pond and other provisions for safety against project.
failure in the operation of waste water treatment
facilities. The project proponent shall also identify
acceptable outfall for treated effluent.
u) The project proponent shall ensure that the stack Adequate stack height will be provided as per CPCB
height of DG sets is as per the CPCB guidelines and guidelines and norms. Regular monitoring and measures
also ensure that emission standards of noise and air shall be undertaken to ensure that the emission levels are
are within the CPCB prescribed limits. Noise and below the prescribed limits.
emission level of DG sets are greater than 800 KVA
shall be as per the CPCB latest standards for high
capacity DG sets.
v) All electric supply exceeds 100 amp, 3 phase shall Current power factor is assumed to be 0.95, which already

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
8
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

S. No. Conditions of Environmental Clearance Status of Compliance

maintain the power factor between 0.98 lag to 1 at gives a lot of saving
the point of connection.
w) The project proponent shall minimize heat island Shading in form of chajjas, screens and roof equipment has
effect through shading and reflective pervious been proposed.
surface instead of hard surface.
x) The project proponent shall not use fresh water for Double stage cooling has not been proposed but yes, we will
HVAC & DG cooling. The project proponent shall use only STP water for HVAC cooling in order to reduce
also use evaporating cooling technology and double water consumption during operational phase. Further, DG
stage cooling system for HVAC in order to reduce sets have been proposed on the surface instead of basement
water consumption. Further temperature, relative and as such water for DG cooling is not required.
humidity during summer and winter season should
be kept at optimal level. Variable speed drive, best
co-efficient of performance, as well as optimal
integrated point load value and minimum outside
fresh air supply may be resorted for conservation of
water and power. Coil type cooling DG sets shall be
used for saving cooling water consumption for
water cooling DG Sets.
y) The project proponent shall ensure that the We shall ensure that the transformer is constructed with
transformer is constructed with high quality grain high quality grain oriented, low loss silicon steel and virgin
oriented. Low loss silicon steel and virgin electrolyte grade copper.
electrolyte grade copper. The project proponent
shall obtain manufacturer’s certificate also for that.
z) Water supply shall be metered among different Water use will be metered down regularly.
users and utilities.
aa) The project proponent shall ensure that exit Stack height and design will ensure that exit velocity from
velocity from the stack should be sufficiently high. the stack is sufficiently high to prevent down-water under
Stack shall be designed in such a way that there is any meteorological condition.
no stack down-water under any metrological
condition.
ab) The project proponent shall provide water Water sprinkling system will be installed in the project area
sprinkling system in the project area to the to suppress the dust particles.
suppress the dust in addition to the already
suggested mitigation measures in the Air
Environment Chapter of EMP.
ac) The project proponent shall adopt adequate Air Adequate measures will be used for controlling the spread of
Pollution Control Measures to mitigate the air dust particles in the neighborhood areas. Adequate Parking
pollution problem and also ensure to provide area will be provided to avoid traffic congestion and easy
sufficient space for parking of vehicles to avoid any move of the heavy vehicles too.
congestion on the road during peak season. Parking
space should be calculated keeping in mind that
much more space is required for trucks to turn and
move as compared to smaller vehicles.
ad) The project proponent shall ensure that no dust is Dust sprinklers , dust screens etc. will be provided to avoid
raised even during peak season operation phase. the spread of dust in neighborhood area to maintain the
NAAQ standards must be maintained during both NAAQ Standards
construction and operation phase.
ae) The Effluent Treatment Plant of 165 KLD capacity ETP of adequate capacity will be installed for the treatment
shall be installed for treatment of processing water of effluents. Regular maintenance of ETP will be done.
(effluent). The project proponent shall ensure that We assure that we will not discharge the Effluents in the
the waste water generation as well as values for public sewer and the effluent should conform to the
different parameters of effluent should conform to standards as prescribed under a Rule 3 of Environment
the standards as prescribed under a Rule 3 of (Protection) Rules, 1986.
Environment (Protection) Rules, 1986. The project

