Revision History
10-Jan-2018 O1
24-May-2018 O2
25-July-2018 O3
10-Oct-2018 A1
Related Documents
Holds
Term Comment
TABLE OF CONTENTS
1.0. PURPOSE
This Document Control Procedure provides systematic methods and routines for establishing and
implementing comprehensive Document Control system across the Duqm Refinery Project including efficient
identification, tracking, filing, storage, retrieval of technical documentation and EDMS PETROCEPTDC
Systems.
2.0. SCOPE
This procedure applies to CONTRACTOR’s Document Control functions, covering all phases of the Duqm
Refinery Project, up to and including handover of Project document records and deliverables to COMPANY.
DC Document Control
TQ Technical Query
4.0. REFERENCES
Ensures availability of positions in the staffing plan to enable the allocation of project control resources to
carryout out Project Control functions effectively for Duqm Refinery Project.
Assigns resources as required by Project Staffing Plan to carry out the Project Control Functions effectively
for Duqm Refinery project.
Supports the Project in Setting up in-house Software (EDMS PETROCEPTDC, PPCS, PCS, etc…) at the start
of the Project and provides assistance for smooth operation of these Software.
Discipline Lead Engineer is responsible for submission of document / drawing to the JV-DCC for submission
to COMPANY.
Periodic verification of the Document Control functions at all locations to ensure compliance to the
systems and procedures.
Site document controllers will be responsible for preparing transmittals and issue Construction documents
generated from CONTRACTOR’s Site Office to COMPANY.
6.1. GENERAL
Documents will be controlled and managed using CONTRACTOR’s in-house software EDMS
PETROCEPTDC.
Discipline Leads will prepare a list of all Engineering Deliverables for the Project utilizing CONTRACTOR’s
in-house software EDMS PETROCEPTDC. This will form the basis of the Technical Document Register
(TDR) which will be issued to COMPANY for review and approval. The common TDR will be referenced
across all the Engineering Centres and it will indicate documents which will be issued for COMPANY
Approval, Review or Information as per Document Class.
EDMS PETROCEPTDC will be used for Detailed Engineering Progress Measurement and formal Document
issue control through transmittals.
JV-DCC will maintain an updated record of the CONTRACTOR’s documents; COMPANY supplied
documents and Supplier documents, showing their latest revisions.
EDMS PETROCEPTDC is an Electronic Document Control and Management system. This application will
function as the ‘Register and Storage’ hub and will be available to CONTRACTOR’s Engineering Centres
and Site personnel working on the Project. EDMS PETROCEPTDC will be used to update the TDR, VDR,
IDC, TQ, DCN & IDIT and Generate Transmittals, Correspondence Registers for formal issue and for
Engineering Progress Measurement.
Documents generated from Engineering Centres and site will be loaded in the EDMS PETROCEPTDC.
After uploading the documents, an email notification will be sent by the Document Controller according to the
Document Distribution Matrix (DDM).
Historical information of all Technical and Vendor Documents Revisions is maintained in the system.
The review class for each document will be indicated in the Technical Document Register (TDR) and
also the Document / Drawing and is as follows:
COMPANY shall acknowledge the receipt of all submissions on the same day after checking the transmittals,
and the above review cycle days for all classes shall be counted from the date of receipt by COMPANY.
The below list shows general groups or types of documents to be reviewed by COMPANY together with
their classification as Class 1, 2, 3 or 4.
Electrical:
Single line diagrams, electrical schematics, equipment
layouts and 2
general arrangements
Criticality Rating 3 and 4 Equipment and Systems
Vendor drawings/documentation, as for Criticality Rating 1
and 2 equipment and systems , Criticality Rating 3 and 4
equipment 2
General
Vendor Piping Data Sheets 3
Piping Speciality Item Drawings and Documents 3
Vendor Performance Test procedures 2
Inspection and test reports for all equipment and materials 3
Expediting reports for Criticality Rating ‘1 and 2' items and
3
for any item slipping to within 4 weeks of critical.
Vendor Noise Data 3
EPC Contractor’s recommendations for commissioning
3
spare parts
Spare Part Forms for initial operating spare parts 2
Vendor Document Indices 4
Vendor Data Books 4
Manufacturing Data Report (MDR) for Tagged Equipment 3
Other Vendor drawings and documentation (if requested) 3
First issue as well as all subsequent revisions of all the technical drawings / documents generated by any of
the CONTRACTOR Engineering Centres, Vendors and Site will be stored either on EDMS PETROCEPTDC
or on the Project server located at CONTRACTOR’s Offices.
