Beruflich Dokumente
Kultur Dokumente
2016
AT
PROPOSED BY
TABLE OF CONTENTS
List of Tables ......................................................................... 4
List of Figures ....................................................................... 5
CHAPTER 1 ............................................................................... 6
INTRODUCTION ......................................................................... 6
1.1 Preamble ....................................................................................................... 6
1.2 Project Location ........................................................................................... 6
1.3 STRUCTURE OF EIA REPORT...................................................................... 9
1.4 OBJECTIVES OF THE STUDY ........................................................................ 10
1.5 METHODOLOGY OF THE STUDY ................................................................. 10
CHAPTER 2 ............................................................................. 12
2.1 INTRODUCTION ......................................................................................... 12
2.2 PROJECT DESCRIPTION ............................................................................ 12
2.2.1 Project Cost .............................................................................................. 15
2.2.2 Land Use .................................................................................................. 15
2.2.3 Built up Area ............................................................................................ 15
2.2.4 Accessibility ............................................................................................. 16
2.2.5 Site Setting ............................................................................................... 16
2.3 PROJECT COMPONENTS............................................................................ 18
2.3.1 Project layout and development concept ................................................. 18
2.3.2 Building and Tenement Statement ....................................................... 18
2.3.3 Car parking Arrangements ....................................................................... 21
2.4 PROJECT INFRASTRUCTURE AND UTILITIES PLANNED....................... 21
2.4.1 Water Supply .......................................................................................... 21
2.4.2 Sewerage System ..................................................................................... 23
2.4.3 Solid waste ............................................................................................... 26
2.4.4 Power supply............................................................................................ 26
2.4.5 Fire Fighting............................................................................................. 26
2.5 RAIN WATER HARVESTING ...................................................................... 26
2.6 STORM WATER‐ COLLECTION AND DISPOSAL ...................................... 27
2.7 ENVIRONMENTAL ASSESSMENT OF BUILDING PLANNING AND USE. 29
CHAPTER 3 ............................................................................. 30
BASELINE ENVIRONMENTAL QUALITY ........................................... 30
3.1 INTRODUCTION ........................................................................................ 30
3.2 SCOPE OF BASELINE STUDIES ................................................................ 30
3.3 AIR ENVIRONMENT .................................................................................. 33
3.3.1 Meteorology ............................................................................................. 33
3.3.2 AMBIENT AIR QUALITY ......................................................................... 35
3.4 NOISE ENVIRONMENT ............................................................................. 39
3.4.1 Methodology for Noise Monitoring ..................................................... 40
3.5 WATER ENVIRONMENT........................................................................... 41
3.6 SEISMOLOGY.............................................................................................. 42
3.7 SOIL ............................................................................................................. 43
3.8 BIOLOGICAL ENVIRONMENT ................................................................... 44
3.8.1 ECOLOGY ................................................................................................... 44
3.8.2 FLORA ........................................................................................................ 45
3.8.3 FAUNA ....................................................................................................... 46
AVIFAUNA........................................................................................................... 46
CHAPTER 4 ............................................................................. 50
List of Tables
List of Figures
Figure 1.1: Layout superimposed on IRS Map ........................................ 7
Figure 1.2: Location Map Indicating Proposed Project and its Surrounding roads
.............................................................................................. 8
Figure 2.1: Layout Plan ................................................................ 13
Figure 2.2: Google Image (Project Site & Its Surrounding) ........................ 17
Figure 2.3: Project Layout plan ....................................................... 19
Figure 2.4: Parking plan ............................................................... 20
Figure 2.5: Water Balance Diagram (Dry Season) .................................. 23
Figure.2.6: Location of STP & vermi‐composting unit on Layout Map ........... 25
Figure 2.7: Storm Water Drainage Plan .............................................. 28
Figure 3.1: Sampling Location Map................................................... 32
Figure 3.2: Wind Rose at study area ................................................. 35
Figure 3.3: Seismic Zone Map of India ............................................... 42
Figure 4.2: Storm Water Drainage Plan .............................................. 56
Figure 4.2: Predicted Noise Levels ................................................... 60
Figure 5.1: Project location ............................................................ 66
CHAPTER 1
INTRODUCTION
1.1 Preamble
1. Cottages G +1 floor 7 28
Administrative
3. Building G +1 floor ‐ 20
(Restaurant)
4. Hotel staff ‐ 20
TOTAL 92
The location map indicating proposed project and its surroundings are
depicted in Figure 1.2.
Figure 1.1: Layout superimposed on IRS Map
Rapid EIA, Construction of Hotel Resort at Borli, Tal ‐ Murud, Dist ‐ Raigad
Figure 1.2: Location Map Indicating Proposed Project and its Surrounding roads
Sr. Frequency of
Attribute Parameters
No Monitoring
1 Ambient air PM10, PM2.5, SO2, Ambient Air Quality
quality NOx and CO samples were
monitored for 24hrs,
twice a week for total
13 weeks
2 Meteorology Surface: Wind speed and Primary data at Site,
direction, temperature and Secondary data
relative humidity and collection from IMD,
rainfall. Santacruz.
3 Water quality Physical, Chemical and Primary data –
Bacteriological Groundwater sample
parameters. was collected from One
borewell, One Surface
water sample
4 Ecology Existing terrestrial and Based on the data
aquatic flora and fauna. collected from
secondary sources.
6 Noise levels Noise levels in dB(A) Continuous 24‐hourly
monitoring at 5
locations during the
study period
7 Soil Parameters related to Sampling at project site
characteristics agricultural & was studied.
afforestation potential.
8 Traffic study Traffic density / pattern Survey at 1 location
once in study period.
9 Geology Geology of the area Based on data collected
from secondary sources.
10 Hydrology Drainage pattern, nature Based on data collected
of streams, aquifer from secondary sources.
characteristics recharge
and discharge areas.
CHAPTER 2
PROJECT DESCRIPTION
2.1 INTRODUCTION
This chapter presents the salient features of the project & infrastructure
required for the construction, functioning of the proposed project at Borli,
Tal‐ Murud, Dist‐ Raigad, Maharashtra.
The proposed site is located at Plot bearing S. No. 47/1, 47/2, 49 & 43 of
village – Borli, Tal – Murud, Dist – Raigad, State – Maharashtra. The project
comprising of 3 Cottages (Ground floor), Administrative Building with
restaurant (G + 1 floor), Standard rooms (G + 1 floor) and Swimming pool.