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
9
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

S. No. Conditions of Environmental Clearance Status of Compliance

proponent shall not discharge the effluent in the


public sewer / drain.
af) The project proponent shall provide sound We will provide the sound reduction in form of green belt
reduction techniques during day time. development and use silent DG Sets.
ag) The project proponent shall dispose off Bio-Medical Bio medical waste will be disposed off as per Bio- Medical
waste as per Bio- Medical (Management & (Management & Handling) Rules, 1998.
Handling) Rules, 1998.
ah) The project proponent shall ensure proper Air Noted. Proper air ventilation and light system will be
ventilation and light system in the basement area developed for comfortable living of human beings in the
for comfortable living of human being and shall basement.
ensure that number of Air Changes per Hour (ACH)
in basement never falls below 15. In case of
emergency capacity for increasing ACH to the extent
of 30 must be provided by the project proponent.
ai) The green space of (21%) of plot area shall be We will maintain 30.24% of the green as per green belt
developed before the project site Is revisited after development plan submitted to SEIAA Haryana.
removal of all deficiencies by end of November,
2014.
aj) The project proponent shall provide green area on Green area will be provided as per green belt development
terrace and roof top. plan submitted to SEIAA Haryana.
ak) The project proponent shall install solar panel for We will install sonar panels for utilization of solar energy for
energy conservation. street lightings and common area illumination and will
minimize the energy consumption.

PART B – GENERAL CONDITIONS

S. No. Conditions of Environmental Clearance Status of Compliance


I. The project proponent shall ensure the commitments Noted. We ensure the commitments made in Form-1,
made in Form-1, Form-1A, EIA/EMP and other Form-1A, EIA/EMP and other documents submitted to the
documents submitted to the SEIAA for the protection of SEIAA for the protection of environment and proposed
environment and proposed environmental safeguards environmental safeguards are complied with in letter and
are complied with in letter and spirit. In case of spirit.
contradiction between two or more documents or any
point, the most environmentally friendly commitment
shall be taken as commitment by the project proponent.
II. The project proponent shall also submit six monthly We will regularly submit six monthly compliance reports
reports on the status of compliance of the stipulated EC along with the test reports both in hard and soft forms to
conditions including results of monitored data (both in the SEIAA and the regional office, MoEF. GOI, Northern
hard copies as well as by e-mail) to the northern region Chandigarh.
Regional Office of MoEF, the respective zonal office of
CPCB, HSPCB and SEIAA Haryana.
III. STP and ETP outlet after stabilization and stack Noted. Monitoring of STP/ETP outlet and DG Stacks
emission shall be monitored daily. Other environmental emissions will be done on daily basis. Other environmental
parameters shall be monitored on monthly basis. After parameters shall be monitored monthly. Environmental
every 3 months the project proponent shall conduct audit will be carried out on three-monthly basis.
environmental audit, and shall take corrective
measures, If required, without any delay.
IV. The SEIAA, Haryana reserve the right to add additional Noted.
safeguards measures subsequently, If found necessary.
Environmental clearance granted will be revoked ir it is
found that false information has been given for getting
approval of this project. SEIAA reserves the right to
revoke the clearance if conditions stipulated are not

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
10
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

