Beruflich Dokumente
Kultur Dokumente
g) That the cutting of the trees and the partial leveling a) That the members and officials of the ZPPO did not
of a landform (which is determined to be an violate, or threaten with violation, petitioner’s right to
"elongated mound" but is alleged to be a "mountain" a balanced and healthful ecology;
by the petitioner) conducted by LAMI in its property in
Brgy. Bolitoc, Sta. Cruz, Zambales do not pose adverse b) That the members and officials of the ZPPO did not
environmental impact on the adjoining communities cover-up any alleged illegal activity of LAMI; and
more so to the larger areas or the entire provinces of
Zambales and Pangasinan.
c) The contents of the Memorandum (Special Report from the DENR; (2) affected the ecological balance of the
re: Police Assistance) dated 6 May 2012 submitted by affected towns and provinces since such leveling was done
S/Supt. Santiago to the PNP Regional Director. without the concurrence of its residents; and (3) instigated
the gradual eradication of the strip of land mass in Sta. Cruz,
On 10 September 2012, Agham presented its first and only Zambales that serves as protective barrier from floods
witness, former Rep. Angelo B. Palmones. Rep. Palmones was brought about by the swelling or surging of the coastal water
cross-examined by counsel for LAMI and counsel for public moving inward reaching other towns of Zambales and
respondents DENR, PPA, and ZPPO. 34 Pangasinan.39
On 26 September 2012, public respondents presented their On 4 February 2013, LAMI filed its Comment/Opposition to
witnesses.35 the Motion for Reconsideration. Agham then filed its Reply
dated 21 February 2013.
On 28 September 2012, LAMI manifested that it was adopting
the testimonies of the witnesses of the public respondents. In a Resolution dated 6 March 2013, the Court of Appeals
On the same hearing, LAMI presented its witness, Felipe E. declared that Agham’s Motion for Reconsideration was
Floria, LAMI’s Vice-President and General Manager. 36 submitted for resolution. Subsequently, Agham filed a
Supplemental Reply dated 29 April 2013 reiterating the same
In a Decision37 dated 23 November 2012, the Court of arguments.
Appeals decided the case in favor of petitioner. The appellate
court found that the government, through the CENRO, In a Resolution40 dated 31 May 2013, the Court of Appeals set
authorized LAMI to cut trees and LAMI strictly followed the Agham’s Motion for Reconsideration for hearing on 13 June
proper guidelines stated in the permit. The appellate court 2013. At the hearing, all parties were given time to argue
also stated that there can be no flattening of a mountain their case. Thereafter, the Motion for Reconsideration was
when there is no mountain to speak of. Thus, for failing to submitted for resolution.
comply with the requisites necessary for the issuance of a
Writ of Kalikasan, the Court of Appeals resolved to deny the Agham then filed a Manifestation dated 17 June 2013
petition. The dispositive portion of the Decision states: summarizing its arguments. On 4 July 2013, LAMI filed a
Motion to Expunge with Ad Cautelam Comment/Opposition.
WHEREFORE, premises considered, the petition is hereby On 11 July 2013, the Court of Appeals, for the last and third
DENIED. time, submitted the Motion for Reconsideration for resolution.
In the present case, Agham, in its Petition for a Writ of In the present case, LAMI was given a Tree Cutting
Kalikasan, cited two laws which LAMI allegedly violated: (1) Permit45 by the CENRO dated 17 April 2012. In the permit,
Section 68 of the Revised Forestry Code, as amended; and LAMI was allowed to cut 37 trees with a total volume of 7.64
(2) Sections 57 and 69 of the Philippine Mining Act. cubic meters within the port site, subject to the condition
that the trees cut shall be replaced with a ratio of 1-30 fruit
Section 68 of the Revised Forestry Code, as amended, states: and non-bearing fruit trees. Thereafter, the Forest
Management Service and Forest Utilization Unit, both under
Sec. 68. Cutting, Gathering and/or collecting Timber, or Other the DENR, issued a Post Evaluation Report 46 dated 3 May
Forest Products Without License. Any person who shall cut, 2012 stating that LAMI properly followed the conditions laid
gather, collect, remove timber or other forest products from down in the permit. The relevant portions of the Post
any forest land, or timber from alienable or disposable public Evaluation Report state:
land, or from private land, without any authority, or possess
x x x the following findings and observations are noted: Next, Agham submitted that LAMI allegedly violated Sections
57 and 69 of the Philippine Mining Act.