Originator will deliver original signed hard copy as well as PDF file to JV-DCC. The signed page will be
scanned where the first page will be replaced by the scanned front signed page by JV-DCC.
The original signed hard copy will be retained by the Document Controller for records and the PDF copy
will reside in project server and EDMS PETROCEPTDC.
Document controller will check the revision number of the document and update the EDMS
PETROCEPTDC.
Submission of all documents and drawings to / from COMPANY will be through the EDMS
PETROCEPTDC. JV-DCC shall upload the documents into Contractor’s EDMS PETROCEPTDC and
notify through official email notification to Company DC.
Company DC shall download from Contractor’s EDMS PETROCEPTDC and upload into Company’s EDMS
PETROCEPTDC and distribute internally. Upon receipt of Company comments and approval from the
Company’s reviewing party, Company DC shall upload in Company’s EDMS PETROCEPTDC and
Contractor’s EDMS PETROCEPTDC followed by generation of transmittal and official email notifications to
Contractor’s JV-DCC.
JV-DCC shall notify Company’s comments upload in Contractor’s EDMS PETROCEPTDC through email
to Contractor’s Engineering Team.
Documents generated in any Engineering Support Centre will be internally transmitted to Sharjah JV-DCC
through the document controller located in the Engineering Support Centre.
Sharjah JV-DCC will distribute the documents to Sharjah Engineering team which in turn will review the
documents and either provide comments so the commented documents are issued back to the Engineering
Support Centres for modification or get approval from the Engineering manager and send the documents
to Sharjah JV-DCC for onward submission to COMPANY.
CONTRACTOR Site Office will have access to EDMS PETROCEPTDC. JV-DCC will mark a copy of the
transmittal of all Approved for Construction documents issued to or received from COMPANY to SJV-DCC
as per the agreed (DDM). SJV-DCC will distribute the documents to concerned engineers at Site Office.
Documents generated at Site office as well as the Site Sub-Contractors will be transmitted directly to
COMPANY (Wherever applicable) using EDMS PETROCEPTDC with appropriate communication to
Sharjah Engineering Centre.
Site Sub-Contractor will issue all their documents / drawings to Site Office for review and approval.
SJV-DCC will check the documents to ensure compliance to the project requirements and update the
incoming reference in EDMS PETROCEPTDC. Documents that require IDC, shall be issued for IDC.
Documents for COMPANY submission, SJV-DCC will prepare a transmittal to COMPANY.
Site Technical Queries (STQs) will be managed by SJV-DCC. Site representative is authorized to sign the
STQs and SJV-DCC will issue the STQs to COMPANY through Email. SJV-DCC will mark a copy of all
STQs issued to COMPANY to Sharjah Design office JV-DCC.
CONTRACTOR will submit electronic (searchable PDF format) copies of all documents / drawings including
supplier documents required for review and approval to COMPANY through transmittals.
COMPANY shall acknowledge all submissions on the same day after checking the transmittals.
Upon completion of review, COMPANY comments will be returned with transmittal and formal email
notification. Document Controller will download the documents / transmittals, update the EDMS
PETROCEPTDC database, and send email notification to relevant CONTRACTOR groups as per the
Document Distribution Matrix (DDM).
The Comments Resolution Sheet (CRS) will be issued together with the next formal issue of the document.
COMPANY review cycle time is 14 Calendar days for Class 1 & 2 documents. If COMPANY comments were
not received within 14 calendar days for Class 1, CONTRACTOR shall remind COMPANY to expedite the
comments on the documents.
If Class 2 documents are not returned either with comments or approval within 14 Calendar days by
COMPANY, CONTRACTOR will inform COMPANY in writing of its intention to proceed on the assumption
that COMPANY has no comments. CONTRACTOR will proceed to the next stage unless COMPANY
instructs in writing to wait for COMPANY comments.
Upon completion of review, COMPANY shall issue the comments on documents in PDF, if any, to
CONTRACTOR by Transmittal with appropriate return codes as follows:
Code Definition
A Accepted: CONTRACTOR can proceed to the next stage. Applicable for class 1 & 2
documents.
B Accepted With Comments: CONTRACTOR can proceed to the next stage, incorporating
the comments. In case comments are challenged, then cannot proceed. Applicable for
class 1 & 2 documents.
E Rejected: CONTRACTOR shall not proceed to the next stage. Applicable for class 1 & 2
documents.
Documents which need review / comments from Licensor or EPC1 Contractor, will be issued to these
parties through email to get their feedback and comments, and these comments will be reviewed and
incorporated (as applicable) before submission for COMPANY review.
