Beruflich Dokumente
Kultur Dokumente
Page No.
1. ALIGNMENT SURVEY 2
2. PRELIMINARY SURVEY 3
3. GEOMETRIC DESIGN 10
5. BIBILIOGRAPHY 34
ALIGNMENT SURVEY
GENERAL
Optimum alignment will be one, which yields the least overall transportation cost,
taking into account the cost of construction and maintenance of the road as well as
the recurring cost of vehicle operation, and at the same time having least adverse
impact on the environmental and ecological balance. The route should avoid the
introduction of hairpin bends as far as possible.
RECONAISSANCE
GENERAL
Study of survey sheets, maps, etc.: Reconnaissance begins with the study of all
the available maps. In India, topographical sheets are available in scale 1:50000.
Aerial reconnaissance: Aerial reconnaissance will provide a bird�s eye view of the
alignment under consideration, along with the surrounding area. It will help to
identify factors, which call for rejection or modification of any of the
alignments.
PRELIMINARY SURVEY
GENERAL
The preliminary survey consists of pegging the route previously selected on the
basis of the reconnaissance survey, cutting a trace 1.0m to 1.2m wide and running
an accurate traverse line along it for the purpose of taking longitudinal and cross
sections and establishing bench marks. The data collected at this stage forms the
basis for the determination of the final center line of the road.
The line and the grade of the selected alternative are pegged and the trace is cut
along the pegged route.
SURVEY PROCEDURE:
The survey should cover a strip of sufficient width taking into account the
degree and the extent of cut/fill, with allowance for possible shift in the center
line of the alignment at the time of final design. In the normal course, a strip
width of about 30m in straight or slightly curving reaches and 60m at sharp curves
and hairpin bends should meet the requirements.
Levelling work includes taking ground levels along the trace cut at intervals of
10m and at abrupt changes in slopes and also establishing benchmarks at intervals
250m exceptionally 500m by running check levels on a closed traverse basis
independently. While levelling along center line, readings of benchmarks should
also be taken to have a crosscheck in regard to accuracy of the field work. It is
particularly important that a single datum GTS datum should be used to tie up all
levels.
MAP PREPARATION:
Scales for the maps should generally be the same as adopted for the final drawings.
Normally, the horizontal scale might be 1:1000 and the vertical scale 1:100.
Determination of final centre line of the road design in the office is a forerunner
to the final location survey. This involves the following operations:
� Making use of plans from the preliminary survey showing the longitudinal
profile, cross-sections and contours, a few alterative alignments for the final
centre line of the road are drawn and studied and the best one satisfying the
engineering, aesthetic, economic and environmental requirements is selected.
� For the selected alignment, a trial grade line is drawn taken into
consideration the controls which are established by mountain passes, intersections
with other roads, railway/river crossings, unstable areas, etc.
� For the alignment finally chosen, a study of the horizontal alignment and
conjunction with the profile is carried out and adjustments made in both as
necessary for achieving proper co-ordination.
� Horizontal curves including spiral transitions are designed and the final
center line marked on the map.
� The vertical curves are designed and the profile shown on the longitudinal
section.
FINAL LOCATION SURVEY
GENERAL
The purpose of the final location survey is to layout the final center line of the
road in the field based on the alignment selected in the design office and to
collect necessary data for the preparation of working drawings.
TRANSIT SURVEY
The center line of the road, as determined in the design office, is translated on
the ground by means of a continuous transit survey and pegging of the center line
as the survey proceeds. All angles should be measured with a transit. It would be
necessary to fix reference marks for this purpose. These marks should be generally
20m apart in straight reaches and 10m apart in curved reaches. To fix the center
line, reference pillars- control burjis should be firmly embedded in the ground.
These should be located beyond the expected edge of the cutting on the hillside.
The maximum spacing between the pillars may be 100m.
The reference pillars should be so located that these will not be disturbed during
construction. Description and location of the reference pillars should be noted for
reproduction on the final alignment plans.
At the road crossings, the angles that the intersecting roads make with the final
center line should be measured with the help of a transit. Similar measurements
should be made at railway level crossings.