1. That the tree cutting implemented/conducted by the
company was confined inside Lot No. 2999, Cad 316-D Sections 57 and 69 of the Philippine Mining Act state:
situated at Barangay Bolitoc, Sta. Cruz, Zambales and
within the area previously granted for tree cutting; Section 57. Expenditure for Community Development and
Science and Mining Technology – A contractor shall assist in
2. It was found that the thirty seven (37) trees of the development of its mining community, the promotion of
various lesser-known species and fruit bearing trees the general welfare of its inhabitants, and the development
with a total volume of 7.64 cubic meters as specified in of science and mining technology.
the permit were cut as subject trees are located within
the directly affected areas of the port facility project of Section 69. Environmental Protection – Every contractor shall
the company; undertake an environmental protection and enhancement
program covering the period of the mineral agreement or
3. The other trees previously inventoried and are not permit. Such environmental program shall be incorporated in
directly affected by the project within the same lot are the work program which the contractor or permittee shall
spared; and submit as an accompanying document to the application for
a mineral agreement or permit. The work program shall
4. There are forty four (44) various species of include not only plans relative to mining operations but also
miscellaneous trees counted and left with a computed to rehabilitation, regeneration, revegetation and
volume of 6.04 cubic meters. reforestation of mineralized areas, slope stabilization of
mined-out and tailings covered areas, aquaculture,
Relative the above findings and in compliance with the terms watershed development and water conservation; and
and conditions of the permit issued, the company should be socioeconomic development.
reminded to replace the trees cut therein as specified in
support with the environmental enhancement program of the These two provisions are inapplicable to this case. First, LAMI
DENR. is not conducting any mining activity on the port site. LAMI’s
mine site is about 25 kilometers away from the port site.
xxxx Second, LAMI secured all the necessary permits and licenses
for the construction of a port and LAMI’s activity was limited
Since LAMI strictly followed the permit issued by the CENRO to preparatory works for the port’s construction. The
and even passed the evaluation conducted after the issuance Philippine Mining Act deals with mining operations and other
of the permit, then clearly LAMI had the authority to cut trees mining activities. Sections 57 and 69 deal with the
and did not violate Section 68 of the Revised Forestry Code, development of a mining community and environmental
as amended. protection covering a mineral agreement or permit.
Here, Agham reasoned that LAMI was destroying the of such magnitude as to prejudice the life, health or property
environment by cutting mountain trees and leveling a of inhabitants in two or more cities or provinces.
mountain to the damage and detriment of the residents of
Zambales and the nearby towns of Pangasinan. Agham Even the Annotation to the Rules of Procedure for
simply submitted a picture taken on 4 June 2012 where Environmental Cases states that the magnitude of
allegedly the backhoes owned by LAMI were pushing the environmental damage is a condition sine qua non in a
remnants of the mountain to the sea. petition for the issuance of a Writ of Kalikasan and must be
contained in the verified petition.
This explanation, absent any concrete proof, is untenable.
Agham, in failing to prove any violation of the Revised
Clearly, Agham did not give proper justifications for citing Forestry Code, as amended, and the Philippine Mining Act,
Sections 57 and 69 of the Philippine Mining Act. Agham did shifted its focus and then claimed that LAMI allegedly
not even present any evidence that LAMI violated the mining flattened or leveled a mountain.
law or any mining undertakings in relation to LAMI’s
construction of a port facility. Agham only alleged in very The mountain, according to Agham, serves as a natural
general terms that LAMI was destroying the environment and protective barrier from typhoons and floods to the residents
leveling a mountain without conducting any scientific studies of Zambales and nearby towns of Pangasinan. Thus, Agham
or submitting expert testimonies that would corroborate such argues that once such natural resources are damaged, the
allegations. residents of these two provinces will be defenseless and their
life, health and properties will be at constant risk of being
Section 2(c), Rule 7, Part III of the Rules of Procedure for lost.
