Sie sind auf Seite 1von 8

Safety

Controlling Risk During


Major Capital Projects
William Bridges Think of process safety management (PSM)
Revonda Tew
Process Improvement as a project deliverable, and follow these
Institute, Inc. best practices for scheduling and performing process
hazard analyses (PHA) and completing other PSM
requirements during key phases of a major project.

T
he construction of a new plant, or a large capital strategic project milestones, but these alone will not ensure
expansion to an existing facility, represents sig- a safe and seamless startup. A holistic approach to man-
nificant risk. That risk increases when construction aging risks on a large project requires some innovative
takes place in an operating environment and when criti- measures that must be supported by the entire project team.
cal tie-ins are made to “live” equipment. AIChE’s Center While the various phases of a major project can spread
for Chemical Process Safety (CCPS) provides excellent over 12 to 36 months, decisions for controlling risk made
guidance in its original process safety management (PSM) during each project phase echo through the next 20 to 50
guideline (1) and in many subsequent publications. Other years of operation. Design features, automated control
papers (2, 3) discuss how to manage major capital projects features, and human interactions must be controlled continu-
to achieve process designs and operating procedures that ously to manage the inherent hazards of chemical processes.
will control process safety.
These resources refer to the standard industry practice PSM requirements
of conducting multiple risk reviews — also called process The U.S. Occupational Safety and Health Administra-
hazard analyses (PHAs), project risk reviews, design safety tion’s (OSHA) PSM standard (4) sets requirements for the
reviews, etc. Typically, a small project includes one or two management of hazards associated with processes that use
risk reviews, whereas a large project (such as a new plant) highly hazardous chemicals (HHC). The regulations list 14
may involve as many as six risk reviews that build upon interrelated elements (outlined in the standard), treating them
each other to yield the initial PHA (Table 1). Although this as part of a holistic continuum. The elements apply to (or are
article focuses on major projects, these best practices apply affected by) capital projects to varying degrees, especially:
to medium and small projects as well. • process safety information (PSI) — developed through-
Conventional risk-analysis tools must be applied at out the project phases

Table 1. As project size and scope expand, more risk reviews are needed.
Project Phase: Preliminary Design
Typical Project Duration Number of Risk
Project Size Example of Project Scope (Concept to Commissioning) Reviews
Small Minor affiliate/plant works (installing piping to bypass a 1–2 mo 1
control valve)
Moderate Works engineered by an affiliate/ plant (installing a new 6–9 mo 2–3
design of knockout pot for a feed to a unit)
Major Major projects handled external to an affiliate/plant 12–36 mo 4–7
(expansions and new facilities)

56 www.aiche.org/cep April 2009 CEP


• operating procedures — developed in the last phases included, PSM involves the same management practices as
of a project required for operational and reliability excellence — so
• management of change (MOC) — the heart of project incorporating these into each project phase makes good busi-
risk control ness sense. By addressing PSM early in the project develop-
• process hazards analysis — the heart of MOC ment, it is easier to expand risk management to “sustainable
• pre-startup safety review (PSSR) — conducted before control of human error” — the key to controlling risks.
highly hazardous chemicals enter and before production starts This not only provides excellent process safety control, but
• emergency planning and response — cannot happen excellent reliability, quality, and efficiency control.
properly if the process layout, design, and operation do not
consider it in advance. The initial phases of risk control
PSM as defined by OSHA does not address all process The first two project phases — conceptual design
safety issues; CCPS/AIChE define several other elements, review and feasibility and detailed specifications — are
such as human factors and project risk management, that are critical for establishing the inherent safety of the process.
not covered in OSHA PSM elements. When all elements are Activities during these phases (Table 2) include:

