Sie sind auf Seite 1von 20

TITAN CHEMICALS CORP. BHD.

(222357-P)

SHORT ASSIGNMENT:

STUDY OF LP DEPROPANIZER (2T-360)

TEE CHEE KEONG

CHEMICAL ENGINEERING

UNIVERSITI TUNKU ABDUL RAHMAN

NOV 2010
ii

Table of Contents

No. Content Page No.

ii
TABLE OF CONTENTS

iii
LIST OF TABLES

iv
LIST OF FIGURES

SECTION 1: INTRODUCTION

1.1 Objective 1
1.2 Study Period 1
1.3 Structure of Tower 1

SECTION 2: TOWER DETAIL

2.1 Process Flow Description 2


2.2 Flow Controller and Analyzer 4
2.3 Design Mole Balance 4

SECTION 3: RESULTS

3.1 Plant Loads 7


3.2 Total Feed In 8
3.3 Total Flow Out 9
3.4 Deviation 10
3.5 Reflux Ratio 11
3.6 Top ≤ C3 Composition 12
3.7 Top C4+ Composition 13

SECTION 4: DISCUSSIONS 14

SECTION 5: CONCLUSION 16
iii

LIST OF TABLES

TABLE TITLE PAGE

1 Structure of the tower 3


iv

LIST OF FIGURES

FIGURE TITLE PAGE

2.1 Process Flow Diagram 3

2.2 Flow Controller and Analyzer Diagram 5

2.3 Design Mole Balance Diagram (Case 1) 6

3.1.1 Graph of plant load before TA 7

3.1.2 Graph of plant load after TA 7

3.2.1 Graph of Total feed in before TA 8

3.2.2 Graph of Total feed in after TA 8

3.3.1 Graph of Total flow out before TA 9

3.3.2 Graph of Total flow out after TA 9

3.4.1 Graph of Deviation before TA 10

3.4.2 Graph of Deviation after TA 10

3.5.1 Graph of Reflux Ratio before TA 11

3.5.2 Graph of Reflux Ratio after TA 11

3.6.1 Graph of Top ≤C3% before TA 12

3.6.2 Graph of Top ≤C3% after TA 12

3.7.1 Graph of Top C4+% before TA 13

3.7.2 Graph of Top C4+% after TA 13


SECTION 1: INTRODUCTION

LP depropanizer is a distillation column in cracker plant which separate C3 and C4. Therefore,
the incoming feed will be separated as a top vapor which is rich in C3, and a bottom liquid of
essentially C4 and heavier components. Partial reflux system where portion of C3 reflux back to
the tower to increase C3 composition in the top stream. The bottom stream is sent to debutanizer
to recover C4 from heavier components.

1.1 Objective

To compare the flow, reflux ratio and the performance of the LP depropanizer before and after
the turnaround project on October 2010.

1.2 Study Period

Before Turnaround – 24, 25, 26 August 2010


After Turnaround – 16, 17, 18 November 2010

1.3 Structure

Table 1: Structures of the tower


Amount 67
Tray
Type Sieve type with 1 pass
Dimension 48.175m (Height) × 22.6m (Diameter)
Cold Insulation from top to tray 28
Insulation
Hot Insulation from tray 28 to bottom

1
SECTION 2: TOWER DETAIL

2.1 Process Flow Description

(Refer to the Fig 2.1 process flow diagram)

1. Main liquid feed from the bottom of the HP depropanizer (2T-365) is cooled by cooling water
in LP depropanizer feed cooler (2E-368) and then enter the LP depropanizer at tray 21.

2. Another feed from the bottom of the propylene stripper (2T-530) enters the column at tray 10.

3. The operating temperature of the LP depropanizer column is controlled to be higher at the


bottom so that C3 or lighter components would vaporize up, and lower temperature at the
bottom so that C4 or heavier components would condense down. Therefore the C3 will go up
and exit as top vapor and C4 will go down and exit as bottom liquid.

4. The condensing duty for the column is provided by the LP depropanizer condenser (2E-359)
using 7°C propylene refrigerant, which totally condenses the overhead vapor into liquid.

5. The liquid is collected in the reflux drum (2V-366). Part of the liquid is pumped back the top
of the LP depropanizer as reflux, through the pumps (2P-360A/S) to reduce the C4 amount in
the top stream.

