PARTIDA DESCRIPCION UNIDAD METRADO DURACIONES % AVANCE DE OBRA


CONTRATADO DE A DIAS Jan - 2018 Feb - 2018 Mar - 2018 Apr - 2018 May - 2018 Jun - 2018 Jul - 2018 TOTAL %
28 dc
TRAMO 01
01.00 TRABAJOS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 1.00 26/03/18 24/04/18 30 20.00% 80.00% 100.00%
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 65.10 26/03/18 24/05/18 60 10.00% 50.00% 40.00% 100.00%
02.00 TRABAJOS EN PLATAFORMA
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 304.00 31/03/18 29/05/18 60 1.67% 50.00% 48.33% 100.00%
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZ m2 405,360.00 05/04/18 03/06/18 60 43.33% 51.67% 5.00% 100.00%
02.03 SUB BASE GRANULAR (E=0.25 M) m3 17,985.00 10/04/18 08/06/18 60 35.00% 51.67% 13.33% 100.00%
02.04 BASE GRANULAR (E=0.15 M) m3 9,999.00 15/04/18 13/06/18 60 26.67% 51.67% 21.67% 100.00%
02.05 IMPRIMACION ASFALTICA m2 478,094.00 20/04/18 18/06/18 60 18.33% 51.67% 30.00% 100.00%
02.06 RECAPADO ASFALTICO (E=2") m2 478,094.00 25/04/18 23/06/18 60 10.00% 51.67% 38.33% 100.00%
03.00 SEÑALIZACION Y SEGURIDAD VIAL
03.01 MARCAS EN EL PAVIMENTO m2 16,926.00 24/06/18 08/07/18 15 46.67% 53.33% 100.00%
04.00 PROTECCIÓN AMBIENTAL
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 326.00 09/07/18 23/07/18 15 100.00% 100.00%
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 326.00 09/07/18 23/07/18 15 100.00% 100.00%
TRAMO 02
01.00 TRABAJOS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 1.00 25/01/18 29/01/18 5 100.00% 100.00%
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 10.60 25/01/18 08/02/18 15 46.67% 53.33% 100.00%
02.00 TRABAJOS EN PLATAFORMA
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 167.00 30/01/18 28/02/18 30 6.67% 93.33% 100.00%
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZ m2 74,200.00 04/02/18 05/03/18 30 83.33% 16.67% 100.00%
02.03 IMPRIMACION ASFALTICA m2 75,684.00 09/02/18 10/03/18 30 66.67% 33.33% 100.00%
02.04 RECAPADO ASFALTICO (E=2") m2 75,684.00 14/02/18 15/03/18 30 50.00% 50.00% 100.00%
03.00 SEÑALIZACION Y SEGURIDAD VIAL
03.01 MARCAS EN EL PAVIMENTO m2 2,756.00 16/03/18 20/03/18 5 100.00% 100.00%
04.00 PROTECCIÓN AMBIENTAL
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 106.00 21/03/18 25/03/18 5 100.00% 100.00%
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 106.00 21/03/18 25/03/18 5 100.00% 100.00%
TRAMO 03
01.00 TRABAJOS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 1.00 14/02/18 28/02/18 15 100.00% 100.00%
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 31.50 14/02/18 15/03/18 30 50.00% 50.00% 100.00%
02.00 TRABAJOS EN PLATAFORMA
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 170.00 19/02/18 30/03/18 40 25.00% 75.00% 100.00%
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZ m2 224,640.00 24/02/18 04/04/18 40 12.50% 77.50% 10.00% 100.00%
02.03 SUB BASE GRANULAR (E=0.25 M) m3 613.00 01/03/18 09/04/18 40 77.50% 22.50% 100.00%
02.04 BASE GRANULAR (E=0.15 M) m3 341.00 06/03/18 14/04/18 40 65.00% 35.00% 100.00%
02.05 IMPRIMACION ASFALTICA m2 231,336.00 11/03/18 19/04/18 40 52.50% 47.50% 100.00%
02.06 RECAPADO ASFALTICO (E=2") m2 231,336.00 16/03/18 24/04/18 40 40.00% 60.00% 100.00%
03.00 SEÑALIZACION Y SEGURIDAD VIAL
03.01 MARCAS EN EL PAVIMENTO m2 8,190.00 25/04/18 04/05/18 10 60.00% 40.00% 100.00%
04.00 PROTECCIÓN AMBIENTAL
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 158.00 05/05/18 14/05/18 10 100.00% 100.00%
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 158.00 05/05/18 14/05/18 10 100.00% 100.00%
1 2 3 4 5 6 7
PARTIDA DESCRIPCION UNIDAD METRADOS
Jan - 2018 Feb - 2018 Mar - 2018 Apr - 2018 May - 2018 Jun - 2018 Jul - 2018