BENCHMARKS:
Levels along the final center line should be taken at all breaks in the ground.
Cross-sections should be taken at 60m interval.
The final location survey is considered complete when all necessary information is
available and ready for the designer to be able to plot the final road profile and
prepare the project drawings. Among other things, field notes should give a clear
description and location of all the benchmarks and reference points. This
information should be transferred to the plan drawings, so that at the time of
construction, the center line and the benchmarks could be located in the field
without any difficulty. In the last stage of alignment survey, hydrological and
soil investigations for the route should be carried out.
FIELD WORK DETAILS
The field work was started from Bench mark 11(connecting road between Melkote
Inspection bungalow to Gowrikatte circle (culvert parapet top) for fly levelling.
Highway alignment was started from TBM4 up to existing major road. The following
details were collected all along the survey route during reconnaissance survey:
� Soil type along the route and observation of the geological features.
� Presence of culvert along the route.
� Additional data regarding the geological function type of rocks were observed
all along the route of survey.
Final alignment was carried out by redesigning the geometric parameters of the road
at the point of curve suitably.
To find out the reduced level we use the dumpy level and levelling instruments. The
dumpy level generally consists of telescope tube finely secured in two collars
fixed by adjusting screws to the stage carried by the vertical spindle. The modern
form of dumpy level has the telescope. This form is known as solid dumpy.
The levelling staff is straight, rectangular rod having graduations; the foot of
the staff represents zero reading. The purpose of the levelling staff is to
determine the amount by which station is above or below the line of sight.
Prismatic compass is the most convenient and portable form of magnetic compass,
which can either be used as a hand instrument or can be fitted on a tripod. A
magnetic needle is attached to the circular ring or compass chord made of aluminium
a non magnetic substance. Using this instrument we measure the bearing (back
bearing and fore bearing).
Chain is another important device, which is generally made of steel, and is of
length 30m. It is a very important instrument to measure the length and also during
the fixing of the alignments in the field.
Another important device in the survey project is the Tape. It is generally made of
plastic. We first measure a certain distance interval with the help of chain or
tape.
After measuring the distance, using the prismatic compass and with the help of then
Ranging Rod we take bearing called fore bearing and back bearing.
WORKING OPERATIONS
REALIGNMENT:
While improving the horizontal alignment of road, improvement in sharp curves and
zig zags should be done after considering the whole alignment and not on a piece
meal basis. The improvement of transition curves would not generally be very costly
and therefore the defects should be rectified wherever necessary. The sight
distance available generally gets increased when the horizontal alignment is
improved or otherwise a set back distance may be increased at horizontal curves by
removing or shifting the obstructions from the inner side of curve upto the desired
extent.
While improving the vertical alignment attempt should be made to provide over
taking sight distance at summit curve. However, if this is not possible, atleast
the stopping sight distance should be available for the design speed at all
locations of the road. Now corrections of minor undulations such as humps and dips
may not involve high cost and so it is not desirable to provide suitable vertical
transition curves for shock free movements of vehicles travelling at the design
speed. Valley curves may be checked for comfort conditions and for visibility under
the head lights of the vehicle during night driving.
STEPS IN REALIGNMENT:
1. Reconnaissance of the stretch of road to be realigned, study of the deficiencies
and the possible changes in alignment.
2. Survey of existing roads recording the topographic features and all other
existing features such as drainage. The field work may be carried out using plane
table and level or by tachometry.
3. Observation of spot levels along the centre line of the road and cross section
levels at suitable intervals to note the gradient, cross slope and superelevation
etc.
4. Soil surveying along the stretch of land.
5. Comparison of economics and consideration of feasibility of alternate proposals
of realignment.
6. Finalisation of design features of realigned road stretches.
7. Preparation of drawings (showing plan, longitudanal section, and cross sections
for re-alignment project)
8. Marking out the centre line of re-aligned road while trying to utilise the
existing road to the maximum extent possible.