All project technical documents and drawings will be numbered in accordance with the Document Numbering
Procedure No. (DRP001-OUF-PRO-U-000-001). Project document and drawing numbers will not be
duplicated under any circumstances.
All project documents are to include a revision code and revision status in the appropriate space on the title
sheet as per the below table:
All documents (not drawings) that are revised at all revisions shall show changes and additional text
highlighted in yellow and deletions shall be retained with strikethrough. The front page shall not include any
yellow marking and/or text added to explain what yellow marking means.
Drawing revisions issued for COMPANY review or approval will be annotated with revision clouds. In addition,
revision clouds will be used to identify any changes made to P&IDs subsequent to those used in the
Preliminary HAZOP reviews.
For the changes made to the document but under same revision, the numeric sequence number shall be
used to differentiate the document revisions (e.g. A1, A2, A3…etc.)
Advance Revision Notice (ARN) will be released by relevant discipline to SJV-DCC for onward
submission. SJV-DCC shall receive the ARN and obtain signature from Field Coordinator, update in
EDMS PETROCEPTDC for issue to the Site Construction Subcontractors.
Prior to submission to COMPANY for comments or approval, each drawing will be signed off with the initials
of the author or originator, checking person and authorizing person into the appropriate boxes of the drawing
file submitted. Originating, Checking and Authorizing shall be by different individuals.
This method for handling of project Technical Queries (TQ’s) raised by CONTRACTOR to COMPANY has
been defined for the following:
Technical Queries (TQ’s) can be generated from various sources within the Project. All TQ’s for the
project, however, are to be handled in a similar manner irrespective of their source (i.e. at site, at
CONTRACTOR’s offices or project management). This enables tracking of all outstanding TQ’s through
a centralized system / register.
The TQ register for the TQs generated from Sharjah Engineering Centre or Site Office will be managed
through EDMS PETROCEPTDC. The JV-DCC and SJV-DCC will be respectively responsible for
allocating all TQ numerations.
The concerned Discipline Engineer will prepare the TQ with the appropriate relevant details and issue to
the Engineering Manager for Engineering Technical Queries or to the Project Director for non-
Engineering Technical Queries for review and approval. Document controller will assign a Technical
Query number and issue the Technical Query to COMPANY for Approval with Scanned (Acrobat PDF)
and Native File (Microsoft Word).
CONTRACTOR will raise the Technical Queries, which shall be numbered from 0001 for each initiating
party, irrespective of discipline in the following manner:
DRP001-OUF-TQ-A-XXX-NNN
DRP001 – Duqm Refinery Project Number Project Code
OUF – Originator Code for CONTRACTOR
TQ - Technical Query
A - Discipline Code (As per the below table)
XXX – Unit Code (Appendix 3)
NNN – 3 digits number which shall be in sequence for all TQs starting from 0001 and generated by
DCC
The first issue of TQ will be Rev O1. Subsequent revisions will be issued at Rev O2, O3. Closed TQ will
be issued to COMPANY in same revision.
Code Discipline
A Technical Information Management
B HVAC
C Civil/Structural/Architectural
D Telecoms
E Electrical
F Fluid Systems
G Project Control & ITC
H Furnaces
I Estimating
J Process Control
K Instrumentation/Controls
L Subcontractors / Construction
M Mechanical
N Procurement
P Plan Design & Piping
Q Quality
R Rotating Equipment
S Marine
T Process
U Project
V Vessel & Tanks
W Materials ( Technology)
X Heat Exchangers
Y Pipelines
Z Safety
7.5.2. Concession Request
Permission to use or release VENDOR / SUPPLIER product that does not conform to specified
requirements.
6.9.2.2. Concession request generation
Concession Requests (CRs) can be generated from various VENDORS / SUPPLIERS within the Project.
All CRs for the project, however, are to be handled in a similar manner irrespective of their source. This
enables tracking of all outstanding CRs through a centralized system / register.
The CR register for all the CRs in the project will be managed through EDMS PETROCEPTDC. The JV-
DCC and SJV-DCC will be respectively responsible for allocating all CR numerations.
Permission to depart from originally specified requirements of a VENDOR / SUPPLIER product prior to
realization.
Deviation Requests (DRs) can be generated from various VENDORS / SUPPLIERS within the Project.
All DRs for the project, however, are to be handled in a similar manner irrespective of their source. This
enables tracking of all outstanding DRs through a centralized system / register.
The DR register for all the DRs in the project will be managed through EDMS PETROCEPTDC. The JV-
DCC and SJV-DCC will be respectively responsible for allocating all DR numerations.