TRAMO 01
01.00 TRABAJOS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb - - 0.20 0.80 - - -
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km - - 6.51 32.55 26.04 - -
02.00 TRABAJOS EN PLATAFORMA
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 - - 5.07 152.00 146.93 - -
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZ m2 - - - 175,656.00 209,436.00 20,268.00 -
02.03 SUB BASE GRANULAR (E=0.25 M) m3 - - - 6,294.75 9,292.25 2,398.00 -
02.04 BASE GRANULAR (E=0.15 M) m3 - - - 2,666.40 5,166.15 2,166.45 -
02.05 IMPRIMACION ASFALTICA m2 - - - 87,650.57 247,015.23 143,428.20 -
02.06 RECAPADO ASFALTICO (E=2") m2 - - - 47,809.40 247,015.23 183,269.37 -
03.00 SEÑALIZACION Y SEGURIDAD VIAL
03.01 MARCAS EN EL PAVIMENTO m2 - - - - - 7,898.80 9,027.20
04.00 PROTECCIÓN AMBIENTAL
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 - - - - - - 326.00
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 - - - - - - 326.00
TRAMO 02
01.00 TRABAJOS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 1.00 - - - - - -
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 4.95 5.65 - - - - -
02.00 TRABAJOS EN PLATAFORMA
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 11.13 155.87 - - - - -
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZ m2 - 61,833.33 12,366.67 - - - -
02.03 IMPRIMACION ASFALTICA m2 - 50,456.00 25,228.00 - - - -
02.04 RECAPADO ASFALTICO (E=2") m2 - 37,842.00 37,842.00 - - - -
03.00 SEÑALIZACION Y SEGURIDAD VIAL
03.01 MARCAS EN EL PAVIMENTO m2 - - 2,756.00 - - - -
04.00 PROTECCIÓN AMBIENTAL
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 - - 106.00 - - - -
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 - - 106.00 - - - -
TRAMO 03
01.00 TRABAJOS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb - 1.00 - - - - -
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km - 15.75 15.75 - - - -
02.00 TRABAJOS EN PLATAFORMA
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 - 42.50 127.50 - - - -
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZ m2 - 28,080.00 174,096.00 22,464.00 - - -
02.03 SUB BASE GRANULAR (E=0.25 M) m3 - - 475.08 137.93 - - -
02.04 BASE GRANULAR (E=0.15 M) m3 - - 221.65 119.35 - - -
02.05 IMPRIMACION ASFALTICA m2 - - 121,451.40 109,884.60 - - -
02.06 RECAPADO ASFALTICO (E=2") m2 - - 92,534.40 138,801.60 - - -
03.00 SEÑALIZACION Y SEGURIDAD VIAL
03.01 MARCAS EN EL PAVIMENTO m2 - - - 4,914.00 3,276.00 - -
04.00 PROTECCIÓN AMBIENTAL
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 - - - - 158.00 - -
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 - - - - 158.00 - -
OBRA: SERVICIO DE RECICLADO Y RECAPEO EN LA CARRETERA: Sullana - Dv. Talara, EMP. PE-1N (Dv. Catacaos) - Catacaos - Ov. Bayovar y Emp. PE-1N (Dv. Catacaos) - Piura (Av. El Progreso - Guardia Civil)
CONTRATISTA: CONSTRUCCION Y ADMINISTRACION S.A.

CALENDARIO DE AVANCE DE OBRA VALORIZADO (POR PARTIDAS)


PARTIDA DESCRIPCION UND P.U. MONTO CONTRATO 25 - ene - 2018 Feb - 2018 Mar - 2018 Apr - 2018 May - 2018 Jun - 2018 23 - Jul - 2018
S/. METRADO MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/.

