Calculation of fee amount to be charged from road users as per fee rule 2008 Kadapa - Kurnool Section of NH-40

(Applicable as per Transition fee rule, 2011)

Total length 60.780 Km, Nandyal (at Km 288.500) For the year 2020-21 (w.e.f. 01.04.2020)

HCM/ EME / Oversized (7 or


Car LCV Truck/ Bus Monthly Pass
MAV (3-6 axles) more axles)

1 Base rates A 0.65 1.05 2.2 3.45 4.2 150


Revised
2 Fixed increase (11*3%) B= A * 39% 0.2535 0.4095 0.858 1.3455 1.638 58.5
base rates
3 Revised base rates C= A+B 0.9035 1.4595 3.058 4.7955 5.838 208.5
4 WPI as on 06.01.07 D 208.7 208.7 208.7 208.7 208.7 208.7
5 WPI for Dec, 19 (123 x 1.873 x1.641= 378.050) E 378.0500 378.0500 378.0500 378.0500 378.0500 378.0500
Variable
increase 40% of increase in WPI (As % of revised base
6 F=(E-D)/D*0.4 0.3246 0.3246 0.3246 0.3246 0.3246 0.3246
rates)
7 Increase in base rates due to change in WPI G=C* F 0.2933 0.4737 0.9926 1.5565 1.8949 67.6751
8 Revised base rates (Cummulative) H=C+G 1.1968 1.9332 4.0506 6.3520 7.7329 276.1751
Road Length Road Length in Kms (excluding length of
9 I 50.350 50.350 50.350 50.350 50.350
(kms) bypass, if any)
10 Fee for the road stretch J=I*H 60.26 97.34 203.95 319.82 389.35 276.1751
11 Base Rate for 2007 – 2008 (10 to 15 Cr.) L 5.00 7.50 15.00 22.00 30.00
For Every Additional 5 Crores from 15 to 100
12 M 1.00 1.50 3.00 4.50 6.00
Crores
13 From 15 to 100 Crores (Units) N 17 17 17 17 17
For Every Additional 5 Crores from 100 to 200
Nandyal O 0.75 1.15 2.25 3.40 4.50
Crores
Bypass for a From 100 to 115 Crores (Units) P 3.00 3.00 3.00 3.00 3.00
length of 14 Base Rate for 2007 – 2008 (15 to 100 Cr.) Q=M*N 17.00 25.50 51.00 76.50 102.00
10.430 km – Base Rate for 2007 - 2008 (15 to 100 Crs.) R=O*P 2.25 3.45 6.75 10.20 13.50
115.00
Crores 15 Base Rate for 2007 – 2008 of Nandyal Bypass S=L+Q+R 24.25 36.45 72.75 108.70 145.50
16 Base Rate for 2019 – 2020 T = (S*39%)+S 33.7075 50.6655 101.1225 151.0930 202.2450
17 WPI as on 6th January 2007 U 208.70 208.70 208.70 208.70 208.70
18 WPI as on December 2019 V 378.05 378.05 378.05 378.05 378.05
19 Applicable Rate of Nandyal Bypass W 44.65 67.11 133.95 200.14 267.89

20 Applicable Total Rate of Toll Plaza 4 section X=W+J 104.9052 164.4486 337.8914 519.9600 657.2422
Present fee rate under fee rules 1997 as
21 Y 100 160 325 500 635
amended 2008 transition plan for FY 2019-20
22 Rate as per transition plan Z = Y + Y*25% 125.00 200.00 406.25 625.00 793.75
Pre rounded fee as per transition plan (X or AA
23 AA 104.91 164.45 337.89 519.96 657.24
whichever is less)
24 Rounding Off to nearest five rupees AB 105 165 340 520 655 275
25 Return trip in a day AC=X*1.5 157.3578 246.6730 506.8371 779.9400 985.8633
26 Rounded off fee for return trip AC 155 245 505 780 985
27 Rate for Monthly passes (50 Trips) AD=X*50*2/3 3496.8409 5481.6213 11263.0459 17331.9995 21908.0734
28 Rounded off fee for monthly passes AE 3495 5480 11265 17330 21910
Approved user Fee Rates for 2020-21 NHAI, RO, Vijayawada