6. The remaining liquid is pumped forward to the C3 hydrogenation system via the C3
hydrogenation feed pumps (2P-361A/S). This liquid consists of mainly C3.

7. The reboil duty for the column is provided by the LP depropanizer reboiler (2E-360) using
133°C quench oil, which heat up part of the bottom stream into vapor and send back to the
bottom of the LP depropanizer.

8. The bottom liquid product is essentially C4 and heavier components. This stream is then
transferred to the debutanizer (2T-560).

2
BTM from C3R
2E-359
2T-530 To C3
2V-366
C3 Vapor Hydrogenation

CW
BTM from
2T-365 2P-360A/S
HP DeC3 2E-368

2T-360
LP DeC3 QO

2E-360A/S

C4+ Liquid

To 2T-560
Debutanizer

Step number: Referred to the process description

Fig 2.1: Process Flow Diagram

3
2.2 Flow Controller and Analyzer

(Refer to Fig 2.2 flow controller and analyzer diagram)

2.2.1 Flow Controllers

1. Flow controller (2FC-3701) regulates the flow of quench oil to the reboiler (2E-
360), reset by the temperature controller (2TC-3704), which used to maintain the
cut point temperature on tray 50.

2. Flow controller (2FC-5303) measures the flow rate of the reflux at the top.

3. Flow controller (2FC-3702) regulates the bottom flow from the LP depropanizer,
which is reset by the column bottom level controller (2LC-3702), to maintain
certain liquid level in the column.

4. Flow controller (2FC-3703) regulates the flow of reflux back to the top of the
column.

5. Flow controller (2FC-3704) regulates the flow to top C3 liquid flow to the C3
hydrogenation system, reset by the reflux drum level controller (LC-3705).

2.2.2 Analyzer

1. Analyzer (2AI-36021) checks on the composition of the main feed from 2T-365.

2. Analyzer (2AI-36012) checks on the top vapor composition.

3. Analyzer (2AI-36022) checks on the bottom liquid composition.

2.3 Design Mole Balance

(Refer to Fig 2.3 design mole balance diagram)

This is the mole balance calculated based on case 1 (fully naphtha feed) used to compare the
actual flow, reflux ratio and performance of the tower.

4
2FC-
2AI-
5303
36012
C3R
BTM from
2E-359
2T-530 To C3
2V-366
C3 Vapor Hydrogenation

CW 2FC-
BTM from 3704
2T-365 2P-360A/S
HP DeC3 2E-368
2FC-
2T-360 3703
2FC- LP DeC3
3604 QO
2AI-
36021 2E-360A/S

C4+ Liquid

2FC-
3702 To 2T-560
2AI- Debutanizer
36022

Controllers: FC – Flow Controller


AI - Analyzer

Fig 2.2: Flow Controller and Analyzer Diagram

5
Total: 3154.27 kg/h Total: 25990 kg/h Total: 8416.37 kg/h
≤C3: 2264.39 kg/h ≤C3: 8305.36 kg/h
BTM from C4+: 889.89 kg/h C3R C4+: 111.01 kg/h
2T-530 2E-359 To C3
2V-366 Hydrogenation

CW
BTM from
2T-365 2P-360A/S
HP DeC3 Total: 17573.63 kg/h
2E-368

Total: 27597.60 kg/h 2T-360


≤C3: 6056.60 kg/h LP DeC3
C4+: 21541.00 kg/h
QO

2E-360A/S

Total: 158508 kg/h

To 2T-560
Debutanizer
Total: 22335.54 kg/h
≤C3: 15.63 kg/h
C4+: 22319.92 kg/h
Reflux Ratio = = 2.088
Legends:
Yield (C3) = = 99.81% Total – Total molar flow rate
≤C3 – C3 and lighter components
Yield (C4) = = 99.51% molar flow rate
C4+ – C4 and heavier components
molar flow rate

Fig 2.3: Design Mole Balance Diagram (Case 1)

6
SECTION 3: RESULTS

3.1 Plant Loads

Plant loads is the percentage of naphtha feed into the furnace decided by maximum naphtha feed based on 100% naphtha feed design.