TRAMO 01 37,098,792.41 - - 61,386.98 9,561,784.09 18,925,484.38 8,460,248.38 89,888.58


01.00 TRABAJOS PRELIMINARES 311,083.01 - - 61,250.64 245,968.55 3,863.82 - -
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 301,423.47 1.00 301,423.47 - - - - 0.20 60,284.69 0.80 241,138.78 - - - - - -
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 148.38 65.10 9,659.54 - - - - 6.51 965.95 32.55 4,829.77 26.04 3,863.82 - - - -
02.00 TRABAJOS EN PLATAFORMA 36,623,019.18 - - 136.34 9,315,815.54 18,921,620.56 8,385,446.74 -
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 26.91 304.00 8,180.64 - - - - 5.07 136.34 152.00 4,090.32 146.93 3,953.98 - - - -
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZADO C/EM m2 38.73 405,360.00 15,699,592.80 - - - - - - 175,656.00 6,803,156.88 209,436.00 8,111,456.28 20,268.00 784,979.64 - -
02.03 SUB BASE GRANULAR (E=0.25 M) m3 40.23 17,985.00 723,536.55 - - - - - - 6,294.75 253,237.79 9,292.25 373,827.22 2,398.00 96,471.54 - -
02.04 BASE GRANULAR (E=0.15 M) m3 54.21 9,999.00 542,045.79 - - - - - - 2,666.40 144,545.54 5,166.15 280,056.99 2,166.45 117,443.26 - -
02.05 IMPRIMACION ASFALTICA m2 3.66 478,094.00 1,749,824.04 - - - - - - 87,650.57 320,801.07 247,015.23 904,075.75 143,428.20 524,947.22 - -
02.06 RECAPADO ASFALTICO (E=2") m2 37.44 478,094.00 17,899,839.36 - - - - - - 47,809.40 1,789,983.94 247,015.23 9,248,250.34 183,269.37 6,861,605.08 - -
03.00 SEÑALIZACION Y SEGURIDAD VIAL 160,289.22 - - - - - 74,801.64 85,487.58
03.01 MARCAS EN EL PAVIMENTO m2 9.47 16,926.00 160,289.22 - - - - - - - - - - 7,898.80 74,801.64 9,027.20 85,487.58
04.00 PROTECCIÓN AMBIENTAL 4,401.00 - - - - - - 4,401.00
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 10.65 326.00 3,471.90 - - - - - - - - - - - - 326.00 3,471.90
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 2.85 326.00 929.10 - - - - - - - - - - - - 326.00 929.10
TRAMO 02 6,101,754.60 49,938.67 4,030,373.32 2,021,442.61 - - - -
01.00 TRABAJOS PRELIMINARES 50,477.91 49,639.07 838.84 - - - - -
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 48,905.08 1.00 48,905.08 1.00 48,905.08 - - - - - - - - - - - -
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 148.38 10.60 1,572.83 4.95 733.99 5.65 838.84 - - - - - - - - - -
02.00 TRABAJOS EN PLATAFORMA 6,023,746.37 299.60 4,029,534.48 1,993,912.29 - - - -
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 26.91 167.00 4,493.97 11.13 299.60 155.87 4,194.37 - - - - - - - - - -
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZADO C/EM m2 39.20 74,200.00 2,908,640.00 - - 61,833.33 2,423,866.67 12,366.67 484,773.33 - - - - - - - -
02.03 IMPRIMACION ASFALTICA m2 3.66 75,684.00 277,003.44 - - 50,456.00 184,668.96 25,228.00 92,334.48 - - - - - - - -