Environmental Cases provides:
However, Agham, in accusing that LAMI allegedly flattened a
Section 2. Contents of the petition. - The verified petition mountain, did not cite any law allegedly violated by LAMI in
shall contain the following: relation to this claim. Agham did not present any proof to
demonstrate that the local residents in Zambales, and even
(c) The environmental law, rule or regulation violated or the nearby towns of Pangasinan, complained of any great
threatened to be violated, the act or omission complained of, danger or harm on the alleged leveling of the land formation
and the environmental damage of such magnitude as to which may affect their lives, health or properties. Neither was
prejudice the life, health or property of inhabitants in two or there any evidence showing of a grave and real
more cities or provinces. environmental damage to the barangay and the surrounding
vicinity.
The Rules are clear that in a Writ of Kalikasan petitioner has
the burden to prove the (1) environmental law, rule or To belie Agham’s contentions, the records, from the
regulation violated or threatened to be violated; (2) act or testimonies of those experts in their fields, show that there is
omission complained of; and (3) the environmental damage in fact no mountain in Brgy. Bolitoc, Sta. Cruz, Zambales.
First, in the Judicial Affidavit0 47 dated 6 August 2012, the exercising rights based on its occupation thereof. The mound
Regional Director of DENR EMB R3, Dir. Claudio, categorically and/or ridge within the private property is only about 23
declared that there is no mountain on LAMI’s property. The meters high. The base or footing of the mound therein which
relevant portions state: the Petitioner insists is a mountain is only 1.5 hectares, and
the height is approximately 23 meters. I have been advised
32. Q: One of the complaints of Mayor Marty in his letter that a mountain, as described by the United Nations
dated 27 April 2012, x x x, is that LAMI is "leveling a Environment Programme – World Conservation Monitoring
mountain" in its property in Barangay Bolitoc, Sta. Cruz, Centre ("UNEP-WCMC"), must be, at least, of a height greater
Zambales. Is there really a mountain in the property of LAMI than 300 meters or 984 feet in addition to other
in the said place? requirements on slope and local elevation range. In other
countries, the United Kingdom for example, the minimum
A: None, sir. The subject landform is not considered as a height requirement is 2,000 ft or 609.6 meters. 50
mountain based on commonly accepted description of a
mountain as having 300 meters to 2,500 meters height over Third, several government entities and officials have
base. The highest elevation of the project area is 23 meters. declared that there is no mountain on the port site: (1) in a
Letter51 to LAMI signed by the Sangguniang Bayan members
33. Q: Do you have any proof that the landform in LAMI’s of Sta. Cruz dated 4 June 2012, the Sangguniang
property is not a mountain? Bayan members stated that there is no mountain in the area;
(2) in a Memorandum52 dated 4 June 2012, the CENRO
A: Yes, sir. The Mines and Geosciences Bureau (MGB), concluded that the "mountain" is a "hill falling under Block I,
Regional Office No. III, through the OIC of the Geosciences Alienable and Disposable land per LC Map 635"; and (3) in a
Division, issued a Memorandum dated June 26, 2012 proving Special Report53 re: Police Assistance dated 6 May 2012, the
that there is no mountain in LAMI’s property. The proper Provincial Director of PNP Zambales reported to the PNP
description of the landform, according to the said Regional Director, citing the findings of the local chief of
memorandum, is an "elongated mound"48 police, that no leveling of a mountain transpired in the area.