The proposed development will involve site formation works and
construction of building/structures, access roads, drains and sewer
connections. The resort is proposed to locate on a flat land.
The Plot area of proposed site is 4030.00 m2 and Total Construction Area
is 1302.22 m2, 12 Standard rooms, 7 cottages, Restaurant, Administrative
building is proposed in this project.
The design of the layout has taken into consideration the state of the art
design features for living atmosphere and arrangements of open space so
as to create a pleasant living environment for tourists.
The proposed development will involve site formation works and
construction of building structures, approach roads and drains. The layout
plan of proposed project is shown in Figure 2.1
The salient feature of the proposed project is given in Table 2.1.
Table 2.1: Project details
SR.
Details Information Unit
No.
Proposed construction of
1 Name of the project Hotel Resort at Borli,
Raigad, Maharashtra
2
2 Total Plot Area 4030.00 m
2
3 FSI Area 1,002.22 m
2
4 Non FSI Area 300.00 m
2
5 Total Construction Area 1,302.22 m
12 standard rooms, 7
6 No. of tenements cottages, Restaurant, Nos.
Administrative building
7 Total water requirement 15 KLD
Sewage generation:9 KLD
8 Sewage and STP details STP Capacity: 10 KLD
STP Technology: Phytorid ‐
9 Total Solid Waste Generation 18 kg/d
Biodegradable component
10 11 kg/d
(Vermi Composting)
Connected Load: 0.12 MW
11 Total Power Requirement
Demand Load: 0.08 MW
12 DG Set 20 kVA
Total Energy Savings
13 Energy Efficiency %
:23.25
4‐W provided : 20 Nos.
14 Parking Provision
2‐W provided:12 Nos
15 RWH Capacity 10 KLD
SWD Generation (300 mm 3
16 458.7 m /hr
wide channel)
Capital cost : 11.15 Rs. Lakhs
17 EMP Cost Operation & Maintenance Lakhs
Cost: 3.1 Rs. /yr
2.2.4 Accessibility
The proposed construction site is located at 18030’47.57” N latitude and
72054’50.48” E longitude. The proposed site is located at about 35 km from the
Roha railway station; Alibagug ST Depot: 23 km; The site is accessible by existing
13.0 m wide Alibaug‐ Murud State highway & 9.0 m wide access Road.
Figure 2.4: Parking plan
LOSSES
3 KLD
TO STP
TO STP
5 KLD
4 KLD
9 KLD
TO STP
STP 9 KLD
CAPACITY:10 KLD
TREATED WATER
0.09 KLD
SLUDGE
DRYING BEDS EXCESS TREATED WATER TO
GARDENING
Quantity
Sr. No. Reuse
(KLD)
1. Flushing 4
2. Gardening 5
4. Total 9
The Location of STP’s on Layout Plan is given in Figure 2.6.
Table 2.8: Expected Characteristics of Raw and treated Water
provided to enable the first rain washings from terrace/ roof to bypass the
storage tank as it would contain undesirable dirt. The excess rainwater from the
tanks will be diverted to storm water drain. The mouths of all pipes and its
openings will be covered with mosquito (insect) proof wire net. For the efficient
discharge of rain water, there will be at least two rain water pipes of 100mm.
diameter for a roof area of 100 sq. m.
The roof top rain water harvesting potential of the project area is around 5 KLD.
The RWH tank will be provided to each building. The excess harvested water will
be discharged in Storm water drains.
The annual rainfall over Raigad district is around 2400 mm/year. Considering
the 95 rainy days, the average rainfall is around 25 mm/day. The roof top rain
water harvesting structure (Tanks) has been designed considering the average
rainfall of 25 mm/day. However the storm water drains are designed for peak
rainfall of 150 mm/hr.
Table 2.10: Roof Top Rain Water Harvesting Potential
Average RWH
Runoff
Sr. No. Area Details Area in m2 Rainfall 25 POTENTIAL
Coefficient
mm/day KLD
1 Roof top area 253 25 0.8 5
Harvesting rain water will be utilised for floor washing, car washing, gardening
during non‐rainy days and flushing etc.
2.6 STORM WATER‐ COLLECTION AND DISPOSAL
Storm water drains inside each plot will be constructed strictly in accordance to
the town planning regulations. Storm water from the entire plot will be collected
through network of storm drains. The storm water drains has been designed for
150 mm/hr of peak rainfall. The overflow of RWH tanks will be discharged in the
existing storm water drains.
The details of storm water generation from plot and surrounding area is given in
following drawing.
CHAPTER 3
BASELINE ENVIRONMENTAL QUALITY
3.1 INTRODUCTION
Baseline environmental status forms the basis for evaluation of the proposed
development on the existing conditions. This can be broadly grouped into
physical, social, aesthetic and economic environment. Physical environment
includes air, water, land, aquatic and terrestrial flora & fauna, civic
infrastructure, public services, etc. Social environment includes demography,
community facilities and services, community characteristics, employment
centres, commercial facilities servicing the area, etc. Economic environment
covers employment levels, sources and levels of income, economic base of the
area, land values, land ownership etc.
For the present EIA study, the attributes of environment considered are:
3.3.1 Meteorology
Meteorology (weather and climate) is the key to understanding the air quality.
The essential relationship between meteorology and atmospheric dispersion
involves the wind in the broadest sense of the term. Wind fluctuations over a
very wide range of time accomplish dispersion and strongly influence other
processes associated with them.
Season Period
Summer March to May
Monsoon June to September
Post monsoon October to November
Winter December to February
Presentation of Secondary Data:
The main source of secondary meteorological data for the study area was the
Gazetteer of India.
The climate of Raigad district is mostly humid all‐round the year and receives
with average annual rainfall in the district is 2874.9 mm. About 94% of the
annual rainfall is received during south west monsoon season.
Mean
No. of Relative
Sr. Temperature Rainfall Wind
Month Rainy Humidity
No (oC) (mm) Speed
Days (%)
kmph
Max. Min.
