Estimate Report
Option A. Discard the terminal tower, and connect cable between last but one tower and
KMML yard by converting that tower as a terminal tower. For this, permission from NH authorities
and long duration interruption will be required
Option B. Discard the terminal tower and construct a new tower in the northern side of
KMML yard and the line can be shifted from the existing deteriorated tower to the newly proposed
tower. Then the newly proposed tower become the terminal tower. From this terminal tower cable
can be drawn to the existing KMML yard. From these two options, option B appears to be cost
effective and interruption will also be minimum and hence it is considered and an estimate
amounting to rupees 1,82,00,000 is prepared. While executing this estimate, the interruption can
be reduced to one day, whereas the cost of execution is considerably large.
The work needs highly experienced and skilled labors and special tools
and hence it is proposed to arrange on contract basis. The work involves dismantling of power
lines and earth wires on both side of the tower , dismantling of damaged tower, erection of new
tower, stringing of new conductors and earth wires , Fabricating supporting structures in tower for
mounting cable end and LAs Connecting cable between yard isolator and towe etc.
The above estimate of Rs. 1,82,00,000/- is prepared on the basis of DSR-
2016 and data from Transmission line maintenance work, substation works and data from the
approved data for Laying of 110KV UG Cable between Location 70 & 71 of 110KV Kalamassery -
Aroor (KLAR) Feeder
Funds to the extent may be met from the budget provision under capital work of EHT lines
under Line Maintenance Section Kundara.