S. No. Conditions of Environmental Clearance Status of Compliance


implemented to the satisfaction of SEIAA / MoEF.
V. The Project proponent shall not violate any judicial We will respect and not violate any judicial orders/
orders /pronouncements issued by court/Tribunal. pronouncements issued by the Court / Tribunal.
VI. All other statutory clearance such as approval for Noted. However, clearance from Civil Aviation
storage of diesel from Chief Controller of Explosives, Department ,Forest Conservation Act,1980, and Wildlife
Fire Department, Civil Aviation Department ,Forest (Protection) Act, 1972 are not applicable on our project.
Conservation Act,1980, and Wildlife (Protection) Act,
1972 etc. shall be obtained, as applicable by project
proponent from the respective authorities prior to
construction of the project.
VII. The project proponent should inform the public that the The general public has already been informed about the
project has been in accorded Environmental clearance project obtaining environmental clearance. Copy of EC
by SEIAA and copies of the clearance letter are available letter shall also be uploaded on our company’s website.
with the State Pollution Control Board & SEIAA. This
should be advertised within 7 days from date of issue of
clearance letter at least in two local newspapers that
are widely circulated in the region and copy of the same
should be forwarded to SEIAA Haryana. A copy of
environmental clearance conditions shall also be put on
the project proponent’s web site for public awareness.
VIII. Under the provision of Environment (Protection) Act, Noted.
1986, Legal action shall be initiated against the project
proponents if it was found that construction of the
projects has been started before obtaining prior
Environmental Clearance.
IX. Any appeal against this Environmental Clearance shall Agreed
lie with the National Green Tribunal, If preferred with
in a period of 30 days as prescribed under section 16 of
the National Green Tribunal Act, 2010.
X. The fund ear-marked for environment protection Funds ear-marked for environment protection measures
measures should be kept in separate account and would be kept in a separate account and would not be
should not be diverted for other purposes and year diverted for other purposes. Year wise expenditure report
wise expenditure report should be submitted to the would be submitted to the SEIAA/RO MoEF, Gol under
SEIAA/RO MoEF, Gol under rules prescribed for rules prescribed for Environmental Audit.
Environmental Audit.
XI. The project proponent shall ensure that no vehicles Agreed & same will be followed in construction as well as
during construction/ operation phase enter the project in operational phase.
premises without valid ‘Pollution Under Control’
certificate from competent Authority.
XII. The project proponent is responsible for compliance of We agree that we are responsible for fulfillment of all the
all conditions in Environmental Clearance letter and conditions given in Environment Clearance Letter of the
project proponent can not absolve himself/herself of project.
the responsibility by shifting it to any contractor
engaged by project proponent.
XIII. The project proponent shall seek fresh Environmental Yes, we will obtain new clearance if at any stage the
Clearance if at any stage there is change in the planning project will be modified.
of the proposed projects.
XIV. The proponent shall upload the status of compliance of Yes, we shall upload the status of compliance of EC
the stipulated EC conditions, including results of conditions including results of the monitored data on the
monitored data on their website and shall update the trust’s website for public domain.
same periodically. It shall be simultaneously be sent to
the Regional Office of MoEF, the respective zonal office
of CPCB and the SPCB. The criteria pollutant levels
namely: PM2.5, PM10, SOX, NOX, Ozone, lead, O,

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
11
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

S. No. Conditions of Environmental Clearance Status of Compliance


Benzene, Ammonia, Benzopyrene, arsenic and Nikel,.
(Ambient levels as well as stack emission) or critical
sectoral parameters, indicated for the project shall be
monitored and displayed at a convenient location near
the main gate of the company in the public domain.
XV. The environmental statement for each financial year Noted. Environmental statement will be filed in the
ending 31st March in Form-V as is mandated to be operational phase of the project.
submitted by the project proponent to the HSPCB
Panchkula as prescribed under the Environmental
(Protection) Rules, 1986, as amended subsequently,
shall also be put on the website of the company along
with the status of compliance of the EC conditions and
shall also be sent to the respective Regional Office of
MoEF by e-mail.
XVI. The project proponent is responsible for compliance of We agree that we are responsible for fulfillment of all the
all conditions in Environmental Clearance Letter and conditions given in Environment Clearance Letter of the
project proponent can not absolve himself/herself of project.
the responsibility by shifted it to any contractor
engaged by project proponent.
XVII. The environmental clearance granted shall be limited to Noted for the compliance.
the issue concerning the environment and all other
issues like ownership of land, lease of land, purpose of
the lease for allotment of land by HUDA, FAR covered
and allowed of any other connected issue and any other
legal issue / court case etc. will be decided and
considered by the concerned competent authority.
XVIII. The EC is subject to the condition that there is no There is no dispute over the land. We have obtained CLU
dispute over the said land by any agency of the from TCP Haryana for development of the eye hospital.
Government including Panchayat of Village before the Copy enclosed as Annexure-7.
court/Govt. and 24 meter wide approach road
connecting the site is as per approved master plan by
the competent authority.
XIX. Corporate Environment and Social Responsibility CSER is not applicable as the firm is a trust.
(CSER) shall be laid down by the project proponent (2%
shall be earmarked) as per guidelines of MoEF, GoI
Office Memorandum No. J-1101/41/2006-IA.II(I) dated
18.05.2012 and Ministry of Corporate Affairs, GoI
Notification dated 27.02. 2014. A separate audit
statement shall be submitted in the compliance
Environmental related work proposed to be executed
under this responsibility shall be undertaken
simultaneously. The project proponent shall select and
prepare the list of the work for implementation of CSER
of its own choice and shall submit the same before the
start of construction.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
12
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