1 January 30.9 19.1 0.6 0.0 62 7.6
2 February 30.8 19.6 0.0 0.0 63 7.6
3 March 31.4 22.4 0.2 0.0 69 8.0
4 April 32.2 25.3 2.2 0.2 71 9.0
5 May 32.7 26.5 40.2 2.3 72 10.1
6 June 30.5 24.9 828.6 19.8 84 12.9
7 July 28.8 24.2 937.6 26.0 89 17.9
8 August 28.5 24.0 612.2 24.3 88 14.8
9 September 29.3 23.6 280.1 14.9 85 8.1
10 October 31.5 23.5 121.8 5.4 77 6.6
11 November 32.9 21.6 41.8 1.8 64 7.4
The project area has a typical coastal climate. The year can be divided into four
distinct seasons. The period from March to May comprises the summer seasons
and in subsequent months from June to September, the area comes under the
influence of south‐west monsoons. The months of October and November
experience the post‐monsoon seasons, while winter seasons lasts from
December to February.
Presentation of Primary Data:
A weather station was installed onsite to collect hourly data. This station
measured wind speed and direction, temperature, relative humidity, and rainfall.
The detailed data on the microclimate of the site was collected for a period of
three month (Dec 2016 ‐ Feb 2017), representing the winter season. A
micrometeorological station was set up in the study area near the project site for
collection of data at hourly intervals during the study period. Temperature,
humidity, wind speed and direction, pressure, rainfall and cloud cover were
monitored at hourly intervals. The data summaries are given in Table 3.2.
Table 3.2: Micrometeorological Conditions
35%
28%
21%
14%
7%
WEST EAST
WIND SPEED
(m/s)
>= 11.1
8.8 - 11.1
5.7 - 8.8
3.6 - 5.7
2.1 - 3.6
0.5 - 2.1
Calms: 20.88%
SOUTH
Air pollution can cause significant effects on humans, animals, vegetation and
materials. The project construction is not a major contributor to the air pollution
except for particulate matter emission during both construction phase due to
plant and machinery and vehicular pollution during use phase. However, air
environment monitoring covered the parameter for which National Ambient Air
Quality standards have been defined by the Ministry of Environment and Forests.
Accordingly, parameters monitored were PM10, PM2.5, Oxides of Nitrogen (NOx),
Sulphur dioxide (SO2) and Carbon monoxide (CO).
(b) To identify the major air pollution sources and their impacts on the area
surrounding the site.
The following sources of air emissions were identified within the impact zone:
Other sources of air pollution within the impact zone include domestic fuel
combustion.
A well devised air quality monitoring program was undertaken to ascertain the
major air pollutants (PM10, PM2.5, SO2, NOX, and CO).
During the time of ambient air quality sampling (winter) the monitoring
locations were selected by taking into consideration the long‐term
meteorological trends to obtain the predominant wind direction. Monitoring
stations were placed at sensitive receptors within 5 km radius from the project
site. Monitoring stations were placed at the height of 3 meters at & are described
in Table 3.3. The locations selected for the air monitoring are shown in Figure
3.1.
Table 3.3: Ambient Air Quality Monitoring Stations Location
Air quality was monitored at five locations for 24 hours, twice a week, for a total
of 12 weeks as per the guidelines specified by the MoEF. The volumetric flow
rate of each sampler was maintained at 1.1‐1.2 l/min. Collected air samples are
analysed by using standard procedures prescribed by Central Pollution Control
Board (CPCB), Indian Standards: IS 5182 and American Public Health Association
(APHA). Details of techniques used for analysis of air samples are given in Table
3.4.
Equipment/
Sr. Code of Methodolog
Parameter Sampler Instruments for
No. Practice y Adopted
Analysis
Respirable
Dust
IS: 5182 Gravimetric
1. PM10 Sampler Balance
(Part IV) Method
with Cyclone
Separator
PM2.5 Gravimetric
2. PM2.5 Balance
Sampler Method
IS: 5182
3. SO2 HVS Colorimeter Colorimetric
(Part V)
IS: 5182
4. NOx HVS Colorimeter Colorimeter
(Part V)
Carbon Gas Flame
IS: 5182 Bladder and
5. monoxide Chromatograph Ionization
(Part X) Aspirator
(CO) with Methaniser Detector
Ambient air quality analysis results for the three monitoring locations, which
were selected to represent baseline conditions of the region, are given below.
Sr. Concentrations
No.
Location RSPM PM 2.5 SO2 NOx CO
(μg/m3) (μg/m3) (μg/m3) (μg/m3) (mg/m3)
1. Project Site
Maximum 61.6 31.9 22.4 23.7 0.8
Minimum 50.3 22.4 13.6 14.5 0.5
Average 57.2 27.9 19.3 19.1 0.7
Standard 3.4 2.8 2.6 3.1 0.1
Deviation
98th Percentile 60.8 31.6 22.4 23.6 0.8
2. Wandeli Village
Maximum 62.5 35 24 25 0.7
Minimum 53.9 25 15 17 0.5
Average 60.6 31 20 22 0.6
Standard 2.8 3 3 3 0.1
Deviation
98th Percentile 62.4 34 24 25 0.7
3. Borli Village
Maximum 61 38 22 24 0.72
Minimum 51 28 12 14 0.44
Average 58 34 18 20 0.60
Standard 3 3 3 3 0.09
Deviation
98th Percentile 61 38 22 23 0.70
Sound pressure level (SPL) measurements were automatically recorded with the
help of an Integrated Sound Level Meter to give the equivalent noise level for
every hour continuously for 24 hours in a day. In this manner, 1 full day (i.e. 24
hourly values) of data was collected at each of the four locations.
Mixed categories of areas may be declared as one of the four above‐mentioned categories
by the competent authority.
Ground water sample of exiting well were identified within the study area.
However the upcoming project will not affect these water bodies directly or
indirectly.
After the analysis of the collected water sample, it was observed that pH of the
water sample was observed to be 7.1.
3.6 SEISMOLOGY
Study area is classified under the Zone III of the Bureau of Indian Standards (BIS)
2000 seismic zone map for India as seen in Figure 3.3. Zone III is defined as
having a maximum intensity expected of around VII on MM scale.
Figure 3.3: Seismic Zone Map of India
Zone Max. MSK Intensity
2 VI
3 VII
4 VIII
5 IX or higher
Structurally, proposed project at has been designed to meet seismic
requirements of Zone III.
3.7 SOIL
Soil sample were collected at project site to establish the baseline characteristics.
Soil sample have been collected using auger from a depth of 60 cm from one
location. Soil sample collected were analysed for physical and chemical
characteristics. The results of the analysis are given in Table 3.13.