Table 2. Conceptual risk reviews should be conducted during the earliest phases of a major capital project.
Project Phases: Conceptual Design, and Feasibility and Detailed Specifications
Goals of Risk Review Risk Review Methodology Key PSM Elements*
Choose inherently safer option Consequence modeling (to help on next Process safety information, including
Ensure overall feasibility project phase) chemical hazards, chemical reactivity,
What-If (no guidewords) hazards of inadvertent mixing, inventories,
Estimate impact on neighbors
applicable codes and standards (d)
Selected checklist for judging inherent
safety Baseline information for future PHA (e)
Baseline information for future mechanical
integrity (MI) (j)
Begin inherently safer concept
Begin leadership
Begin employee participation (c)
Risk Review Team Members: Leader; Scribe; Senior operator for the unit (or from a similar unit); Senior process engineer for the unit (or
from a similar unit); Process/design engineer from the project; Process safety specialist (if the previously listed members do not have
safety expertise)
* Letters in parentheses refer to the relevant section of the OHSA PSM Standard, 29 CFR 1910.119(_).

Table 3. Preliminary risk reviews continue into the preliminary design phase.
Project Phase: Preliminary Design
Goals of Risk Review Risk Review Methodology Key PSM Elements*
Identify and resolve most-expensive design What-If (no guidewords) Process safety information, including
issues, including layout of plant, facility HAZOP/FMEA of selected scenarios applicable codes and standards, process
siting concerns, environmental protection flow diagram, thermal/kinetic chemistry
Layer of Protection Analysis (LOPA) of
issues, and major tie-ins information, material and energy balances,
selected scenarios
and materials of construction (d)
Facility siting basis
Begin emergency response plans and
procedures (n)
Baseline information for future PHA (e)
Baseline information for future MI (j)
Continue employee participation (c)
Risk Review Team Members: Leader; Scribe; Senior operator for the unit (or from a similar unit); Senior process engineer for the unit (or
from a similar unit); Process/design engineer from the project; Process safety specialist (if the previously listed members do not have
safety expertise)
* Letters in parentheses refer to the relevant section of the OHSA PSM Standard, 29 CFR 1910.119(_).

CEP April 2009 www.aiche.org/cep 57


Safety

Table 4. Considerations that guide risk reviews for the conceptual and preliminary design phases.
Key Concern Ways to Address/Evaluate Key Concern
Inherently safe/reliable process selection Evaluate lower-waste chemistries
Evaluate low-inventory processes
Evaluate the use of non-hazardous solvents and reagents
Evaluate low-energy reactor configurations (5)
Plot location relative to other units Process opportunities — reduced pipe runs
Operating logistics — number of operators
Distance between control room and tie-in to control room
Backup contingency considerations — begin utility failure risk review
Effects from major incidents in nearby units; include consequence modeling if necessary
Begin facility siting risk review (checklist-based), if possible
Size of plot areas — based on preliminary Access to utilities and other support systems, sewers, etc.
process designs Cost of real estate, site preparation
Elevation considerations
Precise spacing between unit boundaries — Insurance and industry spacing guidelines
standoff distances between battery limits or Effects on nearby units
between major equipment in nearby units
Business interruption considerations
Inner unit layout Ease of access (begin consideration of human factors)
Operability and maintainability
Constructability and repair (consider future lifting activities for construction and repairs)
Equipment decking and layering (operators should not be expected to climb through
caged ladders to take routine process reading)
Fire protection review Emergency access and escape routes
Firefighting or toxic rescue capability
Placement of detectors
Strategy to protect neighbors from releases
Construction of control rooms to protect “stay-behinds”
Refer to consequence modeling if performed to address plot location concern

• select the process (inherently safe, or at least the a project has been lacking in many companies — despite the
inherently safest design); choose lower-waste chemistries, availability of guidelines (1–3) that explain how to develop
low-inventory processes, nonhazardous solvents and a PHA throughout a project, as well as the broad adoption of
reagents, and low-energy reactor configurations (5) hazard and operability (HAZOP), What-If (brainstorming),
• decide on the maximum level of inherent risk (not and failure mode and effects analyses (FMEA). This is
residual risk) that will be accepted especially true for owners who allow the primary contractor
• establish siting and layout (consider control of to oversee the risk review process.
inherent risk to neighbors) As methods for early-phase risk review have been
• establish grading and drainage improved or customized, project-level risk reviews have
• establish preliminary process design been performed increasingly well. Over the past 15 years,
• establish circuit isolation requirements considerable focus has been placed on inherent safety at
• establish process control philosophy the initial concept phase of a new unit or process. In ad-
• establish strategy for control of ignition sources dition to inherent safety, inherent reliability and inherent
(electrical area classification) environmental protection are also receiving more attention
• establish relief and blowdown requirements during the conceptual design phase and the preliminary
• establish fire protection strategy. design phase (Table 3). Still, weaknesses persist among
No one cares more about controlling the risk of the these improved early-phase risk review practices.
delivered process than the owner/operator. Yet the imple- Several key factors contribute to successful risk
mentation of risk review methods during the early stages of reviews in the conceptual and preliminary phases of a