CHAPTER- 3

DETAILS OF ENVIRONMENTAL MONITORING

3.1 AMBIENT AIR QUALITY MONITORING

3.1.1 Ambient Air Quality Monitoring Stations

Ambient air quality monitoring has been carried out at 3 locations; one being near the main gate,
second one is near project site and third is near back side of the project. This will enable to have a
comparative analytical understanding about air quality and the changes in the air environment in
the study area with respect to the condition prevailing. The locations of the ambient air quality
monitoring stations are given in Table 3.1.

Table 3.1 Details of Ambient Air Quality Monitoring Stations

S. No. Location Code Location Name/ Description

1 AAQ-1 Near Main gate

2 AAQ-2 Near Centre of Project

3. AAQ-3 Near Back Side of the Project

AAQ-1: Near Main Gate:

The sampler was placed near main gate of building and was free from any obstructions.
Surroundings of the sampling site represent commercial environmental setting

AAQ-2: Near Centre of Project:

The sampler was placed at near centre of project and was free from any obstructions.
Surroundings of the sampling site represent commercial environmental setting.

AAQ-2: Near Back Side of the Project:

The sampler was placed at near back side of the project and was free from any obstructions.
Surroundings of the sampling site represent commercial environmental setting.

3.1.2 Ambient Air Quality Monitoring Methodology

Monitoring was conducted in respect of the following parameters:

 Particulate Matter 2.5 (PM2.5)


 Particulate Matter 10 (PM10)
 Sulphur Dioxide (SO2)
 Oxides of Nitrogen (NOx)
 Carbon Monoxide (CO)

Installation of Respirable Dust sampler (RDS) & Fine Particulate Sampler (FPS) was done with
the attachment for the 24 hourly ambient air qualities monitoring as per Gazette Notification
16th November 2009.

The air samples were analyzed as per standard methods specified by Central Pollution Control
Board (CPCB) and IS: 5182. The techniques used for ambient air quality monitoring and minimum
detectable levels are given in Table 3.2.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
13
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

Fine Particulate Sampler instruments have been used for monitoring Particulate Matter 2.5
(PM2.5 i.e. <2.5 microns), and Respirable Dust Sampler was used for sampling Respirable
fraction (<10 microns), gaseous pollutants like SO2, and NOx. Bladder and Aspirator bags were
used for collection Carbon monoxide samples. Gas Chromatography techniques have been used
for the estimation of CO.