Texture is an important parameter of the soil which determines the usefulness
for agriculture purposes. Soil is mainly composed of three minerals i.e. sand, silt,
and clay. According to their size, these mineral particles are grouped into
separates. Soil separate in a group of mineral particles that fit within definite size
limits expressed as diameter in millimetres. A quantitative assessment of the
particle size distribution in the soil was made by wet sieve analysis and
sedimentation analysis using hydrometer, as per procedures laid down in IS:
Rapid EIA, Construction of Hotel Resort at Borli, Tal ‐ Murud, Dist ‐ Raigad
2720 Part IV. According to BIS classification system, soils are primarily classified
based on dominant particle sizes and its plasticity characteristics. Soil particles
mainly consist of four size fractions. The particle sizes are designated according
to the scale mentioned in IS:1498, are shown below:
Table 3.10 A: Particle Size Distribution as per IS:1498
Sr. No. Soil Types Range of Particle Size
1. Gravel 80 – 4.75 mm
2. Sand 4.75mm – 0.075mm (75 microns)
3. Silt 75 – 2 micron
4. Clay less than 2 micron
Table 3.10 B: Particle Size Distribution and Texture of Soil within the Study
Area
Particle Size Distribution
Sr. Locations (%) Texture
Sand Clay Silt
1 Project Site 50.3 49.1 0.6 Sandy Clay
Table 3.11: Soil Quality Parameters in the Study Area
Sr. No. Parameters Location
At Project Site
1 pH 6.7
2 EC+ (mS/cm) 1.45
3 CEC* (mEq/100gm) 12.4
4
Organic matter (mg/kg) 17.5
5 Sodium (mg/kg) 218
6 Nitrogen (mg/kg) 281
7 Phosphorus (mg/kg) 7.26
8 Potassium (mg/ha) 384
9 Copper (mg/kg) 45.1
10 Zinc (mg/kg) 48.2
11 Texture# (%) SC
12 Water holding Capacity (%) 38.4
13 Porosity (%) 32.0
ND – Not Detectable
3.8.1 ECOLOGY
The ecological survey was carried out to establish the baseline ecological
conditions of the region. The project being residential in nature will not affect the
flora and fauna in the vicinity. On the contrary it will help in improving the
general ambience of the locality.
Description of ecological environment accompanied with possible important
delination is essential to impact assessment process. Biological environment has
been defined as all plants and animals in a given place and time and a description
of them. Also, it is defined as a "Science that concerns itself with the
interrelationships of living organisms, plants and animals and their
environment" (A. Macfadyen, 1957). However, only description of plants and
animals is not just sufficient for the EIA, but it is important to know how these
components will be affected adversively or positively due to the proposed
activities.
3.8.2 FLORA
List of flora observed in study area is given in Table 3.12. None of the plant
species is identified as belonging to rare, endangered or threatened category as
compared with records of Botanical Survey of India (Red Book of Data, Nayar,
1987, 1988 & 1990) and other available reports such as data from the district
forest office and the related reference books from the BNHS on the subject
(Billore, 1972; Almeida, 1996).
3.8.3 FAUNA
The fauna of an area is dependent upon the vegetation and there are countless
relationships between the species composing an animal community. Assessment
techniques generally provide information on the dominant species, rare or
endangered species, species sensitive to impacts and important ecological
interrelationships. There are several methods in which animals may be assessed.
The choice of method that is used varies with the extent and purpose of study.
A published list from Forest Departments (Thane and Raigad District) and
information gathered from the people residing in and around the study area was
used as reference materials.
AVIFAUNA
Insecta
Bees Apis mellifica Honey Bee
Spiders Attidae sp Jumping Spider
Argiope sp Signature Spider
Amphibia IV Rana cyanophlyctis Skipper Frog
IV Rana tigrina Indian Bullfrog
Reptilia Calotes versicolor Common Garden Lizard
Mabuya carinata Common Skink
II Xenochropis piscator Checkered Keelback
Mammalia V Bandicota indica Bandicoot Rat
IV Funambulus palmarum Three striped palm squirrel
II Herpestes edwardsi Common Mongoose
V Pteropus giganteus Indian Flying Fox
CHAPTER 4
ENVIRONMENTAL IMPACT IDENTIFICATION, PREDICTION
AND ANALYSIS
4.1 INTRODUCTION
Environmental impact assessment involves identification, prediction and
evaluation of potential impacts of the proposed activities within the study area.
These activities include all the actions that are required for successful
construction of project and its use. The baseline setting for the environmental
components are documented in the previous chapter whereas the present
chapter discusses potential impacts during the construction /Operation phases.
The impact identification and prediction process aims to:
Identify potential source or cause of impact throughout the life of project
Assess the potential of changing likely‐hood of impact through
Environmental Management Plan (EMP).
Storm water: Storm water generation from the entire plot area is 0.22 m3/sec.
SWD are already developed in and around the project site.
Storm water Generation Calculation
2
1) Unpaved area (a) 415.15 m
Figure 4.2: Storm Water Drainage Plan
25
50
75
100
125
150
175
200
225
250
275
300
325
350
375
400
Distance from source (m)
Noise Levels
Use of proper personal protective equipment will mitigate any significant impact
of the noise generated by such equipment. Similarly, as the major work will be
carried out during the day time, the impact on the surrounding area due to the
activity will be negligible.
Functional Phase: The impact on noise during the operation phase of the
project will be due to vehicular traffic. The incremental noise level at project site
will be around 4 dB(A). The noise impact due to traffic on habitable floor is
negligible. Proper management of the entry & exit movement of the vehicle
would reduce the congestion of roads leading in and out of the proposed project.
Implementation of traffic management systems will help in lessening the noise
impacts. The DG Sets shall be as per the guide lines laid down by EPR for specific
noise emission standards. Measures shall be taken for reduction of noise by
using acoustic enclosures.
4.9 AESTHETICS
The project would have significant impact on aesthetics if it would cause any of
the following conditions to occur
Have a substantial adverse effect on a scenic vista;
Substantially damage scenic resources, including, but not limited to, trees,
rock outcroppings, and historic buildings within a state scenic highway
Substantially degrade the existing visual character or quality of the site
and its surroundings
The degree to which the project would contribute to the area's aesthetic
value;
The degree of contrast between proposed features and existing features
that represent the area's valued aesthetic image;
The change in ambient illumination levels as a result of project sources
Construction Phase: The aesthetics of the project area is likely to get disturbed
during the construction phase. However, barricading the construction site will
help in improving its visual aesthetic to the by passers. Also, this will not be a
permanent impact and will be confined to the construction phase only.