58 www.aiche.org/cep April 2009 CEP


major capital project. Table 4 presents key considerations • independent of contractors/vendors
and methods to guide these early-phase risk reviews. • independent of the unit/process/plant that the major
Foremost recommendations are: project is related to
Include a senior operator on the risk review team, • a fully capable PHA team leader/facilitator who is
(not just supervisory personnel) from an existing or similar well-trained and practiced in HAZOP, FMEA, and
unit, even if the person must be contracted or must travel to What-If methods.
attend the risk review. This policy, developed after several Force the consideration of inherently safer and/or
accidents in the 1980s, should be a requirement for all risk more reliable alternatives.
reviews — all project phases, all PHA revalidations, all
management of change (MOC) risk reviews, etc. When The design phases
this does not occur at the conceptual or preliminary design Risk reviews in the detailed design phase (Table 5)
stages, the missed considerations can lead to either a flawed and the final design phase (Table 6) can consist of one to
project (e.g., one with limited scope or vision) or an inher- three progressively more-detailed efforts over one to three
ently unsafe or unstable process. project phases, depending on the size of the project. As
Include a senior process engineer from an existing or the reviews progress, the risk review report is expanded
similar unit, even if the person must be contracted. This, and becomes the initial “official” hazard review report
too, should apply to all risk reviews. for the process unit (discussed in the next section). Risk
These two senior staff members will bring different per- reviews during detailed design typically involve:
spectives to the process based on their different experiences. • using HAZOP, FMEA, and/or What-If analyses in
Allow contingency in budget and schedule. If project progressively more detail
managers are placed in the uncomfortable position with • initiating and progressively improving (from phase
respect to changing scope, adding features, etc., the result- to phase) the risk review record (HAZOP tables, What-If
ing project might be on-time and on-budget, but unsafe or tables, checklists)
run poorly. • maximizing inherently safer design in the selected
Never let the contractor/vendor manage the risk process — for example, tanks and piping designed to
review or provide the risk review leader. Typically, the make overflow hydraulically impossible, lower feed-
contractor’s chief concern is to deliver a project on sched- pump pressures to prevent hydraulic overpressure,
ule for a stated price. The owner/operator should always reactor conditions and recycle loops optimized to
choose the risk review leader and should ensure that the minimize waste, manual charge stations located at the
leader is: appropriate ergonomic work height, hazardous operations
• independent of the project management team sited away from occupied areas to minimize impacts of

Table 5. Risk reviews in this phase evaluate the risk of any design modifications that have been made
or hazards that have been identified since the previous reviews.
Project Phase: Detailed-Design Risk Reviews
Goals of Risk Review Risk Review Methodology Key PSM Elements*
Begin detailed identification of potential HAZOP/FMEA of equipment nodes, Process safety information, including
accident scenarios, primarily focused on focusing on normal (continuous) mode of applicable codes and standards, process
the normal (usually continuous) mode of operation and instrumentation diagrams (P&IDs),
operation What-If of lower-consequence and lower- revised materials of construction, safety
Begin risk assessment for scenarios with complexity systems interlocks and controls, equipment design
large residual risk basis. and some final equipment details (d)
LOPA of 1–5% of the scenarios; determine
safety integrated level (SIL), as necessary Multiple layers of protection
Detailed information for future PHA (e)
Detailed information for future MI (j)
Begin detailed emergency planning and
response (n)
Continue employee participation (c)
Risk Review Team Members: Leader; Scribe; Senior operator for the unit (or from a similar unit); Senior process engineer for the unit (or
from a similar unit); Process/design engineer from the project; Process safety specialist (if the previously listed members do not have
safety expertise)
* Letters in parentheses refer to the relevant section of the OHSA PSM Standard, 29 CFR 1910.119(_).