Table 3.2 Techniques used for Ambient Air Quality Monitoring

S. No. Parameter Technique Technical Protocol

Fine Particulate Sampler, Gravimetric


1 Particulate Matter 2.5 CPCB/MOEF Guidelines
Method

Respirable Dust Sampler, with cyclone


2 Particulate Matter 10 IS-5182 (Part-23)
separator, Gravimetric Method

3 Sulphur dioxide Modified West and Gaeke IS-5182 (Part- II)

4 Oxides of Nitrogen Jacob & Hochheiser IS-5182 (Part-VI)

5 Carbon Monoxide Gas Chromatography IS-5182 (Part-X)

3.1.3 Ambient Air Quality Monitoring Results

The detailed on-site monitoring results of PM 2.5, PM 10, SO2, NOx and CO are presented in Table
3.3.

Table 3.3 Ambient Air Quality Monitoring Results

Test Result
S. No. Parameter Test Method NAAQS*
AAQ1 AAQ2 AAQ3

PM2.5 sampler
1. Particulate Matter (PM2.5), g/m3 43.56 41.50 45.82 60
(Gravimetric)

2. Particulate Matter (PM10), g/m3 84.72 80.20 74.50 IS: 5182 (P-23), 2006 100

IS: 5182 (P-6), 1975


3. Nitrogen Dioxide (NO2), g/m3 32.60 31.15 30.15 80
Reffirmed-1998

4. Sulphur Dioxide (SO2), g/m3 18.44 15.50 19.20 IS: 5182 (P-2), 2001 80

5. Carbon Monoxide (CO) mg/m3 0.70 0.79 0.72 IS: 5182 (P-10), 1999 4

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
14
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

100
90
80
70
60
50
40
30
20
10
0
AAQ1 AAQ2 AAQ3 LIMITS
PM2.5 43.56 41.5 45.82 60
PM10 84.72 80.2 74.5 100
NO2 32.6 31.15 30.15 80
SO2 18.44 15.5 19.2 80

Figure 3.1 Location-wise Variation of PM 2.5, PM10, NO2 & SO2 Ambient Air Quality

4
3.5
3
2.5
2
1.5
1
0.5
0
AAQ1 AAQ2 AAQ3 Limits
CO 0.7 0.79 0.72 4

Figure 3.2 Location-wise Variation of CO in Air Quality

3.1.4 Discussion on Ambient Air Quality in the Study Area

PM10 and PM 2.5 levels at the project site are within the permissible limit of 100 μg/m 3 and 60
μg/m3 respectively (for residential, rural and other areas as stipulated in the National Ambient
Air Quality Standards). SO2, NOx and CO was observed within the corresponding stipulated limits
(Limit for SO2 and NOx: 80 g/m3 and limit for CO: 4.0 g/m3) at all monitoring locations. Station
wise variation of ambient air quality parameters has been pictorially shown in Figure 3.1 & 3.2.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
15
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.2 AMBIENT NOISE MONITORING

3.2.1 Ambient Noise Monitoring Locations

The main objective of noise monitoring in the study area is to assess the present ambient noise
levels in near main gate due to various construction allied activities and increased vehicular
movement. A preliminary reconnaissance survey has been undertaken to identify the major noise
generating sources in the area. Ambient noise monitoring was conducted at 1 location at the
boundary of the project site as given in Table 3.4.

Table 3.4 Details of Ambient Noise Monitoring Stations

S. No. Location Code Location Name/ Description

1 N1 Near Main Gate

2 N2 Near Centre of project

3 N3 Near Back Side of Project

3.2.2 Methodology of Noise Monitoring

Noise levels were measured using sound level meter. Noise level monitoring was carried out
continuously for 24-hours with one hour interval starting at 06:00 hrs to 06:00 hrs next day. The
noise levels were monitored on working days only. During each hour Leq were directly computed
by the instrument based on the sound pressure levels. Monitoring was carried out at ‘A’ response
and fast mode.

3.2.3 Ambient Noise Monitoring Results

The location wise ambient noise monitoring results is summarized in Table 2.5. The location-
wise variation of noise levels are graphically presented in Figure 3.3.

