Project Background:
The project is a competitor analysis of different markets relating to soft plastic recycling to
generate employment and form alliances in the Asia Pacific region.
Activity 1: Decide on 5 competitors as a group that we will be deep diving into. Each team
member will have 1 competitor to do
Activity 2: General analysis of value points between competitors
Activity 3: General analysis of key statistic points between competitors
Resources Required:
Performance results
Research reports
Datasets
Internal Stakeholders (client, people working on the project and employees)
Information on Technology
Challenges
Planning documents
Project Constraints:
Time (managing and planning meetings)
Continents – getting in touch with organisations with only the internet to rely on
Not enough information on the websites as it is a new technology
Discrepancies on the internet
Different ways plastic is primarily used eg in Europe they burn plastic for power not some much
to recycle
Timeline:
Week 1
5/05/19 – 07/05/19
- Discussing Project Plan and activities
06/05/19 Mon – Alex fixes appointments with client and mentor for the next 3 weeks
07/05/19 Tue
- Finalizing project plan (Alex, Keshav and Prashu to put together the project plan)
- Submitting to the Group for review
08/05/19 Wed
- Submission of Project Plan to Mentor before 4pm
09/05/19 Thu
- Zoom Meeting with Group at 6pm
- Implementing Mentor feedback
- Decide on 5 competitors
10/05/19 Fri
- Submission to client before 8am
Week 2
11/05/19 Sat
- Receive feedback from client
- Start outcome 2 and 3
12/05/19 Sun
- Zoom meeting with Group 11AM
- Start drafting Competitor analysis for Mentor
- Start working on Presentation
15/05/19 Wed
- Submission of draft report to Mentor before 4pm
16/05/19 Thu
- Zoom meeting with Group 6pm
- Implement Mentor feedback
17/05/19 Fri
- Submission of draft report to Client before 8am
Week 3
18/05/19 Sat
- Feedback from client
18/05/19 – 21/05/19
- Work on finalizing report
- Work on coordinating and beginning practice of presentation
19/05/19 Sun
- Meet up with Group in person 11AM
22/05/19 Wed
- Submission of final report to Mentor before 4pm
23/05/19 Thu
- Meet in person to discuss and implement feedback
- Final practice before presentation
24/05/2019 Fri
- Submission of final report to Client before 8am
- Assuming presentation is on the same day – Present