CEP April 2009 www.aiche.org/cep 59


Safety

Table 6. Final design phase risk reviews ensure that the occupational safety, process safety, reliability,
and operational risk issues identified in previous reviews have been resolved.
Project Phase: Final Design Risk Reviews
Goals of Risk Review Risk Review Methodology Key PSM Elements*
Update results of previous risk review to Complete HAZOP, FMEA, or What-If for Process safety information (revisions) (d)
account for new details, identify potential nodes started in previous risk review Multiple layers of protection (revisions)
accident scenarios for nodes not previously Perform HAZOP, FMEA, What-If for nodes Revised details building toward initial
reviewed, primarily focused on normal not covered in previous risk review (due to PHA (e)
(usually continuous) mode of operation. previously missing information)
Revised data for MI, including development
Resolve most previous recommendations Begin human factors and facility siting of inspection, test, preventive maintenance
Complete risk assessment for scenarios checklist (PM) plans and populating databases (j)
with large residual risk Perform general utility failure checklist Begin detailed consideration of human
LOPA of 1–5% of the scenarios; determine factors
SIL, as necessary Data and recommendations for developing
operating and maintenance procedures (f, j)
Continue employee participation (c)
Risk Review Team Members: Leader; Scribe; Senior operator for the unit (or from a similar unit); Senior process engineer for the unit (or
from a similar unit); Process/design engineer from the project; Process safety specialist (if the previously listed members do not have
safety expertise)
* Letters in parentheses refer to the relevant section of the OHSA PSM Standard, 29 CFR 1910.119(_).

possible explosions, tanks designed to withstand maxi- Inadequate risk review of nonroutine
mum possible pressure, etc. (5)
modes of operation (which should be analyzed
• conducting a final review of equipment, ventilation,
containment, and environmental safeguards, including by applying HAZOP or What-If to procedural
instrumentation, interlocks, fail-safe decisions, detailed steps) is the most frequently observed
layouts, and fire protection provisions weakness in the project risk review cycle.
• performing a human factors risk review (checklist-based)
• continuing the facility siting risk review (checklist- exposures to these higher risk modes of operation are reduced.
and modeling-based) Write operating procedures designed to control risks.
• applying layers of protection analysis (LOPA) to After the risk reviews are complete, the next important step
complex risk scenarios, and also to define safety instru- in controlling risk before startup is developing the written
mented systems needs. procedures for operations, maintenance, troubleshooting,
As shown in Table 5, the reviews during detailed engi- and emergencies. The data needed for writing procedures
neering will evaluate the risk of any design modifications is typically generated by the end of the final design phase
that have been made or hazards that have been identified (detailed in Table 6), and it is finalized as the project
since the previous reviews. This includes ensuring that the moves into the commissioning phase.
occupational safety, process safety, reliability, and opera- Write the procedures — the correct instruction for
tional risk issues identified in previous reviews have been each step, in the correct sequence — and properly format
resolved in the final detailed design. the instructions to reduce the chance of someone mak-
The most senior operator and process engineers should ing an error when following the procedures. References
continue to actively participate on the risk review team. for drafting, formatting, and validating procedures using
Catch design problems before they create operational subject matter experts (SMEs) are available (6). Correctly
traps. This is the goal through all of the risk reviews for a done, these written procedures will become the basis for
new process unit, but the detailed design phase is the most the initial training of the new unit’s operators and serve as
effective time to detect and eliminate such problems. To a refresher for staff over the long-term. This, in turn, will
accomplish this, equal focus must be given to hazards and help control (but never eliminate) the human-error compo-
operability/quality issues. Look for ways to keep the final nent of process safety risk.
process easy to operate and easy to maintain online, and
ways to avoid process upsets. Pre-commissioning and commissioning
Two-thirds of accidents occur during nonroutine modes of The commissioning phase risk review (Table 7)
operation, so by avoiding deviations from the norm, the plant’s continues to build upon the previous risk reviews. As