02.04 RECAPADO ASFALTICO (E=2") m2 37.44 75,684.00 2,833,608.96 - - 37,842.00 1,416,804.48 37,842.00 1,416,804.48 - - - - - - - -
03.00 SEÑALIZACION Y SEGURIDAD VIAL 26,099.32 - - 26,099.32 - - - -
03.01 MARCAS EN EL PAVIMENTO m2 9.47 2,756.00 26,099.32 - - - - 2,756.00 26,099.32 - - - - - - - -
04.00 PROTECCIÓN AMBIENTAL 1,431.00 - - 1,431.00 - - - -
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 10.65 106.00 1,128.90 - - - - 106.00 1,128.90 - - - - - - - -
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 2.85 106.00 302.10 - - - - 106.00 302.10 - - - - - - - -
TRAMO 03 18,486,082.28 - 1,236,796.98 10,688,634.06 6,527,494.52 33,156.72 - -
01.00 TRABAJOS PRELIMINARES 150,451.88 - 148,114.90 2,336.98 - - - -
01.01 MOVILIZACION Y DESMOVILIZACION TRAMO I glb 145,777.91 1.00 145,777.91 - - 1.00 145,777.91 - - - - - - - - - -
01.02 LIMPIEZA GENERAL (CALZADAS Y BERMAS) km 148.38 31.50 4,673.97 - - 15.75 2,336.99 15.75 2,336.98 - - - - - - - -
02.00 TRABAJOS EN PLATAFORMA 18,255,938.10 - 1,088,682.08 10,686,297.08 6,480,958.94 - - -
02.01 APORTE DE MATERIAL GRANULAR NIVELANTE m3 26.91 170.00 4,574.70 - - 42.50 1,143.68 127.50 3,431.02 - - - - - - - -
02.02 RECICLADO DE PAVIMENTO (E=0.175 M) Y ESTABILIZADO C/EM m2 38.73 224,640.00 8,700,307.20 - - 28,080.00 1,087,538.40 174,096.00 6,742,738.08 22,464.00 870,030.72 - - - - - -
02.03 SUB BASE GRANULAR (E=0.25 M) m3 40.23 613.00 24,660.99 - - - - 475.08 19,112.27 137.93 5,548.72 - - - - - -
02.04 BASE GRANULAR (E=0.15 M) m3 54.21 341.00 18,485.61 - - - - 221.65 12,015.65 119.35 6,469.96 - - - - - -
02.05 IMPRIMACION ASFALTICA m2 3.66 231,336.00 846,689.76 - - - - 121,451.40 444,512.12 109,884.60 402,177.64 - - - - - -
02.06 RECAPADO ASFALTICO (E=2") m2 37.44 231,336.00 8,661,219.84 - - - - 92,534.40 3,464,487.94 138,801.60 5,196,731.90 - - - - - -
03.00 SEÑALIZACION Y SEGURIDAD VIAL 77,559.30 - - - 46,535.58 31,023.72 - -
03.01 MARCAS EN EL PAVIMENTO m2 9.47 8,190.00 77,559.30 - - - - - - 4,914.00 46,535.58 3,276.00 31,023.72 - - - -
04.00 PROTECCIÓN AMBIENTAL 2,133.00 - - - - 2,133.00 - -
04.01 ELIMINACION DE PASIVOS AMBIENTALES m3 10.65 158.00 1,682.70 - - - - - - - - 158.00 1,682.70 - - - -
04.02 ELIMINACION DE PASIVOS AMBIENTALES m3 2.85 158.00 450.30 - - - - - - - - 158.00 450.30 - - - -
COSTO DIRECTO 61,686,629.29 49,938.67 5,267,170.30 12,771,463.65 16,089,278.61 18,958,641.10 8,460,248.38 89,888.58
GASTOS GENERALES 180 6,797,032.12 7 264,329.03 28 1,057,316.11 31 1,170,599.98 30 1,132,838.69 31 1,170,599.98 30 1,132,838.69 23 868,509.64
OBRA: SERVICIO DE RECICLADO Y RECAPEO EN LA CARRETERA: Sullana - Dv. Talara, EMP. PE-1N (Dv. Catacaos) - Catacaos - Ov. Bayovar y Emp. PE-1N (Dv. Catacaos) - Piura (Av. El Progreso - Guardia Civil)
CONTRATISTA: CONSTRUCCION Y ADMINISTRACION S.A.