Second, LAMI, through the Judicial Affidavit 49 dated 3 August Last, in an Inspection Report54 dated 26 June 2012, the Mines
2012 of Felipe E. Floria, LAMI’s Vice-President and General and Geosciences Bureau, Geosciences Division of the DENR
Manager, was able m to establish that Brgy. Bolitoc, Sta. Cruz concluded that the "mountain" is only an elongated mound.
had no mountain. The relevant portions provide: The findings and conclusion of the report provide:
126. Q: Why do you say that this elevated portion is not a FINDINGS
"mountain"?
1. The Bolitoc LAMI Port Facility is approximately
A: The port site where the alleged mountain is located is only centered at the intersection of geographic coordinates
1.8 hectares of alienable and disposable land. It is private 15°45’00.4" north latitude and 119°53’19.9" east
property, lawfully possessed by LAMI, with the latter longitude, x x x. It is bounded on the north by the West
Philippine Sea (Bolitoc Bay), on the west and east by Considering elevated landform of interest measures 164
the continuation of the elevated landform, and to the meters in length and about 94 meters in width disposed in an
south by an unnamed creek and a concrete barangay elongate manner with a maximum elevation of 26 meters
road connecting the Brgy. Bolitoc to the Zambales more or less above mean sea level and is about 16 meters
National Highway. higher than the barangay road and nearby houses and using
the Glossary of Landforms and Geologic Terms x x x by
Brgy. Bolitoc also hosts the port facilities of the DMCI Hawley and Parsons, 1980 above that the elevated
and the Shangfil Corporation both of which occupy the landform is neither a mountain or hill, but instead it is
former loading site of the defunct Acoje Mining considered elongated landmass/or elongated mound.
Corporation.
CONCLUSION
2. The landform of interest is characterized by a
roughly east-west trending elevated and elongated Based on the above geological and landform (geomorphic)
landmass. Within the LAMI site, the elevated landform classification, considering its elevation of 23 to 26
measures 164 meters in length and about 94 meters in meters above mean sea level and which is 16 meters
width and is almost parallel to the coastline. It has a above the barangay road and vicinity, the elevated
maximum elevation located at its eastern end of 26 landform present in the LAMI port facility is neither a
meters above mean sea level more or less. Its western hill or mountain. Its elevation of 16 meters above its
end has an elevation of 23 meters above mean sea vicinity is lower than a hill (30 meters). Its height
level more or less x x x. The landform is about 16 above its vicinity can be possibly categorized as a
meters higher than the barangay road and nearby mound which is defined by the Dictionary of Geological
houses x x x. terms (1976) prepared by the American Geological Institute
as which defines a mound as "a low hill of earth, natural or
From the LAMI area, the landform continues eastwards artificial." In the United Kingdom, mounds are also called
to the DMCI and the Shangfil Port facilities and also hillocks or knolls. The term elongated is prefixed as a
westwards to the vicinity of Brgy. Bolitoc proper. modifier to describe its east-west disposition. Hence, the
elevated landform of interest is considered as
3. The area is underlain by interbedded calcareous elongated mound.55 (Emphasis supplied)
sandstone, shale, and siltstone of the Cabaluan
Formation (formerly Zambales Formation), x x x. Rock On the other hand, the lone witness of Agham, former Rep.
outcrops show the sedimentary sequence displaying Palmones, admitted in the 10 September 2012 hearing
almost horizontal to gently dipping beds cut by a conducted by the Court of Appeals that he was incompetent
minor fault. These rocks weather into a 1-2 meter silty to prove that the elevated ground located in Brgy. Bolitoc is a
clay. mountain. The relevant portions56 of Rep. Palmones’
testimony provide:
DISCUSSION
Atty. Gallos: Mr. Congressman, you conducted an ocular Cong. Palmones: I’m not competent to answer that
inspection in Brgy. Bolitoc in Sta. Cruz, Zambales on May 21? question.
Cong. Palmones: Yes. Atty. Gallos: Your Honor, that’s exactly our point. He
is claiming that there is a mountain but he cannot tell
xxxx us the height, the slope, the elevation, the base, Your
Honor. So you admit now that you do not know, you
Atty. Gallos: That was the first time you were in Brgy. do not have the competence to state whether or not
Bolitoc? there is a mountain?