9. Checking the geometric design elements of the newly aligned stretch of the road.
GEOMETRIC DESIGN
Notes:
� In order to ensure proper sigh distance, it may be necessary to acquire
additional right-of-way over that indicated in the table. The right-of-way should
be enough to ensure a minimum setback of 5mm for building line from the centre line
of the road.
� Additional land with reference to the requirements may be acquired at
locations involving deep cuts. Fills and unstable or landslide areas
� If a road is expected, to be a higher classification in the foreseeable
future, the land width should correspond to the higher class of roads.
Width of carriageway, should and roadway for various categories of roads should be
as given in table.
Highway classification Carriageway width (m) Shoulder width Roadway width (m)
National highway & state highway
Single lane
Double lane
3.75
2x1.25
2x0.9
6.0
8.8
Major district road & other roads 3.75 2x0.5 4.75
Village roads 3.0 2x0.5 4.0
NOTES:
� The roadway width given in the Table are exclusive of parapets (usual width
0.6m)
� The roadway widths for village roads are on the basis of a single lane
carriageway of 3m. Widths greater that 3m may however be adopted judiciously
depending on the type and intensity of traffic, cost and related factors. In that
case the roadway width should be increased correspondingly.
� In hard rock stretches or unstable locations where excess cutting might lead
to slope failure, 0.8m on two-lane roads and 0.4 m in other cases may reduce the
width of roadway. However, where such stretches occur in continuous long length,
reduction in roadway width should not be effected unless requisite passing places
are provided.
� On horizontal curves, the roadway width should be increased corresponding to
the extra widening of carriageway for curvature.
� On roads subject to heavy snowfall, where regular snow clearance is done over
long periods to keep the road open to traffic, roadway width may be increased by
1.5m for MDR�s, ODR�s and VR�s.
CAMBER/ CROSSFALL
DESIGN SPEED:
The designs speeds for various categories of hill roads should be as given in the
Table.
SIGHT DISTANCE:
DESIGN VALUES OF STOPPING AND INTERMEDIATE SIGHT DISTANCES FOR VARIOUS SPEEDS:
The minimum distance open to the vision of the driver of a vehicle intending
to overtake slow vehicle ahead with safety against traffic of opposite direction is
know as the minimum overtaking sight distance or the safe passing sight distance
available.
HORIZONTAL ALIGNMENT
GENERAL:
In general horizontal curves should consist of a circular portion flanked
by spiral transitions, at both ends. Design speed, super elevation and coefficient
of side friction affect the design of circular curves.
Minimum radius curves should be adopted only when absolutely necessary at
reverse curves, sufficient gap should be ensured between the two curves for
introduction of the requisite transition curves. Compound curve may be used only
when it is impossible to fit in a single circular curve.
SUPER ELEVATION:
e= V �
225R
v� = e+f or R= V�
gR 127*(e+f)
Where
V = vehicle speed in m/s v = vehicle speed in km/h
G = acceleration due to gravity in m/s2
e = ratio of super elevation
f = co-efficient of side friction between vehicle tyres and pavement. (Taken as
0.15)
Radii for horizontal curves corresponding to ruling minimum and absolute minimum
design speeds are shown in the Table
MINIMUM RADIUS OF HORIZONTAL CURVES FOR VARIOUS CLASSES OF HILL ROADS
Also, if the deviation angle is less than 1� then horizontal curve is not required
at such places.
TRANSITION CURVES:
Spiral curve should be used for transitions. These are necessary for smooth entry
of vehicles from a straight section into a circular curve. The transition curves
also improve aesthetic appearance of the road, besides permitting gradual
application of the super elevation and extra widening at curves.
Minimum length of transition curves for various radii is given in the table.
The above table indicates the horizontal curves without transition curves.
In such cases, the super-elevation is provided as follows.
� First, calculate the length of transition curve though it is not provided.
Let L= length of transition curve
� Also, calculate the amount of super-elevation E, to be provided.
� Now, 2/3E is provided at the straight portion in a length equal to 2/3L, also
a remaining 1/3E is provided in the curved portion in a length equal to 1/3E
� In a similar way the calculated extra widening We is also provided, i.e.,
2/3We in the straight portion and 1/3We in the curved portion.