CALENDARIO DE AVANCE DE OBRA VALORIZADO (POR PARTIDAS)


PARTIDA DESCRIPCION UND P.U. MONTO CONTRATO 25 - ene - 2018 Feb - 2018 Mar - 2018 Apr - 2018 May - 2018 Jun - 2018 23 - Jul - 2018
S/. METRADO MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/.
UTILIDAD 10.00% 6,168,662.93 4,993.87 526,717.03 1,277,146.37 1,608,927.86 1,895,864.11 846,024.84 8,988.85
SUBTOTAL 74,652,324.34 319,261.57 6,851,203.44 15,219,210.00 18,831,045.16 22,025,105.19 10,439,111.91 967,387.07
I.G.V. 18.00% 13,437,418.38 57,467.08 1,233,216.62 2,739,457.80 3,389,588.13 3,964,518.93 1,879,040.14 174,129.68
TOTAL PRESUPUESTO 88,089,742.72 376,728.65 8,084,420.06 17,958,667.80 22,220,633.29 25,989,624.12 12,318,152.05 1,141,516.75
PORCENTAJE DE AVANCE MENSUAL 0.43% 9.18% 20.39% 25.22% 29.50% 13.98% 1.30%
TOTAL PRESUPUESTO INCLUIDO I.G.V. 376,728.65 8,461,148.71 26,419,816.51 48,640,449.80 74,630,073.92 86,948,225.97 88,089,742.72
PROCENTAJE DE AVANCE ACUMULADO 0.43% 9.61% 29.99% 55.22% 84.72% 98.70% 100.00%
SERVICIO DE RECICLADO Y RECAPEO EN LA CARRETERA: Sullana - Dv. Talara, EMP. PE-1N (Dv. Catacaos) - Catacaos - Ov. Bayovar y Emp.
OBRA:
PE-1N (Dv. Catacaos) - Piura (Av. El Progreso - Guardia Civil)
CONTRATISTA: CONSTRUCCION Y ADMINISTRACION S.A.

RESUMEN DE CALENDARIO DE AVANCE DE OBRA VALORIZADO (POR PARTIDAS)

TRAMO DESCRIPCION MONTO S/. MONTOS MENSUALES S/.

Contrato 25-ene-2018 Feb - 2018 Mar - 2018 Apr - 2018 May - 2018 Jun - 2018 23-jul-2018

Tramo 01 SULLANA - TALARA 37,098,792.41 - - 61,386.98 9,561,784.09 18,925,484.38 8,460,248.38 89,888.58


Tramo 02 EMP. PE-1N (Dv. Catacaos) - PIURA (AV. EL PROGRESO - GUARDIA CIVIL) 6,101,754.60 49,938.67 4,030,373.32 2,021,442.61 - - - -

Tramo 03 EMP. PE-1N (DV. CATACAOS) - CATACAOS - OV. BAYOVAR) 18,486,082.28 - 1,236,796.98 10,688,634.06 6,527,494.52 33,156.72 - -

COSTO DIRECTO 61,686,629.29 49,938.67 5,267,170.30 12,771,463.65 16,089,278.61 18,958,641.10 8,460,248.38 89,888.58

GASTOS GENERALES 6,797,032.12 264,329.03 1,057,316.11 1,170,599.98 1,132,838.69 1,170,599.98 1,132,838.69 868,509.64

UTILIDAD 6,168,662.93 4,993.87 526,717.03 1,277,146.37 1,608,927.86 1,895,864.11 846,024.84 8,988.85


SUBTOTAL 74,652,324.34 319,261.57 6,851,203.44 15,219,210.00 18,831,045.16 22,025,105.19 10,439,111.91 967,387.07

I.G.V. 13,437,418.38 57,467.08 1,233,216.62 2,739,457.80 3,389,588.13 3,964,518.93 1,879,040.14 174,129.68

TOTAL PRESUPUESTO 88,089,742.72 376,728.65 8,084,420.06 17,958,667.80 22,220,633.29 25,989,624.12 12,318,152.05 1,141,516.75

PORCENTAJE DE AVANCE MENSUAL 0.43% 9.18% 20.39% 25.22% 29.50% 13.98% 1.30%
TOTAL PRESUPUESTO INCLUIDO I.G.V. 376,728.65 8,461,148.71 26,419,816.51 48,640,449.80 74,630,073.92 86,948,225.97 88,089,742.72

PROCENTAJE DE AVANCE ACUMULADO 0.43% 9.61% 29.99% 55.22% 84.72% 98.70% 100.00%

25-ene-2018 Feb - 2018 Mar - 2018 Apr - 2018 May - 2018 Jun - 2018 23-jul-2018

PORCENTAJE DE AVANCE MENSUAL 0.43% 9.18% 20.39% 25.22% 29.50% 13.98% 1.30%

PORCENTAJE DE AVANCE ACUMULADO 0.43% 9.61% 29.99% 55.22% 84.72% 98.70% 100.00%

120.00%
35.00%

30.00% 100.00%

25.00%
80.00%

20.00%
60.00%

15.00%

40.00%
10.00%

20.00%
5.00%

0.00% 0.00%
25-ene-2018 Feb-18 Mar-18 Apr-18 May-18 Jun-18 23-jul-2018 25-ene-2018 Feb-18 Mar-18 Apr-18 May-18 Jun-18 23-jul-2018