60 www.aiche.org/cep April 2009 CEP


the equipment design is completed and fabrication and that hazards due to human error in association with the process
construction start, initial staff training begins, using the design have been identified. The risk reviews up to this point
operating procedures discussed above. The pre-commis- will not have covered these modes of operation very well.
sioning risk review should begin 4–6 weeks prior to the This review can be performed using a full eight-guideword
startup of a new facility, or even a bit earlier if possible. HAZOP, a streamlined two-guideword approach, or the What-
The key consideration for this project phase is to complete If method (which does not use guidewords). These techniques
the risk review of nonroutine modes of operations — to ensure are explained in Refs. 7 and 8, as well as in other resources.
Article continues on next page

Table 7. This phase review builds upon the previous reviews, and also serves as the “initial PHA” for the process.
Project Phase: Commissioning Phase Risk Reviews
Goals of Risk Review Risk Review Methodology Key PSM Elements*
Conduct full hazard/risk review of operating HAZOP or What-If of operating procedures Process safety information (revisions) (d)
procedures to control risk of errors during (choose method based on hazard and Multiple layers of protection (revisions)
startup, shutdown, emergency shutdown, complexity of each task)
Complete the initial PHA (e)
and other nonroutine modes of operation Complete HAZOP, FMEA, or What-If for
Revise MI plans, procedures, and
Close out previous risk review issues nodes started in previous risk reviews
database (j)
(from earlier phases of the project) and Perform HAZOP, FMEA, or What-If for
complete the human factors and facility Complete detailed consideration of human
nodes not covered in previous risk reviews
siting checklists factors
LOPA of 1–5% of the scenarios; determine
This risk review serves as the “Initial PHA” Continue employee participation (c)
SIL, as necessary
of the process Complete development of emergency
Complete human factors and facility siting
planning and response procedures (n)
checklists
Complete operating procedures (f)
Complete initial training (g, j, h)
Develop remaining elements of PSM,
including management of change (MOC)
procedures and incident reporting and
investigation system (l, m)
Conduct initial pre-startup safety review
(PSSR) (i)
Risk Review Team Members: Leader; Scribe; Senior operator for the unit (or from a similar unit); New/junior operator for the unit; Senior
process engineer for the unit (or from a similar unit); Process/design engineer from the project; Process safety specialist (if the previously
listed members do not have safety expertise)

Table 8. This review helps to weed out hazards that may have been missed earlier, and can serve as
the first PHA revalidation for the new unit.
Project Phase: Post-Startup Phase Risk Reviews
Goals of Risk Review Risk Review Methodology Key PSM Elements*
Conducted 3–6 mo after startup; similar to Audit of MOCs (and P&IDs and SOPs) since Initial PHA Revalidation (completed much
the revalidations that will be done in the fu- “Initial PHA” (since commissioning risk earlier than the required 5–yr cycle) (e)
ture, but with the goal of compensating for review) to ensure nothing has been missed MOC (l)
weaknesses in MOC process at the initial by MOC
Incident investigation (for lessons learned in
startup of the new unit/process HAZOP or What-If of missed or poorly first 3–6 mo) (m)
reviewed changes
Update PHA for the entire set of changes
(look at the whole picture for effects of all
changes)
Close any pending recommendations
(if possible)
Risk Review Team Members: Leader; Scribe; Senior operator for the unit (or from a similar unit); New/junior operator for the unit; Senior
process engineer for the unit (or from a similar unit); Process/design engineer from the project; Possibly project/design engineer (for
quality assurance of project).
* Letters in parentheses refer to the relevant section of the OHSA PSM Standard, 29 CFR 1910.119 (_).