Functional Phase: The proposed land use of the site would be mainly
Residential & restaurant & Lodging Buildings and will not result in obstruction of
view, scenic amenity or landscape. However, the buildings will be planned in
such a way that the organised open areas and landscaped areas are at the centre
so that all can enjoy the green areas. Internal roads, footpaths/ pedestrian
pathways have been planned within the proposed project. The project has been
designed as per the development control of Town planning Authority. No
anthropological or archaeological sites or artefacts are found near the site area.
There will be around 415.15 m2 open space/RG in project project. The provision
of landscaped garden and green belt development in proposed project will
improve the aesthetics value.
Construction Phase: The traffic impact during construction phase will be due to
increased movement of trucks carrying debris. The parking of the construction
vehicles at the site premises on the road will cause congestion of traffic.
Adequate parking space should be made inside the construction premises to
lessen the impacts.
Functional Phase: In the operation phase there will be increase in the vehicular
movement because of the tourist and visitors.
The site is accessible by existing 13.0 m wide Alibaug‐ Murud State highway & 9.0
m wide access Road.
Proposed Actions
Sr. Environmental
Civil Transportation Machinery
No. Parameter Excavation
Works operation
Air Environment
SPM/RSPM C* C* C* D*
Sulphur dioxide ‐ ‐ D* D*
1.
Nitrogen oxides ‐ ‐ D* D*
Carbon
‐ ‐ D* D*
Monoxides
Water Environment
Ground water
‐ ‐ ‐ ‐
quality
2. Surface water
‐ ‐ ‐ ‐
Quality
Drainage
C ‐ ‐ ‐
system
Land Environment
3. Waste Disposal C ‐ ‐ ‐
Soil Erosion C ‐ ‐ ‐
Proposed Actions
Sr. Environmental
Civil Transportation Machinery
No. Parameter Excavation
Works operation
Noise
4. Ambient noise
C* D* D* C*
levels
Ecological Parameters
Flora ‐ ‐ ‐ ‐
5.
Fauna ‐ ‐ ‐ ‐
Aquatic ecology ‐ ‐ ‐ ‐
Socio Economic Parameters
Employment B* A* A* B*
6. Occupational
‐ ‐ ‐ D
Health
Infrastructure D ‐ D ‐
Table 4.5: Operation Phase Impact Matrix
CHAPTER 5
SPECIFIC STUDIES
Traffic Surveys are necessary to capture the existing pattern and volume of traffic
as a base line data.
Network Inventory Survey and Traffic Volume Surveys were conducted on the
Grampanchayat Road. The Grampanchayat Road is the main road in the study
area for commuting to project site. The traffic survey was conducted near project
site to ascertain the present traffic scenario to evaluate traffic impact that will
result from proposed development.
Figure 5.1: Project location
In the operation phase there will be increase in the vehicular movement because
of the tourists and visitors. The peak hour traffic count for road is as follows:
Table 5.1: Existing Traffic Volumes ‐ Year 2016
Sr. 2
Road Taxi Car LCV Bus Truck Total
No. Wheeler
Alibaug – Murud
1 52 0 12 6 0 3 73
State Highway
Total Capacity General
Sr. V/C
Road PCU of Roads LOS Operating
No. ratio
(V) (C) Conditions
Alibaug – Murud Reasonably
73 900 0.08 A
1 State Highway flow
Rapid EIA, Construction of Hotel Resort at Borli, Tal ‐ Murud, Dist ‐ Raigad
The traffic impact during construction phase will be due to increased movement
of haul trucks carrying excavated soil, debris and construction materials. These
movements of trucks will be very less in numbers as compared to the present
traffic. The parking of the construction vehicles outside the site premises on the
road will cause congestion of traffic. Adequate parking space has been made
inside the construction premises to lessen the impacts.
5.2.2 Functional Phase
In the operation phase there will be increase in the vehicular movement because
of the tourist and visitors.
A traffic survey was carried out during the EIA study period. The details of traffic
movement on the Grampanchayat Road monitored for a period of 12 hrs is given
in the Table 5.2.
The observed traffic data was analysed using the guidelines of Indian Road
Congress (IRC). The IRC has stipulated the standards of number of passenger car
units (PCU) per lane per hour for different roads i.e., divided and undivided and
city roads and Highways. The IRC norms for of PCU’s of different type of vehicles
and type of road are as under:
Table 5.2: Recommended PCU Factors for Various Types of Vehicles on
Urban Roads
After After
Sr.
Road Present LOS 5 LOS 10 LOS
No.
Years Years
CHAPTER 6
ENVIRONMENTAL MONITORING PROGRAMME
6.1 ENVIRONMENTAL MONITORING PROGRAMME
An environmental monitoring programme is required to provide scientifically
defensible information for determining the status of the environmental quality of
the surrounding area of the project site and to check whether the levels of critical
pollutants are within the environmentally acceptable limits. This will help to
obtain an early warning of unacceptable environmental conditions so that control
measures can be taken immediately.
Weekly Checklist
Environmental Aspect Yes / No Comments
Construction camp is neat
and tidy and the labourers
facilities are of an acceptable
standard.
Waste collection and removal
system is being maintained.
Sufficient fire‐fighting
equipment is available at
construction site and is in
good working order.
All construction vehicles are
in good working order and
have valid PUC certificates.
Dust control measures
(wherever necessary) are in
place and are effectively
controlling dust.
Noise‐control measures
(wherever necessary) are in
place and are working
effectively.
Erosion control measures
(wherever necessary) are in
place and are effective in
controlling erosion.
From the monitoring point of view, the important parameters are ground and
surface water quality, aquatic flora and fauna, noise, etc. An attempt is made to
establish early warning system which indicate the stress on the environment.
Suggested monitoring parameters and programs are described in the subsequent
sections.
The ground water quality needs to be monitored at 1 location. The surface water
quality needs to be monitored at 1 location in the study area. The frequency of
monitoring should be once in three months. The parameters to be monitored are
listed as below:
Sr. No. Parameters Sr. No. Parameters
1 pH 13 Phosphates
2 Electrical conductivity 14 Fluorides
3 Turbidity 15 Chlorides
4 TDS 16 Sulphates
5 TSS 17 Sodium
6 Total Hardness 18 Potassium
7 Alkalinity 19 Calcium
8 Carbonate 20 Magnesium
9 BOD 21 Oil & Grease
10 COD 22 Iron (as Fe)
11 DO 23 Manganese
12 Nitrates 24 Copper
25 Total Coliform
Any other frequency prescribed by the MPCB/ MOEF for monitoring shall be
followed.