� Also, the extra widening is introduced on the inner side of the curve for
curves without transition curves also in hilly roads.
VERTICAL ALIGNMENT
GENERAL:
At horizontal curves the gradients should be eased by an amount known as the �grade
compensation� which is intended to offset the extra tractive effort involved at
curves. This may be calculated from the following formula;
Grade compensation (%) = (30 + EJ) /R
Subject to a minimum of 75/R , Where R is radius of the
curve in meters
VERTICAL CURVES
Vertical curves are introduced for smooth transition at grade changes. Both
summit curves and valley curves should be designed as square parabolas. The two
types of vertical curves are:
� Summit curves
� Valley curves
The length of summit curves is governed by the choice of sight, distance, whether
stopping sight distance of the intermediate sight distance.
The required length may be calculated from the following formula:
Case (1); when the length of the curve exceeds the required sight distance, i.e.L
is greater then S.
L= NS�
4.4
Where
N = deviation angle, i.e. the algebraic difference between the two
grades
L = length of the parabolic vertical curve in meters
S = sight distance in meters
Case (ii) when the length of the curve is less than the required sight distance
i.e. is less than S
L= 2S- 4.4
N
b) FOR INTERMEDIATE SIGHT DISTANCE
Case (i) When the length of the curve exceeds the required sight distance, i.e. is
greater then S
L= NS� /9.6
Case (ii) when the length of the curve is less than the required sight distance,
i.e. is less than S
L = 2S- 9.6/N
VALLEY CURVE
The length of the valley curves should be such that for night travel the headlight
beam distance is equal to the stopping sight distance. Based on this criterion, the
length of curve may be calculated as under;
Case (i): when the length of the curve exceeds the required sight distance. i.e. is
greater then S.
L = NS�
1.5+ 0.035S
Case (ii): when the length of the curve is less than the required sight distance,
i.e. is less than S
L= 2S- 1.5+0.035S/N
In both cases :
N= deviation angle, i.e. the algebraic difference between the two grades
L = length of the parabolic vertical curve in meters
S = sight distance in meters
Note: The above formula have been derived with the following Assumptions:
Headlight height = 0.75 m
Upward divergence of the light beam from the longitudinal axis of the vehicle = 10
ALIGNMENT COMPATIBILITY
As a general rule, changes in horizontal and vertical alignment should be phased to
coincide with each other, i.e. the vertical curve should roughly extend from 1 the
commencement to the end of the corresponding horizontal curve. More preferably, the
horizontal curve should be somewhat longer than the vertical curve. Sharp
horizontal curves should not be introduced at or near the top of the summit
vertical curves or the lowest point of valley curves.
HAIRPIN BENDS
Inner and outer edges of the roadway should be concentric with respect to the
centre line of the pavement, where a number of hairpin bends have to be introduced,
a minimum intervening length of 60m should be provided between the successive bends
to enable the driver to negotiate the alignment smoothly. At hair-pin bends,
preferably the full roadway width should be surfaced.
PASSING PLACES
Passing places or lay-byes are required on hill roads to cater to the following
requirements:
� To facilitate crossing of vehicle approaching from the opposite direction;
and to tow aside a disabled vehicle so that it does not obstruct traffic.
� There is no specific need of passing places on two-lane National and State
Highways. But in the case of single lane sections on National/State Highways which
have narrow roadway, provision of some passing places may be desirable.
� Normally the passing places or lay-byes should be 3.75m wide, 30m long on the
inside edge (i.e., towards the carriageway side), and 20m long on the farther side.
LATERAL CLEARANCE:
Desirably the full roadway width at the approaches should be carried through
the underpass. This implies that the minimum lateral clearance (i.e. the distance
between the extreme edge of the carriageway and the face of the nearest support)
should equal the normal shoulder width.