CEP April 2009 www.aiche.org/cep 61


Safety

During this final risk


review before startup, the How Many Risk Reviews are Needed?
project team must also The number of risk reviews required for any major capital project will depend on project
ensure that all of the PSM size, process complexity, and process risk/hazard.
requirements for the initial Example 1 is a large process with 250 nodes of equipment (vessels, columns, fired
PHAs have been met. If all heaters, lines/exchanger circuits, etc.), that handle hazardous chemicals. The installed
preceding risk reviews have cost is more than $100 million, and the project spans two or more years. As is typical for
this size process, the operating and maintenance procedures are complex — high pres-
followed the guidelines for
sures and temperatures, and complex controls. About five risk reviews are needed before
controlling risk at each project the plant is fully commissioned.
phase, meeting the initial
PHA requirements will not
Conceptual Preliminary Detailed Construction Pre-Startup Total
entail a tremendous amount
Meeting 1 wk 3 wk 5 wk 3 wk 3 wk 15 wk
of additional effort, other than
Time
the risk review of nonroutine
modes of operation. Team Size 8 8 8 6 6
This pre-commissioning Total Staff 164 1,152 2,120 864 984 5,284
risk review should not be Hours
confused with the pre-startup Cumulative 2 mo 6 mo 14 mo 18 mo 22 mo 24–30
safety review (PSSR), the Schedule mo
purpose of which is to validate Focus Plot plans, Cursory HAZOP, Rigorous Changes SOP hazard
that the process design and process options, FMEA, and WI; HAZOP, since previous review and
tie-in options, start checklists FMEA, and review; finish changes
specifications have been met. (What-If [WI] and WI; finish checklist since previ-
This final risk review some modeling) checklists ous review
before startup consists of:
• evaluating changes made
during construction, to ensure Example 2 is a small process — Detailed Pre-Startup Total
that no new hazards have been 10 nodes of equipment handling low-
Meeting 2 days 2 days 4 days
added since the last hazard hazard material (i.e., rock/ore), less
Time
review; high priority is given than $100 million of installed cost,
1 yr of project time, and relatively Team Size 10 10
to detecting details that may
simple operating and maintenance Total Staff 218 202 419
have been overlooked, and procedures (e.g., conveying of iron ore Hours
plans to cope with operating from a port to a steel plant). Only two
emergencies that might arise Cumulative 3 mo 9 mo 10–11
low-intensity risk reviews are needed
Schedule mo
• maximizing inherently for this process.
safer design in the selected Focus Rigorous SOP hazard
WI, some review and
process, such as planning for FMEA; start changes
rework of the initial product (5) checklists since previ-
• completing reviews for ous review
facility siting and access issues
• completing the review
for human factors issues close the PSSR (which is not part of the risk review, but
• HAZOP or What-If analysis of startup, shutdown, is part of PSM in general), and finalize the initial PHA
emergency shutdown, and online maintenance procedures. report for the new unit. Typically, the plant MOC system
More than just another validation of procedures, begins to take control of new risks after the pre-commis-
this review ensures that there are adequate safeguards sioning risk review meeting is closed.
(hardware, interlocks, safety integrity level [SIL], etc.) There are, of course, many deliverables from the
to offset the errors of skipped or incorrectly performed project team, among them the finished equipment,
steps. Human errors will occur, it is just a matter of operating and maintenance procedures, populated data-
when (7). bases for mechanical integrity (MI), and process safety
After this risk review, the project team can proceed to information (i.e., files of all necessary design bases for
close recommendations, decide which (if any) of the rec- relief valves, completed drawings, complete equipment
ommendations can be deferred until after initial startup, files, etc.).

62 www.aiche.org/cep April 2009 CEP


Post-startup • risk review teams that include experienced opera-
Many companies require a final risk review related to tors and experienced process engineers from the start of
a new process unit about three to six months after startup the project
(Table 8). This practice was implemented when managers • the development and application of PSM elements
realized that the MOC system often becomes overwhelmed at each project phase to better design for process safety
by the magnitude of changes necessary in the final push to • operating, maintenance, and lab procedures de-
start up a new unit. To avoid missing a key risk factor, it veloped by subject matter experts and subjected to risk
is wise to schedule a post-startup (9) risk review — which reviews to ensure that there are sufficient safeguards to
can also serve as the first PHA revalidation for the new protect the new process when imperfect humans fail to
process unit. follow the procedures perfectly.
The ultimate deliverable from the project team (in
In summary cluding the risk review teams) is a process and related
For new process units, there may be only one opportu- procedures that will sustainably control human error dur-
nity to adequately assess and manage risk — and that ing all modes of operation. The project team cannot ensure
is during the project phases before startup. Sound indus- that these safeguards will stay in place over the long term,
try practices exist to manage the risk of the final process but anticipating and controlling human error at each phase
operation during a major capital project, but unfortu- of a project by following the steps outlined here will be a
nately, many have not learned these lessons. The renewed good start toward the control of human error — and
focus on designing inherently safer and more reliable pro- therefore the control of accidental losses. CEP