Ambient air quality monitoring will have to be conducted at 3 locations within the
study area. The parameters to be monitored are PM10, PM2.5, SO2, Nox & CO. The
post‐project ambient air quality monitoring work will be carried out from MoEF
6.7 NOISE
Rate of Survival
Greenbelt Project Site and
6. and Growth of Once in a month
development Surroundings
Various species
CHAPTER 7
RISK ASSESSMENT & DMP
Risk assessment study deals with identifying and evaluating the magnitude of
impending risks to the population is exposed due to occurrence of accidents from
project construction and development. This assists in illustrating the guidelines
for preparation of disaster management plan which will be executed to handle the
situation if any emergency. Following are the risks that are identified in buildings.
The incidence of fire or other disasters occurring in buildings often endangers the
safety of the persons working in the structure, in the event of an emergency.
The only way of reducing the damage to public life and property is by conducting
fire safety drills and installing well equipped fire safety equipment’s such as
smoke detectors, heat sensors, sprinklers, fire extinguisher, water jet, hooters &
fire detection system.
The plan should be reviewed at periodic intervals. The plan should be also
reviewed and updated when:
Major alteration or extension of existing structure is carried out.
Major change in habitation or land use of the neighbourhoods takes place.
Important telephone numbers used are altered or changed.
Mock drills activities should be conducted periodically for ensuring its efficiency
during emergency as well as for refinement and up gradation. These drills based
on the plan will help achieve its objectives of the disaster management plan.
Table 7.1: Building Emergency Plan
Building Information
Emergency Assembly Area Location
Emergency Management Area Number
Emergency Staff
Potential Fire Hazards
Fire Prevention Procedures
Medical and Rescue Duties for Employees
IMPORTANT PHONE NUMBERS
Telephone Numbers for Life‐Threatening
Emergencies
Where to Get Information During a Large‐
Scale Emergency
What to Do When You Hear Building
Warning Sirens / Signs
Telephone Numbers for Non‐Life
Threatening Emergencies
EMERGENCY PROCEDURES
Emergency Notification Procedures
Evacuation Procedures
Fire Procedures
Earthquake Procedures
Explosion or Bomb Threat Procedures
Utility Failure
Elevator Failure
Flooding, Plumbing or Steam Line Failure
Natural Gas Release or Leak
Ventilation Problem
EMERGENCY PREPAREDNESS
Supplies
Securing Building Contents
7.6.3 Earthquake Procedures:
During an earthquake:
Inside the Building:
Duck under the nearest sturdy object and hold onto it until the shaking
stops. If you are not near a sturdy object, make yourself as small as
possible and cover your head and neck.
If you stand in a doorway, brace yourself against the frame and watch out
for a swinging door or other obstruction.
Avoid windows, filing cabinets, bookcases, and other heavy objects that
could fall or shatter.
If safe, before evacuating, neutralize / turn off any flammable source
(cooking gas, electricity etc.) that could lead to further danger.
Outside the Building:
Move away from trees, signs, buildings, electrical poles and wires, fires,
and smoke.
Protect your head with your arms from falling debris.
7.6.4 Flooding, Plumbing or related Failure:
If your building has a plumbing failure, a flood, or related failure:
Cease using electrical equipment.
Call XXX Plumbing service. For water removal call XXXX Service.
7.6.5 Gas Release or Leak (PNG, LPG etc): If you smell natural gas:
Cease all operations immediately.
Do not operate light switches.
Evacuate as soon as possible.
Call the service providers emergency numbers
Call Facilities Services or society Manager for leased space.
CHAPTER 8
PROJECT BENEFITS
8.1 PHYSICAL INFRASTRUCTURE
The proposed project is the part of Rural infrastructure development (Town
planning) and its associated activities will help to build physical infrastructure
like accomodation, roads, telephones line, electric substations, and water supply
lines in study area. The benefits of the proposed project are as follows:
1‐ The project will create an additional stock for tourist people for their
accommodation
2‐ Adequate parking facilities to the tourist
3‐ Good sanitation facilities
4‐ The expected outcome of the proposed project will be the good quality of
livelihood to people
5‐ Water recycling and rain water harvesting
6‐ Solar hot water to tourist, solar lighting within compound wall
7‐ The establishment of a vegetation covering land in and around the
proposed project will result in many direct and indirect benefits
8.2 EMPLOYMENT
Proposed project would employ personnel during construction phase that will
help in improving the existing socio‐economic status
The significant positive impact on employment and occupation is envisaged on
account of
Better economic status of the community due to better earnings
Employment of local people in activities like housekeeping, security,
office/hotel staff etc. – 10‐15 people employed.
CHAPTER 9
ENVIRONMENTAL MANAGEMENT PLAN
9.1 INTRODUCTION
Identification and prediction of impacts further needs to suggest the mitigation
measures which play a vital role in prevention of environmental pollution during
construction and implementation phase of proposed project. This leads to
preparation of environmental management plan. Environmental management
plan therefore forms an imperative part of Rapid EIA process.
The Environmental Management Plan (EMP) is a site specific plan developed to
ensure that the project is implemented in an environmental sustainable manner
where all contractors and subcontractors to understand the potential
environmental risks arising from the proposed project and take appropriate
actions. EMP also ensures that the project implementation is carried out in
accordance with the design and by taking appropriate mitigative actions to reduce
adverse environmental impacts during its life cycle.
The potential environmental impacts, which need to regulate are mentioned
below:
Air pollution due to the emission of Particulate Matter and gaseous pollutants;
Noise pollution due to various noise generating equipment as well as vehicular
movement;
Wastewater generation from sanitary/domestic activities; and Solid waste
disposal.
The major sources of air pollution during the construction period will be from the
movement of vehicles for construction activity, the emissions are from the
stationary sources like generator sets during emergency service only, and
excavation for foundation. Dust suppression by spraying of water will reduce
these impacts considerably.
To mitigate the impact of SPM/dust during the construction phase of the
proposed project, the following measures are recommended:
A Fugitive dust control.
Procedural changes to construction activities.
‐ Fugitive Dust Control
Source wise Fugitive dust control measures are tabulated below:
Drip irrigation system shall be used for the lawns and other green area.