Table 3.5 Ambient Noise Monitoring Results

Location Code
Parameter N1 N2 N3
Day Time Night Time Day Time Night Time Day Time Night Time
Lmax 62.10 51.60 63.30 52.70 59.80 51.30

Lmin 43.60 38.40 44.10 39.80 42.30 37.80

Leq 54.20 43.65 53.50 42.15 51.40 41.58

CPCB Limit(Leq in
dB(A) 55.00 45.00 55.00 45.00 55.00 45.00
(Commercial Limit)

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
16
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

70
60
50
40
30
20
10
0
Day Time Night Time Day Time Night Time Day Time Night Time
N1 N2 N3
Lmax 62.1 51.6 63.3 52.7 59.8 51.3
Lmin 43.6 38.4 44.1 39.8 42.3 37.8
Leq 54.2 43.65 53.5 42.15 51.4 41.58
Limit 55 45 55 45 55 45

Figure 3.3 Location-wise Variation of Ambient Noise Levels

3.2.4 Discussion on Ambient Noise Levels in the Study Area

Day Time Noise Levels (Lday):


The day time noise level at all the locations were found to within limits prescribed for Commercial
area i.e. 55 db (A).

Night Time Noise Levels (Lnight):


The night time noise level at all the locations were found to within limit prescribed for commercial
area i.e. 45 dB (A).

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
17
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.3 WATER QUALITY MONITORING

3.3.1 Drinking water Quality Monitoring Locations

Keeping in view the importance of drinking water as an important source of drinking water to
the local population, sample of drinking water was collected from the project site for the
assessment of impacts of the project on the groundwater quality.

Water sample was collected from the project site. The sample was analyzed for various parameters
to compare with the standards for drinking water as per IS: 10500. The details of water sampling
locations are given in Table 3.6.

Table 3.6 Details of Water Quality Monitoring Station

S. No. Location Code Location Name/ Description

1. DW 1 From Project Site

3.3.2 Methodology of drinking water Quality Monitoring

Sampling of drinking water was carried out on May, 2015. Samples were collected as grab sample
and sampling forms are filled in as per the sampling plan. The preservative sample were properly
added to preserve as per standard operating procedures (SOP) and stored immediately in ice
boxes, which were ensured for appropriate temperatures. Sample for chemical analysis was
collected in polyethylene carboys. Sample collected for metal content were acidified to <2 pH with
1 ml HNO3. A sample for bacteriological analysis was collected in sterilized glass bottles.

Soon after the completion of sampling, chain of custody sheets for the samples are filled in and then
they were transported by road to Vardan Enviro Lab, Gurgaon for further analysis. Proper care was
taken during packing and transportation of samples. All the samples reached the central laboratory
within the holding times for different parameters. After ensuring the same the samples were
forwarded immediately for analysis.

The samples were analyzed as per the standard procedures specified in 'Standard Methods for the
Examination of Water and Wastewater' published by American Public Health Association (APHA)
and CPCB. The analytical techniques and the test methods adopted for testing of ground water are
given in Table 3.7.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
18
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.3.3 Drinking water Quality Monitoring Results

The detailed Drinking water quality monitoring results are presented in Table 3.7.

Table 3.7 Drinking water Quality Monitoring Results


Limits of IS:10500 -2012
Permissible limit
S. No. Parameter Test-Method Result Unit Desirable
in the Absence of
limit
Alternate Source
(Max.)
(Max.)
1. pH (at 25 0C) APHA 22nd Edition, 4500-H+ B 7.58 -- 6.5 to 8.5 No Relaxation