Cong. Palmones: Yes. Cong. Palmones: I really don’t know what is the
technical description of a mountain but based on the
Atty. Gallos: That was also the first and the last ocular information that we got from the community during
inspection that you did so far in Brgy. Bolitoc? the consultation it’s full of vegetation before it was
leveled down by the operation, Your Honors. (Emphasis
Cong. Palmones: Yes. supplied)
In view thereof, the Committee would like to express its Dir. Claudio: It is just localized; it is just confined within
appreciation for the apt and prompt action on the matter. We the project area because we required them to put up the
expect that the subject company’s conformity to drainage system, the drainage, the canals and the siltation
environmental laws, as well as its activities’ impact on the ponds and the laying of armour rocks for the sea wall and the
environment, will remain closely monitored and evaluated. construction of causeway, Sir, to avoid erosion and
sedimentation. We also required them to rehabilitate the
xxxx exposed slopes which they already did.
The composite team gathered data and the following are the The construction of the access road on the low ridge
initial observations: does not pose adverse environmental impact to the
adjoining communities more so to the larger areas or
1. Site preparation which includes site grading/surface the entire province of Zambales and Pangasinan.
stripping, low ridge cut and fill and reclamation works
were observed to have been undertaken within the It was determined as a result of our verification and based on
project area; the above findings supported with field GPS reading
that there had been no leveling of the mountain presumption of regularity in the performance of such official
undertaken in the project site as there is no mountain duty stands. It is incumbent upon petitioner to prove
existing inside the area covered by the ECC issued by otherwise, a task which it failed to do here.
EMB-Region 3. The landform claimed by Mayor Marty to be a
mountain is actually an elongated low ridge with a peak of Expert findings are afforded great weight
approximately 23 meters above sea level which is located in
a private land falling under Block 1, Alienable and Disposable The findings of facts of administrative bodies charged with
Land per LC Map 635 with Lot No. 2999 originally owned by their specific field of expertise, are afforded great weight by
Mr. Severo Monsalud which was transferred to Sta. Cruz the courts, and in the absence of substantial showing that
Mineral Port Corporation with a Contract of Lease with LAMI such findings are made from an erroneous estimation of the
(data provided by CENRO Masinloc through a Memorandum evidence presented, they are conclusive, and in the interest
dated June 4, 2012). The proponent (LAMI) only implemented of stability of the governmental structure, should not be
road cutting of low ridge in the middle to make an access disturbed. x x x.64
way to the proposed marine loading facility. More so, tree
cutting done by LAMI is covered by a Permit to Cut issued by In sum, contrary to the findings of the appellate court in its
DENR-Region 3-CENRO, Masinloc which is responsible for the Amended Decision dated 13 September 2013, we find that
inventory and monitoring of cut trees. LAMI did not cause any environmental damage that
prejudiced the life, health or property of the inhabitants
x x x x63 (Emphasis supplied) residing in the municipality of Sta. Cruz, the province of
Zambales or in the neighboring province of Pangasinan.
Thus, from all the foregoing, we agree with the appellate Agham, as the party that has the burden to prove the
court, in its original Decision dated 23 November 2012, when requirements for the issuance of the privilege of the Writ
it denied the petition for a Writ of Kalikasan: ofKalikasan, failed to prove (1) the environmental laws
allegedly violated by LAMI; and (2) the magnitude of the
As between the too general and very hypothetical allegation environmental damage allegedly caused by LAMI in the
of large-scale environmental damage at one hand, and the construction of LAMI' s port facility in Brgy. Bolitoc, Sta. Cruz,
remarks of government experts on the other, We are inclined Zambales and its surrounding area. Thus, the petition for the
to give more credit to the latter. Below is the further issuance of the privilege of the Writ of Kalikasan must be
articulation of our stance: denied.