Drip irrigation can save between 15‐40% of the water use, compared with
other watering techniques.
Plants with similar water requirements shall be grouped on common zones
to match precipitation heads and emitters.
Use of low‐volume, low‐angle sprinklers for lawn areas.
Select controllers with adjustable watering schedules and moisture
sensors to account for seasonal variations, and calibrate them during
commissioning.
Selecting a drought resistant grass, and using lawn chemicals and fertilizer
sparingly also reduces watering needs.
Place 3 to 5 in. of mulch on planting beds to minimize evaporation.
Promoting reuse of water after treatment & development of closed loop
systems:
To promote reuse and development of closed loop system for water, segregation
of two schemes namely (i) Sewage treatment scheme (ii) Roof top rain Water
harvesting has been proposed.
Harvested roof top water will be utilised for floor washing, car washing,
gardening, and other domestic purposes and treated Sewage shall be recycled for
flushing and gardening
It is estimated that reusing wastewater will save approximately 35 to 40% of
potable water per day.
As discussed earlier, most of the storm water produced on site will be harvested
for ground water recharge, thus proper management of this resource is must to
ensure that it is free of contamination. The details of Storm water management
proposed is given in chapter 2.
Contamination of storm water is possible from the following sources:
Diesel and oil spills in the Diesel Power Generator & fuel storage area.
Waste spills in the solid waste storage area.
Storm Water Management Plan will be developed which will consider the above
sources and will incorporate following best management practices:
Regular inspection and cleaning of storm drains.
Cover waste storage areas.
Avoid application of pesticides and herbicides before wet season.
Secondary containment and dykes in fuel/oil storage facilities.
Conducting routine inspections to ensure cleanliness.
Preparation of spill response plans, particularly for fuel and oil storage
areas.
Good housekeeping in the above areas.
Construction Debris:
Construction debris is bulky and heavy and re‐utilization and recycling
is an important strategy for management of such waste. As concrete
and masonry constitute the majority of waste generated, recycling of
this waste by conversion to aggregate can offer benefits of reduced
landfill space and reduced extraction of raw material for new
construction activity. This is applicable to proposed site since the
construction is to be completed in a phased manner.
Recycled aggregate will be used for filler application, and as a sub‐base
for road construction. Mixed debris with high gypsum, plaster, shall not
The philosophy of solid waste management will be to encourage the four R’s of
waste i.e. waste reduction, reuse, recycling, and recovery (materials & energy).
This will result in lesser reliance on land filling.
The Environmental Management Plan for the solid waste focuses on three major
components of the waste management system i.e. collection & transportation,
treatment or disposal and closure & post closure care of treatment/disposal
facility.
9.7 AESTHETICS
Also the impacts on aesthetic environment are short term and restricted only in
the initial stages of project construction. Further in the operation phase it will be
compensated by tree plantation and gardens.
Architectural Design:
Maximize the use of natural lighting through design.
Energy conservation aspects such as selection of appropriate building
material having adequate thermal resistance value (R value) and solar water
heating systems. A solar hot water will be provided to population. Solar
lights will be provided for street lighting and garden lighting.
Energy Saving Practices:
Purchase of energy efficient appliances.
Adjusting the settings and illumination levels to ensure minimum energy
used for desired comfort levels.
Use of LED’s in common areas
Behavioural change on consumption:
Training staff on methods of energy conservation and to be vigilant to such
opportunities.
Over and above the energy conservation measures proposed and % saving of
energy is given in chapter 5
Treated domestic sewage and grey water after treatment will be used for
gardening and flushing purpose thus, serving the purpose of water
conservation.
A well planned rain water harvesting unit is proposed which will help in
recharging the underground water table.
The details of Solid waste generation and its management is given in Chapter 2.
The resources required for implementing the EMP and its corresponding budget
is given below
During Operation Phase
Operational Potential Implementing
Mitigation Measures
Activities Impacts Responsibility
• The use only low flow and low • Project Proponent
flush – water saving plumbing • Society Chair Person &
fixtures, automatic level controllers Appointed AMC
Impact due to
at water tanks to reduce/optimize
Water
the demand side of water
Consumption Fresh water
resource.
& consumption
• Treated waste water from STP will
Wastewater
be used for green belt & flushing.
Generation
This will reduce the demand for
fresh water.
Potential
Mitigation Measures Accountability
Impacts
• Tree plantation is proposed along the periphery of the site ensuring adequate buffer and reducing heat
Energy gain by the building so that the buildings will remain naturally
Project Proponent
Consumption for • The project design will use high energy performing building materials which would have low U value
Society Chair Person &
Thermal Comfort (Thermal Conductance) as compared to the conventional materials. The external wall of building would
Appointed AMC
of Residents use fly ash blocks, which will have mandatory SHGC as required by ECBC.
• The units in the project are extensively naturally ventilated
• Internal and external lighting design will be provided as required by ECBC which will have Lighting Power
Energy Density as per space requirements.
Society Chair Person &
Consumption for • The project would provide 20% lower LPD than as specified in ECBC, to achieve energy saving, while
Appointed AMC
Lighting providing the require illumination levels, by using high efficacy lighting.
• Solar street lights will be provided
• The Transformer or the Sub Station for the project shall be adequately protected from entry, allowing only
authorized personnel to enter the facility Society Chair Person &
Safety hazards
• All required energy protection measures such as high voltage cut-off, shock protector etc. shall be Appointed AMC
installed.
• Future residents and Cleaning AMC shall be encouraged to: do the following. A Manual will be created by
the PP to make residents aware of these measures to be undertaken:
• Choose non-toxic, biodegradable substitutes for household cleaning agents.
• Avoid products with potentially harmful ingredients such as sponges with antibacterial ingredients.
• Conserve water, sweep instead of wet mop when possible.
Impacts due to • Use biodegradable drain clog removers made with natural enzymes.
Society Chair Person &
Cleaning & • Don't pour hazardous chemicals through the sink or the drain; Don't use chlorine based bleach for
Appointed AMC
repairing activities cleaning
The regular monitoring & repairing of the equipment's such as STP, SWM, DG sets etc to avoid the
sudden failure.
• Cleaning of building premises, parking areas, common areas shall be done on a regular basis., taking
care to see that no solid waste is carried to the storm water drains.
• Green Guideline Brochure will be circulated to future residents & AMC workers.