2. Colour APHA 22nd Edition, 2120 B BDL (DL 5Hazen) Hazen 5 15

3. Turbidity APHA 22nd Edition, 2130 B BDL (DL 1 NTU) NTU 1 5

4. Odour APHA 22nd Edition, 2150 B Agreeable -- Agreeable Agreeable

5. Taste APHA 22nd Edition, 2160 B Agreeable -- Agreeable Agreeable

6. Total Hardness as CaCO3 APHA 22nd Edition, 2340 C 97.75 mg/l 200 600

7. Calcium as Ca APHA 22nd Edition, 3500 Ca B 25.40 mg/l 75 200

8. Alkalinity as CaCO3 APHA 22nd Edition, 2320 B 154.32 mg/l 200 600

9. Chloride as Cl APHA 22nd Edition, 4500-Cl- B 75.15 mg/l 250 1000

10. Cyanide as CN APHA 22nd Edition, 4500 CN- D BDL(DL 0.02 mg/l) mg/l 0.05 No Relaxation

11. Magnesium as Mg APHA 22nd Edition, 2340 B 8.35 mg/l 30 100

12. Total Dissolved Solids APHA 22nd Edition, 2540 C 228.00 mg/l 500 2000

13. Sulphate as SO4 APHA 22nd Edition, 4500 E 18.20 mg/l 200 400

14. Fluoride as F APHA 22nd Edition, 4500-F- D 0.79 mg/l 1.0 1.5

15. Nitrate as NO3 IS 3025 (P-34) 1988 5.6 mg/l 45 No Relaxation

16. Iron as Fe APHA 22nd Edition, 3500-Fe B 0.21 mg/l 0.3 No relaxation

17. Aluminium as Al APHA 22nd Edition, 3111 B BDL(DL 0.03 mg/l) mg/l 0.03 0.2

18. Boron APHA 22nd Edition, 4500B C 0.30 mg/l 0.5 1

19. Hexa Chromium as Cr+6 APHA 22nd Edition, 3111 B BDL(DL 0.01 mg/l) mg/l 0.05 No Relaxation

20. Phenolic Compounds APHA 22nd Edition, 5530 C BDL(DL 0.001 mg/l) mg/l 0.001 0.002

21. Mineral Oil Clause 6 of IS:3025(Part 39) BDL(DL 0.01mg/l) mg/l 0.5 No Relaxation
Anionic Detergents as MBAS APHA 22nd Edition, 5540 C BDL(DL 0.02 mg/l) 0.2 1.0
22. mg/l

23. Zinc as Zn APHA 22nd Edition, 3111 B <0.2 mg/l 5 15

24. Copper as Cu APHA 22nd Edition, 3111 B <0.2 mg/l 0.05 1.5

25. Manganese as Mn APHA 22nd Edition, 3111 B BDL(DL 0.10 mg/l) mg/l 0.1 0.3

26. Cadmium as Cd APHA 22nd Edition, 3111 B BDL(DL 0.001 mg/l) mg/l 0.003 No Relaxation

27. Lead as Pb APHA 22nd Edition, 3111 B BDL(DL 0.01mg/l) mg/l 0.01 No Relaxation

28. Selenium as Se APHA 22nd Edition, 3111 B BDL(DL 0.01 mg/l) mg/l 0.01 No Relaxation

29. Arsenic as As APHA 22nd Edition, 3111 B BDL(DL 0.01 mg/l) mg/l 0.01 No Relaxation

30. Mercury as Hg APHA 22nd Edition, 3111 B BDL (DL 0.001 mg/l) mg/l 0.001 No Relaxation

31. Total Coliform IS 1622,1981(Reaffirmed 2003) <2/100ml MPN/100ml - 10.00

32. E. Coli IS 1622,1981(Reaffirmed 2003) Absent MPN/100ml Absent Absent

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
19
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.3.4 Discussion on Drinking water Quality in the Study Area

The drinking water quality in the project area is observed to be alkaline in nature with total
alkalinity reaching up to 154.32 mg/L at project against desirable limit of 200 mg/L, however,
alkalinity is less than the permissible limit of 600 mg/L. Total dissolved solids in the drinking water
is 228.00 mg/L at project site against prescribed limit of 500 mg/L. However, remaining
parameters are within the CPCB prescribed limits.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
20
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.4 SOIL MONITORING

3.4.1 Soil Monitoring Locations

The objective of the soil monitoring is to identify the impacts of ongoing project activities on soil
quality and also predict impacts, which have arisen due to execution of various constructions
allied activities. Accordingly, a study of assessment of the soil quality has been carried out
To assess impacts of ongoing project activities on the soil in the area, the Physico-chemical
characteristics of soils were examined by obtaining soil samples from selected points and
analysis of the same. Single sample of soil was collected from the project site for studying soil
characteristics, the location of which is listed in Table 3.8.