Plant Load Before TA Plant Load After TA


100 100
90 90
80 80
70 70
Percentage %

Percentage %
60 60
50 plantload2 50 plantload2
40 40
30 30
20 20
10 10
0 0
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/201 11/16/201 11/17/201 11/17/201 11/18/201 11/18/201 11/19/201
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00
Time Time

Fig 3.1.1: Graph of plant load before TA Fig 3.1.2: Graph of plant load after TA

By comparing the two graphs above, obviously the plant load after the turnaround was much higher. This may be due to the change in
feed where feedstock used was naphtha and LPG before turnaround, and fully naphtha after turnaround.

The plant load is higher after turnaround because of 100% naphtha feed.

7
3.2 Total Feed In

Total feed in is the summation of the flows of main feed from the bottom of 2T-365, and from the bottom of 2T-530

Total In = 2FC-3604 + 2FC-5303

Total In Before TA Total In After TA

50000 50000
45000 45000
40000 40000
35000 35000
Flow Rate (kg/hr)

Flow Rate (kg/hr)


30000 30000
Actual Actual
25000 25000
Design Design
20000 20000
15000 15000
10000 10000
5000 5000
0 0
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/201 11/16/201 11/17/201 11/17/201 11/18/201 11/18/201 11/19/201
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00
Time Time

Fig 3.2.1: Graph of Total feed in before TA Fig 3.2.2: Graph of Total feed in after TA

By comparing the two graphs above, although the total amount of feed flow after the turnaround was fluctuating due to instability, but
the value is almost the same to the feed flow before turnaround.

The feed flow rate has not much different before and after turnaround.

8
3.3 Total Flow Out

Total flow out is the summation of the top product that is going to C3 hydrogenation and the bottom liquid flow.

Total Flow Out = 2FC-3702 + 2FC-3704

Total Out Before TA Total Out After TA

50000 50000
45000 45000

40000 40000
35000 35000
Flow Rate (kg/hr)

Flow Rate (kg/hr)


30000 30000
Actual Actual
25000 25000
Design Design
20000 20000
15000 15000
10000 10000

5000 5000
0 0
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/201 11/16/201 11/17/201 11/17/201 11/18/201 11/18/201 11/19/201
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00
Time Time

Fig 3.3.1: Graph of Total flow out before TA Fig 3.3.2: Graph of Total flow out after TA

By comparing the two graphs above, although the total amount flow out from the tower after the turnaround was fluctuating due to
instability, but the value is almost the same to the total flow out before turnaround.

The amount of flow out from tower has not much different before and after turnaround.

9
3.4 Deviation

Deviation is the difference between Total In and Total Out

Deviation = Total In - Total Out

Deviation Before TA Deviation After TA


30000 30000

25000 25000

20000 20000
Flow Rate (kg/hr)

Flow Rate (kg/hr)


15000 15000

10000 10000
Actual Actual
5000 5000

0 0

-5000 -5000

-10000 -10000

-15000 -15000
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/201 11/16/201 11/17/201 11/17/201 11/18/201 11/18/201 11/19/201
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00
Time Time

Fig 3.4.1: Graph of Deviation before TA Fig 3.4.2: Graph of Deviation after TA

By comparing the two graphs above, although the amount of deviation after the turnaround was fluctuating due to instability, but the
value is almost the same to the amount of deviation before turnaround.

From the comparison, the amount of deviation has not much different before and after turnaround.

10
3.5 Reflux Ratio

Reflux ratio is a ratio that the amount of top product reflux back to tower divided by the amount of top product sent to the next stage.

Reflux Ratio = 2FC-3703 / 2FC-3704

Reflux Ratio Before TA Reflux ratio After TA

5.00 5.00

4.00 4.00
Reflux Ratio

Reflux Ratio
3.00 3.00
Actual Actual
Design Design
2.00 2.00

1.00 1.00

0.00 0.00
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/2010 11/16/2010 11/17/2010 11/17/2010 11/18/2010 11/18/2010 11/19/2010
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00
Time Time

Fig 3.5.1: Graph of Reflux Ratio before TA Fig 3.5.2: Graph of Reflux Ratio after TA

By comparing the two graphs above, obviously the reflux ratio after the turnaround is lower than that before turnaround. This reflux
ratio can be controlled by the Boardman by controlling the amount of top product flowing to the C3 hydrogenation, higher reflux ratio
helps to get higher purity product.

Therefore, the reflux ratio is lower after the turnaround.