VERTICAL CLEARANCE:
Minimum vertical clearance of 5m should be ensured over the full width of the
roadway at all underpasses and similarly at overhanging cliffs and any semi-tunnel
section etc. the vertical clearance should be measured with respect to the highest
point of the carriageway, i.e., the crown or the super elevated edge of the
carriageway.
BLOCK LEVELLING
The method is used when the area to be surveyed is small and the ground
is not very much undulating. The area to be surveyed is divided into a number of
squares. The size of the square may vary from 5 to 20m depending upon the contour
and contour interval. The elevations of the comer of the contour and contour
interval. The elevations of the comers of the square are then determined by means
of a level and a staff. The contour lines may then be drawn by interpolation. It is
not necessary that the squares may be same size. Sometimes, rectangles are also
used in places of squares. When there are appreciable breaks in the surface between
corners, guide points in addition to those at comers may also be used. The squares
should be as long as practicable, yet small enough to conform 1 to the inequalities
of the ground and top the accuracy required.
V=50kmph
SSD = 0.278vt + v�
254f
= 0.278*50*2.0 + 50�
254(0.4)
= 53m
For speed of 50kmph the minimum recommended SSD is 60m.
L = 0.38vNV� kmph
= 0.38v0.0353*50�
= 24.0m
2. Length of valley curve for SSD condition
L = NS�
2h1 + 2S tana
= 0.0353*(60.0)�
1.5 + 0.035*60.0
L = 2S - (1.5+0.035S)
N
= 2*60 - (1.5+0.035*60)
0.0353
L= 18m
Provide L = 24m
R L of T2 = 966.670+((12*3.7)/100)= 966.226m
R L of E = �( RL of T1 + RL of T2)
= (966.649+ 966.226)/2
= 966.438m
R L of F = �( RL of E + RL of pi)
= �(966.438+966.226)
= 966.332m
SUMMIT CURVE
= 24.5mt
N= 1 / 25 � 1 / 110
= 0.030 radius
Therefore length of summit curve = 24.5 m
R.L of T1 = 979.306
R.L of T2 = 978.424
R.L of E = (979.306 + 950) / 2 = 964.653 mt
Spiral Angle = ?S = L(180)/ 2pR = 45X 180/(2X89.47X3.14) = 14.41� = 14� 24� 67��
Central angle for circular curve = ?C = ?- (2?S) = 90-(2X14.14) = 61.48� =
61�10�48��
CIRCULAR CURVE:
Length of circular curve = pR?C/180 = pX87.89X61.18/180 = 95.54m
Length of combined curve = pR?C/180+2L = pX87.8X61.18/180 + 2(45) = 185.54m
Calculations : -
Chainage of point of intersection = 335+121.91 = 456.91m
Subtract tangent length OT1 = 456.91 � 121.91 = 335m
Add length of transition curve = 335+45m = 380mts
Chainage of beginning of circular curve = 380mts
Length of circular curve = A = 95.54m
Chainage at end of circular curve B = 380+95.54 = 475.54mts
Add length of transition curve = 475.54+45 = 520.52m
Chainage at end of transition curve T2 = 520.54m
Extra widening of curve
We = nl^2/2r+v/9.5(r)�
={2(6.1)��(2*89.47)}+{100�(9.5*(89.47)�)}
=0.42+1.11
=1.53m
Total raise of outer edge above the inner edge
E= (17+1.53)*0.07= 1.29m
1. SSD = 0.278Vt+V�/254(f�0.01n)
= 0.278(50)(2.5)+(50)�/254(0.35�0.01*5)
=34.75+24.61
=59.36mts
2 . OSD=0.278Vst+0.278VbT+2S+0.278VT
Vb=50-16=34kmph
T=2sec
S=0.2Vb+6=0.2(34)+6=12.8m
T=(14.45/a)�=(14.4(12.8)/3.2)�=7.59
OSD=d1+d2+d3
OSD=0.278(34)(2)+0.278(34)(7.59)+2(12.8)+0.278(50)(7.59)
OSD=221.74m
FIRST PART OF THE TRANSITION CURVE
CIRCULAR CURVE
Length of first sub chord =5m
Length of unit sub chord =6m
Length of last sub chord =.54m
Total no of chords =15
Point Unit chord d
?