Table 3.8 Details of Soil Quality Monitoring Location

S. No. Location Code Location Name/ Description


1. S1 Near Project Site

3.4.2 Methodology of Soil Monitoring

The sampling has been done in line with IS: 2720 & Methods of Soil Analysis, Part-1, 2nd edition,
1986 of American Society for Agronomy and Soil Science Society of America. The homogenized
samples were analyzed for physical and chemical characteristics (physical, chemical and heavy
metal concentrations). The soil samples were collected in the month of May, 2015.

The samples have been analyzed as per the established scientific methods for Physico-chemical
parameters. The heavy metals have been analyzed by using Atomic Absorption Spectro-
photometer.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
21
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.4.3 Soil Monitoring Results

Single sample of soil is collected from the site to check the quality of soil of the study area .The
Physico-chemical characteristics of the soil, as obtained from the analysis of the soil sample, are
presented in Table 3.9.

Table 3.9 Physico-Chemical Characteristics of Soil in the Study Area

S. No. Parameter Protocol Result Unit


0
1. pH (at 25 C) IS : 2720 (P-26,1987) 8.20 --
2. Conductivity IS:14767-2000 Reaffirmed 2006 0.415 mS/cm
3. Soil Texture USDA Method, 1968 Silty Loam --
4. Color USDA Method, 1968 Yellowish Brown --
5. Water holding capacity USDA Method, 1968 34.15 %
6. Bulk density USDA Method, 1968 1.68 gm/cc
7. Chloride as Cl USDA Method, 1968 78.95 mg/100gm
8. Calcium as Ca USDA Method, 1968 33.55 mg/100gm
9. Sodium as Na USDA Method, 1968 27.46 mg/100gm
10. Potassium as K USDA Method, 1968 175.05 kg/hec.
11. Organic Matter IS:2720 (P-22, 1972) 0.75 %
12. Magnesium as Mg USDA Method, 1968 22.68 mg/100gm
13. Available Nitrogen as N IS:14684, 1999 240.50 kg./hec.
14. Available Phosphorus USDA, APHA-4500PC 32.40 kg./hec.
15. Zinc as Zn APHA-3030D, APHA-3111B 6.20 mg/100gm
16. Manganese as Mn APHA-3030D, APHA-3111B 4.85 mg/100gm
17. Chromium as Cr APHA-3030D, APHA-3111B 1.34 mg/100gm
18. Lead as Pb APHA-3030D, APHA-3111B 1.24 mg/100gm
19. Cadmium as Cd APHA-3030D, APHA-3111B 1.62 mg/100gm
20. Copper as Cu APHA-3030D, APHA-3111B 3.75 mg/100gm

3.4.4 Discussion on Soil Characteristics in the Study Area

The soil in study area is characterized by moderate organic content. The soil quality in the project
area has not been affected by the project activities.

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
22
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

3.5 Site Photographs

Ambient Air Monitoring

Ambient Noise Monitoring

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
23
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

Soil Sampling

Drinking Water Sampling

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
24
Project: Proposed Eye Hospital, Village- Ullahawas, District- Gurgaon (Haryana)
EC No. SEIAA/HR/2015/308 dated 19-03-2015

Project Site

Project Site

Vardan Enviro Net, D-142, Sushant Lok-lll, Golf Course Road, Sector 57, Gurgaon
E-mail: vardanenviro165@gmail.com, vardanenvirolab@gmail.com
25

Das könnte Ihnen auch gefallen