Sie sind auf Seite 1von 6

SET-1

Q1. For the truss shown below the virtual work method to find the following (take E=250
Gpa[250x10⁶kn/m²] and A=350mm² for the members).

If no loads act on the truss, and member AB is 3mm short. Then the vertical displacement of joint
C; C” Cv is:

a. Zero
b. ἃ€3.0mm
c. +4.0mm
d. +3.0mm

Q2. Calculate the reaction Ra.


A uniform load on a beam is shown below. It has a value of 2.5KN per metre.

a. 5 KN
b. 1.25KN
c. 10 KN
d. 0

Q3. QCS means

a. Qatar construction services


b. Qatar contract standard
c. Qatar construction specification
d. None of the above

Q4. The final step in the definition of Work breakdown structure is to

a. Assign codes for each activity of the work package


b. Assign the cost account to a manager
c. Assign the package to a manager
d. Develop the responsibility matrix
e. None of this are included in the final step
Q5. What is the correct sequence on a network of these activities?

a. 1-2-3-4
b. 2-1-4-3
c. 2-1-3-4
d. 1-3-2-4

Q6. A monitoring station record the following pattern of discharge (cfs) in a stream following a
storm. The catchment area for the stream is estimated to be 125 acres 1 acre= 43,500ft²

The average depth of excess precipitation from the storm is most nearly

a. 1.2 in
b. 1.5 in
c. 1.8 in
d. 2.1 in

Q7.

The maximum moment in the beam is

a. 4200 N.m
b. 5600 N.m
c. 5400 N.m
d. 5800 N.m

Q8. The error resulting from using a tape that is too short as a (n)______ error

a. Systematic
b. Random
c. Erratic
d. Compensating

Q9. A line connecting points of equal elevations on a map is called a/an

a. Property line
b. Critical areas line
c. Line of equal elevations
d. Contour line

Q10. Seismic design categories are develop

a. Base on soil type and building type


b. Base on risk and importance of the structure with regards of loss of life
c. Base on soil type only
d. Base on the probability of earthquake in the region

Q11. A workforce of 6 electricians has to install 420 lights fixtures in a new office building.
Normally, two electricians are working together can install one fixture in 20 min. The crews
expect to have a 0.8 efficiency factor due to environmental conditions on this job. The crews
schedule for 9 hours workdays, which include 1 hour break for lunch. The duration of this
construction activity is (days, hours) is most nearly

a. 5 days, 8 hours
b. 6 days, 5 hours
c. 7 days, 3 hours
d. 21 days, 8 hours

Q12. A steel beam a uniformly distributed live load w= 6kips/ft. over a simple span L= 25 ft. as
shown below. The code permits a maximum live load deflection of L/480. The required moment
of inertia of the beam section is most nearly

a. 2600 in⁴
b. 2800 in⁴
c. 2900 in⁴
d. 3000 in⁴

Q13. Activated sludge process is best describe as

a. Re-introduce aerated sludge back to the waste to increase the level of bacteria
b. Re-introduce aerated sludge back to the stream to increase the level of bacteria
c. Activate the sludge by adding chemicals
d. None of all

Q14. The moment diagram for a simply supported with a load at the mid-point is

a. Triangle
b. Parabola
c. Trapezoid
d. Rectangle
e. Semicircle

Q15. The advantage of using plywood is that the

a. Tensile strength is equal in all directions


b. Higher tensile strength in longer directions
c. Higher tensile strength in shorter directions
d. Longer tensile strength in longer directions

Q16. Find the total float of activity D for the project

a. 1
b. 3
c. 9
d. 2

Q17. The beam shown is subjected to a uniform load and a moving concentrated load.
Design data:
Uniform live load: 1kip/ft.
Concentrated live load: 10kips
Assumption:
The uniform live load may extend the entire length of the beam from A to C
The maximum live load shear kips (kips) on the right of support B most nearly

a. 32
b. 36
c. 40
d. 46

Q18. A section of Major Street an urban arterial with six traffic signalized intersections is shown
below. The traffic signals at each intersection have a total cycle length of 90 sec. with 50 sec. of
green (and yellow) time on the major streets. It is required that the progressive signals system
having a maximum bandwidth of green movement from the 1st avenue intersection toward the
6th avenue intersection with a progressive speed of 30 mph be designed. The offset (sec) at 6 th
avenue is most nearly
a. 36
b. 43
c. 50
d. 63

Q19. Sustainable development involves

a. Reducing consumption, increasing efficiency and using renewable energies.


b. Larger building using stronger design and materials.
c. Developing better transportation by building more roads
d. Using all resources at maximum rates
e. Searching for more deposits of fossil fuels

Q20. An activated sludge reactor with a solids retention time of nine days is to achieve
nitrification. pH control may be necessary because

a. Nitrification produces acid


b. The activated sludge process consume alkalinity
c. Nitrification releases ammonia
d. Nitrification produces acid and the activated sludge process consume alkalinity

Q21. For the steady flow of gas in the conduit shown, what is the mean velocity at section 2?

a. 20 m/s
b. 40 m/s
c. 60 m/s
d. 80 m/s

Q22. The advantage of a Design/Bid/Build contractual arrangement is (are)

a. Reduces project time


b. Non adversary relationships among participants
c. Known project cost before construction
d. All of the above

Q23. Resource leveling usually results in

a. Using fewer amounts of resources per activity


b. Shortening the project duration
c. More efficient used of labor and equipment
d. More work space for workers
Q24. A concrete mix has the following specification
Cement content= 660 lb/ydᶟ (SG of cement = 3.10)
Fine aggregate (SSD) = 1250 lb/ydᶟ (SG of SSD fine aggregate = 2.65)
Water cement ratio= 5 gal per sacks, wt. of cement/sack= 94 lbs.
Air content= 6
The volume of coarse aggregates required per cubic yard of concrete is most nearly

a. 9.7 ftᶟ
b. 8.6 ftᶟ
c. 8.2 ftᶟ
d. 7.7 ftᶟ

Q25. The extensive use of gypsum wallboard in residential, commercial and industrial
construction stems from all the following EXCEPT

a. Low cost
b. Ease of installation
c. Recyclability

Q26. A precast wall panel 20 ft. long (perpendicular to drawing plane) x 14 ft. high x 4 inches thick
is being titled into position using a single horizontal cable connected to the top of the panel
shown on the figure below. The unit weight of the wall materials is 80lb/ftᶟ. At the position
shown, the tension in the cable (kips) is most nearly

a. 2.2
b. 3.6
c. 5.2
d. 6.6

Q27. If a project has a CPI of 0.95 and an SPI of 1.01, this indicates

a. The project is progressing slower and costing more than planned


b. The project is progressing slower and costing less than planned
c. The project is progressing faster and costing more than planned
d. The project is progressing faster and costing less than planned

Das könnte Ihnen auch gefallen