A 0 0�0'0" 0�0'0"
1 5 1�36'3.61" 1�36'3.61"
2 6 1�55'16.33" 3�31'19.94"
3 6 1�55'16.33" 5�26'36.27"
4 6 1�55'16.33" 7�21'52.6"
5 6 1�55'16.33" 9�17'41.59"
6 6 1�55'16.33" 11�12'25.26"
7 6 1�55'16.33" 13�7'41.59"
8 6 1�55'16.33" 15�2'57.92"
9 6 1�55'16.33" 16�58'14.25"
10 6 1�55'16.33" 18�53'30.58"
11 6 1�55'16.33" 20�48'46.91"
12 6 1�55'16.33" 22�44'3.24"
13 6 1�55'16.33" 24�39'19.57"
14 6 1�55'16.33" 26�34'35.9"
B 0.54 1�55'16.33" 26�44'58.37"
2nd TRANSITION CURVE:
Length of first sub chord =5m
Length of last sub chord =6m
No. of unit chords = 8
FLEXIBLE PAVEMENTS
Flexible pavements are those, which on the whole have low or negligible
flexural strength and are rather flexural in their structural under loads.
The flexible pavement layers reflect the deformation of the lower layer to
the surface of the layer. Thus if the lower layer of the pavement or soil sub-grade
is undulated, the flexible pavement surface also gets undulated. A flexible
pavement consists of four pavements:
1. Soil sub-grade
2. Sub-base course
3. Base course
4. Surface course
RIGID PAVEMENTS:
Rigid pavements are those, which possess noteworthy flexural strength or flexural
rigidity. The stresses are not transferred from grain to grain to the lower layers
as in the case of flexible pavements layers. The pavements are made of Portland
cement concrete plain, reinforced or prestressed concrete. The rigid pavements are
usually designed and the stresses are analyzed using elastic theory, assuming the
pavement as an elastic plate resting over elastic or a viscous foundation. It
consists of three components:
Ns=C.S.A
A=Initial traffic * D.F.
R= rate of growth
F= vehicle damage factor
TRAFFIC TERRAIN
VDF
UN-SURFACED THIN SURFACED THICK SURFACED
<150 HILLY 0.5 0.75
ROLLING 1.5 1.75
PLAIN 2 2.25
150-1500 HILLY 1.0 1.25
ROLLING 2.0 2.25
PLAIN 2.5 2.75
>1500 HILLY 1.25 1.5
ROLLING 2.25 2.5
PLAIN 2.75 3
With the thick bituminous surface and if rainfall is 500 mm / yr. and if
D= 1m at least.
= 1 m for sandy soil
= 3 m for sandy clay
Then, soaking is not required.
Sub- base: materials are natural sand, moorum, gravel, laterite, and brick metal
and crushed stone.
Min. CBR = 20% to 30%
(If sub grade CBR is higher than 20% to 30% value, then sub-base is not required.)
Base : consists of WBM or wet mix macadam.
Its CBR value = 100%
Min. Thickness = 15 cm.
Bituminious surface :
SD= surface dressing.
Soil test;
� Re-moulded specimen; sieve the soil on a 19mm sieve. Take the soil that
passes through 19mm sieve, allowance for larger material is made by replacing it by
an equal amount of material which passes the 19mm sieve but is restrained on the
4.75mm sieve.
Dynamic compaction
Penetration test:
RECORD OF OBSERVATIONS:
1. Soil identification.
2. Amount of soil fraction above 20mm that has been replaced.
3. Density.
4. Moisture content.
5. Expansion ratio.
6. Penetration test readings.
7. Surcharge wt used.
8. Plot load penetration curve.
9. Apply correction to curve if necessary.
10. Find the CBR value.
6. BIBILIOGRAPHY
1. Highway Engineering
By Khanna S.K. & Justo C E G
2. Highway Engineering
By Kadiyali L.R.
3. Transport Engineering 1
By K.P Subramanyam.