Beruflich Dokumente
Kultur Dokumente
I. INTRODUCTION
Fig. 3. Dynamometer with a minimum breaking load. Fig. 5. Pole on the minumum braking load – side view
Fig. 11. Base region shortly after the withdrawal of the flame.
Fig. 12. Base region 15 seconds after the withdrawal of the flame.
The activities take place directly at the workplace, which Fig. 23. Fixed model.
may install and assemble the entire structure with a small
crane, as seen in Figures 18 to 20.
The union between the modules is made with the expansive
sleeve and inner link plate of the walls, so that the parts do not
suffer from vibration effects since this system does not transfer
the effort to the pin, turning the two walls in a single fiber piece
shown in Figures 21 to 26.
B. Foundations
In this project was observed a difference practically in all
items of the structures foundation, such as excavation, con-
crete, backfill, steel armor, reused moulds, soil deposit, flexi-
ble conduit; no item listed above is used in the foundations of
FRP structures.
For all structures, the foundations follow basically the pat-
tern used for the wooden structures, which at the base of poles
is fixed two pieces of wood to length of 2.00 meters, as seen in
figures 27 and 28.
These parts are installed horizontally into each pit, and in
different depths, of 45 cm to the first piece and 65 cm to the
second, from the ground level.
Fig. 26. Assembly of the structure after completed connections. Fig. 27. Foundation project.
For this transmission line was used 496 fiber poles, totaling
248 structures, of which no steel needed in foundations.
The material saving was not envisioned in this item, there
was an increase by 11%, but the assembly had about 3% reduc-
tion, just by reducing weight and ease of transport.
The major differential of reduction for this item was in the
foundation, by 84% reduction, which can be seen in table 1.
TABLE 1
COMPARASION OF VALUES.
C. Execution time
Another significant item for using this type of structure is
the time to install the foundations, which for a similar transmis-
sion line last 7 months on average. Using FRP structures, it was
performed 3 months on average, just for the facility of in-
stalling the foundation and assembly, as seen in Table 2.
TABLE 2 E. Sustainability
SCHEDULE OF EXECUTION;
This project had a significant reduction of all materials and
services used comparatively in foundations of the steel struc-
ture. No use of mineral resources such as steel and concrete,
and also preserve the integrity of soil, minimizing the excava-
tions. Table 3 shows the result of reduction of these resources.
TABLE 3
COMPARATIVE
V. REFERENCES
Standards:
[1] Associação Brasileira de Normas Técnicas – Projeto de Linhas Aéreas
de Transmissão e Subtransmissão deEnergia Elétrica – NBR 5422 – Brasil.
Books:
[2] Labegalini, P. R.; Labegalini, J. A.; Fuchs, R. D.; Almeida, M. T. “Pro-
jetos Mecânicos das Linhas Aérea.
[3] Marinucci, G. Materiais Compósitos Poliméricos. Ed. Artliber, 2011.
[4] Carvalho, A. Tosfac - Total Strain Failure Criterion. Ed. Artsim, 2009.
[5] Abmaco. Compósitos I – Materiais, Aplicações, Desempenho e Tendên-
cias. Ed. SLEA, 2008.
[6] Abmaco. Compósitos II – Processos. Ed. SLEA, 2009.
[7] Abmaco. Compósitos III – Processos. Ed. SLEA, 2010.