cesses, and on controlling risk during nonroutine modes


of operation, may not have migrated to some companies’
project control systems. Literature Cited
The most important factors related to controlling risk 1. Center for Chemical Process Safety, “Plant Guidelines for
dur ing the design and startup of a new process unit are: Technical Management of Chemical Process Safety,” American
• effective company leadership and effective project Institute of Chemical Engineers, New York, NY (1991).
management — where the primary goal is an efficient 2. McGrath, P. F., “Using Qualitative Methods to Manage Risk,”
operating unit (emphasizing long-term process reliability AIChE Center for Chemical Process Safety, New York, NY
(1989).
and safety) over the secondary goal of bringing in the
3. Center for Chemical Process Safety, “Risk Management on
project on-schedule and on-budget a Major Facility Expansion,” American Institute of Chemical
Engineers, New York, NY (2001).
4. U.S. Occupational Safety and Health Administration,
“Process Safety Management of Highly Hazardous Chemicals,”
WILLIAM (BILL) G. BRIDGES is president of Process Improvement Institute 29 CFR 1910.119, OSHA, Washington, DC.
(PII; Knoxville, TN; E-mail: wbridges@piii.com). He has more than
30 years of chemical industry experience in process engineering, 5. Berger, S., et al., “A Cost and Time-Efficient Framework for
process/product development, management, safety evaluation, and Inherent Safety and Pollution Prevention during Process
operations. An authority on process safety engineering, risk manage- Development and Engineering,” AIChE Center for Chemical
ment, and human error prevention, he has helped many companies in Process Safety, New York, NY (1996).
the petroleum, petrochemical, plastic and process industries develop,
implement and assess PSM and risk management programs. He has 6. Bridges, W., et al, “Create Effective Safety Procedures and
led more than 250 large process hazard analyses (PHAs) — from Operating Manuals,” Chem. Eng. Progress, 93 (12), pp. 23–37
conceptual design through pre-commissioning — delivering PSM at (Dec. 1997).
completion. He has taught safety courses on PHA and HAZOP leader- 7. Bridges, W., et al, “Include Human Errors in Process Hazard
ship, incident investigation and root-cause analysis, and management
Analyses,” Chem. Eng. Progress, 90 (5), pp. 74–82
of change (MOC). He has BS and MS degrees in chemical engineering
from the Univ. of Akron. (May 1994).
8. Center for Chemical Process Safety, “CCPS Guidelines for
REVONDA TEW is a senior instructor for PII (rtewe@piii.com), with more Hazard Evaluation Procedures,” American Institute of Chemical
than 15 years of chemical industry experience in process develop- Engineers, New York, NY (2008)
ment, process engineering, and process safety management and
evaluation. She has experience leading and documenting PHAs and 9. Frank, W. L., and D. K. Whittle, “Revalidating Process
PHA revalidations, MOC risk reviews, investigations, and PSM audits. Hazard Analyses,” AIChE Center for Chemical Process Safety,
She has also developed training materials for topics such as MOC, New York, NY (2001).
PHA leadership, and PSM auditing, and she is a co-instructor for
these topics and for incident investigation. She has experience with
both community relations and crisis management, and is currently Further Reading
involved in local emergency planning committee (LEPC) activities.
Kletz, T. A., “Inherently Safer Design Achievements and
She has a BS in chemical engineering from North Carolina State
Univ. and an MBA from the Univ. of North Carolina’s Kenan-Flagler Prospects,” AIChE Center for Chemical Process Safety,
Business School. New York, NY (1996).

CEP April 2009 www.aiche.org/cep 63

Das könnte Ihnen auch gefallen