11
3.6 Top ≤ C3 composition

Top ≤ C3 composition is the molar percentage of C3 and lighter components in the top stream

Top Composition (≤C3) Before TA Top Composition (≤C3) After TA

100.00 100.00
90.00 90.00
80.00 80.00
70.00 70.00
60.00 60.00
mol%

mol%
50.00 Actual 50.00 Actual
Design Design
40.00 40.00
30.00 30.00
20.00 20.00
10.00 10.00
0.00 0.00
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/201 11/16/201 11/17/201 11/17/201 11/18/201 11/18/201 11/19/201
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00 0 12:00:00 0 0:00:00

Time Time

Fig 3.6.1: Graph of Top ≤C3% before TA Fig 3.6.2: Graph of Top ≤C3% after TA

By comparing the two graphs above, obviously the percentage of ≤ C3 in top stream became lower after turnaround. Besides, the C3
composition before turnaround not so fluctuate compares to after turnaround which is fluctuate within 70% to 90%.

The percentage of C3 in top stream is lower after the turnaround.

12
3.7 Top C4+ Composition

Top C4+ composition is the molar percentage of C4 and heavier components in the top stream

Top C4+ Composition Before TA Top C4+ Composition After TA

6 6

5 5

4 4
mol%

mol%
3 Actual 3 Actual
Design Design
2 2

1 1

0 0
8/24/2010 8/24/2010 8/25/2010 8/25/2010 8/26/2010 8/26/2010 8/27/2010 11/16/2010 11/16/2010 11/17/2010 11/17/2010 11/18/2010 11/18/2010 11/19/2010
0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00 12:00:00 0:00:00

Time Time

Fig 3.7.1: Graph of Top C4+% before TA Fig 3.7.2: Graph of Top C4+% after TA

By comparing the two graphs above, although the top C4+ molar percentage after the turnaround was fluctuating due to instability, but
the average value is almost the same to the top C4+ molar percentage before turnaround. Besides, the C3 composition before
turnaround not so fluctuate compares to after turnaround which is fluctuate within 70% to 90%.

The average top C4 + molar percentage has not much different before and after turnaround.

13
SECTION 4: DISCUSSION

By comparing the actual flows to the design flows, most of the actual flows are closed to
the design flow, except for the Total In Flow. The Total In is about 3500 kg/h higher than the
design feed flow, due to the high flow of main feed from the bottom of HP depropanizer (2T-
365). For the reflux ratio, the actual reflux ratio is closed to the design one before turnaround but
lower to the design after turnaround. For the analyzer part, both the C3≤ and C4+ percentage in
the top stream showing under performance of tower if compared to the design.

From the comparison of Total In and Total Out flows, deviation keeps happening for the
tower no matter before or after turnaround which does not happen in the design condition. This
shows that certain amount of stream has been “missing” from the tower. This may be due to the
following reasons:

1. Sent for flaring or blowdown. However, this reason is not appropriate since the flaring
amount is only little when the plant is running in normal condition.

2. Inaccuracy of the flow indicator. This is reasonable to explain the missing of the flow.
Example like the inaccuracy of flow indicator for the main feed from 2T-365, this could
explain the increase of about 3500kg/h flow compared to the design value.

3. Accumulation in the tower. The product is kept in the tower to maintain the operation
parameter, causes the deviation to occur.

14
Besides that, there are a few parameters founded that change after the turnaround:

1. The plant load has been increased. Plant load is the percentage of naphtha feed into the
plant compared to the amount of naphtha feed in the design (100%). This may be due to
the change in feed condition whereby naphtha was mixed with certain amount of LPG as
feed before turnaround, but used fully naphtha after turnaround. Therefore the plant load
used has been increased after turnaround.

2. The reflux ratio has been reduced. Reflux ratio is a ratio that the amount of top product
reflux back to tower divided by the amount of top product sent to the next stage. This
reflux ratio can be controlled by the Boardman by controlling the amount of top product
flowing to the C3 hydrogenation, higher reflux ratio helps to get higher purity product.

3. The percentage of C3 in top stream has been reduced. This shows that the under
performance of the tower after the turnaround. This might be due to the decrease of reflux
ratio, or the change on the plant load.

15
SECTION 5: CONCLUSION

In a conclusion, LP depropanizer (2T-360is under performance compare to the design value after
the turnaround. However, the cracker plant is not so stable at the investigation period. Therefore,
a further study should be performed once the cracker plant becomes more stable.

16

Das könnte Ihnen auch gefallen