GANTT CHART- TWO MONTH IMPLEMENTATION PROCESS OF CPA CONSTRUCTION COMPANY

OBJECTIVE SPECIFIC ACTIONS WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7
Submission of Revision proposal to
the Head Admin Staff              
Evaluating the importance of the
revisions before informing the higher
management              
Submission of the revisions by the
AIM 1- Revising the
Head admin to Mr. Caballero              
Company's Contract
Initial Review of the Plan by Mr.
Terms and
Caballero together with the Board of
Conditions
Directors              
coordinated with Mr.
Meeting with the BOD and Project
Alejandro Caballero
Management department head              
Processing the documents necessary
for the revisions              
Mr. Caballero calls for a company
meeting together with the head of
each department              

Schedule a meeting with Mr. Rondo


Pascual. The project owner of C5
Villa Fuerde
             
Discuss the revisions occurred in the
AIM 2- Changing management policy such as 2% for
Management Process every 30 days due policy.              
Gantt chart - Current Present evidences or document of
Plan for C5 Villa revisions signed and approved by
Fuerde BOD              
Explain further the nature of
revisions together with its legalities              
Prepare the new contract              
Proceed to the formal signatory of
contracts              
Table No. 5. Gantt Chart of Two month Implementation Process of CPACC