Capital
O & M Cost
Cost
Component (Rs. In Frequency
(Rs. In
Lakhs/year)
Lakhs)
Continuous O & M
Environment Monitoring:
STP (Tertiary) 2.00 0.2 Monthly, STP outlet water
quality for pH, BOD, COD,
SS and O&G
Continuous O & M
Solid Waste 0.15 0.1 Environment Monitoring:
Management Monthly to assess the
compost quality
Landscape and 3.00 0.2
tree plantation Twice a Week
11.15 3.1
Total Cost
CHAPTER 10
EXECUTIVE SUMMARY
INTRODUCTION
4. Hotel staff ‐ 20
TOTAL 92
The project comes under the purview of CRZ notification 2011. The land
falling between 500 m from HTL on the landward side. The proposed
project falls under the CRZ III area as per the CRZ notification 2011.
PROJECT LOCATION
The proposed Hotel Resort is planned at plot bearing S. No. 47/1, 47/2, 49
& 43 of village – Borli, Tal – Murud, Dist – Raigad, State – Maharashtra. Its
Google location is 18030’47.57 N latitude and 72054’50.48 E longitude. The
site is accessible by existing 13.0 m wide Alibaug‐ Murud State highway &
9.0 m wide access Road.
2
4 Non FSI Area 300.00 m
Total Construction 2
5 1,302.22 m
Area
12 standard rooms, 7
6 No. of tenements cottages, Restaurant, Nos.
Administrative building
Total water
7 15 KLD
requirement
Sewage generation:9 KLD
Sewage and STP
8 STP Capacity: 10 KLD
details
STP Technology: Phytorid ‐
Total Solid Waste
9 18 kg/d
Generation
Biodegradable
10 component (Vermi 11 kg/d
Composting)
Total Power Connected Load: 0.12 MW
11
Requirement Demand Load: 0.08 MW
12 DG Set 20 kVA
13 Energy Efficiency Total Energy Savings :23.25 %
4‐W provided : 20 Nos.
14 Parking Provision
2‐W provided:12 Nos .
15 RWH Capacity 10 KLD
SWD Generation
3
16 (300 mm wide 458.7 m /hr
channel)
Capital cost : 11.15 Rs. Lakhs
17 EMP Cost
O & M Cost: 3.1 Rs. Lakhs/yr
Water Supply
Power Supply
The power supply (Max Demand Load) necessary for the proposed buildings are
estimated as 0.08 MW (Functional phase). The power will be made available from
the MSEB. The network of power supply in this region is well established. DG set
will be provided in the case of emergency of capacity 20 kVA.
Socio‐economic Environment
In construction phase it will create work opportunity for the local population. No
negative impact is envisaged. Overall positive impact in the functional phase, as
the project will create long term employment in activities such as maintenance of
buildings and ancillary services.
Environment Management Plan
Measures which will be adopted to reduce the magnitude of negative impacts
from the proposed project during construction and functional phase are discussed
below in the Environment Management Plan.
Environmental Management Plan during Construction Phase
Sr. Environmental
Mitigation Measures
No. Components
1. Ambient Air To avoid dust, regular sprinkling of water on road.
Quality Covering jute sheet over the haul trucks sprinkling
through water Tanker.
Barricading to Plot
Periodic maintenance of construction equipment.
Barricading along the plot boundary.
Use of Personal Protective Equipment
Ensure that all vehicles and machinery are fitted
with appropriate emission control equipment,
maintained frequently
DG: as per CPCB norms, proper maintenance, LSD
fuel use, safe storage of fuel.
2. Noise Equipment’s will be regularly serviced. Heavy
constructions activity limited to day‐time hours
only
PPE to workers Silencers will be fitted on
construction equipment and DG sets
3 Water Avoid excavation during monsoon season, Care
shall be taken to avoid soil erosion
Sedimentation pits along the plot boundary to
avoid the excessive soil runoff
Supply of Adequate drinking water
Tyre Cleaning
Ground water‐hydraulic containment and
Treatment
Sr. Environmental
Mitigation Measures
No. Components
4. Land To minimize disruption of soil and for
conservation of topsoil, topsoil will be kept aside
and after the construction activity is over, topsoil
shall be utilized for landscaping activity
Reutilization of construction debris at site only
CHAPTER 11
CREDENTIALS OF CONSULTANTS
NAME OF THE CONSULTANTS
Mahabal Enviro Engineer Pvt. Ltd.
Plot No F‐7, Road No‐21,
Wagle Estate, Thane West‐400 604,
Maharashtra.
Telephone No: 90‐22‐2582 3154/3139/0658
Fax: 91‐22‐2582 3543
Email: thane@mahabal.com, dap_24@hotmail.com
Web site: www.mahabalenviro.com
Mahabal Enviro Engineers Pvt. Ltd. (MEEPL) incorporated on 19th Oct., 1984 is a
company engaged in providing environmental consultancy services. It has a
laboratory established under the Environment (Protection) Act and is located at
its Head Office at F‐7, Road No. 21, Wagle Estate, Thane‐ 400604. Although the
jurisdiction of the Head Office extends all over the country, it is assisted by the
branches located at Nashik, Pune, Delhi, Aurangabad, Jalgaon and Nagpur (all in
Maharashtra), Chhindwara in Madhya Pradesh, and Bharuch in Gujarat. The
Branches do also have laboratories established either in the office or at the
client’s site for analysis of general parameters in Air, Water and Waste Water
samples.
Mahabal Enviro Engineers Pvt. Ltd. is an ISO 9001‐2000 Certified Company and
laboratory is accredited by:
Ministry of Environment and Forest (MoEF), Govt. of India, New Delhi.
NABL
IMS 18001
The firm has been engaged in the jobs of preparation of Environmental Impact
Assessment (EIA) & Environmental Management Plan (EMP) for more than 15
years for the purpose of obtaining clearance from Ministry of Environment &
Forest.
The firm has major experience in operation and maintenance of STP in Pune,
Nagur, Nashik and Shimla.
Some of the other Services Offered by firm are given below.
Environmental Clearance From MoEF and SEIAA
CRZ Clearances from MoEF
Environmental Quality Monitoring
Noise Mapping and Design of Noise Barriers
Stack & Work place Monitoring
Environmental Due Diligence study
Plant Ventilation Study
Consent to Operate/Establish/Renewal
1 Dr. D. A. Patil
Associated Functional
Area Expert
12 Swati Sawant WP, SHW (B)