When a document is cancelled, the document will be issued with revision “XX”.
Document withdrawal information will be maintained in register with agreement between either party
(COMPANY / Vendor / Sub-contractor).
Project management documents such as Project procedures will be prepared by the respective departments
such as Projects, Procurement, Planning, Contracts, Quality, and HSSE etc. and then will be issued to
COMPANY for review and approval. The cycle of Technical documents / deliverables will be followed until
the final issue of each document and will be monitored in EDMS PETROCEPTDC. The status of these
documents will be shown in the Technical Document Register (TDR).
Documents and drawings provided by Subcontractors will be issued to CONTRACTOR in both PDF
searchable format and the native format. The PDF format of the drawings will be in the same size of the
native drawing size. The Subcontractor will upload the files onto a FTP server and inform CONTRACTOR by
e-mail. CONTRACTOR will review Subcontractor documents and send the comments back to the
Subcontractor for incorporation and re-submission.
The Subcontractor will list all the documents to be generated by Subcontractor once agreed by
CONTRACTOR, the information will be loaded into EDMS PETROCEPTDC, which is used to record receipt
of documents and to report document status.
Letters
Documents generated from Sub-Contractors will be transmitted directly to COMPANY (Where applicable)
using EDMS with appropriate communication to Sharjah Engineering Centre.
CONTRACTOR’s Site DCC will check the documents to ensure compliance to the project requirements and
update the incoming reference in EDMS PETROCEPTDC. Documents that require IDC, shall be issued for
IDC. Documents for COMPANY submission, CONTRACTOR’s Site DCC will prepare a transmittal to
COMPANY.
The below return codes will be used when CONTRACTOR returns the documents to Subcontractor:
Code Definition
Rejected: Revise and resubmit.
1
Comments as noted: Revise and resubmit. Work may proceed subject to incorporation
2
of comments.
Acceptable: Incorporate comments, if any. Resubmit as Certified Final. Work may
3
proceed
No Comments: Acceptable. Certified Final issue. Do not resubmit. Work may proceed.
4
Information Only: Accepted for information only. Work may proceed. Do not resubmit.
5
Documents and drawings provided by Vendors will be issued to CONTRACTOR in both PDF searchable
format and the native format. The PDF format of the drawings will be in the same size of the native drawing
size. The vendor will upload the files onto a share point server and inform CONTRACTOR by e-mail.
CONTRACTOR will review Vendor documents and send the comments back to the Vendor for incorporation
and re-submission. Critical Vendor Documents / Drawings will be issued to COMPANY if required.
Vendor Documents Requirement List (VDRL) will be included in the Purchase Order / Purchase Requisition
issued to Vendors.
The VDRL will list all documents to be generated by Vendor. Once agreed by CONTRACTOR, the information
will be loaded into EDMS PETROCEPTDC, which is used to record receipt of documents and to report
document status.
Document Controller will record the receipt of Vendor document within the EDMS PETROCEPTDC and
forward the same as per the Vendor document distribution matrix. The concerned Engineer will co-ordinate
an IDC process and collates all information from disciplines and COMPANY (if required) and returns to SHJ-
DC for issue to Vendor.
Originating discipline will compile all the comments on the Vendor documents and return the same to Vendor
via the CONTRACTOR’s Document Controller with appropriate approval/review code.
Revised documents received from Vendors will be recorded in EDMS PETROCEPTDC and distributed by
the Document Controller to all recipients of previous revisions.
The below return codes will be used when CONTRACTOR returns the documents to Vendor:
Code Definition
The documents will be issued through sequentially numbered Document Transmittal to COMPANY, Sub-
contractors, and CONTRACTOR’s site. The Transmittal will clearly specify the purpose of the issue i.e.
Review, Approval, Information and the following documents will be submitted under the cover of a transmittal:
Document Transmittal Notes (DTN) will accompany all submittals of Drawings, Data Sheets, Calculations,
Requisitions, Manuals, and Reports. The DTN will contain the revision no., quantity and purpose of
submittal.
Document Controller shall scan and issue the transmittal and associated drawings/documents to
COMPANY through Share Point following with email notification to COMPANY DCC.
CONTRACTOR will submit all documents (Native and PDF files) along with a copy of the Transmittal
(PDF) electronically to COMPANY DCC.
CONTRACTOR will submit all revised documents along with Comments Resolution Sheets (CRS) to
facilitate convenient/expeditious review by COMPANY.
Transmittal Codes
T: Transmittal
9.0. ATTACHMENTS